C BRICK WORK
BASIC PRICES
Skilled Labour Rs. 0.00 per day
Un Skilled Labour Rs. 0.00 per day
Cement Rs. 770.00 cube.
Sand Rs. 6,500.00 cube.
Water Rs. 0.00 gall.
Bricks Rs. 5.00 no.
Overheads & profit. 0 %
C BRICK WORK
C. 01 One brick thick brick wall in common brick Cube Rs. 12,955.00
in cement and sand 1 : 5 in ground floor..
C. 02 One brick thick brick wall in common brick
in cement and sand 1 : 5 in first floor.. Cube Rs. 12,955.00
C. 03 One brick thick brick wall in common brick
in cement and sand 1 : 5 in second floor.. Cube Rs. 12,955.00
C. 04 Half brick thick brick wall in common brick
in cement and sand 1 : 5 in ground floor. Sqr. Rs. 5,105.00
C. 05 Half brick thick brick wall in common brick
in cement and sand 1 : 5 in first floor. Sqr. Rs. 5,105.00
C. 06 Half brick thick brick wall in common brick
in cement and sand 1 : 5 in second floor. Sqr. Rs. 5,105.00
C. 07 9 " x 9 " brick columnin cement and sand
1 : 5 in ground floor. l. ft. Rs. 83.60
C. 08 9 " x 9 " brick columnin cement and sand
1 : 5 in first floor. l. ft. Rs. 83.60
C. 09 9 " x 9 " brick columnin cement and sand
1 : 5 in second floor. l. ft. Rs. 83.60
C. 10 12 " x 12 " brick columnin cement and sand
1 : 5 in ground floor. l. ft. Rs. 114.73
C. 11 12 " x 12 " brick columnin cement and sand
1 : 5 in first floor. l. ft. Rs. 114.73
C. 12 12 " x 12 " brick columnin cement and sand
1 : 5 in second floor. l. ft. Rs. 114.73
C. 13 One brick thick brick wall in common brick in
cement and sand 1 : 5 in ground floor sqr. Rs. 9,810.00
C. 14 One brick thick brick wall in common brick in
cement and sand 1 : 5 in first floor sqr. Rs. 9,810.00
C. 15 One brick thick brick wall in common brick in
cement and sand 1 : 5 in second floor sqr. Rs. 9,810.00
BRICK WORK
C. 01 One brick thick brick wall in common brick in cement
and sand 1 : 5 in ground floor level
1 Cube
Materials
1650 no Bricks at. Rs. 5.00 Rs. 8,250.00
4.00 bag Cement at. Rs. 770.00 Rs. 3,080.00
0.25 cube Sand at. Rs. 6,500.00 Rs. 1,625.00
75 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 12,955.00
Labour
2.00 day Mason at. Rs. 0.00 Rs. 0.00
2.50 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Add
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
12,955.00
Overheads & profit. Rs. 0.00
Cost for one cube with overheads & profits. Rs. 12,955.00
C. 02 One brick thick brick wall in common brick in cement and sand 1 : 5
in first floor
1 Cube
Materials
1650 no Bricks at. Rs. 5.00 Rs. 8,250.00
4.00 bag Cement at. Rs. 770.00 Rs. 3,080.00
0.25 cube Sand at. Rs. 6,500.00 Rs. 1,625.00
75 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 12,955.00
Labour
2.25 day Mason at. Rs. 0.00 Rs. 0.00
3.00 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Add
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
12,955.00
Overheads & profit. Rs. 0.00
Cost for one cube with overheads & profits. Rs. 12,955.00
C. 03 One brick thick brick wall in common brick in cement and sand 1 : 5 in
second floor
1Cube
Materials
1650 no Bricks at. Rs. 5.00 Rs. 8,250.00
4.00 bag Cement at. Rs. 770.00 Rs. 3,080.00
0.25 cube Sand at. Rs. 6,500.00 Rs. 1,625.00
75 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 12,955.00
Labour
3.00 day Mason at. Rs. 0.00 Rs. 0.00
3.25 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
12,955.00
Overheads & profit. Rs. 0.00
Cost for one cube with overheads & profits. Rs. 12,955.00
C. 04 Half brick thick brick wall in common bricks in cement
and sand 1 : 5 in ground floor
1 sqr.
Materials
660 no Bricks at. Rs. 5.00 Rs. 3,300.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
25 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 5,105.00
Labour
1.25 day Mason at. Rs. 0.00 Rs. 0.00
1.50 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
5,105.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 5,105.00
C. 05 Half brick thick brick wall in common bricks in cement
and sand 1 : 5 in first floor
1 sqr.
Materials
660 no Bricks at. Rs. 5.00 Rs. 3,300.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
25 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 5,105.00
Labour
1.50 day Mason at. Rs. 0.00 Rs. 0.00
2.00 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
5,105.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 5,105.00
C. 06 Half brick thick brick wall in common bricks in cement
and sand 1 : 5 in second floor
1 sqr.
Materials
660 no Bricks at. Rs. 5.00 Rs. 3,300.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
25 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 5,105.00
Labour
1.75 day Mason at. Rs. 0.00 Rs. 0.00
2.25 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
5,105.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 5,105.00
C 07 9 " x 9 " brick column in cement and sand 1 : 5 in ground floor.
10 no columns 5' 0" high
50.00 l. ft.
Materials
475 no Bricks at. Rs. 5.00 Rs. 2,375.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
50 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 4,180.00
Labour
1.50 day Mason at. Rs. 0.00 Rs. 0.00
1.25 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
4,180.00
Preliminaries Rs. 0.00
Rs. 4,180.00
Cost for one l. ft. with overheads & profits. Rs. 83.60
C 08 9 " x 9 " brick column in cement and sand 1 : 5 in first floor.
10 no columns 5' 0" high 50.00 l. ft.
Materials
475 no Bricks at. Rs. 5.00 Rs. 2,375.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
50 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 4,180.00
Labour
1.50 day Mason at. Rs. 0.00 Rs. 0.00
1.50 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
Rs. 4,180.00
Overheads & profit. Rs. 0.00
Rs. 4,180.00
Cost for one l. ft. with overheads & profits. Rs. 83.60
C 09 9 " x 9 " brick column in cement and sand 1 : 5 in second floor.
10 no columns 5' 0" high 50.00 l. ft.
Materials
475 no Bricks at. Rs. 5.00 Rs. 2,375.00
1.50 bag Cement at. Rs. 770.00 Rs. 1,155.00
0.10 cube Sand at. Rs. 6,500.00 Rs. 650.00
50 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 4,180.00
Labour
1.75 day Mason at. Rs. 0.00 Rs. 0.00
1.75 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
4,180.00
Overheads & profit. Rs. 0.00
Rs. 4,180.00
Cost for one l. ft. with overheads & profits. Rs. 83.60
C 10 12"x12 " brick column in cement and sand 1 : 5 in ground floor.
6 no columns at 5 " 0 " high 30.00 l. ft.
Materials
415 no Bricks at. Rs. 5.00 Rs. 2,075.00
1.10 bag Cement at. Rs. 770.00 Rs. 847.00
0.08 cube Sand at. Rs. 6,500.00 Rs. 520.00
60 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 3,442.00
Labour
1.00 day Mason at. Rs. 0.00 Rs. 0.00
1.00 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
3,442.00
Overheads & profit. Rs. 0.00
Rs. 3,442.00
Cost for one l. ft. with overheads & profits. Rs. 114.73
C 11 12 " x 12 " brick column in cement and sand 1 : 5 in first floor.
6 no columns at 5 " 0 " high 30.00 l. ft.
Materials
415 no Bricks at. Rs. 5.00 Rs. 2,075.00
1.10 bag Cement at. Rs. 770.00 Rs. 847.00
0.08 cube Sand at. Rs. 6,500.00 Rs. 520.00
60 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 3,442.00
Labour
1.25 day Mason at. Rs. 0.00 Rs. 0.00
1.00 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
3,442.00
Overheads & profit. Rs. 0.00
Rs. 3,442.00
Cost for one l. ft. with overheads & profits. Rs. 114.73
C 12 12 " x 12 " brick column in cement and sand 1 : 5 in second floor.
6 no columns at 5 " 0 " high. 30.00 l. ft.
Materials
415 no Bricks at. Rs. 5.00 Rs. 2,075.00
1.10 bag Cement at. Rs. 770.00 Rs. 847.00
0.08 cube Sand at. Rs. 6,500.00 Rs. 520.00
50 gal. Water at. Rs. 0.00 Rs. 0.00
3,442.00 Rs. 3,442.00
Labour
1.25 day Mason at. Rs. 0.00 Rs. 0.00
1.50 day Un skilled labour at. Rs. 0.00 Rs. 0.00
0.00 Rs. 0.00
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
3,442.00
Overheads & profit. Rs. 0.00
Rs. 3,442.00
Cost for one l. ft. with overheads & profits. Rs. 114.73
One brick thick brick wall in common brick in cement
C 13
and sand 1 : 5 in ground floor level
1 sqr.
Materials
1240 no Bricks at. Rs. 5.00 Rs. 6,200.00
3.00 bag Cement at. Rs. 770.00 Rs. 2,310.00
0.2 cube Sand at. Rs. 6,500.00 Rs. 1,300.00
125 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 9,810.00
Labour
2.00 day Mason at. Rs. 0.00 Rs. 0.00
2.25 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Add
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
9,810.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 9,810.00
C 14 One brick thick brick wall in common brick in cement
and sand 1 : 5 in first floor level
1 sqr.
Materials
1240 no Bricks at. Rs. 5.00 Rs. 6,200.00
3.00 bag Cement at. Rs. 770.00 Rs. 2,310.00
0.2 cube Sand at. Rs. 6,500.00 Rs. 1,300.00
125 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 9,810.00
Labour
2.75 day Mason at. Rs. 0.00 Rs. 0.00
3.25 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Add
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
9,810.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 9,810.00
C 15 One brick thick brick wall in common brick in cement
and sand 1 : 5 in second floor level
1 sqr.
Materials
1240 no Bricks at. Rs. 5.00 Rs. 6,200.00
3.00 bag Cement at. Rs. 770.00 Rs. 2,310.00
0.2 cube Sand at. Rs. 6,500.00 Rs. 1,300.00
125 gal. Water at. Rs. 0.00 Rs. 0.00
Rs. 9,810.00
Labour
2.75 day Mason at. Rs. 0.00 Rs. 0.00
3.50 day Un skilled labour at. Rs. 0.00 Rs. 0.00
Rs. 0.00
Add
Tools
3 % of labour cost Rs. 0.00
Scaffolding
5 % of labour cost Rs. 0.00
9,810.00
Overheads & profit. Rs. 0.00
Cost for one sqr. with overheads & profits Rs. 9,810.00