Engineering Design - Capability Statement - August 15 2017 - Lowres
Engineering Design - Capability Statement - August 15 2017 - Lowres
www.brightwater.co.nz
Minimise risk and ensure your project’s
success by selecting an experienced
team utilising the latest technology to
deliver fit for purpose design solutions.
ZEROHARM
ALL ACCIDENTS ARE PREVENTABLE
Engineering Design Process
The engineering design process is flexible and adapted to meet client’s individual requirements and the
size or complexity of any given project, however the following process is an example of a typical design
process that may be followed for a significant project:
Concept Development
Feasibility Studies
• Basis of Design Created & Approved • Specifications for, and Evaluation of,
• Lead Engineer & Design Team Selected Proprietary Equipment for Procurement.
• Finalise General Arrangements, Process • Electrical Supply & Service Reticulation
Flow Diagrams & Piping/Instrument Design
Diagrams • Mechanical equipment Modeling &
• Create an Interactive Project Model Design Review
• Define all Design Elements • Manufacturing Drawings & Bills of
• Engineering Calculations and Analysis Materials
• Design Development Specifying Scope • Civil Drawings for Foundations, Concrete
for all Design Elements Works, Buildings, Infrastructure,
• Design Process Controls, Automation & Drainage & Roading etc.
SCADA • Hazard & Operability Studies (HAZOP)
• Create Lists/Schedules for Equipment, • Statutory Certification & Producer
Piping, Instruments, Cables, and Motors Statements
etc. • Document Management & Control
• Operations Manuals
• Engineering Advise for Manufacturing
• Maintenance Manuals
• Engineering Supervision
• As Built Drawings
• Installation Drawings & Methodology
• Document Archiving
• Installation Bills of Materials
• Lifting Plans
• Electrical Testing & Certification
• Structural Certification
• Safety & Hazard Audits
Project Examples
Higgins Meremere Plant Upgrade
Overview:
Higgins Aggregates supplies over two million tonnes of aggregates per year throughout New Zealand. Located near Te Kauwhata in the Waikato, Higgins
Meremere Quarry supplies high PSV aggregates to the road construction industry. In an initiative by the company to drive greater efficiencies, the Meremere
Quarry was required to undergo a transformation from diesel powered mobile equipment to a new fully electric fixed plant.
Solution:
Brightwater was contracted to design, manufacture and install a purpose built fully electric plant that utilised existing tracked mobile equipment on site to
help reduce costs. The Design was a joint collaboration between Brightwater and Higgins. Brightwater completed a high level concept sketch and used three
dimensional modelling to capture and communicate the most efficient solution given the challenging topography of the quarry site.
The result of this design lead to a modular plant where mobile equipment was fixed into position, extra conveyors were added along with larger more efficient
screening plant. The design increased production from approximately 60 tonne per hour up to 180 tonne per hour capacity.
A new elevated feed bin was also designed to allow 30 tonne dump trucks to provide continuous feed material into the plant at a set rate.
The entire process from design concept to site installation and commissioning was completed within an eight month time frame.
Overview:
Nelson Pine Industries Ltd engaged Brightwater to design and supply a new outfeed stacking deck for their Line 1 MDF press to handle larger pack sizes. The
MDF press produces a range of MDF products in different thicknesses and sizes and the finished sheets must be stacked, squared and fed out without any
slowing or stopping of the press.
Solution:
Due to space constraints and the requirement to handle the larger pack size, the stacking deck design had to be completely different to the existing stacking
deck. The new stacking deck that was designed included automated variable side alignment rams to allow for board sizes ranging from 3m to 5.1m. Quick
acting lifting deck driven off a single hydraulic ram able to raise and lower the deck within 6 seconds and driven outfeed decks capable of feeding out a
complete pack within 10 seconds.
The brief was to design a new stacking deck capable of handling board packs up to 1.35m thick which would reduce forklift movements on site. Brightwater
achieved this with the design but also managed to produce a stacking deck significantly simpler in operation to the existing with fewer moving parts and which
took up a smaller footprint on site. The quality of design meant the both the fabrication and installation went together smoothly with zero rework required on
site.
Project Examples
Stockton Coal Handling & Processing Plant
Overview:
Solid Energy New Zealand operates an open-cast coal mine on the Stockton Plateau, 35km north of Westport, on the West Coast of the South Island, New
Zealand. The Stockton mine produces high-quality coal for export to the steelmaking industry. In 2008 Solid Energy New Zealand engaged Brightwater as the
head contractor to design, procure, and manage fabrication and construction of the green-fields Coal Handling and Processing Plant project, all within a fast-
track schedule.
Solution:
Brightwater’s Design team’s contribution was the design of the Coal Handling Plant (CHP) to support the Coal Preparation Plant (CPP) in-feed and product
out-feed. This comprised of a ROM station with rotary breaker, two feed conveyors, a surge bin, thickener (for CPP), and four product stockpile conveyors.
A key design challenge was the high wind speeds at the Stockton site which would result in high loadings on conveyor truss sections of rectangular profile.
Brightwater designed totally enclosed circular cross-section conveyors, with a resultant drag force coefficient 40% lower than those of the rectangular type.
The site layout also called for long conveyor spans; traditionally square gallery style conveyors would be specified but the required size and leg spacing proved
costly. Brightwater’s innovation was the introduction of tubular gallery sections for the CPP feed conveyors, which offered significant cost savings to the client.
A new elevated feed bin was also designed to allow 30 tonne dump trucks to provide continuous feed material into the plant at a set rate.
The entire process from design concept to site installation and commissioning was completed within an eight month time frame.
Overview:
Fulton Hogan (FH) were awarded a contract to repair and reline the Tekapo Canal. This project required a new replacement liner to be placed through a seven
kilometre section of canal that had been leaking water. As a part of replacing the liner, FH’s scope of work required 20-200mm river run rock (AP 200-20 MM0)
to be placed on top of a 10mm thick geotextile mat that directly covered the 2.5 mm thick geo-composite PVC membrane liner. This placement of the rock acts
as ballast to keep the liner firmly located on the base and inverts of the canal.
The challenge for Fulton Hogan was to deliver this ballast material from the top section of the invert, which was several metres higher than the canal floor
and the deliver the ballast 25 metres out into the centre of the canal floor. This had to be accomplished whilst ensuring the newly laid PVC canal floor was not
damaged in the process.
Solution:
The Brightwater Design team worked closely with Fulton Hogan’s operational staff to develop several engineered solutions before settling on a combination of
newly applied technologies and proven mobile plant technologies. The process created was a Gravel Feeder mobile machine that accepted 30 tonne payloads
from articulated dump trucks into a specifically designed steel constructed mobile bin. The product was then retrieved from the bin via a 20 tonne excavator
and delivered into a hopper located on a specifically designed trailer mounted hopper. The hopper then fed the product directly onto a belt feeder conveyor in
turn delivering the product onto a declining conveyor down to the centre of the canal floor. The process created a delivery rate of 2000 tonnes per day.
Nelson Greymouth Auckland
Physical Address: 7 Spencer Place Brightwater, Nelson, 7022 Physical Address: 69 Jacks Road, Greymouth, 7805 Physical Address: 6 George Bourke Drive, Mt Wellington, Auckland 1060
Postal Address: PO Box 43, Brightwater, Nelson 7051 Postal Address: PO Box 138, Greymouth 7840 Postal Address: PO Box 132 072, Sylvia Park, Auckland 1644
Phone: +64 (3) 768 5374 Phone: +64 (9) 480 8409
Phone: +64 (3) 543 5300
Fax: +64 (3) 768 5379 Fax: +64 (9) 480 8109
Fax: +64 (3) 543 5301
Email: [email protected] Email: [email protected]
Email: [email protected]
Website: www.brightwater.co.nz Website: www.brightwater.co.nz
Website: www.brightwater.co.nz