Method Statement For Earth Works
Method Statement For Earth Works
Table of Contents
1. SCOPE
2. REFERENCE
3. DEFINITION
4. RESPONSIBLITIES
5. EXECUTION ORGANIZATION
6. WORK PROCEDURE
7. QUALITY REQUIREMENT
9. SUBMITTAL
(Client Logo) Project Name (Company Logo)
1. (PROJECT SCOPE)
2. REFERENCE
The selection of material and equipment, and the construction, maintenance shall
be referenced and comply with the latest edition of the codes and standards
listed below, unless otherwise noted.
2.1
3. DEFINITION
3.5. Contractor
(Contractor Name), the party responsible for performing excavation and backfill
work.
3.6. Dune Sand
3.7. Marl
Marl is a wide variety of calcareous soil materials found in Saudi Arabia which may
vary from clay to gravel sizes and often include cobble and boulder sized pieces.
3.8. Rocks
Rocks have various hardness and engineering properties. "Rock" may refer to
anything from boulder‐size individual pieces to hard, intact bedrock. See
section
7.5 for classification of rock by excavation method.
(Client Logo) Project Name (Company Logo)
3.9. SABKHA
4. RESPONSIBLITIES
Establish, maintain, and implement the approved Project Quality Plan and Overall
responsible in quality for all construction activities including materials
receiving as to the applicable codes and standards and control the quality
control personnel’s inspection activities to ensure compliance with the quality
requirement.
Implement the Project Quality Plan to the project and direct responsible in quality and
establish the ITP, manage the inspection of the work, and review the activity of the Quality Control
Inspector. All field quality control document and inspection records as to the requirement of Quality
shall be prepared, maintained, and submit to QCM
procedures and deliver the technical advice to the construction team to keeping
the quality requirement. All the inspection activity shall record as per the
designated checklist submit to QCS and raise the RFI as upon satisfaction of the
inspection result guided by QCS/QCM
Ensure all work permits are available prior to commencement of any work
as per (CLIENT) Work Permit System. Check personnel’s compliance
with safety requirements, such as wearing Personnel Protection
Equipment (PPE). Check work areas for any unsafe conditions. Liaise
with Field Supervisors and Foremen that work is carried out in
accordance with Project Safety Plan / Procedure.
5. EXECUTION ORGANIZATION
The capacity of the below mentioned equipment and manpower shall be mobilized
in accordance with site conditions and requirements. Below listed equipment
will be the principal.
5.1.1. H/Equipment Plan (Each Zone)
Description Capacity
Dump Truck
Motor Grader
Wheel Loader
Vibratory Roller
Water Truck
(Client Logo) Project Name (Company Logo)
6. WORK PROCEDURE
a) Earthworks: ±2.5cm
b) Formation Level: ±2.5cm
c) Subgrade Material: ±2.5cm
(Client Logo) Project Name (Company Logo)
Excavations and trenches where there are no surcharge loadings (from vehicles or spoil
etc.) or adjacent buildings.
Depth of up to 1 meter:
Proprietary trench box (which the manufacturers guidance book will form the
design
Designed trench supports (with calculations and a drawing showing how this will
support the excavation or trench and the position of the props)
Edges of the excavation angled and battered to the correct angle for the depth of
the excavation (the record of design can be a sketch by a competent person with
the angle ratio detailed)
(Client Logo) Project Name (Company Logo)
Stepped and benched, this is the least preferred option and is not permitted in clay
soil areas (the height of each step must be documented in the daily task brief).
6.2 Embankment
(a) Embankment
(b) Fill material shall be placed in lifts not exceeding 600 mm in loose
depth. Fill materials shall be placed in lifts not exceeding 100 mm in
loose depth for hand‐ operated compaction. Other lift thicknesses may
be approved by the (Client) based on the proposal of ‘Field Trial’ using
the intended compaction equipment.
(c) For foundation for asphalt and concrete pavement subgrades, fill shall
be compacted to 95% relative density for cohesion‐less soils or 95%
of the maximum density as determined by ASTM D1557 for cohesive
materials.
(d) The moisture content of the material being compacted shall be within
± 2% of the optimum moisture content for subgrades and backfill materials. as
determined by ASTM D1557. However, for cohesion‐less free draining soils
when ASTM D4253/ASTM D4254 is the appropriate test procedures, there is no
applicable optimum moisture content
(Client Logo) Project Name (Company Logo)
6.3 Excavation
7. QUALITYREQUIREMENT
The quality control of the Work shall be implemented as per the approved Project
Quality Control Plan and the quality control personnel shall be assigned satisfy
to the Industry/(Client) standard.
The QC Inspectors of (Contractor and Client) Representative shall carry out the
necessary tests and inspections in various stages of the earthworks. Inspection
shallbe based on approved ITP or as stated on the latest IFC drawing. Daily
Inspections must be carried out and recorded.
- Other lift
thicknesses may
be approved by
the appropriate
(CLIENT)
Inspection Representative
based on a
Field test section using
the
intended compaction
equipment
(a) All access routes in and around the site should be properly
constructed and carefully planned with route identifiers and traffic
control measures such as speed limit, speed humps, flagman and
safety signage to guide drivers.
(b) All personnel shall receive and wear appropriate clothing and
Personal Protective Equipment to protect them at site.
(c) All personnel shall receive Induction, Job Specific Training,
Competencyand Refresher trainings before he is deployed at site to
do work.
(d) All personnel shall be properly and regularly briefed on all emergency
procedures, with particular emphasis placed on those procedures
applicable to their area of work.
(e) All working platforms, especially those used in work at heights of more than
1.8 meters (6ft.) shall be regularly inspected and scaffolding with
scaffolding tags.
(f) The sides of excavations more than 1.2 m (4ft.) shall have a valid
excavation and confined space entry permit with protective measures
such as but not limited to shoring, timbering and benching whichever
maybe applicable.
(g) All areas involving hazardous work shall be isolated by barricade and
adequate signage to warn workers of the presence of hazard/s. (h) All
operatives using plant, tools
(h) and equipment shall be properly trained and certified by 3rd party
certification body to ensure working safely.
(i) Access to areas of hazardous work will be strictly controlled by means of
(Client Logo) Project Name (Company Logo)
TRAFFIC LAYOUT
(Client Logo) Project Name (Company Logo)
8.1.3 Maintenance
Planned preventative maintenance will be undertaken on all plant and equipment
as per the (Contractor) Maintenance Schedule. Any defective plant and equipment
identified during the operators pre use inspection shall be isolated in the plant
quarantine area and repaired or removed from site.
8.1.4 Public Safety
- Worker’s transportation
2. Security Plan
‐ Transporting of Construction
Material/Machines/Equipment‐ outside
The main means of providing security to personnel and materials during the
construction works is by way of, but not limited, the following methods:
1. Providing fence around the site office, storage, and fabrication, with
each area having a controlled access by means of gates (barriers) and
security guards.
2. Provide suitable lockable site office accommodation for site
staff withinappropriate manned reception area.
3. Provide suitable storage areas and lockable stores with the
implementation of an adequate storekeeping system.
4. Materials not placed in stores will be placed on suitable hard
standings and properly stacked.
5. Firefighting equipment will be placed in the vicinity of storage areas.
6. All areas at site will be properly and adequately illuminated
to preventany security related incidents concerning personnel
at site.
(Client Logo) Project Name (Company Logo)
Access to and around the site will be controlled by way of, but not limited to, the
following methods:
5. All personnel at site are expected to cooperate when being asked by the
Security personnel for security issues that are to be addressed at site.
6. Vehicles entering the site area must have a (CONTRACTOR) sticker for
easy Identification. All vehicles without a sticker will be discarded of entry
andwill stay outside the jobsite.
- The Safety Manager shall report directly to the Site Manager and shall
be responsible for all on‐site safety matters including the
implementation of all safety regulations and procedures by ensuring
that all activities are undertaken in accordance with approved safety
procedures.
- Advice the Site Manager on the measures to be taken in the interests of
safety and health of all persons engaged upon the site.
- Before starting field activities, instruct all site personnel and
subcontractors to follow and comply with approved safety Procedures,
Rules and Regulations.
- Perform a continuous (CONTRACTOR) check to ensure that activities
organized by field supervisors are performed by their workers, or
subcontracts’ workers, in accordance with Safety Procedures, Rules
and Regulations.
- Review with supervisors the detail of major works (lifting of major
equipment, work in hazardous areas) to make sure that all precautions
are taken into consideration to maintain safety.
- Monitor all infringements of Safety Procedures, Rules and Regulations and
inform the supervisor to rectify the unsafe acts.
- Investigate advice on and keep records of all accidents and injuries and
up‐date statistical data.
(Client Logo) Project Name (Company Logo)
The safety supervisors shall report direct to the Safety Manager and be
responsible for, but not limited to, the following:
- Make sure that all site operatives are acquainted with and obey
all safetyinstructions.
- Ensure that careless or reckless practices or actions that are likely to
result in accidents or injuries are prevented.
- No site workers, unless duly authorized, should interfere with, remove
alter or displace any safety device or other appliance furnished for his
protection or theprotection of others, or interfere with any method or
process adopted with view to avoiding accidents and injuries.
- All personnel in sections/departments concerned with construction
work should cooperate in taking preventive action that will ensure the
safety of site workers.
- Ensure that workmen are acquainted with the Emergency
Procedures andconduct regular practices.
- Inspect all fire protection equipment and their readiness of operation.
- Administer any “permit to work “schemes.
- Supervise site security.
- Supervise the inspection and maintenance of all temporary
installations,access ways, escape routes and the like.
The Security Officer shall report directly to the Safety Supervisor and shall be
responsible for all matters of site security consisting of, but not limited to, the following
Shall liaise and co‐operate with the safety supervisors on all matters relating
to safety particularly in respect of, but not limited to, the following:
(h) All individuals (general staff and workers) are responsible for the
following:
The main cause of excessive noise levels can be identified as emanating from construction
vehicles, equipment, and construction activities.
The following are some of, but not limited to, the methods by which noise levels
caneffectively be reduced.
(a) All plant and equipment with petrol or diesel engines shall be equipped
with such omission control devices that comply with the local legal
requirementson omission control.
(b) All unwanted waste material and rubbish arising from site operations
shall be collected in bulk bins and regularly be disposed of at approved
dumpsites.
(c) All site effluent and wastewater arising from site operations shall be
disposed of by means of a temporary site drainage system installed
with the necessary grease, silt traps and sedimentation tanks in
accordance with local authority requirements before final discharge.
(d) Where practicable, site haul roads will be hard surfaced to eliminate
dust generation, failing which they will be sprayed with water to
reduce dust.
(e) A paved wash bay shall be provided for washing vehicles before they
leave the site.
Silt traps will be provided before final discharge into suitable outlets.
(f) Protect site stockpiles from wind action by means of covers and water
dampening.
(g) Pay special attention to minimize cement dust at bulk storage sites,
batching plant, weigh hoppers and conveyor belts.
The following are some of, but not limited to, the methods by which inconvenience
to the public from construction activities can be minimized.
(a) The site or working areas are to be cordoned off, with adequate
hoarding toprevent unauthorized entry and to reduce noise levels.
(b) Adequate steps are to be taken to reduce excessive noise and
vibration levelssuch as by working to restricted hours or by noise
suppression devices.
(c) All footpaths and road diversions are to be properly
constructed, wellsign posted and illuminated.
(d) Adopt procedures to prevent mosquito breeding and the attraction
of vermin and flies.
One of the main causes of inconvenience to the public emanating from construction
vehicles, equipment and activities can be identified as the disruption of
pedestrian and vehicular traffic.
The following are some of, but not limited to, the methods by which the
inconvenience to the public from traffic disruption can be minimized.
(a) All footpaths and roadways adjacent to the site are to be always
kept in a clean and tidy state.
(b) All temporary roads and footpaths are to be adequately and
properly constructed.
(c) Flagmen must be at the entire working equipment’s
operation from sideward and backward moving vehicles.
Flagmen shall be at 7 to 15 metersaway from the moving
equipment’s. Flagmen / Banks men will be used to control
movement of equipment at intersection, near to traffic road
of busy work area to avoid collision. Our aim however is to
keep all boots of the ground where applicable and possible
to eliminate the possibility of man and machine accidents
from happening.
(Client Logo) Project Name (Company Logo)
(d) Trucks shall be covered with sheeting’s at the roof deck top to
prevent from the spoiled materials loaded blown by the wind
while vehicles are inmotioned.
(e) All road and footpath diversions are to be planned well in
advance withadequate notices being given to the public of such
diversions.
(f) All road and footpath diversions are to be clearly illuminated,
sign postedand marked out.
(g) All temporary traffic control devices such as traffic signs, blinking
lights, barriers, lane markings and the like are to be regularly
maintained (or replaced) to ensure safe and smooth pedestrian and
traffic flow.
(h) All temporary pedestrian and road installations are to be
installed,maintained, and operated (where necessary) by
suitably trained personnel.
(i) Vehicle and Pedestrian will have separate ways and safety
signage willbe posted to kept them abreast of safety
instructions at site.
9. SUBMITTALS
Reports including all laboratory and field test logs and comments. Field test reports
shall include density and moisture content test logs indicating location by
coordinates and elevation. Reports shall be submitted on the following:
- Bi‐weekly.
- At earthwork completion: A complete record of all test
logs and comments for permanent project records.
End of Document