Annexure 10 - FQAP Format No. 21.20.21-Tower Construction - 20190903173116
Annexure 10 - FQAP Format No. 21.20.21-Tower Construction - 20190903173116
CHECKED
SR.
DESCRIPTION REMARKS REFERENCE/ INSTRUCTION
NO.
YES NO
B STUB SETTING
Ensure correct pits are excavated for the
foundation based on the specific foundation/ Foundation/pit marking
1
pit marking drawing & make of the tower for drawing
that particular location
Carry out stub setting as per set procedure &
2 RFC drawing RFC drawing
CHECKED
SR.
DESCRIPTION REMARKS REFERENCE/ INSTRUCTION
NO.
YES NO
E TOWER ERECTION
CHECKED
SR.
DESCRIPTION REMARKS REFERENCE/ INSTRUCTION
NO.
YES NO
Ensure all Nuts/Bolts, flat/spring washers are
8 available at site as per BOM & approved Refer BOM & RFC drawing
drawings.
Ensure all horizontal Bolt heads are facing
9 inside and vertical Bolt head facing upwards By visual inspection
Ensure subsequent sections are erected only
after complete erection and bracing of Refer RFC drawing
10
previous section
CHECKED
SR.
DESCRIPTION REMARKS REFERENCE/ INSTRUCTION
NO.
YES NO
F STRINGING
Check for cleanliness of insulators and
1 mechanical breakage / damage of insulators.
Check IR value of insulator string using 5kV
2 Megger before hoisting is within permissible
limits.
Ensure all stringing tools, plants
3 and safety equipments are tested & in Test certificates
good working condition.
Ensure that the sequence of paying out shall
4 be from top onwards . Ground wire shall be
payed out first.
Ensure that all angle/dead end towers shall be
provided with stays/anchors to balance the
5
one sided load on them while stringing is done
initially on one side only.
Ensure that standing tress or any other object
6 or tower legs should not be used for providing
stays.
Ensure that stay pits are excavated to a
7 minimum depth of 2 meters.
Ensure all compression joints should be
8 carefully made and record of initial and final
lengths of the joints is to be maintained.
Ensure that not more than one joint in a
9
conductor is provided in one span
Ensure that no mid span joint is provided in
major crossings for main roads, railway
10
crossing, power line crossing and major
rivers.
Ensure that all mid span joints on
conductors/earthwire and repair sleeves of
11
compression type are free from sharp edges,
rust and dust
Check for any damage to hardware of
12 insulators, conductor, earth wire/OPGW
Ensure continuous check of conductor and
13 ground wire for loose/broken strands or any
other damage while installation.
Check for any damage to insulators,
14
conductor, earth wire/OPGW
Ensure proper tightening of copper bond
15 connection.
Check Final tension and sag length are as per
16 sag tension chart. Refer Sag Tension chart
Ensure correct ground clearance is
17 maintained as specified in IE rules Refer IE rule for ground
clearances
Ensure Jumpers in the tension tower are
18
properly intact with conductor and form a
ERECTION AND COMMISSIONING TEST FORMATS
CHECKED
SR.
DESCRIPTION REMARKS REFERENCE/ INSTRUCTION
NO.
YES NO
parabolic shape in order to achieve adequate
clearance from tower steel structure.
Check Jumper bolts are properly tightened.
19
G PRE- COMMISSIONING
Ensure verticality of tower is checked
with help of Total Station for both
1
longitudinal & transverse direction
This is within specified Limits.
Check IR value of each phase of line with
2 respect to ground and phase to phase are
within limits.
Check conductor continuity test with help of
3
10kV Megger.
Ensure placement and no. of dampers on
4 each phase are verified as per damper Refer damper placement chart
placement chart / drawing. / RFC drawing
Ensure that all foreign materials viz dead bird,
Fallen tree branches, bird nests etc. on
4
conductors, earth wires, Jumper, insulator By visual inspection
string, cross arms are re-moved.
Check value of tower footing resistance after
5 earthing in dry season with the help of 10kV
megger (permissible limit less than 10 ohm). Refer Format No. 21.57.01
H COMMISSIONING
Ensure checking of Line continuity by using
1 off line fault locator.
Ensure all statutory approvals are received
2 for charging of the Line.
I POST COMMISSIONING
Note : Following checklists will be shared during pre bid meeting and duting execution works.