Method Statement For PEB Work

1) Lloyd Insulations (India) Limited will supply and install a pre-engineered mock up building for Tata Projects Limited at the Noida International Airport site. 2) The scope of work includes structural steel fabrication, roof and wall panel installation, and flashing. 3) Erection will begin with foundation bolt fixing and erecting braced bays, followed by column and rafter installation and connecting all structural members. Roof and wall panels will then be installed along with flashing.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
80% found this document useful (5 votes)
4K views

Method Statement For PEB Work

1) Lloyd Insulations (India) Limited will supply and install a pre-engineered mock up building for Tata Projects Limited at the Noida International Airport site. 2) The scope of work includes structural steel fabrication, roof and wall panel installation, and flashing. 3) Erection will begin with foundation bolt fixing and erecting braced bays, followed by column and rafter installation and connecting all structural members. Roof and wall panels will then be installed along with flashing.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

Lloyd Insulations Quality Management System

(India) Limited Method Statement 14|Aux|JI-7016/QMS-15


New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

0 20.04.2023 Method Statement for PEB Work


Rev. Date: Description

Method Statement for PEB Work

Description Prepared By Reviewed By Approved By


Organization Lloyd Insulations Lloyd Insulations TPL

Name Saurav Jitendra Dadlani

Chakraborty

Designation DGM GM

Signature

Note: This is a ‘Controlled Document’. Any copies – partial or complete must be marked as
“Uncontrolled Copy”. Controlled Copies be obtained from the Quality Control and
Assurance Department with the consent of the Project Manager.

1
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

TABLE OF CONTENTS

Content Page

1. INTRODUCTION
2. SCOPE
3. GENERAL INFORMATION
4. CONDITION OF WORK
5. CHECKING OF FOUNDATION & WORK FRONT
6. ERECTION SEQUENCE
7. TOOLS, TACKLES & EUIPMENTS REQUIRED
8. KEY PROJECT TEAM POSITION AND JOB DESCRIPTION
9. PRE ERECTION PROCEDURE AND CHECK LIST
10. ERECTION PROCEDURE
11. QUALITY INDICATORS AND ACCEPTANCE CRITERIA
12. GENERAL REQUIREMENT OF SAFETY MANAGEMENT
13. CONCLUSIONS

2
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

1) INTRODUCTION:

The scope of the documents is to present the controls of methodology adopted by


M/s. Lloyd Insulations (India) Ltd for construction of Pre-Engineered Building
(hereinafter referred as “PEB”)

M/s. Tata Projects Limited (TPL, hereinafter referred as “Owner”) is going to set
up Pre-Engineered Mock Up building for their client Noida International Airport,
Jewar, UP.

M/s. Lloyd Insulations (India) Ltd (LIIL, hereinafter referred as “Company”) will
supply & install the Pre-Engineered Mock Up building.

2) SCOPE:

Company is responsible for complete Detailed Fabrication drawing preparation,


engineering, fabrication, erection of Pre-Engineered Mock up building complete
with Panel excluding all kind of civil, electrical, Door/ Window & Crane etc.

Building to be executed in accordance to approved engineering drawing by Owner


here under:

a. Structural Work
b. Roof Panel
c. Wall Panel
d. Flashing

3
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

3) GENERAL INFORMATION:

Company will carry out their job at Mock Up building at Noida International Airport
under project site of Client.

Weight age description

Pre-Engineered Mock Up Building : 1 Unit Building

 Structural Steel with building accessories = 90 MT


 Roof PUF Panel- 50mm = 1400 M2
 Wall PUF Panel- 50mm = 1400 M2
 Ridge / Flashing = 209 M2

4) CONDITION OF WORK:

 All Engineering (AB & GA) drawing will be developed by the Owner & shared
to Company for detailed fabrication & subsequent construction work at site.
 All Fabrication drawing & BOQ will be submitted by Company to Owner for
record and subsequently proceed into materials procurement and erection at
site.
 All Construction drawing will be issued by company as developed according to
the approved engineering drawing.
 All materials required to complete the work will be supplied by the Company.
 Construction power and water will be in scope of Owner.
 All related civil work like civil foundation, Brick wall, access roads, hard sand
for crane, storage yard and area of assembly to be provided by Owner in
good level condition.
 Check List, FQP, Work methodology, HSE, daily reports will be according to
the acceptance norms by Owner.
4
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

5) CHECKING OF FOUNDATION & WORK FRONT:

Joint checking has to be done before the start of work and report with
photographs to be prepared for record.

a. Check the Centre to Centre distance of the Installed foundation bolts.


b. Check the diagonal Distance of the centre of installed foundation bolts.
c. Check correct projection above the RCC column and plumb of the anchor bolt.
d. Check the thread condition of all installed foundation bolts.

Stability certificate of RCC Columns should to be issued by the civil agency before
commencement of PEB.

6) ERECTION SEQUENCE:

1. Fixing of Foundation Bolt


2. Erection of Braced Bay columns with cleat fixed onto it at ground.
3. Complete wall brace and runner at braced bay.
4. Assemble the braced rafter on ground and erected cleat fixed on to it.
5. Complete the braced bay with checking proper alignment line and level.
6. Continue column and rafter erection from the erected braced bay.
7. Complete all structural members along with connection bolts, sag rods,
flange brace etc. as per the construction drawing.
8. Touch up painting wherever is required.
9. Installation of Roof Panel.
10. Installation of Wall Panel.
11. Fixing of Flashing etc.
12. Fixing of Opening items i.e. Door, Window, Rolling Shutter by Owner.

5
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

7) TOOL, TACKLES & EQUIPMENTS REQUIRED:

S.N Description / Specification Photo

1 Hydra- 14 MT

2 Wire Rope Sling

3 D-Circle

4 Spirit level

5 Plumb-bob

6 Chalk Line

7 Screw Machine

8 Drill Machine

6
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

9 Hammering Machine

10 Rivet Gun

11 Sheet Cutter (Hand)

12 Round Cutter (Hand)

Jig Saw M/c

13 Sheet Cutting Machines Nibbler

Stone Cutter

14 Level Strip (water level pipe)

7
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

15 Measuring Tape

16 Bit Grinder

17 Drill Bits

18 Sockets

19 Screw driver Set

20 Pliers

21 Line Dori / Plumb Bob

22 P.V.C. Insulation Tape

8
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

23 Sealant Gun

24 Electric Board

25 Electric Wire

26 Manila Rope

27 Pulley

9
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

8) KEY PROJECT TEAM POSITION AND JOB DESCRIPTION :

Roles and Responsibilities.

This section include project specific organization chart identifying the key position
of the organization, along with the organization chart. The organization chart shall
be reviewed and modified as appropriate by the project manager time to time
during the project.

Company will place the best project management team which will be the key to the
success of the project and propose and organization of clearly define the roles and
responsibility accordingly.

The following define the roles and responsibility of the key personnel forming the
part of the project team.

Role Responsibility

Project Manager  Overall responsibility for managing the project.


 Co-ordinate with the Client & Owner.
(At Delhi Head  Project Scheduling & task allocation.
Office)  Project monitoring & status reporting.
 Review project standard of all work.
 Quality metrics collection and reporting
 Project related interface
 Quality assurance and deliverable.
Project –In –  Overall responsibility of execution of the project.
Charge /  Managing the site activities.
 Requirement understanding & analysis.
Construction
 Coordinating all site activities and interacting with owner & client daily
Manager basis.
 Implementing project task set forth by Project manager.
 Overall responsibility for achieving the project milestone.

10
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

 Monitoring and reporting the project progress.


 Perform and deliverable review.
Site Supervisor  Overall responsibility for achieving the project quality requirement.
 Ensuring the conformity of deliverables with requirement
 Indentifying, Reporting and resolving Non Conformities and adopting
the corrective and preventive action.
 Ensuring implementation of corrective and preventive action.
 Rectifying the deliverables in case of defects.
 Interface with Owner Inspector / TPI.
 Responsibility of Inspection, Welding & NDE functions.
 Quality documentation.
Design Engineer  Prepare functional & detail design & drawing.
 Participate deliverable review.
(At Delhi)  Prepare / modify deliverables
 Giving input for resolving non-conformities, as required
 Support acceptance testing
Procurement  Overall responsibility for all project procurements
Engineer  Indentifying, assessing and approving different vendors for
different product / services
(At Delhi Head  Placing purchase orders on selected vendors ensuring that all relevant
information to suitably describe the product/service is incorporated
Office)
in PO.
 Keeping track of orders placed for timely delivery
 Assessing the suppliers performance as regards to quality,
commitment/ delivery, promptness in response etc.
HSE  Overall responsibility for achieving project HSE Requirement.
Coordinator  To prepare, approve, maintain, implement and update project HSE
manual and HSE procedure.
 To prepare, approve and implement Method Statement, Job safety
analysis and obtain acceptance of client.
 Overall responsibility for complying with statutory requirement
 To interact with client’s HSE personnel, as required, on behalf of
company and assist in providing the solutions to HSE related matter

11
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

The Various workmen involve for erection are:

 Engineer
 Supervisor
 Safety Officer
 Fitter
 Rigger
 Helper
 Electrician
 Store/Admin Assistant
 Supervisor (QC)
 Driver
 Security Guard

9) PRE ERCTION PROCEDURE AND CHECK LIST:

Scope:

This system provides a general outline of requirements, which must be concluded


prior to start of project field construction.

General:

These activities are required to take place prior to construction mobilization and
may be broadly classified under two headings:

Project office construction activities, which influence design and procurement pre-
construction related activities that must be concluded prior to start of
mobilization at site.

12
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

The prescribed activities will include both key company construction management
personnel and key management personnel of the selected constructions sub-
contractor(s), who will be operating at field locations.

Other Activities related to constructions are as follows:

i) Materials availability
ii) Materials shifting
iii) Material Preparation
iv) Equipment, machineries and tools availability
v) Electrical Power availability
vi) Workmen availability

i) Material Availability :

All materials related to above job is under scope of the company. On


receipt of materials at site, company will inform Owner for checking and
acceptance.

ii) Material Shifting :

Company will make arrangement for shifting of materials from yard to


work site near locations.

iii) Material Preparation :

The materials required for erection is checked with the erection


drawings. If any defect is observed, same should be corrected under the
guidance of Owner.

13
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

iv) Equipment, Machineries and Tools Availability:

All equipments used for erection are to be assembled by qualified and


experience persons.

Company will ensure the availability of all erection tools required for
erection.

v) Electrical Power Availability:

Electrical power to be provided by the Owner at free of cost near the


erection site area. Further distribution to be done by the company at own
cost.

vi) Workmen Availability:

Company will arrange required manpower for meeting the project


requirement. Safety Induction is compulsory to be done by the company
to all workers before engagement in work.

14
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

10) ERCTION PROCEDURE:

10.1: Methodology of material handling:

1. Material Layout: Materials storage place should be in such way that there
should not double handling. Depending upon the size of the building and
site condition, storage layout should be finalized. Storage layout to be
prepared keeping in mind the Erection Sequence.
2. .Handing & Storage : Structural Materials should be staked above the
ground on wood blocks. The materials should be stored one on another with
in between wood block for safe handling at the time of erection.
All hardware and building accessories materials should be stored under the
cover area to avoid the misplace of stolen of the same.
The colour coated sheet have tendency to become wet from rain, natural
condensation or other causes, patches of white rust may result. While
staking the materials, we should take precautionary steps to avoid the event.
For temporary storing of sheet in open area, then they should be covered
with Tarpaulin or any water proof materials. Never use plastic since it
promotes build up of moisture. If, no cover is available, we to adopt the
special staking methodology as follows.

15
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Panel materials are to be staked on top each other and wooden supports
need to be placed under the bottom panel to provide air space. The top panel
“3” is extended outward at least 900mm and the second panel “2” to be
extended down yard to the near the ground to protect the bunch of panels
“1” below. Cover the upper portion of the sheets “1” by wrapping with
tarpaulin at least 300mm.
The colour coated panel should be kept away from whitewash, cement, lime,
muds etc.

Cautions:
 Avoid twisting of back and lifting a load above the shoulder height.
 Do not try to lift alone any load that is too large or heavy, gloves should be
worn while working.
 Keep tools safely when not in use.
 Helmet, Safety shoes, goggles, filters, respirators and protective cloths
must be worn.
 Smoking is strictly prohibited near store/godown.
 Wire sling to be checked before taking the load
 Clamps and plates required to be handled, should be free from moister and
oil.

10.2: Methodology of Staging:

 Staging or man lift to be arranged wherever required to start the work.


 All scaffolding and other materials intended for staging should be carefully
examined before taking in use.
 All staging should good construction and proper maintained.
 While erecting / dismantling of scaffolding, workmen should wear proper
safety items to avoid accident.
 While Lifting the scaffolding materials, precaution to be taken to avoid
slippage and falling down .

16
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

 No Adjustment in staging should be carried out while workmen are on the


staging.
 All ladders giving access to the staging should be properly secured.
 Barricading of the work front and put safety display to restrict other
agency to enter at working area

10.3: Methodology of Structural Erection:

Step 1:

a) The erection should be started at braced bay.


b) All columns should be erected first in braced bay.
c) Stand the columns in place and secure anchor bolts with initial tightening.
d) Install temporary bracing followed by permanent bracing and secure
bolts/ nuts.
e) Plumb the columns, check all dimensions at base and at tie beam location
and tighten all nuts in sequence.

Step 2:
a) Assemble Roof Rafter components on the ground.
b) Rafter should be aligned and straight before raising roof rafter to
reduce erection time as it is easier to assemble these pieces on ground
than doing it in the air.
c) Install all bolts in rafter splice to the proper tension using turn of nuts
method.
d) Where the bay has rod bracing, ensure the hill side washer is fitted to
have proper nut tightening.
e) While, raising rafter beam into place, keep the sling holding the rafter
until it is securely bolted to the column and bracing and purlins are
installed to hold assembled rigid frame in place.

17
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Step 3:
a) Install eave struts of bay.
b) Install all purlins of the bay.
c) Install all bracing of the bay.

Step 4:
a) Finish alignment of the bay.
b) Check the plumb and square. Use temporary bracing(sling) to align the
bay.
c) When all columns of the bay is perfectly plumb, tighten all anchor bolts,
bracing bolts, eave struts bolts, girt bolts and column to rafter bolt.

Step 5:
a) Erect the consequent bay.
b) The same procedure to be followed.
c) Install at least 1/3 of the quantity of roof purlin and wall girts on the
structure before releasing the temporary bracing (sling).
d) Erect the Jack Beam/ Tube Strut/ crane beam if any.

18
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Step 6:
a) Complete all frames in continuation.
b) Put all secondary structures of the frames on roof & wall.
c) Check all members as per drawing is fitted.

 Refer Construction drawing complete all frame erection with secondary


members, exact quantity and size of the bolts at every connection. All bolts
should be installed and tighten as per the torque chart given by bolt
manufacturers.
 Touch up painting to be done wherever is required.

10.4: Methodology of Fixing Panel:

 Arranging the electrical connection and get it checked by the certified


electrician.
 Cleaning of panel and removing the guard film from the top of the panel.

19
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

 Fixing of panel should be started from one end of the roof or the bottom
line of the wall.
 Fastening the panel by self-drilling & Self tapping type screw using Power
driven screw machine.
 Checking the alignment of the panel.
 Installation of progressive panel maintaining the lapped as mentioned in
drawings. Insert sealing materials inside all end lapped of the panel.
Periodically alignment checking should be done during the fixing of panel.
 Fixing of flashing/ trims as per the drawings. Use of sealing materials inside
the end lap is mandatory.
 Cleaning of Finish Roof & Working Area.
 Housekeeping to be done on daily basis (Evening).

11) QUALITY INDICATORS AND ACCEPTANCE CRITERIA:

Stage wise inspections and final inspection are to be done by Owner as per
approved drawings and acceptance norms.
 Alignment & Level of erected panels are to be checked by Owner.
 All bolting and tightening are to be checked by Owner.
 Technical records are to be reviewed.
 Construction check list should be prepared.

20
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

QUALITY CHECK LIST:

JOB No. Building Name Inspection


Location:

Inspection Date

YES NO

Roof 1.00 Are sheet correctly lap at side & end


Sheeting
2.00 Is the tail line at eave are straight

3.00 Has at end lap mastic been installed

4.00 Have the correct fastener been used

5.00 Have the fastener been fixed at correct location

6.00 Has the roof been cleaned

7.00 Have the sheet been crimped at ridge & Lean to connection

8.00 Have the foam closure been installed

Wall 1.00 Are the sheet fastened in correct location


Sheeting
2.00 Have the correct fastener been used

3.00 Are the sheets plumbed

4.00 Are the sheets correctly lapped

5.00 Are the corner & Trims correctly fitted & Fastened

6.00 Are the Gable trims correctly fitted & Fastened

7.00 Are the external foam closure is fitted at Gable & Eave

8.00 Are the internal foam closure is fitted at Bottom

21
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

General 1.00 Have the work is cleaned off, specially roof & Gutter

2.00 Have all trims & flashing is installed

3.00 Are the flashing is self-draining

4.00 Have the trims been sealed at overlap

5.00 Has the trimming been neatly executed

6.00 Are the flashing in proper line & level

12) GENERAL REQUIREMENT OF SAFETY MANAGEMENT:

 Company is committed to deliver the services to client in an “incident free


injury free” environment under strict rules of Health, Safety and
Environment (HSE).
 This commitment must be understand and freely accepted by all sub-
contractors and sub-contractor personnel who may be associated with this
project in any capacity.
 All HSE requirements and method of implementing the same shall be
addressed in project HSE plan. The project HSE plan shall incorporate
client’s regulations & procedures and represent the minimum requirements
for all sub-contractors performing the project related work. The company’s
policy, procedures and regulations shall, in all instances, exceed or equals
those referenced in the plan.
 The HSE plan shall be communicated at every level within the organization.
Management’s commitment to HSE issues shall be highly visible to the
organization.
 The systems shall define accountability of achieving HSE goals and
objectives at levels of the organizations.
 Ensure demonstrable, active employee involvement in the system.
 Include provision of share learning across the organization.
 Require periodic reporting o management.

22
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Necessary Measures:

 Before the construction of panel, personnel must know safety and technical
work. Construction personnel should be clearly aware the construction task,
construction requirement and construction attention, they can construct
after their sign them name.
 Construction persons enter site must be with helmet & Safety shoe. Drinking
any alcohol is strictly prohibited inside the premises of project.

Construction personnel prior to climb up every day, should check the security
products and the safety protection facilities such as scaffolding, Only confirm
that there is no danger then start the next step work, steel structure
construction process, aerial worker must pierced seat belt and confirmed hanging
above the reliable components before carrying out the work.

Construction of power supply installed by professional electrician, people who isn’t


professional electrician is prohibited to install wiring for power supply, workers
carry or transfer electromotive spanner only without carrying power lines.

In the rain, fog and severe weather, it don’t allow hoisting assignment Construction
personnel should pay attention to skid, wearing slippers are not allowed in CHP
area, when the winds reach more than 5 in the job site, construction personnel
should stop lifting operations.

On-site installation personnel shall designate personnel to unify command, command


signal should be unified, and the signal is clear, definite division.

Hosting wire rope must be intact and meet the lifting load requirements in each
lifting equipments, weigh equipment should be recognized, in accordance with the
requirements select the wire rope a fast mouth edges parts should add wrapping
angle which can prevent to cut the wire rope.
23
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Lifting work area irrelevant personnel do not stay or go through, in the arms
outstretched and hanging objects prohibited anyone to stay or go through. When
lifting Steel structure, installation personnel must pull rope to set alert around the
Frame furnace, extra personnel shall not enter.

During the construction and installation, the job must be strict executed the one-
on-one safety monitoring system; ensure construction personnel should be safety
controlled in construction process.

DAILY SAFETY CHECK LIST:

JOB No. Induction Location:

Induction Date

YES NO

1.00 Check the availability Insurance policy i.e. CAR, ESI, WC etc.

2.00 Are all lifting equipments in good condition

3.00 Are all access equipment like scaffolding, ladder are in good
condition

4.00 Are all personal safety equipment in good condition

5.00 Are all electrical equipments in good condition & properly

24
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

insulated.

6.00 Is the work front safe for execution/ Work permission is


available from Owner

7.00 Check the condition of life line support at work front

8.00 Are all workers physically fit for the work

9.00 Check the weather condition

10.00 Check all workers are equipped by personal safety equipments

11.00 Ensure the working area are barricaded to restrict entry of


others

12.00 Have all workers proper knowledge of working area regarding


nearby working of other agency & evacuation route in case of
emergency.

13.00 Ensure all workers are adopting proper safety while sitting &
movement at height.

14.00 Is the workers are moving on valley of the Roof sheet, not
stepping on crest.

15.00 Is the site cleaned & tidy by daily housekeeping at the end of
work

16.00 Are all materials properly tied & covered in bundles at


specified locations near the work front

25
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

List of General Safety Equipment

S.N Description / Specification Photo

Helmet ( Ordinary / Special )


1

Safety Belt ( Half Body / Full Body )


2

Safety Ribbon ( RED / YELLOW )


3

Nose Mask
4

Safety Goggles
5

Safety Ear Plug


7

Hand Gloves
8

Sign Boards
9

Safety Shoes
10

26
Lloyd Insulations Quality Management System
(India) Limited Method Statement 14|Aux|JI-7016/QMS-15
New Delhi Revision : 0
for PEB Work
Mock Up Building for M/s Tata Projects Limited, Noida
Project:
International Airport, Jewar Noida, UP

Fall Arrester
11

Safety Ladder
12

Safety Net
13

Man Lifter
14

13. Conclusion:

In this procedures mentioned above, the erection of Structural building / Panel


is alone considered. All the procedures mentioned are tentative. However if
any better procedure are met, the same will be followed to enhance the
erection.

Always the best possible procedure for erection with safety, Quality and in
time is maintained by Lloyd Insulations (India) Ltd.

--END--
-------