Stream Restoration Guide
Stream Restoration Guide
*554360*
SDMS Doc ID 554360
INC STATE UNIVERSITY I
North Carolina State University and North Carolina A&T State University commit themselves to positive
action to secure equal opportunity regardless of race, color, creed, national origin, religion, sex, age or
disability. In addition, the two Universities welcome all persons without regard to sexual orientation.
Contents
Design Procedures 7
Structures 8
Riparian-Buffer Re-establishment 9
Flood Studies 11
Appendices
Preface
Streams and rivers serve many purposes, including water supply, The authors would like to thank the following people for reviewing
wildlife habitat, energy generation, transportation and recreation. the document:
A stream is a dynamic, complex system that includes not only Micky Clemmons
the active channel but also the floodplain and the vegetation Rockie English, Ph.D.
along its edges. A natural stream system remains stable while Chris Estes
transporting a wide range of flows and sediment produced in its Angela Jessup, P.E.
supply significantly affect this equilibrium, the stream may Todd St. John
Stream restoration is the re-establishment of the general structure, EPA 319 Grant Program
function and self-sustaining behavior of the stream system that N.C Department of Transportation
existed prior to disturbance. It is a holistic process that requires
an understanding of all physical and biological components of
the stream system and its watershed. Restoration includes a
broad range of measures, including the removal of the watershed
disturbances that are causing stream instability; installation of
structures and planting of vegetation to protect streambanks and
provide habitat; and the reshaping or replacement of unstable North Carolina
stream reaches into appropriately designed functional streams
and associated floodplains.
This document promotes a natural channel design approach
to stream restoration. It is intended primarily as a reference for
natural resource professionals who plan, design, review and
implement stream-restoration projects. This document is not a
substitute for training and experience. Users should take advantage
of training opportunities and work closely with experienced
stream-restoration professionals to learn more about natural
channel-design principles. Users must recognize that all stream-
restoration projects are different and require applications of specif
ic techniques to meet project objectives. This document provides
a general framework and some design aids to help planners and
designers address complex stream-restoration projects.
The techniques and methodologies described in this document
are evolving rapidly. New design aids are being developed that
will improve design efficiency and confidence. We encourage
stream-restoration professionals to carefully document their
experiences—including project successes and failures—so that
the restoration community can better understand the appropriate
techniques for various conditions.
its longitudinal zone and the relative size and depth of its channel.
sustain stream flow through
The uppermost channels in a drainage network (i.e., headwater
out the year, perennial
Though streams
1.1. Bankfull Discharge and Stage
and rivers vary in size,
The most important stream process in defining
shape, slope and bed
channel form is the bankfull discharge, which is essentially
composition, all streams
the same as the effective—or dominant—discharge.
share common characteris Bankfull discharge is the flow that transports the
tics. Streams have left and
majority of a stream's sediment load over time and
right banks and beds consisting
thereby forms and maintains the channel. Any flow
of mixtures of bedrock, boulders,
that exceeds the stage of the bankfull flow will move
cobble, gravel, sand or silt/clay.
onto the floodplain; therefore bankfull stage is consid
Other physical characteristics shared
ered the incipient point of flooding. This may or may
by some stream types include pools,
not be the top of the streambank. If the stream has
riffles, steps, point bars, meanders,
become incised due to changes in the watershed or
floodplains and terraces. All of these streamside vegetation, the bankfull stage may be a
characteristics are related to the interactions among climate, small bench or scour line on the streambank. In this
geology, topography, vegetation and land use in the watershed. case the top of the bank, which was formerly the
The study of these interactions and the resulting streams and floodplain, is called a terrace. A stream that has
rivers is called fluvial geomorphology. terraces close to the top of the banks is considered
Streams are classified—or ordered—according to the hierarchy an incised—or entrenched—stream (Figure 1.3). If the
of natural channels within a watershed. The order of a stream stream is not entrenched, then bankfull is near the
can provide clues about other stream characteristics, including top of the bank (Figure 1.4). For examples of bankfull indicators,
refer to River Course Fact Sheet Number 3 (Appendix A). On aver-
6 Chapter 1 Stream Restoration Stream Restoration Chapter 1 7
age, bankfull discharge occurs every 1.5 years. In
other words, each year there is about a 67 percent
chance of a bankfull discharge event. The Rosgen
stream-classification system (Rosgen, 1996) uses
bankfull stage as the basis for measuring the width-
to-depth and entrenchment ratios. Therefore, it is
critical to correctly identify bankfull stage when
classifying streams and designing stream-restoration
measures. The Rosgen stream classification is
discussed in detail in Chapter 3 and in River Course
Fact Sheet Number 2 (Appendix A).
1.8 Conclusions
A stream and its floodplain comprise a dynamic environment
where the floodplain, channel and bedform evolve through natu
ral processes that erode, transport, sort and deposit alluvial
materials. The result is a dynamic equilibrium in which the stream
maintains its dimension, pattern and profile over time, neither
degrading nor aggrading. Land-use changes in the watershed,
channelization, culverts, removal of streambank vegetation,
impoundments and other activities can upset this balance. As a
result, large adjustments in channel form, such as extreme bank
erosion and/or incision, will happen. A new equilibrium may
eventually result, but not before the associated aquatic and ter
restrial environment are severely damaged. Understanding natu
ral stream processes and applying this knowledge to stream-
restoration projects will help create a self-sustaining stream with
maximum physical and biological potential.
Office Procedures
the benchmark and as much of The composition of the streambed and banks is an important
the site as possible are visible. facet of stream character. It influences channel form and
This is a difficult task in North hydraulics, erosion rates, sediment supply and other parameters.
Carolina because of the dense Each permanent reference site should include a basic characteri
vegetation. A lot of turning zation of bed and bank material. For more information on
points may be necessary. The substrate sampling, see Bunte and Abt, 2001 (Section 13.3).
best survey locations often are You may download this report, RMRS-GTR-74, from the U.S. Forest Service’s Rocky
in the channel, which usually Mountain Research Station Web site, http://www.fs.fed.us/rm/main/pubs/
means the survey instrument electronic/rmrs_gtr.html. Studies of fish habitat, riparian ecosystems or
may be below the top of the stream hydraulics may require more detailed characterization of
streambank. In this case, use a substrates and bank materials than is provided in this manual.
hand level and survey rod to See papers by Dorava (2001), Gore (1988), Merritt (1984), Frothingham (2001),
measure the distance between Montgomery (2001) and Statzner (1988) referenced in Section 13.3.
the survey instrument and the The composition of the streambed (substrate) influences how
top of the bank. This distance streams behave. Steep mountain streams with beds of boulders
is referred to as a negative and cobbles act differently than low-gradient streams with beds
foresight. When possible, set of sand or silt. This difference may be documented by a quantitative
the instrument atop the bank description of the bed material called a pebble count. Figure 2.8
or terrace and clear any limbs There are three methods of pebble counts, each with different Field measurement of
and leaves from the line of purposes. The first and most efficient method, a reachwide radius of curvature
sight. Stretch a tape along the pebble count (developed by Wolman, 1954, and modified by
thalweg, starting at the Rosgen, 1996), samples a
upstream riffle. Make sure that total of 100 pebbles from
the thalweg distance surveyed cross sections throughout
is at least 20 times the bankfull the longitudinal reach of
Fig. 2.6 width or encompasses a minimum of two full meander wave the stream. This count is
lengths. If flags are not still in place from the bankfull identifi used for stream classifica
Sinuosity measurement
Rosgen, 1998b, 211 cation, replace them for verification during the survey. tion. The second method
Step 4: Record the longitudinal station from the tape, then use samples 100 pebbles at a
the level to read a foresight for the thalweg, water surface, single cross section. This
inner berm (if present), bankfull and top of the low bank. is for cross-section analysis.
Collect this data at the head of every feature (riffle, run, pool The third method also
and glide) and the maximum pool-depth location. Note the samples 100 pebbles at a
channel feature associated with the longitudinal station, i.e., riffle, but includes only the
riffle, run, pool or glide. See Harrelson, 1994 (available for download at pebbles from the wetted
www.stream.fs.fed.us/PDFs/RM245.PFD) for longitudinal-survey methods perimeter (anywhere the
and examples of how to set up field-survey notes. Sample field water is in contact with
data sheets are in Appendix B. Be sure to collect information the channel bed) at normal
for each bed feature. For a long feature such as a riffle or run, flow. This count is used
take a measurement at least every bankfull width. to calculate entrainment
Step 5: Once the longitudinal survey is finished, close the and velocity.
survey back to the benchmark. The longitudinal profile data
will allow calculation of the length and slopes for all the stream ● Reachwide characterization of the substrate (Wolman Pebble
features. Count)
Step 1. This technique requires two people—an observer with a
metric ruler to wade the stream and a note-taker to wade or
remain on the bank with a notebook. For stream characteriza
tion, sample pools and riffles in the same proportion as they
Figure 2.7 occur in the study reach. Once the longitudinal profile is complete,
Radius of curvature compute the percentage of the total length of the profile that is
Rosgen, 1998b, 186 riffle/run and the percentage that is pool/glide. For example,
the reach may be 60 percent riffle/run and 40 percent pool/
glide. Use these percentages to determine the number of
18 Chapter 2 Stream Restoration Stream Restoration Chapter 2 19
samples to take from these features. If six riffles exist in the measurements is taken. The note-taker should keep count.
longitudinal profile, sample 10 pebbles (left bankfull to right Continue traversing the stream until all areas between the
bankfull) at each riffle. This will give a total of 60 pebbles in left and right edges of water are representatively sampled.
● Subpavement Sample
Step 1. Collect the subpavement sample beneath the pavement
sample. The bucket should continue to define the boundaries
of the sampling area. Excavate and remove the material below
the pavement sample to a depth equal to twice the intermediate
axis of the largest particle that was collected from the pavement
sample. If an armored layer is reached, do not continue to
excavate below this layer, even if a depth equal to twice the
median diameter of the largest particle in the pavement layer
has not been reached. Place all subpavement sample material
in a separate bucket or bag for weighing and sieving. The sub-
pavement sample is the equivalent of the bar sample; therefore,
the largest particle from the subpavement sample is used in
lieu of the largest particle from the bar sample for entrainment
calculations (see Section 7.2). Note: If larger particles are collected
from the subpavement than from the pavement layer, discard
the sample and select a new sampling location.
Step 2. Wet-seive both the pavement and subpavement samples
separately using a standard sieve set with a 2-millimeter
screen size for the bottom sieve. (The standard sieve set
should include the following sizes in millimeters: 2, 4, 8, 16, 32,
64, 128 and 256.) Place a bucket below the 2-millimeter sieve
to catch the smaller material. (Materials in the 256-512 millime
ter range should be measured and weighed individually rather
than sieved.) Weigh and record each sieve fraction (less the
tare weight). Weigh the bucket with fine materials after draining
off as much water as possible. Subtract the tare weight of the
bucket to obtain the net weight of the sand and fine material.
Include the intermediate axis widths and weights of the two
largest particles collected from the pavement and the largest
collected from the subpavement.
Step 3. Determine size-class distribution for the materials by
plotting the cumulative frequency of each fraction. From the
cumulative frequency plot, determine size-class indices, i.e.,
d16, d35, d50, d84, d95, for both the pavement and subpavement
samples. The d100 should represent the actual intermediate axis
24 Chapter 2 Stream Restoration Stream Restoration Chapter 2 25
width of the largest particle when plotted. The intermediate Hydraulic Radius is determined using equation 2:
axis measurement of the largest particle will be the top end of A
the catch range for the last sieve that retains material. Note: d100=di. R= WP Equation (2)
Scour chains installed in the bed of the stream can measure WP = Wetted Perimeter of the channel bottom at bankfull
the depth of scour or bed deposition. Bulk substrate samples stage (ft)
collected in conjunction with scour-chain monitoring can help A = Cross-Sectional Area of the riffle at bankfull stage (sq. ft.)
through the stream substrate. Include the location of the chain in using the cross-section survey data. Wetted Perimeter, WP, can
the cross-section survey data so it can be found later. Place the also be approximated using equation 3. Equation 3 assumes a
top of the chain level with the existing streambed surface. When rectangular channel shape.
tion at the depth to which the bed material was scoured and D = Average Bankfull Depth of the riffle cross-section (ft)
newly deposited during the flow. To measure the depth of scour W = Bankfull Width at the riffle (ft)
(length of chain from the top to the point where the chain was
folded over), dig through the newly deposited material to the Manning’s Roughness Coefficient can be estimated by using
chain. If deposition (or aggradation), rather than scour, has Chow’s coefficients for various channel substrate and vegeta
occurred, the chain will remain in a vertical position, concealed tion characteristics (1959). Velocity, v, can then be determined
by the deposited sediment load. To obtain a scour-chain sub using the Continuity Equation (Equation 4):
strate sample: Q
Step 1: Place a 5-gallon bottomless bucket over the location of V= A Equation (4)
the chain prior to excavating. The bucket will define the sub
strate sampling area. Where:
Step 2: Collect a pavement and subpavement sample over the V = Bankfull Velocity (fps)
chain. For the subpavement sample, continue to excavate Q = Bankfull Discharge (cfs)
down to the chain (rather than to the depth equal to twice the A = Bankfull Cross-Sectional Area at the riffle cross-section
intermediate axis of the largest particle found on the pave (sq. ft.)
ment).
2.10 Assessing Riparian Condition
2.9. Estimating Bankfull Discharge and Velocity Compose a general description of the topography or promi
Discharge is the volume of water flowing through a stream nent topographic features in the floodplain, as well as soil texture
channel cross section per unit time. If the stream has a USGS and type. Important features may include ditches, old crop rows,
gage, use the stage-discharge rating table to determine the sloughs and pools, wetlands, knolls or steep banks. Note the
discharge for the specific elevation of the field-determined bank- length and width of the valley. If the project is in an urban setting,
full stage (see Chapter 4 for more information on gage-station note obvious constraints, such as location of utilities, structures
analyses). However, most stream reaches are not gaged, so it and roads.
probably will be necessary to estimate the bankfull discharge Examine and describe soils throughout the floodplain. County
and velocity using other methods. Bankfull discharge, Qbkf, can soil-survey classifications are useful in preparing descriptions.
be estimated using Equation 1, which is Manning’s equation (Chow, During this initial assessment, appropriate labs, including the
1959). N.C. Department of Agriculture (NCDA) Agronomic Division’s
2/3 1/2
soil-testing lab, can perform soil-fertility tests. This information
Q = ( 1.49AR S ) Equation (1) will help determine the nutrient needs of vegetation planted at
n
the project site. An example of a soil-sample form is found in
Where:
Appendix H.
Q = Discharge (cfs)
Next, take a plant inventory. Note the type, size and relative
R = Hydraulic Radius of the riffle cross-section at bankfull
abundance of each species in the project area. Also note and
stage (ft)
flag potential vegetation for transplanting. Utilizing on-site vege
s = Average Channel Slope (ft/ft)
tation that might otherwise be destroyed by construction is an
n = Manning’s Roughness Coefficient
excellent way to save money and to maintain locally adapted
26 Chapter 2 Stream Restoration Stream Restoration Chapter 2 27
plant ecotypes. Note invasive and exotic plants that occur within
the project area. Throughout much of North Carolina, stream-
banks and floodplains are infested with invasive and exotic
plants that include kudzu (Pueraria lobata), English ivy (Hedera
helix), Chinese privet (Ligustrum sinense) and multiflora rose
(Rosa multiflora). This vegetation can outcompete native riparian
plants, leading to a decrease in wildlife habitat and food diversity
along the streambanks. Also, non-native vegetation often is less
nutritious for native fauna. If invasive exotic plants inhabit the
project area, take measures to control them before restoring
native vegetation.
3.1 LEVEL I
Level I is a broad-level description of Rosgen’s major stream
types (Figure 3.2). This description is based on general map and
visual assessment of valley types; landforms; and the stream’s
shape, slope and channel patterns. Valley morphology has a
profound influence on stream type (See Rosgen 1996, Chapter 4).
3.2 LEVEL II
Step 1. Determine single or braided channel. A braided channel
consists of three or more distinct channels. Anything less is
considered a single channel. The only stream types for braided
channels are "D" and "DA." Single or braided channel determi
nation can be made from aerial photograph or field observation.
Table 3.1 Substrate Material Classification For more information, see Rosgen, 2001b (Section 13.1), available for download at
www.wildlandhydrology.com.
Removal of vegetation
Constructed Trapezoidal cross sec
II (Channelized) tion; linear bank sur
faces; flow line lower
relative to top bank
Degradation Degradation; basal erosion on Pop-out Heightening and steep Riparian vegetation
III banks failures ening of banks; alter high relative to flow
nate bars eroded; flow line and may lean
line lower relative to toward channel
top bank
Threshold Degradation; basal erosion on Slab, Large scallops and Riparian vegetation
IV (Degradation banks rotational bank retreat; vertical high relative to flow IV
and Widening) and pop-out face and upper-bank line and may lean
failures surfaces; failure blocks toward channel
on upper bank; some
reduction in bank
angles; flow line very
low relative to top bank
V
Aggradation
and Widening
Aggradation; development of
meandering thalweg; initial
Slab, rotational
and pop-out
Large scallops and
bank retreat; vertical
Tilted and fallen ripari
an vegetation; re
III
deposition of alternate bars; failures; low- face, upper bank and establishing vegetation
reworking of failed material angle slides of slough line; flattening on slough line; deposi
on lower banks previously of bank angles; flow tion of material above
failed material line low relative to top root collars of slough-
bank; development of
new floodplain
line vegetation V
Restabilization Aggradation; further develop Low-angle Stable, alternate chan Re-establishing vege
VI (Quasi-equilibrium) ment of meandering thalweg; slides; some nel bars; convex-short tation extends up
further deposition of alternate pop-out vertical face on top slough line and upper
bars; reworking of failed failures near bank; flattening of bank bank; deposition of
material; some basal erosion flow line angles; development of material above root
on outside bends; deposition new floodplain; flow collars of slough-line
on floodplain and bank sur line high relative to top and upper-bank vege
faces bank tation; some vegeta
tion establishing on
bars
University and NC Division of Soil monitored and validated the bank erosion at three of the university’s
and Water Conservation. study reaches (14 cross sections) and established six cross sections
at three new study sites (Jessup, 2002). Figure 3.13 shows the
results of the follow-up study. Sites with moderate BEHI ratings
exhibited bank erosion rates ranging from 0.04 to 0.74 ft/yr; sites
with high BEHI ratings exhibited 0.11 to 0.45 ft/yr of erosion;
sites with very high BEHI ratings exhibited 0.48 to 1.7 ft/yr; and
sites with extremely high BEHI ratings exhibited 2.19 to 11.15
ft/yr. Additional bank erosion monitoring is needed to expand the
data set and increase the length of the sampling period to
accommodate potential climatic influences.
● Materials
1. Particle size of channel material (riffles and pools)
(Reachwide pebble-count frequency distribution): d15, d35,
d50, d84, d95.
5.1 Priority 1:
Stream Bed Remaining at the Present Elevation.
ect can produce a Widen the Floodplain at the Existing Bankfull Elevation.
stream system with Priority 3 is similar to Priority 2 in its objective to widen the
long-term stability if floodplain at the existing channel elevation to reduce shear
designed and con stress. This is accomplished by excavating a floodplain bench on
structed properly. It one or both sides of the existing stream channel at the elevation
may be more expen of the existing bankfull stage (Figure 5.4). The existing channel
sive and complex to may be modified to enhance its dimension and profile based on
construct than a reference-reach data. The resulting channel is typically a B or Bc
Priority 1 project, (low slope) stream with bankfull stage located at the elevation of
depending on valley the newly widened floodplain. Priority 3 projects typically do not
conditions. Priority 2 increase sinuosity to a large extent because of land constraints.
projects usually can A Priority 3 project can produce a stream system with long
be constructed in dry term stability if it is designed and constructed properly. But it
Figure 5.3 conditions while may require more structural measures and maintenance than
stream flow continues in its original channel or is diverted around Priority 1 or 2 projects. It may be more expensive and complex
Cross section of a Priority 2 the construction site. Typically, water is diverted into the new to construct, depending on valley conditions and structure
restoration project
channel as soon as all or part of it is constructed and stabilized requirements. Priority 3 projects are constructed in wet conditions
with structures and temporary bank-protection measures. unless stream flow is diverted around the construction site.
Because the new floodplain is excavated at a lower elevation, These projects typically have little impact on flooding potential
Priority 2 projects do not increase—and may decrease—the unless there are large changes in channel dimension. Priority 3
potential for flooding. Also, the stream corridor created by the projects typically do not produce large quantities of extra cut
excavated floodplain may enhance riparian wetlands. material or require extensive changes to surrounding land uses.
Unlike Priority 1 projects, which are normally short on material They also do not typically affect riparian wetlands or elevation of
to fill the old channel, Priority 2 projects typically produce a sur the water table.
plus of cut material. Designers must consider the expense and In-stream structures are important to the success of Priority 3
logistics of managing extra soil material excavated from the projects. In many projects, a channelized stream must remain in
Figure 5.4 its current location because of surrounding land uses or utilities.
The resulting stream may be classified as a B or Bc channel even
Cross section of a Priority 3
restoration project though the valley conditions support a more meandering E or C
channel. In this case, boulder cross-vane structures should be
used to protect streambanks, provide grade control and support
scour pools for habitat (see Chapter 8).
3 Results in moderately stable stream May disturb existing vegetation 5.5 Priority 1 Case Study:
Improves habitat values Does not enhance riparian wetlands Yates Mill Pond Tributary
May decrease flooding potential Requires structural stabilization measures
The Yates Mill Pond
Maintains narrow stream corridor May require maintenance
Tributary project is located
Figure 5.5
in a rural watershed in Wake
4 May stabilize streambanks Does not reduce shear stress County just south of Raleigh. Cross-section survey of
Maintains narrow stream corridor May not improve habitat values Yates Mill Pond tributary-
May not disturb existing vegetation May require costly structural measures The existing intermittent
restoration project
May require maintenance stream was incised due to
historic straightening and
Table 5.1 Advantages and disadvantages of restoration options for incised streams removal of riparian vegetation.
The upstream end of the
project reach was not incised, meaning that the new channel
could be connected with the existing channel at its current eleva-
tion. At the downstream end of the first phase of construction in
2000, the existing channel was six feet below the new streambed Figure 5.6
elevation. A temporary boulder-drop-structure connected the Yates Mill Pond tributary-
new and old channels until the second phase of construction restoration project before
was completed in 2002. construction
Table 5.2 lists physical param
Parameter Existing Design
eters for the existing and new Figure 5.7
Watershed Area (sq mi) 0.12 0.12 stream channels. A cross-sec-
Yates Mill Pond tributary-
Stream Classification E6-G5 C5 tion survey depicting the exist- restoration project after
ing and as-built stream channels construction
Bankfull Cross-Sec Area (sq ft) 8 8
is shown in Figure 5.5. Before
Width/Depth Ratio (ft/ft) 5-12 14 and after photos of the project
Entrenchment Ratio (ft/ft) 0.6-4.0 15 are shown in Figures 5.6 and
Bank Height Ratio (ft/ft) 1.0-3.7 1.0 5.7. The project design called
Length (ft) 750 800 for constructing a new, stable
Sinuosity (ft/ft) 1.1 1.2 C5 stream on the floodplain west
of the existing channel. All of the
Riparian Buffer Width (ft) 5-10 50-80
construction was completed in
Table 5.2. Parameters of Yates Mill Pond tributary-restoration project dry conditions before water was
turned into the new channel.
Because the excavated soil didn’t completely fill the existing
incised channel, several small ponds were created to provide
habitat. To help stabilize the new channel, several log vanes and
log weirs were installed along the streambank in addition to root
wads, transplants and erosion matting.
54 Chapter 5 Stream Restoration Stream Restoration Chapter 5 55
5.6 Priority 2 Case Study:
Pine Valley Golf Course Tributary
The Pine Valley Golf Course tributary project is located in an
urban watershed in New Hanover County in Wilmington. The
existing perennial stream was incised due to historic ditching and
draining for construction of the golf course and surrounding resi
dential community. The upstream end of the project reach was a
drainage culvert that prevented
Parameter Existing Design a Priority 1 approach. Project
constraints included a sewer
Watershed Area (sq mi) 0.5 0.5 line along the left streambank,
Figure 5.9
Stream Classification F E two permanent golf-cart bridges,
two irrigation-line crossings and Pine Valley Golf Course
Bankfull Cross-Sec Area (sq ft) 10 10 restoration project before
vegetation concerns at three
Width/Depth Ratio (ft/ft) 15 10 construction
golf holes crossing the stream
Entrenchment Ratio (ft/ft) 1.5 5 reach.
Bank Height Ratio (ft/ft) 2 1 Table 5.3 lists physical
Length (ft) 789 906 parameters for the existing and
Sinuosity (ft/ft) 1.04 1.2 design stream channels. A cross- Figure 5.10
Riparian Buffer Width (ft) 10 50 section survey depicting the
Pine Valley Golf Course
existing and as-built stream restoration project after
Table 5.3 Parameters of Pine Valley Golf Course restoration project channels is shown in Figure construction
5.8. Before and after photos of
the project are shown in figures 5.9 and 5.10. The project design
called for constructing a new, stable E5 stream and floodplain at
the elevation of the existing channel. Stream flow was diverted
through a pump during construction, after which water was
turned into the new channel. Because the excavated soil exceed
Figure 5.8
ed the amount needed to fill the existing channel, excess soil
was hauled to a stockpile area on the golf course property. To
Cross-section survey of Pine help stabilize the new channel, several log cross-vanes and log
Valley Golf Course restoration
project
weirs were installed along the streambank in addition to root
wads, transplants and erosion mats.
Figure 5.13
Cove Creek restoration
project at bankfull flow
after construction
Figure 5.16
Streambank armoring
using gabion baskets
Figure 5.15
Channel armoring using
riprap at the toe of the
streambank
Figure 5.17
Armoring of streambank
using log-crib wall
Office Procedures
Profile Data Summary 6.7
Dimension Data Summary 6.8
Pattern Data Summary 6.9
Reference Reach Summary Table 6.10
Dimensionless Ratio Calculations 6.11
Vegetation Reference Reach 6.12
North Carolina Reference Reach Data 6.13
spacing/Wbkf;
6.12 Vegetation Reference Reach
pool slope ratio=Spool/Savg;
Riparian and floodplain restoration should be based on a ref
glide slope ratio=Sglide/Savg
erence area found within close proximity of the project site. This
should be chosen based on the initial riparian assessment of the
project site, if possible. Choose a site that has topographic and
vegetative characteristics similar to the project site. Reference
sites should be as pristine as possible. Ideal areas will not have
been disturbed recently and will be free of exotic vegetation
(see Figure 6.4). If the project site has no native riparian characteristics
(i.e., it is urbanized or farmed), look upstream or downstream of
the project site to determine the stream’s riparian characteristics.
Once the riparian reference site has been chosen, follow the
Figure 6.3 riparian assessment process for describing topography, soil and Figure 6.4
vegetation as discussed in Section 2.10.
Riffle and pool cross- Example of a reference
sections and dimensionless reach for vegetation
ratios 6.13 North Carolina Reference Reach Data
NC State University conducted a
study of reference reach streams (Clinton et
bankfull mean depth
al., 1999) that included detailed morpholog
(Dbkf)=Abkf/Wbkf;
ic surveys of 14 streams from the Blue
entrenchment ratio
Ridge/Piedmont physiographic regions
(ER)=Wfpa/Wbkf;
of North Carolina (Table 6.1). The reference
width to depth ratio=Wbkf/Dbkf;
reaches included in the study were
max depth ratio=Dmax/Dbkf;
stable streams with: consistent land use
bank height ratio
over the past 60 years, no channelization,
(BHR)=DTOB/Dmax;
and no severe bank erosion. The bankfull
pool max depth ratio=Dpool/Dbkf;
width of the channels ranged from 8.7 to
pool area ratio=Apool/Abkf;
69 feet. The data from the stream reaches
pool width ratio=Wpool/Wbkf
were analyzed to develop channel pattern
and profile relationships. These relation
ships are described in Table 6.2 and figures
6.5-6.10. Williams (1986), Leopold and
Wolman (1960) and Rinaldi and Johnson
66 Chapter 6 Stream Restoration Stream Restoration Chapter 6 67
ty
t /ft) osi
(1997) also developed interrelationships for river meander and (f in u
1.02
1.1
1.1
1.2
1.1
1.1
1.2
1.5
1.2
1.2
1.1
1.1
1.7
1.1
S
channel size. Their data are presented in Table 6.2 for comparison. eac
h
18.7
26.3
30.3
tio hm
2.1
1.9
1.4
1.3
1.3
3.1
3.4
3.0
2.8
3.2
6.0
for belt width, radius of curvature and meander wavelength as Ra enc
tr
functions of bankfull channel width are shown in Table 6.2 and En
figures 6.5-6.7. All three data sets indicate high variability with )
the best regression fit occurring for belt width and worst for /ft h
(ft ept
21.8
22.3
30.7
25.1
17.8
19.3
16.3
18.0
16.4
23.8
10.8
7.3
7.1
6.6
io
radius of curvature. The relationship for pool-to-pool spacing as t
Ra h to
D
a function of bankfull channel width is shown in Figure 6.8. id
t
Channel-profile relationships are described in figures 6.9 and
W
100/380
100/370
135/512
144/512
streams that dissipate energy through changing bed features and
33/370
40/210
75/362
45/145
38/130
45/400
40/110
45/125
9.5/30
8.6/77
)
provide stable aquatic habitat. They also can be used to estimate (m
m
maximum depth of riffles and maximum depth of pools for a 84
/d
given stream-type and watershed condition. Regression relation
0
d5
ships (figures 6.9 and 6.10) provide a good fit to the measured data for )
both of these parameters. /ft
0.055
0.019
0.016
0.033
0.010
0.009
0.005
0.013
0.014
0.004
0.011
0.013
0.008
0.009
(ft ace
Channel-morphology relationships on reference streams are e f
op ur
Sl er S
valuable tools for engineers, hydrologists and biologists involved at
in stream restoration and protection. They also can help evaluate W
.)
the relative stability of a stream channel. This study created a (ft n
h Mea
good fit for most regression equations, indicating strong correla t
1.1
1.8
1.8
1.1
2.0
3.4
3.2
0.9
1.9
2.9
1.2
1.2
2.1
2.0
p l
De kful
tion between morphology relationships in reference stream n
channels in the rural Piedmont of North Carolina. However, Ba
users must consider the natural variability represented by these
h
relationships. The data and relationships from the NC State .) dt
24.6
39.1
54.0
28.8
35.0
64.9
52.3
16.7
30.7
69.0
13.7
21.5
(ft Wi
8.7
8.7
University study can be useful for comparing additional reference kf
ul
l
reach data collected in North Carolina’s Piedmont region. Ba
n
t.) al
However, the availability of this data does not replace the need q. f tion
for a reference reach survey that is specific to each individual (s ec
218.0
168.8
199.0
ea X-S
27.8
68.5
95.1
33.0
68.8
15.5
57.4
10.4
10.6
28.3
42.8
r
restoration project. A ll
fu
a nk
B
i) ea
m r
q eA
24.8
29.0
s
1.1
7.9
9.2
1.8
6.5
6.8
0.2
0.5
4.7
1.9
(
23
g
1
na
rai
D
pe
Ty
B3a
B3c
B3c
B4c
am
C3
C3
C4
C4
C4
B4
E4
E4
E4
E4
re
St
Richland Creek
Spencer Creek
Barnes Creek
Steels Creek
Clinton et al., 1999
Sal's Branch
Basin Creek
Craig Creek
STREAM NAME
Big Branch
Mill Creek
68 Chapter 6 Stream Restoration
Table 6.2 Reference-reach relationships
Clinton et al., 1999
Williams (1986)
North Carolina
Figure 6.5 Figure 6.6
Meander Wavelength
4.9 ≤ W ≤ 13,000 ft
Applicable Range:
Applicable Range:
Applicable Range:
Applicable Range:
Clinton et al., 1999 Clinton et al., 1999
9.8 ≤ W ≤ 14.8 ft
8.7 ≤ W ≤ 69 ft
Lm=2.86W
Lm=6.5W
Lm=1.8W
Lm=9.7W
n/a
1.12
1.54
1.1
1.13
Applicable Range:
4.9 ≤ W ≤ 7,000 ft
8.7 ≤ W ≤ 69 ft
Wblt =0.57W
Wblt =4.4W
1.12
1.49
Applicable Range:
Applicable Range:
4.9 ≤ W ≤ 7,000 ft
8.7 ≤ W ≤ 69 ft
Rc=2.5W
Rc=1.3W
Rc=2.4W
n/a
1.02
1.12
0.94
Sinuosity, K
d16 (mm)
d35 (mm)
d50 (mm)
d84 (mm)
d95 (mm)
Stream Restoration Chapter 7 79
7.2 Sediment Transport Step 4. Once τ∗ci is determined, calculate the minimum bankfull
A stable stream has the capacity to move its sediment load mean-depth required for entrainment of the largest particle in
without aggrading or degrading. The total load of sediment can the bar sample (or subpavement sample) and the bankfull
be divided into bedload and suspended load. Suspended load is water-surface-slope required for entrainment of the largest
normally composed of fine sands, silts and clay and transported particle using equations 3 and 4, respectively.
in suspension. Bedload moves by rolling, sliding or hopping
(saltating) along the bed. At higher discharges, some portion of Dr=( 1.65 τ∗ci di ) (Equation 3)
se
the bedload can be suspended, especially if it contains sand.
Sr=( 1.65 τ∗ci di ) (Equation 4)
The movement of particles depends on their physical properties— De
notably size, shape and density. Grain size directly influences the
mobility of a given particle. Where: Dr=bankfull mean depth required (ft)
1.65=sediment density (submerged specific weight)=
Gravel Bed Streams (d50 > 2 millimeters):
density of sediment (2.65g/c3)–density of water (1.0g/c3)
Sediment transport in streams with gravel and/or cobble beds τ∗ =critical dimensionless shear stress
ci
is usually analyzed by estimating the shear stress or the compe di=largest particle from bar sample (or subpavement
tency of the stream to move a particular-size particle. Critical sample) (ft)
dimensionless shear stress τ∗ci is a measure of the force required Se=existing bankfull water surface slope (ft/ft)
to mobilize and transport a given-size particle resting on the Sr=bankfull water surface slope required (ft/ft)
channel bed. It can be calculated using a bar sample and a wet De=existing or design mean bankfull depth (ft)
ted-perimeter cross-section pebble count or the pavement and
subpavement particle sample from a representative riffle in the If the design mean-riffle-depth is significantly larger or smaller
reach (see Section 2.7-2.8 for pebble count, pavement, subpavement and bar sampling than the depth needed to move the largest particle, the width-to
methods).
depth ratio may need to be adjusted up or down, respectively, to
Step 1: Collect bar samples from several key points along the correct the depth.
stream reach that is being restored and the reference reaches. Step 5. Check the bankfull shear stress at the riffle using Shield’s
Key points include anywhere there are changes in stream type, curve (Figure 7.4) to ensure sediment-transport competence using
bed-material composition or stability. For example, two or more Equation 5 (for wetted perimeter equations and information on
samples may be needed to represent a 1,000-foot reach of calculating hydraulic radius, see Section 2.9). The shear stress
stream. Collect pavement and subpavement samples from any placed on the sediment particles is the force that entrains and
areas of the design channel and reference reaches at which a moves the particles, given by:
bar sample is not possible. Also collect a wetted-perimeter
cross-section substrate analysis (pebble count) for both the τ=γ RS (Equation 5)
slopes for the design reach from the longitudinal profile. s=average stream slope (ft/ft)
τ∗ =0.0834 ( dˆ
ci ) – 0.872
(Equation 1)
Shield’s Diagram
SAM, can be used to model the design channel and compare the
Leopold, 1994, 194 sediment-discharge rates to a section of reference stream,
preferably upstream and downstream of the restoration reach. In
this way, a sediment budget can be created in which the inflow
of sediment is equal to the outflow. In addition, individual stream
sections can be modeled to show localized competency and
capacity. The same procedure can be applied to streams whose
beds are sand/silt. In a stream with a cohesive-clay bed, little
bed load transport would be expected. Clay-bed streams are
typically stable or erode at very low rates; however, bed load
could move through a stream reach. For example, sand and silt
may pass through the stream reach as a result of low cohesion
between sand and clay.
Ideally, the trunk of the tree above the root wad should have a Vanes come in four types: single vane, J-hook vane, cross
10- to 24-inch basal diameter. Root wads with larger diameters vane and W-weir. Vanes can be constructed from large tree
are more expensive to install and disturb more soil and vegeta trunks or boulders, but most are built using boulders. Single and
tion. Regardless of diameter, the trunk length should be 10 to 15 J-hook vanes protect the streambank by redirecting the thalweg
feet. Install root wads where the primary flow vectors intercept away from the streambank and toward the center of the channel.
the bank at acute angles. It generally is not necessary to place They also improve in-stream habitat by creating scour pools and
root wads against each other for the entire length of a meander providing oxygen and cover. Cross vanes serve a similar purpose
bend. Install root wads at the toe of the bank, as low as possible. and also may control the grade in both meandering and step-
Generally, one-third to one-half of the root wad is placed below pool streams.
the base-flow elevation. Where scour depths are high, install
footer logs below the root wads. Where bank heights are low—1 Design Criteria
to 1 1/2 times bankfull height—place boulders at least 1 ton or All four vanes are oriented upstream at 20- to 30-degree
heavier behind the root wad. If banks are high and have plenty of angles off the bank. Single and J-hook vanes are located just
vegetation and root mass, footer logs and boulders may not be downstream of where the stream flow encounters the stream-
needed (Figure 8.1). Boulders and transplants prevent back-eddy bank at acute angles. Vanes should be highest next to the bank,
scour that may be caused by the root wad during high flow. In generally starting at or slightly below bankfull. Rock vanes along
North Carolina, root wads are most successful on the outside of the outside of a meander bend are shown in Figure 8.3. If the
gentle meanders (high ratio of radius-of-curvature to bankfull potential for bank erosion is not too high, start the structures
width) and upstream of streambank vegetation, where they will between bankfull and the inner berm. In either case, slope the
help prevent erosion from any back eddies that occur during structures downward, pointing them upstream. The size of rock
high flow. will depend on the size of the stream, the dominant bed material
and the depth of scour in the channel at high flow. In streams
Installation with substrate of gravel or larger rock, the boulders should be
Root wads are installed by either the drive-point method or generally 1 to 2 tons. Flat rocks are preferable. In a newly creat
trenching methods. The drive-point method is preferred because ed channel (i.e., Priority 1 restoration), consider using sills on the
it disturbs the least amount of soil and adjacent vegetation and is vane structures. Sills extend into the bank where the highest rock
more cost-effective. The drive-point method uses a track hoe meets the streambank. The purpose of the sill is to prevent water Figure 8.3
with a hydraulic thumb to insert the root wad directly into the from cutting around the boulders next to the bank during high
bank (Figure 8.2). Sharpen the end of the log with a chainsaw before Rock vanes on outside
flow. This is especially important on newly excavated channels
of meander bend imme
driving it into the bank. A loader or second track hoe may be that may have unconsolidated materials on the banks and little or diately after installation
used to hold the root wad in place while the track hoe with the no vegetation for a while. All structures (diagrams) shown in this (looking upstream)
hydraulic thumb grasps the root fan and drives the trunk into the section include sills.
bank. To prevent destruction of the root fan, don’t ram the track- The length of a
hoe bucket into the root wad excessively (if the streambank is single-vane struc
resistant to the root wad and trunk, consider the trenching ture may span up to
method or substitute another structure). If vegetation exists on one-half of the
the streambanks, avoid destroying these plants during installa base-flow channel
tion. Orient root wads upstream so that the stream flow meets width. The slope of
the root wad at a 90-degree angle, deflecting water away from the structures may
the bank (Figure 8.1). If a back eddy is formed by the structure, range from 2 to 20
place a transplant or boulder on the downstream side of the root wad. percent; the longer
If the root wad cannot be driven into the bank or the bank and flatter the struc
needs reconstruction, use the trenching method. For this tures, the more
method, excavate a trench for the log portion and install a footer streambank protect
log underneath the root wad. Place the footer log in a trench ed and habitat
excavated parallel to the bank and well below the streambed. enhanced. The
Place the root wad on top of the footer. Keep at least one-third of rocks in all three
the root wad below normal base-flow conditions. Once the root structures (except
wad is installed, backfill the trench and rebuild the bank with the last two rocks of
transplants or sod mats. Grade the upper bank or terrace scarp a J-hook) must
to a maximum slope of 1.5:1, seed it with a rye grain or other touch each other,
native seed material, and cover it with an erosion-control fabric. and footer rocks
must be placed at
86 Chapter 8 Stream Restoration Stream Restoration Chapter 8 87
the depth of scour. One to two rocks underneath and down This placement sets the elevation of the upstream pool and holds Figure 8.6
stream of the top rock usually will suffice. To prevent the struc the elevation of the downstream riffle. A cross vane at the head
J-hook placement in
ture from toppling into a scour hole, place the footer rock down of a riffle is typical in small streams that have a short distance meander bend
stream of the top rock. between features. In larger streams, the cross vane is placed in
J-hook vanes are built like single vanes except for the last the glide (Figure 8.9).
two to three rocks. Space these rocks apart about one-half the With cross vanes
Figure 8.4 diameter of the rock to create flow-convergence (figures 8.4 and 8.6). and log structures,
Looking downstream at This flow-convergence creates a large scour hole to dissipate geotextile material is
a J-hook vane energy and provide aquatic habitat. used on the upstream
Cross vanes side of the boulders
provide grade or logs. Footers help
control, keep the prevent movement of
thalweg in the the structure during
center of the channel high flow, but spaces
and protect between the boulders
streambanks from can allow material to
erosion. A cross move through, creat
vane has three ing a "hole" in the
components: two cross vane. Even if
rock vanes and the rocks are touch
one center structure ing, these holes still
placed perpendicu may appear (Figure 8.10).
lar to the flow. The If the hole is large
center structure enough, the majority,
sets the grade of if not all, of the flow
the streambed. at base-flow level
Installed cross may move through it. If the chan
vanes are shown nel has a variety of substrate
sizes (small gravel to cobble),
back-filling on the upstream side
of the structure may close these
gaps. But if the material is too
Figure 8.5 uniform or the gaps too large,
Rock vane and J-hook the structure may eventually
vane (looking upstream) be compromised. To prevent this,
place geotextile fabric on the
upstream side of the structure
during construction and bury it
to the depth of the footers (this
is strongly recommended for
structures that provide critical
grade-control on a project). The
Figure 8.7
fabric will help to prevent water from piping between or under
neath the rocks or logs. Once the backfill material is placed Cross-vane structure with
upstream of this, no material should move through at all. Figure woody debris for habitat
enhancement
8.11 shows fabric being used on a log vane. To ensure stability
of important grade-control structures, such as in a step-pool
system, minimize the drop in elevation for each structure. The
larger the difference in elevation from immediately upstream to
downstream of the structure, the more stress is placed on the
structure itself. In this case, grade control may fail and jeopardize
in figures 8.7 and 8.8. Since a cross vane raises or holds the bed the entire project.
elevation, it is often placed within the glide or at the head of The W-weir structure is very similar to the cross vane, in that
the riffle. it maintains the grade of the streambed and provides excellent
aquatic habitat. W-weirs can be used only on large rivers
88 Chapter 8 Stream Restoration Stream Restoration Chapter 8 89
because they span a signifi
cant distance across the
channel. Their design is
described as a W formation
in the downstream direction.
From the plan-view perspec
tive, the weir is similar to
two cross-vanes joined in
the center of the channel.
Figure 8.12 shows a
schematic of the W-weir.
Due to the double cross-
vane effect of the W-weir,
two thalwegs are created.
This design helps to
enhance fish habitat.
The W-weir also can
be designed to maintain
recreational boating, stabilize streambanks, facilitate irrigation
diversions, reduce scour of a bridge’s center pier and foundation, Figure 8.11
Figure 8.8
and increase sediment transport at bridge crossings. Two W-weirs Use of geotextile fabric on the
Cross vane showing place may be constructed together on very wide rivers and/or where upstream side of log structure
ment and measurements
* The lowest slope is most
two bridge center piers (three cells) require protection (Rosgen, 2001c).
desirable, but in small streams
a narrow channel may neces 8.3 Stream Crossings
sitate higher slopes (10 to 20
percent). Design road crossings to minimize negative impacts on stream Figure 8.12
stability, sediment transport, aquatic habitat and fish passage
Plan, cross section and profile
while meeting prescribed hydraulic and structural criteria. The views of the W-weir
ultimate goal is to construct a stable stream system that neither Rosgen 2001c
Figure 8.9
Placement of cross-vane
structure in a meandering
stream
Figure 8.10
Hole formed on
cross vane due to
gap in structure
Figure 9.4
9.5. Permanent Seeding
Installing potted plants
For maximum habitat diversity and ground cover, include
Type Spacing # Per 1,000 sq ft seeds among the planted material. Permanent (perennial) seeding
Shrubs mixtures are available from nurseries and can vary widely. A site-
(<10 ft) 3-6 ft 25-110 specific combination of herbaceous species and grasses based
on surrounding native flora is recommended. Site conditions and
Shrubs and trees project requirements will determine the vegetation needs and
(10-25 ft) 6-8 ft 15-25 installation methods. Appendix F lists appropriate herbaceous
Trees species for North Carolina. Follow nursery recommendations
(>25 ft) 8-15 ft 4-15 for appropriate planting times and methods. Before planting the
permanent seed mix, see the site-preparation and soil-amend
ment procedures in Section 10.2.
Table 9.1. Spacing guidelines for shrubs and trees
Figure 9.5
9.4. Container Plant Material Example of permanent
Some projects may require container, or potted, plants. These seed mix
come in many different sizes and shapes. Check with local nurseries
and growers for availability. When installing potted plants, dig a
hole that is twice the diameter of the pot. Remove the plant from
the container and tease roots apart if the plant is root-bound.
Place plant in hole, making sure the root collar is even with the
ground surface and the stem is upright. Back-fill with potting soil
or fill from the hole. Make sure the fill is free of clods and stones,
loose and evenly distributed around the plant. Tamp firmly
around the plant to eliminate air pockets. Add mulch to retain
moisture. Refer to Section 9.3 for installation techniques and
spacing requirements. Appendix F lists appropriate species for
North Carolina.
Figure 11.6
Cove Creek after
restoration
Troendle, C. A., D. L. Rosgen, S. E. U.S. Environmental Protection Frothingham, K. M., B. L. Rhoads and Schiechtl, H. M. June 1986. FAO
Ryan, L. S. Porth and J. M. Agency, Office of Water, River E. E. Herricks. 2001. Stream geomor- Watershed Management Field Manual:
Nankervis. 2001. Developing a refer- Corridor and Wetland Restoration phology and fish community structure Vegetative and Soil Treatment
ence sediment transport relationship. http://www.epa.gov/owow/wetlands/ in channelized and meandering reach- Measures. Rome, Italy: Food and
In Proceedings of the 7th restore/ es of an agricultural stream. In Agriculture Organization of the United
International Sedimentation Understanding Geomorphic Processes Nations.
Conference, Reno, NV, March 25-29 U.S. Geological Services, Water and Riverine Habitat. Water and
Resources of North Carolina Science Application Volume 4: 105 Schiechtl, H. M. and R. Stern.
U.S. Department of Agriculture, Natural http://nc.water.usgs.gov/ 117. Washington, D.C.: American December 1996. Water
Resources Conservation Service. 1986. Geophysical Union. Bioengineering Techniques for
Urban Hydrology for Small Watersheds: Wildland Hydrology Consultants Watercourse Bank and Shoreline
Technical Release 55. 210-VI-TR-55, http://www.wildlandhydrology.com/ Gore, J. A. 2001. Models of habitat Protection. Cambridge, Mass:
Second Ed. use and availability to evaluate anthro- Blackwell Science Inc.
pogenic changes in channel geometry.
13.3 Recommended Reading
U.S. Geological Survey. 1982. In Understanding Geomorphic Schiechtl, H. M., R. Stern and L.
Guidelines for Determining Flood Bunte, K. and S. R. Abt. 2001. Processes and Riverine Habitat. Laklitsch (translator). July 1996.
Flow Frequency. Bulletin 17B of the Sampling Surface and Subsurface Water and Science Application Ground Bioengineering Techniques for
Hydrology Subcommittee, Water Particle-Size Distributions in Volume 4: 27-36. American Slope Protection and Erosion Control.
Resources Council, pp. 14-20. Wadable Gravel- and Cobble-Bed Geophysical Union. Cambridge, Mass.: Blackwell Science
Streams for Analyses in Sediment Inc.
Williams, G.P. 1986. River meander Transport, Hydraulics, and Harrelson, C. C., C. L. Rawlins, and J.
and channel size. Journal of Streambed Monitoring. General P. Potyondy. 1994. Stream Channel Statzner, B., J. A. Gore and V. H.
Hydrology 88:147-164. Technical Report RMRS-GTR-74. Reference Sites: An Illustrated Guide Resh. 1988. Hydraulic stream ecolo-
Fort Collins, Colo.: U.S. Department to Field Technique. General Technical gy: observed patterns and potential
Wolman, M.G., 1954. A method of sam of Agriculture Forest Service, Rocky Report RM-245. Fort Collins, Colo.: applications. J. N. Am. Benthol. Soc.
pling coarse river-bed material. Mountain Research Station. USDA Forest Service, Rocky 7(4)307-360.
Transactions of American Geophysical Mountain Forest and Range
Union 35: 951-956. Calow, P. and G. E. Petts, eds. Vol.1, Experiment Station. Thorne, C. R., R. D. Hey, and M. D.
1992; Vol. 2, 1994. The Rivers Newson, eds. 1997. Applied Fluvial
13.2 Web Information Handbook: Hydrological and Leopold, L. B., G. M.. Wolman and J. Geomorphology for River Engineering
Federal Interagency Stream Ecological Principles. Cambridge, P. Miller. 1992. Fluvial Processes in and Management. New York: John
Restoration Working Group: Mass.: Blackwell Science, Inc. Geomorphology. Mineola, N.Y.: Dover Wiley and Sons.
http://www.usda.gov/stream_restoration/ Publications Inc.
126 Chapter 13 Stream Restoration Stream Restoration Chapter 13 127
Notes:
Appendices
Office Procedures
Watershed Drainage Area Measurement 2.1
Land-Use Survey 2.2
Field Procedures
Bankfull Identification 2.3
Dimension 2.4
Pattern 2.5
Profile 2.6
Substrate Analysis 2.7
Bar, Pavement and Subpavement Sampling
Methods and Scour Chains 2.8
Estimating Bankfull Discharge and Velocity 2.9
Assessing Riparian Condition 2.10
3 Rosgen Classification
Rosgen Stream-Classification System/
Channel Assessment and Validation Procedures Chapter 3
Level I 3.1
Level II 3.2
Level III 3.3
Level IV 3.4
Bankfull Verification and Gage Station Analyses Chapter 4
4 Gage Analyses
Priority Options for Restoring Incised Streams Chapter 5
5 Restoration Options
6 Reference Reach
Reference Reach Survey Chapter 6
Field Procedures
Bankfull Identification 6.1
Longitudinal Profile 6.2
Pool and Riffle Cross-Section Survey 6.3
Pebble Count 6.4
Rosgen Stream Classification 6.5
Plan-Form Measurements 6.6
Office Procedures
Profile Data Summary 6.7
Dimension Data Summary 6.8
Pattern Data Summary 6.9
Reference Reach Summary Table 6.10
Dimensionless Ratio Calculations 6.11
Vegetation Reference Reach 6.12
North Carolina Reference Reach Data 6.13
7 Design Procedures
Design Procedures Chapter 7
8 Structures
Root Wads 8.1
Vanes 8.2
Stream Crossings 8.3
Structures and Design Features
for Habitat Enhancements 8.4
Vegetation Stabilization and Riparian-Buffer Re-establishment Chapter 9
9 Vegetation
Erosion and Sediment Control Plan Chapter 10
Pollution Control:
Construction Sequence and Structures 10.1
Pollution Control:
Seeding 10.2
10 Erosion Control
11 Flood Studies
Flood Studies Chapter 11
Introduction 11.1
FEMA Maps and Nomenclature 11.2
FEMA Requirements and Flood Modeling 11.3
Case Study 11.4
12 Monitoring
Restoration Evaluation and Monitoring Chapter 12
Methodology 12.1
Morphology 12.2
Success Criteria 12.2.1
Photo Documentation 12.3
Vegetation 12.4
Plot Location 12.4.1
Plot Size 12.4.2
Timing 12.4.3
Additional Monitoring Opportunities 12.5
Bank Stability Monitoring 12.5.1
Shading and Temperature 12.5.2
Fish and Invertebrate Data 12.5.3
13 Reference/Resources
References and Resources Chapter 13
Appendices
Appendices