Week 3: Assignment 3: Assignment Submitted On 2023-02-15, 17:11 IST

The document appears to be a summary of an assignment completed for an NPTEL online course on digital protection of power systems. It provides the questions asked in the assignment, the student's answers, and whether each answer was correct or incorrect. There were 10 multiple choice questions covering topics like the operation of Buchholz relays, compensation methods in digital transformer differential protection, and calculations of operating and restraining currents for a transformer.

Uploaded by

Suraj Naik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
126 views3 pages

Week 3: Assignment 3: Assignment Submitted On 2023-02-15, 17:11 IST

The document appears to be a summary of an assignment completed for an NPTEL online course on digital protection of power systems. It provides the questions asked in the assignment, the student's answers, and whether each answer was correct or incorrect. There were 10 multiple choice questions covering topics like the operation of Buchholz relays, compensation methods in digital transformer differential protection, and calculations of operating and restraining currents for a transformer.

Uploaded by

Suraj Naik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

X

[email protected]

(https://swayam.gov.in)

(https://swayam.gov.in/nc_details/NPTEL)

NPTEL (https://swayam.gov.in/explorer?ncCode=NPTEL) » Digital Protection of Power System (course)

Course outline
Week 3: Assignment 3
How does an NPTEL The due date for submitting this assignment has passed.
online course work? () Due on 2023-02-15, 23:59 IST.

Week 0 ()
Assignment submitted on 2023-02-15, 17:11 IST
Week 1 () 1) The Gas actuated relays (Buchholz relay) can be used to detect which type of faults inside the transformer? 1 point

Week 2 () internal fault


turn-to-turn fault
Week 3 () failure of the Transformer cooling system

Digital Protection of external fault


Transformer-I (unit? No, the answer is incorrect.
unit=31&lesson=32) Score: 0
Accepted Answers:
Digital Protection of
turn-to-turn fault
Transformer-II (unit?
unit=31&lesson=33)
2) How many types of compensation are done as pre-processing in digital transformer differential protection? 1 point
Digital Protection of
Transformer-III (unit? 1
unit=31&lesson=34)
2
Digital Protection of 3
Transformer-IV (unit?
None of the above
unit=31&lesson=35)
No, the answer is incorrect.
Digital Protection of Score: 0
Transformer-V (unit? Accepted Answers:
unit=31&lesson=36) 3
Quiz: Week 3:
Assignment 3 3) The differential relay generates a tripping signal if  1 point
(assessment?name=90)
Operating current (IOP) > k × Restraining current (IRT)
Solution of Week 3 (unit?
Operating current (IOP) < k × Restraining current (IRT)
unit=31&lesson=108)
Restraining current (IRT)  > k × Operating current (IOP)
Week 4 () Restraining current (IRT)  < k × Operating current (IOP)

Yes, the answer is correct.


Week 5 () Score: 1
Accepted Answers:
Week 6 () Operating current (IOP) > k × Restraining current (IRT)

Week 7 () 4) In digital transformer differential protection, the second slope of the differential characteristics will take care of the issues related to  1 point

Week 8 () tap changer


external Fault
FEEDBACK FORM ()
external fault with CT saturation
tap changer and Non-identical CTs
DOWNLOAD VIDEOS ()
No, the answer is incorrect.
  Score: 0
Accepted Answers:
external fault with CT saturation

5) For a transformer having configuration is Dyn11, which of the following statement is correct. 1 point
HV winding is Delta and LV winding is Star, HV leads LV by 30 degree
HV winding is Star and LV winding is Delta, HV leads LV by 30 degree
HV winding is Delta and LV winding is Star, LV leads HV by 30 degree 
HV winding is Star and LV winding is Delta, LV leads HV by 30 degree

Yes, the answer is correct.


Score: 1
Accepted Answers:
HV winding is Delta and LV winding is Star, LV leads HV by 30 degree 

6) For a transformer having configuration is YNd11, which of the following statement is correct. 1 point

HV winding is Delta and LV winding is Star, HV lags LV by 30 degree


HV winding is Star and LV winding is Delta, LV lags HV by 30 degree
HV winding is Delta and LV winding is Star, LV lags HV by 30 degree 
HV winding is Star and LV winding is Delta, HV lags LV by 30 degree
Yes, the answer is correct.
Score: 1
Accepted Answers:
HV winding is Star and LV winding is Delta, HV lags LV by 30 degree

7) In transformer protection, the most common cross-blocking method used to restrain during magnetizing inrush current is  1 point

1-out-of-3
2-out-of-3
Per-phase-method
Averaging

Yes, the answer is correct.


Score: 1
Accepted Answers:
1-out-of-3

8) Transformer configuration in the digital relay should be added as per  1 point

IEC 61850-9
IEC 60073-1
IEC 60076-1
IEC 60075-1

No, the answer is incorrect.


Score: 0
Accepted Answers:
IEC 60076-1

9) Calculate the primary (TAP1) and secondary side (TAP2) TAP scaling factor considering below mentioned data: 1 point
5 MVA, 66/11 kV, YNd11 transformer having high voltage side CT ratio as 50/1 and low voltage side CT ratio as 100/5.

TAP1 = 13.121 and TAP2 = 0.874


TAP1 = 0.874 and TAP2 = 2.624
TAP1 = 2.624and TAP2 = 0.874
TAP1 = 0.874 and TAP2 = 13.121

No, the answer is incorrect.


Score: 0
Accepted Answers:
TAP1 = 0.874 and TAP2 = 13.121

10) Using the below mentioned transformer data, calculate the operating (Iop) and restraining (Irst) current when the transformer is 1 point
operating at the Higher Tap i.e. at +2.5%.
Transformer data:
1500 MVA, 765/400 kV, YNa0d11 transformer having high voltage side CT ratio as 2000/1 and low voltage side CT ratio as 3000/1. TAP-HV =
0.5660 and TAP-LV = 0.7216. Tapping Range (Max ratio to Min ratio in %) = +5.50% to -5.50% in 11 steps.

Iop = 0.052 p.u. and Irst = 0.9739 p.u.


Iop = 0.9878 p.u. and Irst = 0.024 p.u.
Iop = 0.024 p.u. and Irst = 0.9878 p.u.
Iop = 0.058 p.u. and Irst = 1.029 p.u.

No, the answer is incorrect.


Score: 0
Accepted Answers:
Iop = 0.024 p.u. and Irst = 0.9878 p.u.