E C M 5 78 - C ONTR A CT A DM INISTRATION
Construction
Contract
Types of
G R OU P 2 | 7 C 1
Presentation Outline
Building Construction Contracts Type
Today's Topics
E C M 5 78 - C ONTR A CT A D M INISTRATION
Common Contract Procurement Methods
Construction Project / Contract Participants
Standard Forms of Contract
Factors in Considering Type of Contract
01
E C M 5 78 - C ONTR A CT A D M INISTRATION
1 2 3
Lump Measurement Cost
Sum Contract Reinbursement
Price is fixed,
payment made
No individual only once after
rates quoted for project
each item of executed No BQ is
work provided
E C M 5 78 - C ONTR A CT A DM INISTRATION
Suitable for
simple project
What is Higher risk to
owner ;
Example :
Bridge Painting
Lump Sum? contractor rate
items are not
specified
Lesser time Contractor will
needed to reduce his cost
prepare tender to increase his
document profit
No provision to
vary the
contract,
proceed even if
the actual work
executed differs
in quantity
E C M 5 78 - C ONTR A CT A D M INISTRATION
• Apply when the design / type of works can be
described in reasonable detail
• Allow an early start on site, before design is
completed and allow changes to be made
• Accurate
• Quantities of each item of work • Document with schedule of item, but need to enter price
• 'Contract Price' is the sum total of prices of each item of work mentioned in • Document with schedule of item with price. Can choose to agree
BQ or quote a percentage
• BQ assist in keeping tenders figures as low as possible • Both type above will include approximate quantities to be
• Payments are generally made on the basis of the actual measured quantity executed for each item of work
of work executed for each item in the BQ and the rate quoted • Suitable for maintenance, jobbing, urgent works
E C M 5 78 - C ONTR A CT A D M INISTRATION
BILL OF
QUANTITIES
MEASUREMENT SCHEDULE OF
R AT E
CONTRACT
Advantages and Disadvantages
Adantages and Disadvantages
• Variation in quantities are easily accommodated
• Can identify particular items on which to reduce the cost
• Experienced engineer able to forecast the type of work
• All the work schedule will be carried out
without drawing
• Lesser risk to owner and contractor, payment are exactly to the rate
• Lesser time spends to prepare BQ
quoted
• No implied guarantee given all work will be carried out
• Quantities stated is abstract from drawings, which have certain level of
• Quotation might be high since the volume of work is
accuracy of work executed
uncertain
• A lot of time spends to prepare BQ
• No guarantee as quantities indicates estimate amount
Provide data for
cost analysis for
use in cost
planning for
Future
Price Data
future projects Project
Base prices on
Comparable
the same
information,
thus tenders are
Why BQ usually
E C M 5 78 - C ONTR A CT A DM INISTRATION
strictly Basis Payment
comparable
used in Provide a convenient
basis for valuation of
Malaysia?
During
certificated stage
payments during the
contract, before the
accurate figure Convenient
(actual) is available
Provide an
Provide a fair
Checklist Before actual
approximate
checklist for the basis for valuing
contractor to order variations and
materials and adjustments for
other resources the final account
Material Adjustment
E C M 5 78 - C ONTR A CT A DM INISTRATION
Example Bill of Quantities
• Charges an agreed fee in
terms of % of the cost of
the actual work executed
• Use in emergency &
small project; kitchen
renovation
E C M 5 78 - C ONTR A CT A DM INISTRATION
• An agreed sum paid
to contractor will be • Fee paid to contractor
the actual cost in based on some of sliding
execution works plus scale
fixed fee and does
not fluctuate
• Actual fee paid to the
contractor is by
Suitable Project :
increasing/reducing the basic
Maintenance and
fee by an agreed percentage
Emergency work
• Suitable for project that both
parties will gain benefit
Eg; Bridge Collapsed
E C M 5 78 - C ONTR A CT A DM INISTRATION
Target + Cost
Cost + Fluctuating Fee
Cost + Percentage Cost + Fixed Target + Cost
Encourage contractor to
Allow contractor to Contractor not inclined to execute work as cheaply
involve in design stage push up the cost as possible
E C M 5 78 - C ONTR A CT A DM INISTRATION
Contractor can confident
If work accelerated, Fluctuation cost is shared
an equitable payment for
contractor will received and owner have flexibility
changes and unforeseen
fixed fee early to involve in the project
event
Dishonest contractor Contractor may reduce
No incentive to complete
could increase the the cost of supervision,
the work as quick as
contract price to increase expedite the work,
possible
his profit neglecting correct
construction process to Contractor try to reduce the
No incentive to complete increase profit cost of supervision, expedite
the work early or to try to with the work, neglecting
reduce the cost the correct construction
process
02
E C M 5 78 - C ONTR A CT A D M INISTRATION
1 2 3 4
Traditional / Design and Build Construction Others
Design-Bid-Build Method Management
E C M 5 78 - C ONTR A CT A DM INISTRATION
(by bidding)
documents
completed
Tender
Advantages Disadvantages
Provide opportunities for the contractors to bid Time consuming
The design and cost are certainty Contractor not be able to improve the
E C M 5 78 - C ONTR A CT A DM INISTRATION
design
Ensure quality of material used Contractor has little flexibility to manage
the price
Owner is protected
Government
E C M 5 78 - C ONTR A CT A DM INISTRATION
KLCC Holdings Sdn Bhd
Ranhill Bersekutu
1)Hazama Corporation
1)Samsung Engineering &
Construction
E C M 5 78 - C ONTR A CT A DM INISTRATION
Advantages Disadvantages
Can reduce the time of overall Unexpected Cost
project delivery
Direct contact client to developer Less supervision from owner
E C M 5 78 - C ONTR A CT A DM INISTRATION
All risks (design) are on developer Financial risk on developer
Developer can save cost (economical design) Developer might charge extra fees on
consultant's fees
Good communication and collaboration in a
team
Putrajaya
Corporation
E C M 5 78 - C ONTR A CT A DM INISTRATION
KLCC Project
Bhd
1)Putrajaya
Holdings
E C M 5 78 - C ONTR A CT A DM INISTRATION
(by bidding)
Advantages Disadvantages
Can save time
Ability to closely manage cost during No cost certainty
E C M 5 78 - C ONTR A CT A DM INISTRATION
design
Can ensure the quality and performance of Reliance on management capability of
work construction manager
Minimize impact of change Risk on client
What is the
difference?
E C M 5 78 - C ONTR A CT A DM INISTRATION
Consultant
Design
Consultant
Client Client Construction
Client Developer
Manager
Contractor Construct
Trade
Contractors
E C M 5 78 - C ONTR A CT A DM INISTRATION
Let's Recap!
BUILD OPERATE TRANSFER
Private entity receives
Advantages Disadvantages
concession from public sector
Minimizes public cost Only works for large projects
E C M 5 78 - C ONTR A CT A D M INISTRATION
Suitable for large-scale
infrastructure projects Reduce public debt Place the public sector at a
disadvantage
Private party manage the finance, Allow public sector funds Requires strong corporate
design, construction and operate
the facility. the most needed governance
BOT : Project Timeline
SELECTION
• Prequalification CONCESSION PERIOD
• Investors,
Proposals
• Preliminary work
E C M 5 78 - C ONTR A CT A D M INISTRATION
• Evaluation of
Proposals CONSTRUCTION TRANSFER
• Revised
• Execution • Transfer
Concession
• Delivery
Agreement
PRELIMINARY PROJECT OPERATION
STUDY IMPLEMENTATION
• Initiative • Maintenance
• Final work
• Feasibility Study and Operation
• Final
• Preliminary Concession
Concession Agreement
Agreement
Advantages Disadvantages
E C M 5 78 - C ONTR A CT A D M INISTRATION
Less construction time Time taking
PFI is a type of Public Private Partnership
procurement method implemented in UK
construction industry in 1992. Delivery against budget Risk allocation
PFI requires private financers to put its own
capital at risk to deliver clearly defined public Innovation approach
projects for long-term period, ensuring the quality
of work delivered within time and budget.
03
E C M 5 78 - C ONTR A CT A D M INISTRATION
E C M 5 78 - C ONTR A CT A DM INISTRATION
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
04
E C M 5 78 - C ONTR A CT A D M INISTRATION
1 2 3
Government / Private International
Public Sector Sector Sector
A printed form and published by an
authoritative body on industry which
E C M 5 78 - C ONTR A CT A DM INISTRATION
recognized by both parties. The forms is set
of terms and conditions which need to be GOVERN/
PUBLIC
carried out by those parties
SECTORS
PRIVATE
INTERNATIONAL
E C M 5 78 - C ONTR A CT A D M INISTRATION
E C M 5 78 - C O NTR A CT A D M INISTRATION
E C M 5 78 - C ONTR A CT A D M INISTRATION
E C M 5 78 - C O NTR A CT A D M INISTRATION
E C M 5 78 - C O NTR A CT A D M I NI STRATI O N
E C M 5 78 - C ONTR A CT A D M INISTRATION
05
E C M 5 78 - C ONTR A CT A D M INISTRATION
TIME EXTERNAL
CONSTRAINT FACTORS
E C M 5 78 - C ONTR A CT A DM INISTRATION
COST FACTORS CLIENT
ISSUES RESOURCES
PROJECT ABILITY TO
CHARACTERISTICS MAKE
CHANGES