Section 16-Part 9-Accuracy of Erected Steelwork

This document specifies the accuracy requirements for erected structural steelwork. It provides tables that define the maximum permitted deviations for foundations, walls, foundation bolts, and various erected steel components like columns, beams, floors and crane gantries. Contractors must advise subcontractors of these accuracy standards to ensure proper clearances during subsequent construction phases. Deviations are defined for factors like plumbness, alignment, levelness and gaps between bearing surfaces.

Uploaded by

Adam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
107 views6 pages

Section 16-Part 9-Accuracy of Erected Steelwork

This document specifies the accuracy requirements for erected structural steelwork. It provides tables that define the maximum permitted deviations for foundations, walls, foundation bolts, and various erected steel components like columns, beams, floors and crane gantries. Contractors must advise subcontractors of these accuracy standards to ensure proper clearances during subsequent construction phases. Deviations are defined for factors like plumbness, alignment, levelness and gaps between bearing surfaces.

Uploaded by

Adam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

TENDER#37852-IALP-AW/AP-23

9 ACCURACY OF ERECTED STEELWORK

9.1 GENERAL

9.1.1 Scope

1 This Part the requirements for the accuracy of erected structural steelwork.
2 Related Parts and Sections are:
This Section
Part 7 Accuracy of Fabrication
Part 8 Erection
9.1.2 General Requirements
1 Permitted maximum deviations in erected steelwork shall be as specified in Clause 9.4.2 of this
Part taking account of the following:
(a) All measurements be taken in calm weather, and due note isto be taken of temperature effects
on the structure. (See Clause 8.4.2 of this Section).
(b) The deviations shown for I sections apply also to box and tubular sections.
(c) Where deviations are shown relative to nominal centrelines of the section, the permitted
deviation on cross-section and straightness, given in Part 7 of Section, may be added.

9.2 INFORMATION FOR SUB CONTRACTORS

9.2.1 General
1 The Contractor shall advise sub contractors engaged in operations following steel erection of the
deviations acceptable in this document in fabrication and erection, so that they can provide the
necessary clearances and adjustments.

9.3 DEVIATIONS

9.3.1 Permitted Deviations For Foundations, Walls And Foundation Bolts


1 The permitted deviations for foundations, walls and foundation bolts are given in Table 9.1.

Table 9.1
Permitted Deviations for Foundations, Walls and Foundation Bolts

Item Component Deviation


1 Foundation Level
Deviation from exact level.

ACCURACY OF ERECTED STEELWORK Page 1 of 6


TENDER#37852-IALP-AW/AP-23

Table 9.1 (Continued)


Permitted Deviations for Foundations, Walls and Foundation Bolts

Item Component Deviation


2 Vertical Wall
Deviation from exact position at
steelwork support point.

3 Pre-set Foundation Bolt or Bolt


Groups when Prepared for
Adjustment
Deviation from the exact location and
level and minimum movement in
pocket.

4 Pre-set Foundation Bolt or Bolt


Groups when Not Prepared for
Adjustment
Deviation from the exact location
level and protrusion.

9.3.2 Permitted Deviations of Erected Components

1 Permitted deviations of erected components is given in Table 9.2.

ACCURACY OF ERECTED STEELWORK Page 2 of 6


TENDER#37852-IALP-AW/AP-23

Table 9.2
Permitted Deviations of Erected Components

Item Component Deviation


1 Position at Base of First Column
Erected
Deviation of section centreline from the
specified position.

2 Overall Plan Dimensions


Deviation in length or width True overall dimension “ L”
L 30 metres, = 20
mm
L 30 metres, = 20
mm +
0.25 (L - 30) mm
where L is in metres
3 Single Storey Columns Plumb
Deviation of top relative to base,
excluding portal frame columns, on
main axes. See Clause 3.4.4 (c) of this
Section regarding pre-setting
continuous frames.

= H/600 or 5 mm
whichever is greater
Max = 25 mm

ACCURACY OF ERECTED STEELWORK Page 3 of 6


TENDER#37852-IALP-AW/AP-23

Table 9.2 (Continued)


Permitted Deviations of Erected Components

Item Component Deviation


4 Multi-storey Columns Plumb
Deviation in each storey and
maximum deviation relative to
base.

h = h/600 or 3 mm
whichever is greater
H = 50 mm maximum
5 Gap Between Bearing Surfaces
(See Clauses 4.4.3-3, 6.3.1 and
Item 3 of Table 7.1)

6 Alignment of Adjacent Perimeter


Columns critical face of columns
Deviation relative to next column on
a line parallel to the grid line when
measured at base or splice level.

= 10
mm
Floor Beams Level
Deviation from specified level at
supporting stanchion.

ACCURACY OF ERECTED STEELWORK Page 4 of 6


TENDER#37852-IALP-AW/AP-23

Table 9.2 (Continued)


Permitted Deviations of Erected Components
Component Deviation
Item
8 Floor Beams Level at Each End of
Same Beam
Deviation is level.

9 Floor Beams Level of Adjacent


Beams within distance of 5 metres
Deviation from relative horizontal
levels (measured on centreline of top
flange)

10 Beams Alignment
Horizontal deviation relative to an
adjacent beam above or below.

h 3 m, = 5 mm
h 3 m, = h/600

11 Crane Gantry Columns Plumb


Deviation of cap relative to base.

= Hc /1000 or 5

mm whichever is
greater Max = 25
mm

ACCURACY OF ERECTED STEELWORK Page 5 of 6


TENDER#37852-IALP-AW/AP-23

Table 9.2 (Continued)


Permitted Deviations of Erected Components

Item Component Deviation


12 Crane Gantries Gauge of Rail
Tracks
Deviation from true gauge

=
13 Joints in Gantry Crane Rails 10

= 0.5 mm

END OF PART