WMS - Floor Screeding Works

This document outlines the method statement for floor screeding work on a tourism development project in Pahang, Malaysia. It describes the scope of works, work sequence, and methods for surface preparation, setting out markings and mortar pegs, batching and mixing mortar screed, and applying the screed. Quality control measures include inspection and testing to ensure work meets construction standards and tolerances. The floor screeding work is part of the overall proposed construction and completion of the Pantai Hiburan Tourism Development.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
644 views5 pages

WMS - Floor Screeding Works

This document outlines the method statement for floor screeding work on a tourism development project in Pahang, Malaysia. It describes the scope of works, work sequence, and methods for surface preparation, setting out markings and mortar pegs, batching and mixing mortar screed, and applying the screed. Quality control measures include inspection and testing to ensure work meets construction standards and tolerances. The floor screeding work is part of the overall proposed construction and completion of the Pantai Hiburan Tourism Development.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

FNA BUILDERS AND METHOD OF STATEMENT PROJECT: THE PROPOSED

CONSTRUCTION AND
COMPLETION OF PANTAI
SERVICES DN.BHD. FLOOR SCREEDING WORK HIBURAN TOURISM
DEVELOPMENT, ROMPIN,
PAHANG DARUL MAKMUR FOR
Page No. : 1 of 5 THE EAST COAST ECONOMIC
REGION DEVELOPMENT
Revision No. : 00
COUNCIL (ECERDC)
Issued : 10/03/2023

AUTHORIZATION & RECORD

R
e Reviewed Approved
Description Prepared by Date
v by by
.

1
.
0

2
.
0

Important

The information contained herein is the proprietary property of FNA BUILDERS AND
SERVICES SDN.BHD. It shall not be reproduced, copied, revealed, published, or distributed in
whole or partly without authorization.

TABLE OF CONTENT

Ref. Description Page No.


1.0 INTRODUCTION ………………………………………………………………………………
2
2.0 SCOPE OF WORKS 2
3.0 WORK SEQUENCE FLOW 2
4.0 WORK SEQUENCE FLOW 2
5.0 QUALITY: INSPECTION TEST & PLAN 4
6.0 MATERIAL 5
6.0 MACHINERY 5
8.0 MANPOWER..................................................................................................................................... 5
9.0 SAFETY AND ENVIRONMENT 5
FNA BUILDERS AND METHOD OF STATEMENT PROJECT: THE PROPOSED
CONSTRUCTION AND
COMPLETION OF PANTAI
SERVICES DN.BHD. FLOOR SCREEDING WORK HIBURAN TOURISM
DEVELOPMENT, ROMPIN,
PAHANG DARUL MAKMUR FOR
Page No. : 2 of 5 THE EAST COAST ECONOMIC
REGION DEVELOPMENT
Revision No. : 00
COUNCIL (ECERDC)
Issued : 10/03/2023

1.0 INSTRUCTION
This method statement outlines are to Floor Screeding Work for project The Proposed Construction
and Completion of Pantai Hiburan Tourism Development, Rompin, Pahang Darul Makmur for The
East Coast Economic Region Development Council (ECERDC).
2.0 SCOPE OF WORKS
This work method statement describes all the Floor Screeding Works

3.0 WORK SEQUENCE FLOW

Surface Preparation

Floor Screeding Setting Out: Marking and


Mortar Pegs

Floor Screeding: Batching and Mixing

Floor Screeding: Application


FNA BUILDERS AND METHOD OF STATEMENT PROJECT: THE PROPOSED
CONSTRUCTION AND
COMPLETION OF PANTAI
SERVICES DN.BHD. FLOOR SCREEDING WORK HIBURAN TOURISM
DEVELOPMENT, ROMPIN,
PAHANG DARUL MAKMUR FOR
Page No. : 3 of 5 THE EAST COAST ECONOMIC
REGION DEVELOPMENT
Revision No. : 00
COUNCIL (ECERDC)
Issued : 10/03/2023

4.0 METHOD OF STATEMENT FOR PAINTING WORKS

4.1 Surface Preparation:


4.1.1.1 All the substrate/concrete surfaces shall be clean, free from grease, oil,
laitance or other loosely adhering particles and sharp edges.
4.1.1.2 All substrate/concrete surfaces shall be dried, clean, smooth and even, free
of ridges and hollows.
4.1.1.3 For toilet area, waterproofing shall be completed, fully cured and ready to
receive floor screeding works.

4.2 Floor Screeding Setting Out: Marking and Mortar Pegs:


4.2.1.1 Setting Out: Marking
➢ From 1m Floor Finish Level (FFL) the level pegs marked along
the wall as reference line.
4.2.1.2 Mortar Pegs
➢ Mortar pegs provided at every 1500mm to 2000mm interval
between two mortar pegs.
.
4.3 Floor Screeding: Batching and Mixing:
4.3.1.1 Mortar screed shall be properly mixed with suitable measuring method eg:
gauge box. In order to achieve consistent mortar mixing, screeding mixing
ratio shall comply to the following design mix:-
Cement : Sand
1 : 4 to 6

4.3.1.2 Concrete mixer machine shall be used to mix the mortar screed.

4.4 Floor Screeding: Application:


4.4.1.1 Sprinkle water onto the surface to receive floor screed where and when
necessary, before applying coats. This is to obtain uniform suction and
reduce excessive suction.
4.4.1.2 Mortar screed poured to the floor screed area. Mortar screed trowel to the
floor screed finish level by follow mortar pegs as guidelines.
4.4.1.3 When mortar screed reached to the finish level, mortar screed shall be
smoothly floated using timber float until the surface of the mortar setting
bed is absolutely true and even in plane.
4.4.1.4 Final coat shall be finished with float and sponged to fine, lightly
trowelled with steel trowel.
FNA BUILDERS AND METHOD OF STATEMENT PROJECT: THE PROPOSED
CONSTRUCTION AND
COMPLETION OF PANTAI
SERVICES DN.BHD. FLOOR SCREEDING WORK HIBURAN TOURISM
DEVELOPMENT, ROMPIN,
PAHANG DARUL MAKMUR FOR
Page No. : 4 of 5 THE EAST COAST ECONOMIC
REGION DEVELOPMENT
Revision No. : 00
COUNCIL (ECERDC)
Issued : 10/03/2023

5.0 QUALITY: INSPECTION & TEST PLAN


5.1 Inspection & Test Plan
5.2 Construction Standard & Tolerance CIS 7: 2006 (QLASSIC)
• BS 8204: 2002 Part 1 – BS for Workmanship on Building Sites
FNA BUILDERS AND METHOD OF STATEMENT PROJECT: THE PROPOSED
CONSTRUCTION AND
COMPLETION OF PANTAI
SERVICES DN.BHD. FLOOR SCREEDING WORK HIBURAN TOURISM
DEVELOPMENT, ROMPIN,
PAHANG DARUL MAKMUR FOR
Page No. : 5 of 5 THE EAST COAST ECONOMIC
REGION DEVELOPMENT
Revision No. : 00
COUNCIL (ECERDC)
Issued : 10/03/2023

6.0 MATERIALS
6.1 Cement Mixer Machine.
6.2 Hand Tools : Timber Floating, Flat Edge Trowel, Angle Float.
6.3 Aluminium Ruler with water level / Sprit Level.
6.4 Hammer and Nails.
6.5 String and Sprit Level & Plum bob.
6.6 Spade/ Scope

7.0 MACHINERY
7.1 -N/A

8.0 MANPOWER
8.1 Supervisor
8.2 Site Safety Supervisor
8.3 General Worker
8.4 Skilled Worker

9.0 SAFETY AND ENVIROMENT


9.1 All construction work will be carried-out in accordance with Project Safety plan, Owner
Safety Procedures, Vendor Safety Instruction and statutory regulations.
9.2 Personal protective equipment (PPE): Wear appropriate PPE, including safety goggles,
gloves, and protective clothing to prevent exposure to chemicals and materials used in
screeding.
9.3 Ventilation: Ensure that the work area is properly ventilated to prevent inhalation of fumes
and dust.
9.4 Tools and equipment: Use tools and equipment that are in good condition and appropriate
for the task at hand. Inspect all equipment before use, and ensure that they are properly
maintained and used according to manufacturer guidelines.
9.5 Material handling: Use proper lifting techniques when handling heavy bags of screed or
other materials. Use equipment such as dollies or forklifts to move heavy materials, and
avoid overloading equipment.
9.6 Slip and fall prevention: Keep the work area clean and free of obstacles to prevent slips,
trips, and falls. Use caution when working on elevated surfaces, and use appropriate fall
protection equipment when necessary.
9.7 Electrical safety: Avoid using electrical equipment near water or in damp conditions.
Ensure that all electrical equipment is properly grounded and has proper insulation.
9.8 Fire prevention: Keep flammable materials away from heat sources, and use fire-resistant
materials when possible.
9.9 Emergency procedures: Ensure that all workers are familiar with emergency procedures in
case of accidents or injuries, including first aid and evacuation procedures.