JSA - Non-Destructive Testing (NDT) - Magnetic Particle Test
JSA - Non-Destructive Testing (NDT) - Magnetic Particle Test
TASK DESCRIPTION: JOB SAFETY ANALYSIS TEAM (FIRST NAMED-JSA TEAM LEADER)
Non-Destructive Testing (NDT) – Magnetic Particle Test NAME POSITION
Cairn Construction Civil Engineer
Contractor Site Supervisor
Contractor Site HSE Engineer
Cairn Construction HSE Engineer
SIGNATURE
DATE :
Sl ACTIVITY HAZARD HAZARD EFFECT IR CONTROL MEASURES Responsibility RR
no
E P R E P R
Over Collision with 3 2 M Tool box talk to be given before start Section In charge / 2 1 L
speeding other vehicle work Site Engineer
vehicle Property Follow speed limits as specified in
Damaged cairn road transport safety policy.
Injury to person Follow road sign board/ follow speed
limit
Inexperienc Collision with 3 2 M Driver shall have valid driving Section In charge / 2 1 L
e driver other vehicle license. Site Engineer
engaged for Property Drivers shall attend HSE induction
driving. Damaged before engaging them on job.
Injury to person Follow traffic rules & make sure
1. Traffic Hit injury brakes are function all the time.
Mobilization Hazards Don’t use cell phone while driving.
of Crew Make sure your vehicles lights;
dippers are functional all the time
especially night.
CIL approved vehicle shall be used
Don’t drive the vehicle under
influence of alcohol
Sharp curve Collision with 3 2 M Follow the instruction given on safety Section In charge / 2 1 L
/bend on other vehicle signage. Site Engineer
road.
Magnetic Injury due to Injury to 3 3 H Tool box Talk Section In charge / 3 1 L
particle test fall of workmen Skill person shall handle the job. Site Engineer
2. equipment. Property Machine shall be handling as per
Damaged manufacture’s instruction.
Ensure that trained person only
handling the equipment
Page | 2
Sl ACTIVITY HAZARD HAZARD EFFECT IR CONTROL MEASURES Responsibility RR
no
E P R E P R
Manual Back Injury Reduce manual handling and use Section In charge /
Handling Entrap Finger mechanical aids Site Engineer
Hazard Pinch point Follow manual handling procedure
Maintain good communication and
cooperation during team lifting
Conduct tool box talk and discuss
about the pinch point.
Page | 3
Sl ACTIVITY HAZARD HAZARD EFFECT IR CONTROL MEASURES Responsibility RR
no
E P R E P R
Page | 4
Sl ACTIVITY HAZARD HAZARD EFFECT IR CONTROL MEASURES Responsibility RR
no
E P R E P R
g & close of hazard during the activity and at the end of Site Engineer
work for the job
of debris
day Remove all unwanted materials
from the site
6 Emergency Extreme Collapse of 2 2 M Evacuation procedure shall be in Section In charge / 2 1 L
response weather individual, Fire, place Site Engineer
condition, Explosion, Emergency Response action to be
Lack of Unviability of communicated during TBT
supervision, emergency Radio officer to be informed in case
of Emergency
Leakage of vehicle
Ensure emergency vehicle
toxic or arrangement is place
flammable
gases
Page | 5
Page | 6