MPW-Bldg. Code
MPW-Bldg. Code
merged into MPHW, later DPWH, the BRDS ceased to be a regular Service Staff of the
Secretary and the activities of the BRDS were somehow suppressed. When problems in the
Implementation of the Code began to pile up, the Secretary realized the need of the services of
the BRDS. The BRDS was revived and the members of its staff were picked from selected
personnel of the Bureau of Design (BOD) and the Legal Service with the BOD Director as
Executive Director and the Chief of the Architectural Division, BOD, as Deputy Executive
Director, but all of them in interim capabilities and without being relieved of their regular duties.
The only updating of the IRR occurred in 1992 when Permit Fees were raised 100% to alleviate
and augment the needs of the Offices of the Building Officials in the performance of their
functions.
The provision of this Code shall apply to the design, location, siting, construction,
alteration, repair, conversion, use, occupancy, maintenance, moving, demolition of, and addition
to public and private buildings, structures, except traditional indigenous family dwelling
intended for the use and occupancy by the family of the owner only and constructed of native
materials.
All buildings and structures constructed prior to the enactment of this Code, if legally
done according to RA 6541 or to existing city or municipal codes then, shall be respected subject
to the limitations established in this Code. However, alteration, additions, conversions and/or
repairs to be made shall be subject to the provisions of this Code.
Section 1.6. Are there any laws Superceding and/or Complementing the NBC?
The passage of RA 7160, otherwise known as the Local Government Code of 1991, has
affected the administrative set-up as envisioned in PD 1096 in that it removed from the powers
of the Secretary of Public Works and Highways to designate the Building Official when the later
Law provided that the city or municipal engineer, who is appointed by the local chief executive
shall also act as Building Official. Moreover, the city or municipal engineer shall be a duly
registered civil engineer whose qualification for the city engineer is five years experience and for
the municipal engineer is three years experience without specifying the nature of the experience.
Note that with this provision only civil engineers may be designated as acting building officials
since architects cannot be appointed as city or municipal engineers. Likewise, the minimum
experience as provided in Section 206 of the NBC is not satisfied. However, in some
progressive cities and municipalities where the local government recognizes the need for a
separate office of the Building Official, the government council can invoke Section 454 of the
Local Government Code to create such an Office wherein an architect or a civil engineer may be
designated as Building Official.
In accordance with the Opinion of the Secretary of Justice, the Chief Executive of the
Local Government Unit (LGU) has administrative jurisdiction over the city or municipal
engineer even in his capacity as acting Building Official, but the Secretary of Public Works and
Highways retains appellate jurisdiction on cases appealed in connection with the implementation
of the National Building Code. In Opinion No. 140, Series of 1987 the Secretary of Justice
stated in no uncertain term that “the power to appoint Building Officials throughout the country
including Metro Manila pertains to the Secretary of Public Works and Highways and to no other
officials.” Hence, if the LGU decides to create a separate Office of the Building Official distinct
from that of the Office of the City or Municipal Engineer, the Building Official has to be
appointed or confirmed by the Secretary of DPWH.
There are other laws complementing the NBC such as the Fire Code of the Philippines
(PD 1185), the Labor Code of the Philippines (PD 442), the Accessibility Law (BP 344) and the
various Agency Codes. The DOLE also came out with the Occupational Safety and Health
Standards (OSHS) that included Electrical and Mechanical Safety Orders previously issued prior
to PD 442. The OSHS divided inspection activities into Technical and General Safety Inspection
described as follows:
Technical Safety Inspection – for the safety determination of boilers, pressure vessels,
internal combustion engines, electrical installations, elevators, hoisting equipment and other
mechanical equipment.
General Safety Inspection – inspection of work environment including the location and
operation of machinery not covered by technical safety inspection, adequacy or work space,
ventilation, lighting, conditions of environment, handling, storage, or work procedures,
protection facilities and other safety and health hazards in the work place.
[As now the Bureau of Working Conditions (BWC) DOLE, is still implementing Rule
1160 of the OSHS. Section 1162.1 of which states “No boiler shall be installed and/or operated
in the Philippines without the permit issued for the purpose by the Minister (of Labor) or his
authorized representative”. For instance, the 1,200 MW coal fired plant of MIRANT in Sual,
Pangasinan, is still being inspected yearly by the BWC DOLE inspectors. This issue as to
whether it is the BWC or the OBO who shall conduct the inspection is still unresolved].
The different technical Professional Codes of the Professions involved in the design and
construction of building/structures are also complementary laws and referred to as Referral
Codes of the NBC.
The need to update the IRR has become imperative to be relative to the present
development in building design and construction, so that in the year 2000, the Secretary issued a
Memorandum Order organizing the Board of Consultants (BOC) composed of officers and
members of the different professional organizations involved in building design and construction
and headed by Architect/Engineer Angel Lazaro, Jr. The Secretary also reconstituted the BRDS
into the National Building Code Review Committee (NBCRC) of the DPWH. The work lasted
for more than three years of deliberation, revisions, compilations and another year for the final
review and editing. The new or revised and Updated IRR was approved by the Secretary on
November 04, 2004. Pursuant to Section 211m the IRR has to be published once a week for
three consecutive weeks in a newspaper of general circulation; the first publication was on April
01, 2005 in the Manila Standard, Subsequent publications were on April 08, 2005 and April 15,
2005.
Section 1.1. How does the Old IRR compare with the Revised or New IRR?
The old IRR has nineteen Rules and Regulations promulgated by the Building and
Research Development Staff (BRDS) of the Minister of the MPWTC on different dates in a
continuing process as the NBC is being implemented and as problems are encountered in the
field. There was not much activity in pursuing other rules and regulations after Rule XIX was
issued except in 1992 when it became imperative that Permit Fees had to be adjusted to be
compatible with the value of the peso and the rising cost of construction, so that Rule III had to
amended.
The New IRR has twenty four (24) Rules and Regulations that adhere to the Chapters of
the NBC for easier reference. It still contains the nineteen (19) Rules of the previous IRR but
some are with amendments and distributed in the Rule Number corresponding to the Chapter
Number as they appear in the MBC. Other rules that have yet to be formulated have been
provided in compliance with the NBC.
1.2.1. To update the provisions and to include those still to be promulgated by the
Secretary as called for in the NBC. As stated earlier, it has become imperative that various
provisions of the existing IRR be updated/amended and amplified to be realistic and relevant to
the present time as demanded by technological advances in building design and construction,
rapid urbanization, development of mega cities characterized by high-rise building/structures and
the relevant requirements of related laws and other agencies of the government.
1.2.2. To organize the sequence of the provisions as they appear in the Chapters of the
NBC for easy reference. The rules and regulations have been rearranged following the same
sequence and numbering as those of the Chapters and Sections of the NBC for purposes of
clarity, continuity and homogeneity.
1.2.3. To identify who shall be responsible and liable for the design, supervision or
construction of a building/structure. This is in consonance with Article 1723 of the Civil Code
of the Philippines which provides that the architect or engineer who designed the building shall
be liable for damages should it collapse due to defect in plans and specifications or defect in the
ground; the contractor of the building shall be liable if the collapse is due to defect in
construction or to the use of materials of inferior quality or violation of the terms and condition
of the contract; the one who supervised the construction shall be solitarily liable with the
contractor. Hopefully this will minimize/eliminate corruption by reducing the burden on the
Building Official, shifting the responsibility of complying with the requirements of the Code to
the owner and the design, supervision and construction professionals.
The new or revised Implementing Rules and Regulations contain, in brief, the following:
1.3.1. RULE I – GENERAL PROVISIONS. This Rule simply states the Title of the
IRR, the Declaration of Policy and the Scope and Application.
1.3.3. RULE III – BUILDING PERMITS AND INSPECTIONS. In this Rule the
kind of Permits are defined and explained. The steps on how to secure a Building Permit is
clearly stated including the necessary documents and the detailed requirements that should be
contained by every discipline involved in the preparation of the plans and specifications of the
project being applied for. The step-by-step procedure in the processing of building permit
applications, and in the processing of certificates of occupancy/use after the structure is
completed, is fully explained in this Rule (Section 303 and 309). See also Chapter 5 – Section
5.1 of this Manual.
A notable feature introduced in this Rule is the set of conditions required in the issuance
of the Ground Preparation and Excavation Permit to prevent excavations from being abandoned
for specified period of time (Section 304.4). Noteworthy also is the emphasis on the provision of
Article 1723 of the Civil Code of the Philippines regarding the responsibility of the designer, the
contractor and/or the one who supervise the construction in case the building collapses (Section
304.5a).
The other Groups such as Educational and Recreational, Institutional, Business and
Mercantile, Industrial, etc., are similarly tabulated with particular emphasis on the use and
character of the buildings that fit the Zones.
1.3.8. RULE VIII – LIGHT AND VENTILATION. The Rule on “Light and
Ventilation” in the previous Implementing Rules and Regulations was the familiar Rule XVI. In
the new IRR it is now Rule VII to correspond to Chapter 8 of the NBC, for easier reference.
There are lots of acronyms to be familiar with in order to go through the Rule more
conveniently. Such things are PSO or Percentage of Site Occupancy, PLO or Percentage of Lot
Occupancy. AMBF or Allowable Maximum Building Footprint, TLA or Total Lot Area, ISA or
Impervious Surface Area, USA or Unpaved Surface Area, MACA or Maximum Allowable
Construction Area, TOSL or Total Open Spaces within Lot, RROW or Road Right-of-Way, PUD
or Planned Unit Development, CLUP or Comprehensive Land Use Plan, ZO or Zoning
Ordinance must be within the fingertips of the reader as he goes through the Rule.
One must also be well versed in Rule VII – “Classification and General Requirements of
Building/Structures by Use or Occupancy” which deals with Zoning Classification because
zoning is an important element in siting of buildings for proper light and ventilation.
An Example or portion of the TABLE is shown below. Please see Notes below the Table
to understand the asterisks, number, and plus signs indicated in the Table.
Building/ Maximum
Structure Duly-Approved Maximum Allowable Minimum
Use or Zoning** Allowable ISA*** USA TOSL****
Occupancy PSO*** (Paved (Unpaved (ISA + USA)
(or Land Use)* *** Open Open
Spaces) Spaces)
# without firewall
+ with firewall
The Table simply leans that for a lot classified as Residential in a Residential 2 Zone, say 120
sq.m. lot, the maximum allowable lot occupancy (PSO) is 66 sq.m. (55%) if the building does
not abut the property line and 72 sq.m. (60%) if it abuts the property line using a firewall. The
rest of the table follows the same pattern for other building uses and occupancies.
Included in this Rule is Rule XIV – Occupant Loads of the old IRR as it should be, since
this is Section 1207 in Chapter 12 of the NBC and similarly numbered 1207 in this Rule. Of
particular interest is in the determination of width of exits where the Code provides that the total
width in meters shall not be less than the occupant load divided by 165. This presupposes that
165 persons can exit in one-meter opening in one minute.
In the Fire Code of the Philippines (PD 1185) the width and capacity of egress is
expressed in number of persons per unit of exit width. For level aggress components and Class
A ramps – 100 persons, and for inclined egress components and Class B ramps – 60 persons.
The means of egress shall be measured in units of exits of fifty five (55) centimetres. Fractions
of a unit shall be counted, except that thirty (30) centimetres added to one or more full units shall
be counted as one-half (0.5) of a unit of exit width. (FCP IRR Section 3.401D). This means that
the capacity of any door leading to the outside of the building shall be 100 persons per unit of
exit width (55 cm.) per minute for Class A ramps, and 60 persons per minute for Class B Ramps.
(FCP IRR Section 3.801-2 of Educational Occupancies).
On the other hand the Occupational Safety and Health Standards (OSHS) of the DOLE
(Section 1943.03-5) provides that the width of the exits shall be computed by dividing the total
occupants of a floor or a storey (maximum allowable) by sixty (60) in industrial and commercial
establishments, by forty five (45) in service establishments, and by seventy five (75) in places of
assembly and the quotient multiplied by fifty five (55) to get the width of the exit in centimeters.
Obviously, there are instances that the Building Code provision is more stringent than the
Fire Code and there are stricter. But in most cases, the OSHS provision is much more stringent
as they apply to industrial and hazardous occupancies. The designer, therefore, should be careful
which to adopt in his design. He should be aware that the BO refers a set of plans and
specifications to the BFP for all types of occupancies and another set to the DOLE for Industrial
Occupancies for verification if the design conforms to their Code and Standards. Although the
NBC provision is much simpler to use by simply dividing the Occupant Load by 165 to
determine the width of exits, but when there are stairs (ramps) classified as Class B, that is,
where the riser is 20 cm. or more and the tread is 23 cm. less (FCP IRR Section 3.403-B)
included in the way to the exit, then he might have to adopt the FCP provisions. In a multi-
storey building, the floor requiring the greatest number of units of exit widths dictates the
minimum width of exits from that point on in the direction of exit travel. When, for instance, the
direction of exit travel includes corridors and stairs to reach the exit level, then the 100 person
per unit width of exit might not hold true anymore but rather, the 60 persons as provided in the
FCP and thus, wider exit door than those computed under the NBC should be provided. For
similar occupant loads and similar conditions, the OSHS standards require wider exit widths.
EXAMPLE:
Compute the exit width if the Occupant Load of an assembly area is 1650 persons.
Pursuant to the NBC, for occupant loads over 1000, there should be a minimum of four
(4) exits.
a) Using the NBC formula the total width of exits in meters is 1650/165 = 10 meters.
Each exit therefore has a width of 10/4 = 2.50 meters.
b) Using the FCP formula, the number of exit width of 100 persons per unit width in
1650/100 = 16.50 exit widths. The total width of exit in centimetres is therefore
16.50 x 55 = 907.50 centimeters or 9.075 meters. Each exit width is 9.075/4 = 2.28
meters.
c) Using the OSHS formula, 1650/74 = 22 exit widths. 22 x 55 = 1210 cm. or 12.10
meters. Each exit width therefore is 12.10/4 = 3.025 meters.
From the above example it is shown that the exit widths vary depending on the formula
used. The OSHS requires a wider exit width to vacate the area and presumably is much safer to
adopt because the assembly area can be emptied much faster (less than one minute) if the
occupants move at 100 persons per exit width rather than 75 as computed.
The BO’s concern however is on the provisions of the NBC while the Bureau of Fire
Protection of the Fire Marshall, that of the provisions of the FCP, and the DOLE, that of the
provisions of the OSHS. Whatever the case, in the interest of safety, the more stringent and
stricter provisions should prevail.
1.1.13.2.1. Mechanical systems, equipment and installations are easier identified as:
a) Mechanical Equipment and Machinery – These include all prime movers such as
steam engines and turbines, internal combustion engines, gas engines and turbines;
steam generators such as boilers, furnaces; heat exchangers such as cooling towers,
kilns and dryers, coolers and heaters; materials handling equipment such as pumps,
cranes, conveyors, hoist, elevators, escalators, mechanized dumbwaiters, moving
ramps and walkways, heating, air conditioning, ventilating and refrigeration
equipment and machinery, compressors and centrifugal fans, mechanical pollution
abatement and environmental control system, piping system with a working pressure
of not less than 70 kpd., fired and unfired pressure vessels, printing machines;
mechanical working machines for metallic and non-metallic materials and other
mechanical equipment and machinery whether installed on land, underground or on
board watercraft.
1.1.13.2.3. Responsibility – The Forms prescribed in the IRR are clearly presented
and the OBO is duty bound to follow them to the letter. Inspections
rendered by the OBO require a certification by a duly licensed
professional mechanical engineer or lower level mechanical engineer or
certified plant mechanic as followed by RA 8495 (the Mechanical
Engineering Law) certifying to the integrity of the installation. This
mandatory participation of the practicing mechanical engineer hired by the
owner enhances awareness and enforcement of standard safety measures.
Any installation inspected or tested performance in the presence of both
the OBO inspector and the engineer hired by the owner and issued the
Certificate of Inspection/Operation binds both for any failure of the
installation for the duration of one (1) year upon issuance of the
Certificate. Section 7.7.3 of the revised PSME Code for boilers and
pressure vessels require that a boiler inspector and plant inspector shall be
professional mechanical engineers.
1.3.14. RULE XIV – PHOTOGRAPHIC AND X-RAY FILMS. This Rule is merely a
repetition of what is provided in the NBC with emphasis on safety requirements for storage and
handling of photographic and x-ray films. It provides the designer much leeway in allocating
spaces in his design to satisfy his client’s needs. He is therefore, governed by the requirements
of his professional Code and applicable provisions of the NBC as to safety of the whole
structure.
1.3.16. RULE XVI – PLASTICS. The provisions of this Rule are merely a repetition of
the provision of Chapter 16 of the NBC since these actually are implementing rules and
regulations. The BO must ascertain that the product particulars and technical data complying
with the minimum standards as required in this Rule or generally accepted standards of any
plastic material used in the construction are also indicated in the specifications signed and sealed
by the designer.
1.3.17. RULES XVII – SHEET METAL PAINT SPRAY BOOTHS. Paints spray
booths are potential fire hazard where dangerous quantities of flammable vapors or combustible
residues, ducts or deposits are present due to the process of spraying; hence, special provisions
are required. This Rule specifies the thickness of the sheet metal (steel) to be used, the area of
the booth, floor protection, fire protection, type of illumination and manner of ventilation, it
would be wise for the Building Official to refer the plans and specifications to the Fire Marshall
to evaluate consonance particularly to Division 2 of the FCP from Section 22.201 to 22.210.
1.3.18. RULE XVIII – GLASS AND GLAZING. Most of the requirements in this Rule
are already in the NBC except for a few additional safety provisions and limitations to be
observed. Since the designers are the ones responsible for providing the safety features of the
building/structure, the Professional Codes (the Architectural Code, for instance) to which they
should also adhere more explicit in the requisites of safety and of types of glasses, as well as the
guidelines and specifications of the glass manufacturers and of the materials used in the
installation of glasses.
1.3.19. RULE XIX – THE USE OF COMPUTERS. The Rule simply states the
requirements on what should be submitted to the Building Official whenever computer generated
computation are used in the designed of a building/structure such as: reference where the
detailed description or the theoretical background of the program including a description of the
algorithms are found, software name, version number and the company’s address that developed
the software, and the output sheets duly certified by the designer.
1.3.20. RULE XX – SIGNS. In the Old IRR and even in this New IRR, much leeway is
given to adherence to the Code of Ethics for Advertising and Promotions and the rules and
regulations of the appropriate agency in-charge of the conduct of the business. It is becoming
obvious that such Code of Ethics is not being strictly observed since giant billboards are
sprouting without regards either to aesthetic or to distance between billboards. Completion has
gone wild as to what billboard can attract attention from the motorist. Moreover, there is no
definite sanction or penalty for violations of the Code of Ethics that makes it difficult for the
Building Official to enforce the NBC. He is dependent more on the Local Government
Ordinance as to what constitute obstruction of the natural landscape since it is only the LGU that
can determine or define what natural beauty of the locality it wishes to remain unobstructed. The
Building Official can only conveniently enforce the IRR, which is more definite as to the safety
features of the sign structure (like Structural and Electrical), the clearances and dimensions of the
signs and the conditions itemized in the Sign Permit.
The Ancillary Permits are permits forms duly signed and sealed by the corresponding
professionals who prepared the documents like plans/drawings, specifications, design analysis
and pertinent documents that are submitted together with the Building Permit. The Ancillary
Permits are the following:
Section 5.1. What are the activities of the OBO during the pre-construction phase?
The OBO checks whether or not the requirements needed for the approval of the Building
Permit have been complied with. Assuming that the clearances are in order, the OBO inspects
the site where the structure is to be constructed to verify the conditions in the site. In some cases
the construction has already been started even if the Building Permit has not yet been issued. In
which case the corresponding fines should be imposed. There are cases where the location
pointed to by the applicant does not match the location plan and technical descriptions submitted
with the application for Building Permit. The necessary rectifications and clarifications should
be made for obviously, some misrepresentations or errors were committed.
Step 1
a. Application for Building Permit is received. All required documents are
checked as to completeness including verification of Land Use Zoning and
other clearances.
Step 2
a. Documents are forwarded to the Architectural Section for compliance to
setback/easement requirements, safety, parking and accessibility features. If
found deficient, plans are returned to the applicant together with comments on
the deficiencies in writing, for adjustment/correction/explanation by his
designer.
Step 3 to 6 (Could be less for simple structure or more for complicated structures
involving voluminous sheets/pages; depends also on the volume of applications received
daily by the OBO)
a. Continuing processing activities with lateral and vertical coordination between
Sections.
Step 7 to 10
a. Consolidation of processed Documents and corresponding Evaluations.
Step 11
a. All processed and evaluated Documents together with the Final Evaluation
and Recommendation by the OBO staff are forwarded to the BO.
Step 12
a. BO signs appropriate documents including Building Permit and return all
documents to the Recording and Releasing Section.
Step 13
a. The Recording and Releasing Section releases to the applicant the Building
Permit including copies for the owner/applicant of signed Documents, upon
presentation of Official Receipt of Payment.
The BO reserved the right to invite/summon (in writing) the owner/applicant and his
designer whenever there are questionable or ambiguous items in the plans, specifications, or
other documents that need to be explained or corrected.
In the event that the BO has to exercise Section 306 of the NBC re: Non-issuance,
Suspension or Revocation of Building Permits, the owner/applicant has 15 days from the date of
advice of receipt of the order of the BO to file an appeal with the DPWH Secretary (See Part IV
– Chapter 1 of this Manual).
Section 6.1 What are the activities of the OBO during the construction phase?
The OBO conducts periodic inspection on the on-going construction. Copy of the plans
and specifications as noted by the Building Official including the logbook should be in the site of
the on-going construction for the scrutiny of the inspectors of the OBO at all times. Particular
attention should be taken by the inspectors regarding excavations whether or not the necessary
safeguards are provided, setbacks, firewalls, safety provisions for workers and pedestrians,
laboratory test results on concrete samples and reinforcing bars, compliance with plans and
specifications. The inspectors registers in the logbook all observations and instructions to the in-
charge of construction. Amendatory plans/specifications duly signed and sealed by the designer
should be required for proposed changes in the original plans and specifications and submitted to
the OBO for proper notation. Changes, modifications and alterations shall not be started before
the issuance of the Amendatory Permit.
Section 7.1 What are the activities of the OBO immediately after the
building/structure is in placed?
Upon submission by the owner of the Certificate of Completion together with the
logbook and the Building Inspection Sheet duly accomplished by the contractor (if the
construction was done by a contractor) and signed and sealed by the in-charge of the
construction work, the OBO shall undertake the final inspection, verification or review of the
building based on the Certificate of Completion, logbook, plans or as-built plans as the case may
be, and specifications. The BO shall issue the corresponding Certificate of Occupancy if the
building is found to have been constructed in accordance with the submitted documents.
For mechanical equipment, the final inspection/test shall be made in the presence of the
Mechanical Engineer hired by the owner and the OBO mechanical inspector. A Certificate of
Inspection is issued if the integrity of the equipment is found satisfactory. Both the mechanical
engineer hired by the owner and the OBO inspector are jointly liable for the failure of the
equipment within a one (1) year duration upon issuance of the Certificate.
The BO gives the assignment to the Inspection and Enforcement Division of the OBO.
The Chief of the Division forms a team of technical inspectors under a team leader, composed of
the different disciplines depending on the structure to be inspected. The date of the annual
inspection is reckoned from the date the Certificate of Occupancy was issued. The owner shall
be notified as to when the annual inspection is to be conducted. Each team member shall prepare
a report on the aspect he/she is more knowledgeable. Photographs should be taken to supports
the reports. A consolidated report is prepared by the team leader together with the assessment on
fees based on the schedule of fees in the IRR, submits the same to the Chief of the Division who,
in turn, forwards it to the BO with his recommendations. Assuming that the building is well
maintained and that no substantial changes were made, the BO issues a Certificate of Annual
Inspection after the owner has paid the corresponding fees. For failure to pay the annual
inspection fee within thirty (30) days from the prescribed date, a surcharge of 25% of the
inspection fee shall be imposed. In case there were substantial changes made in the
building/structure constituting illegal addition or change in use or occupancy (without the proper
building permit) or that should remit removal, the BO shall issue the necessary order/s
corresponding to the violation/s for compliance by the owner/applicant.
The DPWH Secretary of his authorized representative prescribes and imposes the fines
not exceeding ten thousand pesos (P 10,000.00). The terms and conditions are as enumerated in
SECTION 212 of the IRR. Violations are classified as Light Violations, Less Grave Violations,
and Grave Violations. The amount of fines for Light Violations is P 5,000.00, for Less Grave
Violation P 8,000.00 and for Grave Violations P 10,000.00. In addition to the imposed penalty,
the owner shall correct/remove the violations as directed.
PART IV – INVESTIGATIONS
Chapter 1 – Appeals
Section 1.1 – What is the appellate function of the Secretary of Public Works and
Highways?
Section 307 of the NBC provides that “within fifteen (15) days from the date of receipt of
advice of the non-issuance, suspension or revocation of permits, the applicant/permittee may file
an appeal with the Secretary who shall render his decision within fifteen days from date of
receipt of notice of appeal. The decision of the Secretary shall be final subject only to review by
the office of the President.”
From the provision of Section 307 of the NBC, the presupposes that the Building Official
has rendered a decision that the applicant/permittee find unfavourable and hence, his desire for
the Secretary to reverse the decision of the Building Official. The NBCDO of the secretary is
tasked to conduct a review or reinvestigation of the case in order for the Secretary to render a just
and unbiased decision. The following steps should be taken in the conduct of investigation:
1.2.1 Secure certified true copies of the case including the decision of the Building
Official to determine whether he has complied with the proper procedures before
rendering his decision i.e., serving notices to the appellant(s), investigation and
hearing in order for the parties involves to present evidence(s) and argument on
all issues, etc. (see Procedures for Abatement under Rule II of the IRR). If not,
the case should be remanded to the Building Official for observance of the proper
procedures.
1.2.2 Determine whether or not the appeal was elevated within the prescribed period.
1.2.4 The Team shall be given an Official Order to conduct the inspection and each
team member should wear the proper uniform and ID to gain access to the subject
structure.
1.2.5 The Team should be provided with gears, equipment or instruments appropriate
for said investigation such as safety helmets, measuring devices, camera, type
recorder, transit if necessary and such other instruments that could be used to
cover the aspects of the questioned decision of the Building Official.
1.2.6 Each Team member must submit an individual report on his/her findings to the
best of his/her ability focusing on the safety aspects of the subject structure
whether life, limbs, health and property are endangered or not, without undue
influence of the personalities involved in the subject appeal. Photographs should
be taken to support and sustain the findings.
1.2.7 The Head of the Team shall prepare and submit to the NBCDO a consolidated
report presenting a true picture of the subject structure with recommendation(s)
on whether the conditions demand repair, vacation, or demolition depending upon
the degree of danger to life, health, and safety. (See Section 214 of the NBC and
refer also to Articles 482, 389, 694 to 707, 1654, 1723, 2190 and 2192 of the Civil
Code of the Philippines for possible actions to be taken).
1.2.8 The NBCDO shall review and evaluate the report and prepare the Decision for
approval of the Secretary thru the DPWH Legal Service.
Building failures refer to those that collapsed or are severely damaged due to causes that
can be traced: a) bad design, b) faulty construction, c) foundation failure, d) extraordinary loads
(earthquakes, winds or typhoons), e) unexpected future loads, f) combination of causes, and such
other causes like fires, termite infestation, mechanical malfunctions, and electrical overloads.
Bad design is often the result of poor concept, errors in computation, failure to take into
account imposed loads, erroneous theories or wrong assumptions, inaccurate data, ignorance of
effects of impulsive stresses, inappropriate detailing and improper use of materials. Failure to
conduct soil-boring test often leads to wrong assumptions in the design of the foundation.
Unethical practice can also be blamed for design flaws. There are the so-called walk-in
“professionals” who are, reportedly, readily available to sign and seal plans and specifications
prepared by unlicensed individuals in order for the applicant to secure a building permit.
Hopefully, the new Building Permit Form, which is duly notarized, will minimize if not
eliminate such unethical practice.
Faulty construction is usually due to substitution of inferior materials to that specified,
poor workmanship especially in reverting and welding, and other short-changing used by
unscrupulous contractor and conniving inspectors to reduce cost of construction.
Way back on December 12, 1983, then Minister Jesus S. Hipolito issued Ministry Order
No. 76 outlining the “Procedure in the Investigation of the Cause(s) of Failure of a Building or of
a Related Structure” and addressed to: All Acting Building Officials and Building Officials and
all Concerned”. The Ministry Order is reproduced as follows with some modifications to update
the agencies referred to:
All Building Official shall adopt the following procedures in the investigation of the
cause of partial or total failure of a building or a related structure, arising from earthquakes,
winds or fire:
1. Where rescue work will not be hampered, the structure shall be immediately cordoned
partially or totally, as the case may be, so as to prevent untoward destruction to life and
property due to falling debris and shall be secured with the assistance of the Philippine
National Police against looting, salvaging of materials, and other acts that could
adversely affect securing test samples of materials, until the investigation thereof has
been completed.
2. A preliminary report on the damage to life and property to the Secretary of Public Works
and Highways thru the Executive Director, National Building Code and Development
Office, copy furnished the Chief, Local Executive, shall be submitted within three (3)
days after the incident together with the following:
2.1 Copy of the approved plans, specification and structural design computations.
2.2 True copy of the Logbook including results of test of materials during
construction.
2.4 Names and postal addressed of the owner, contractors, designers (architect and
engineers particularly structural civil engineer), in-charge of construction and/or
project inspector.
3. Provide assistance to and coordination with the investigation work and securing test
samples from structural components of the structure by an investigation team composed
of technical personnel of the Bureau of Design, National Building Code and
Development Office, Bureau of Materials and Quality Control and/or private consultants
designated by the Secretary of DPWH or the Chief Local Executive.
4. The securing of test samples and subsequent testing shall, preferably, be witnessed by the
Building Official, owner, contractor, designer and structural civil engineer or their
authorized representatives.
5. At least three (3) test samples as representative for each of the structural components of
the structure, such as slabs, beams, columns. Bearing/shear, etc. shall be secures at
random; the sampling and testing thereof shall be in accordance with the requirements of
the American Society for Testing of Materials (ASTM), latest edition.
6. The test samples shall be identified and attested (carded) by the sampler, and shall be
properly handled, stored and transported to the testing laboratory.
7. The actual testing of the samples shall, preferably, be witnessed as mentioned in Section
4.0.
8. A final report of the incident shall be submitted to the DPWH Secretary thru the
Executive Director, NBCDO, copy furnished the LGU Chief Executive, within fifteen
(15) days after the investigation work had been completed, and at which time the
Demolition Order shall be issued in accordance with applicable provisions of Rule II and
Rule XI of the Implementing Rules and Regulations of the National Building Code (PD
1096).
PART V – LEGAL
Section 1.1 National Master Plumbers Association of the Philippines, Plaintiff vs.
The Philippine Society of Sanitary Engineers Inc. et. Al Defendant
ORDER
Submitted for Resolution is the application for the issuance of a temporary restraining
order filed by defendant Philippine Society of Sanitary Engineer (PSSE). The said defendant
seeks to enjoin herein plaintiff from implementing Section 101, 102, and 102.2, Chapter 1 of the
revised Plumbing Code of the Philippines which was proposed by the plaintiff and adopted by
the Board of Master Plumbers of the Professional Regulation Commission and approved by the
President of the Philippines on September 30, 1999 and took effect on 30 April 2000.
This law the validity of which is being seriously challenged by defendant PSSE and
whose implementation is being sought to the enjoined is very much different from the law which
is the subject of the instant petition. The present petition has for its subject matter Section
3.2.2.2 of the Implementing Rules and Regulations of the National Building Code of the
Philippines. The settled rule is that the jurisdiction over the subject matter is determined by the
allegation of the Complainant (Ganadin vs. Ramos, et.Al, L-23547, September 14, 1980).
Clearly, the court has no jurisdiction to try and hear the said issue. To rule otherwise will
be to widen the area of litigation between the parties and will allow both of them to question the
legality of any law that will subsequently passed affecting their respective profession/works
putting no end to the present suit.
The respondent PSSE’s argument that this Court has jurisdiction over their petition
because the passage of the Revised Plumbing Code renders ineffectual the Order of this Court
dated April 13, 1998 upholding the validity of Section 3.2.2.2 of the Implementing Rules and
Regulations of the National Building Code. Such argument is devoid of merit.
While this Court declared as valid the provision of the said Implementing Rules and
Regulations vesting only on duly licensed sanitary engineers the right to install more than 20
units of plumbing installations, limiting licensed master plumbers’ work and function to
installation of 20 or less units of plumbing installations, such Court ruling does not operate to
limit the rule-making power of the agency of the government in which the same is vested as to
preclude it from adopting rules that will provide otherwise. The Court does not legislate. Its
mandate is to interpret and apply laws (Enrile vs. Salazar, 186 SCRA 217).
The Court notes that under the previous law specifically under Republic Act No. 1378
(the Plumbing Code), the licensed master plumbers were authorized to put up more than 20 units
of plumbing installations a right reverted to them by the Revised Plumbing Code being
questioned by defendant PSSE.
Even granting arguendo that this Court has jurisdiction to resolve the said issue, the
defendant PSSE’s petition for temporary restraining order is bereft of any merit.
The injury that the members of defendant PSSE will allegedly suffer as a result of the
implementation of Section 101, 102 and 102.2 of Chapter 1 of the Revised Plumbing Code of the
Philippines cannot be considered irreparable.
Injury is considered irreparable if it such constant and frequent recurrence that no fair or
reasonable redress can be had therefore is a court if law or where there is no standard by which
their amount can be measured with reasonable accuracy, that is, not susceptible of mathematical
computation (PVTA vs. de los Angeles, G.R. No. L-27829, August 19, 1998, 164 SRA 543). It
is beyond possibility of repair or possible compensation in damages. In the present case, the
injury can very well be estimated in money terms. Engineer Linda Mendoza a witness for
defendant PSSE, even place specific figures for the alleged damages.
The confusion being complained about by said defendant revolving on which between
Sections 101, 102, and 102.2 of Chapter 1 of the Revised Plumbing Code of the Philippines shall
be applicable, is more imagined than real. And even if it were really and actually existing, the
same should be brought up in the proper forum and in a separated action.
In the same vein, its petition for a writ of injunction is likewise DENIED.
SO ORDERED.
PRISCILLA BALTAZAR-PADILLA
Presiding Judge
Chapter 2 – Legal Opinions
Republika ng Pilipinas
KAGAWARAN NG KATARUNGAN
Department of Justice
Manila
January 9, 2005
Sir:
This has reference to your request for opinion concerning the interpretation of the
pertinent provisions of the Civil Engineering Law (R.A. No. 544) and the Architects Law (R.A.
No. 545) both as amended, in order to determine the realm of practice of both professions and at
the same time, avoid the alleged conflict in the enforcement of the National Building Code (PD
No. 1096) and its Implementing Rules and Regulations (IRR).
The request, we assumed, is made in connection with promulgation and issuance of the
revised/updated IR of the National Building Code, the approval of final draft of which, you say,
has been deferred pending resolution of the claimed conflicting provisions of R.A. No. 544 and
R.A. 545 relating to the practice of structural and architectural plans and specifications needed in
securing building permits.
It appears that civil engineers relying on the provisions of Section 2 and 23 of R.A. No.
544, believe that it is their inherent right to sign and seal building structural and architectural
plans, while architects, quoting the provisions of section 14 of R.A. No. 545, complain that civil
engineers are “unlawfully practicing architecture” when they sign and seal plans and
specifications of residential buildings from single detached dwelling, multi-storey condominium
office buildings, commercial and industrial buildings and other buildings since the act of
planning, architectural and structural designing, among others, are included in the “practice of
architecture”.
It also appears that under the final draft of the revised/updated IRR, it is proposed that
only architects can sign architectural plans/documents and only civil engineers can sign
structural plans/documents; and that the Philippine Institute of Civil Engineers (PICE), however,
opposed the proposal, hence, the request.
Although, in line with settled policy and precedents, the Secretary of Justice does not
pass upon issues which, as in this case, involve the substantive rights of private parties, i.e., the
PICE and its members, upon whom the opinion of this Department has no binding effect and
which might, in all probability, take the matter to courts when they find the opinion adverse to
their interest, we would like to state some relevant observation for your enlightenment.
SEC. 2. Definition of Terms – (a) The practice of civil engineering within the
meaning and intent of this Act shall embrace services in the form of consultation, design,
preparation of plans, specifications, estimates, erections, installation and supervision of
the construction of streets, bridges, highways, railroads, airports, and hangars, port works,
canals, rivers and shores improvements, lighthouses and dry docks; building fixed
structures for irrigation, flood protection, drainage, water supply and sewerage works;
demolition of permanent structures; and tunnels. The enumeration of any work in the
section shall not be construed as excluding any other work requiring civil engineering
knowledge and application.
Upon the other hand, Section 14 and 30 of RA No. 545, as amended, in so far as material,
respectively read:
It is clear from a reading of the above-quoted provisions of the subject laws, that the
making of plans and designs, not to mentioned the supervision of construction, are activities that
are more or less common to both “architecture” and “engineering”. However, the distinction
between an architect and civil engineer is clear. Thus, in one case, it was held:
An “architect” is defined as one who, skilled in the art of architect designs buildings,
determining the disposition of both their interior and exterior spaces, together with structural
embellishment of each, and generally supervises their erection; while “civil engineer” is one
whose field is that of structures, particularly foundations, and who designs and supervises
construction of bridges, great buildings, etc., xxx.
Indeed, the language of both laws confirms this distinction. The practice of engineering
embraces services in the form of structural plans, designs, specifications, etc. and construction of
streets, bridges, highways, canals and other engineering structures specifically mentioned in
Section 2 of R.A. No. 544. The law, however, is silent on whether the practice covers the
preparation of architectural plans/designs of said engineering structures. Upon the other hand,
the practice of architecture clearly concerns with the act of planning, architectural and structural
designing of buildings as well as the architectural designs of engineering structures or any part
thereof.
Having this mind, it can, therefore, be safely said that the proposal to the preparation,
signing and sealing of architectural plans and designs to architects and the preparation of signing
and sealing of structural plans and designs to civil engineers to be in order.
(Original Signed)
MA. MERCEDITA N. GUTIERREZ
Acting Secretary
Section 3.1 Issuance of Locational Clearance and Building Permit in the Absence of
Homeowners’ Association and Barangay Clearance
REPUBLIC OF THE PHILIPPINES
CITY OF PARANAQUE
OFFICE OF THE CITY ATTORNEY
The subject provision in the Comprehensive Land Use Plan and Zoning Ordinance or
Paranaque City (City Ordinance No. 97-08), particularly Section 11.6 is merely
permissive/directory. The preliminary requirement for securing clearances from homeowners’
association and Barangay should not be understood to be mandatory in character as this
requirement is a mere formal requisite which does not in any way affect the validity of the main
official act of issuance of Locational Clearance and Building Permit by the government officials
mandated to implement the law.
UNDER Sec. 152 (c) of the Local Government Code of 1991, (R.A. 7160), the city or
municipality can issue a license or permit if the Barangay fails to act on the application within
seven (7) working days from filing thereof.
As gleaned from the letter of the said provision of law, we can very much feel free to
follow/adopt the clear legislative intention which is to uphold the hierarchy in the exercise of
government authority.
In this regard, with more reason that the city or municipality’s exercise of governmental
power prevails as against a mere association of private individuals endowed with no
governmental power like the homeowners’ association. This is specially true as when a local
government unit like the Barangay in the first place cannot prevent or hinder the exercise of
powers by the city/municipal government under the aforestated provision of the Local
Government Code by its unreasonable inaction. As long as the city government through its
public officials is acting in accordance with law in the performance of their assigned duties as
mandated law, no irregularity/illegality in exercise of that power may be attributed to them. The
declaration of said area as commercial zone thru a municipal ordinance is an exercise of police
power to promote the good order and general welfare, may interfere with personal liberty, with
property, and with business and occupations. Thus, persons may be subjected to certain
restraints and burdens in order to secure the general welfare of the state and to this fundamental
aim of government, the rights of individual may be subordinates. Patalinhug vs. Court of
Appeals, 229 SCRA 554.
Hence, the City Building Official and the City Planning Official can validly dispense
with the formal requisite of prior clearance from the Barangay and homeowners’ association
when their inaction thereof shows a clear whimsical, capricious and abusive exercise of
delegated authority. Absence of such requisite which is not an essential element in the legal
issuance of Locational clearance/building permit will not invalidate the same. To reiterate, the
subject provision in Sec. 11.6 of City Ordinance No. 97-08 only deals with sub-delegation of
authority for purposed of expediency and achievement of maximum efficiency in public service.
(Original Signed)
LEO LUIS P. MENDOZA
Section 5.1 Role of Building Officials and Other Local Government Officials in the
Demolition of Squatter Dwellings.
This Ministry has received queries as to whether squatter dwellings should or should not
be covered by the National Building Code (PD 1096) and alleging that these illegal constructions
fall under the classification of Dangerous Building pursuant to Section 3 of Rule VII of the
Implementing Rules and Regulations (IRR) of PD 1096, and therefore the Building Official can
order their demolition.
In fine, the foregoing clarification, by analogy, draws the dividing line of the area of
jurisdictional responsibility of the Building Official and other agencies charged with the
ejectment and relocation of squatters. Thus, whether the structure subject of a complaint for
demolition/condemnation pertains to a squatter, the case against him should be dismissed
outright and the matter referred to the appropriate agency enforcing the anti-squatting laws.
Under the condition set forth in LOI 691, the City Mayor or Municipal Mayor, as the case may
be, has exclusive administrative jurisdiction in the enforcement of anti-squatting laws.
All Building Officials, therefore, are enjoined to police their area of jurisdiction and to
report and monitor squatter activities to the proper authorities for their appropriate action.
For compliance.
(Original Signed)
JESUS S. HIPOLITO
Minister
TANGGAPAN NG PANGULO
PANGKAT NG PAMAMAHALANG PAMPANGULO
(PRESIDENTIAL MANAGEMENT STAFF)
PMS BLDG., MALACANANG ANNEX
ARLEGUE ST., METRO MANILA
MEMORANDUM
This is in connection with the implementation of Batas Pambansa 344, an Act to enhance the
mobility of disabled person, by requiring certain buildings, institutions, establishments, and
public utilities, to install facilities and other devices.
Pursuant to this law, you are hereby instructed to impose the implementation of Batas Pambansa
344, using the rules and regulations, implementing the law to enhance the mobility of disabled
persons, as jointly promulgated by the then Ministry of Public Works and Highways, Ministry of
Transportation and Communication, in coordination with the National Commission concerning
Disabled Persons. Refer to your copies of the National Building Code of the Philippines and its
Implementing Rules and Regulations, with the Law to Enhance the Mobility of Disabled
Persons, pages 353 to 402.