ABB 66kV EDF Manual
ABB 66kV EDF Manual
Product Manual
1HYB 800001-25 Rev. A
EDF SK 1-1
with operating mechanism
Type FSA
Product Manual
1
HIGH VOLTAGE CIRCUIT-BREAKER-TYPE
ED 1 H Y B 8 0 0 0 0 1 - 2 6
FUNCTIONAL VALUES
1HYB800001-27
2
LUBRICANTS
1HYB800001-28
3
LOCKING LIQUID FOR THREADS
1HYB800001-29
4
GENERAL INSTRUCTIONS FOR
MAINTENANCE, TRANSPORT & STORAGE
1HYB800001-30
5
GOODS MARKING AND TRANSPORT
1HYB800001-31
6
STORAGE PRIOR TO ERECTION
1HYB800001-32
7
INFORMATION
SF6 GAS AND GAS MIXTURES
1HYB800001-33 8
SAFETY REGULATIONS
1HYB800001-35
9
DISPOSAL AND RECYCLING
1HYB800001-36
10
INSTRUCTIONS FOR ERECTION,
OPERATION AND MAINTENANCE
1HYB800001-37
11
INSTRUCTIONS FOR OPERATION
AND MAINTENANCE OPERATING
MECHANISM TYPE FSA -
1HYB800001-38
12
1HYB800001-26 Rev. A
Page 1
The circuit-breaker is built up of three separate poles, which consist of three main
parts. At the bottom the mechanism housings made of aluminium. The hollow post
insulators through which operating insulators run and on top the breaking units. Each
breaking unit consists of a hollow insulator which together with an upper and a lower
flange constitute the casing and a lower and an upper current path with a contact
system. The moving contacts are assembled on the lower current path whereas the
fixed contacts are assembled on the upper one.
The circuit-breaker poles to ED SK are permanently filled with SF6 - gas, normally to
the pressure 0.7 MPa absolute at 200C. For monitoring the pressure the circuit-
breaker is equipped with a density monitor. The poles are mounted on a common
supporting frame, consisting of a front and a rear pole beam. The latter is mounted
on two supports which are anchored to the foundations. The beams and supports are
hot-dip galvanized.
The pressure rise and gas flow which are necessary for extinguishing the arc during
the course of breaking are produced partly by compression of the gas, partly by the
energy given from the arc.
At the opening operation the moving contact is pulled downwards over the fixed
piston and the confined quantity of gas is compressed and at high speed forced out
through the springs in the upper end of the cylinder. At the same stage the arcing
contacts are separated and an arc occurs. A specially formed nozzled leads the
outflowing gas towards the arc. The gas is allowed to pass both downwards through
the moving arcing contact and upwards past the fixed arcing contact.
For the continuous current there are separate contacts which are not affected by the
arc at breaking.
At closing operation the moving contact is pushed upwards at which time the con-
tacts engage and the cylinder is filled with gas again.
Functional Values
SF6 CIRCUIT-BREAKER TYPE ED-SK 1-1 WITH OPERATING MECHANISM TYPE
FSA 1
*) Close - Open time means the time during which the main contacts are closed at a
closing operation when the tripping impulse is connected in simultaneously, via
the auxiliary contact.
1HYB800001-28 Rev. A
Page 1
Grease “G” :
Low temperature grease for all types of bearings, gears and worm gears as well as
valves in air-blast circuit-breakers. Also suitable for lubrication of silverplated con-
tacts in air (e.g. contacts in disconnectors).
Also used when greasing O-rings made from nitrile rubber and as a crevice corrosion
prevention.
Grease “N” :
For lubrication of moving contacts in SF6-insulated circuit breakers (e.g. puffer
cylinders). A very thin layer of the grease shall be rubbed on the sliding surface of
the contacts.
Grease “L” :
Low temperature grease specially suitable for lubricating of fine mechanics-e.g. catch
devices in operating mechanism which shall operate in strong cold.
Grease “M” :
Low temperature grease for long-duration and permanent lubrication of worm gears
and other machine elements. Prevents wear and corrosion.
Grease “P” :
Grease “R” :
EP-grease for heavily-loaded roller bearings, slide bearings, cam discs and catches
(Lithium grease. Solvent refined mineral oil with lithium soaps and molybdenum
disulphide) in operating mechanisms type FSA.
Grease “S” :
Fluoro-silicone grease for greasing of O-ring made from EPDM and as a corrosion
prevention of gaps in circuit-breakers type ED.
Grease “SV”
Grease for lubricating moving contacts, silver plated connections and brushed
aluminium surfaces in fixed joints outdoors.
1HYB800001-28 Rev. A
Page 3
1HYB800001-29 Rev. A
Page 1
Pre-treatment of surfaces : The surfaces shall be free from oil, grease, wax, paint and
rust-preventive. Locking Liquids “A”, “B” and “C” are designed for use in only surfaces
also.
Locking Liquid “B” : Medium strong locking of threads and sealing of screws and
nuts.
Locking Liquid “C” : Strong locking and sealing of studs and bolts up to M36.
Difficult ot dismantle.
Contents :
1. Safety precautions
2. Cleanliness
3. Cleaning
4. Waste disposal
5. Emptying of gas
1HYB800001-30 Rev. A
Page 1
1. Safety precautions
Follow the local high-voltage safety regulations. Put the breaker in the “OPEN”
position.
Disconnect and earth the high voltage side.
Disconnect the operating and heating voltage.
Work on the insulators of the breaker or live parts as well as transport and
dismounting of complete breaking poles may not be done before the breaker is
emptied till a max. pressure of 0.15 MPa abs. Before the opening of the normally
pressurised vessel, it shall be emptied completely till atmospheric pressure. If the
gas will be emptied into the free air, this shall be done through a dust and absorbtion
filter. See under clause “Emptying of gas”.
2. Cleanliness
Very high dielectric requirements are placed on the SF6 gas and on the insulating
parts and correspondingly also on their cleanliness and dryness.
On all work on the open circuit breaker be aware that not only dirt but also air
moisture and hand perspiration are deleterious.
If for any reason gas spaces or parts thereof are exposed to air for longer than 24
hours, the gas spaces are to be closed temporarily and filled with SF6 gas to Pabs =
120 kPa (1.2 bar). Single parts are to be sealed in plastic bags and kept in storage.
Unused SF6 gas is non-poisonous, odourless and colourless. However, it is heavier
than air and with substantial outflow it gathers easily in low situated spaces like
cable trenches, tanks and such.
With large amount of SF6 in these spaces, there is a risk of suffocation due to lack
of oxygen.
- Only perform overhaul work with adequate room ventilation.
- The decomposition products which are formed in the breaking elements are in
combination with humidity corrosive and can cause skin, eye and mucous
memberane irritation. During the opening and internal cleaning of the breaker,
a close fitted mask with a filter against fine dust and acid gases, protective
plastic or rubber gloves and a long sleeved overall shall be used.
The dust (decomposition products), that is formed in the breaker, shall be sucked
with a vacuum cleaner provided with a dust filter and wiped off with a cloth that is
sprinkled with ethanol or toluol.
All the dust as well as the used absorbtion agent is stored in a sealed container and
is disposed off as chemical waste according to the valid provisions. During waste
disposal and handling with decomposition products, it is necessary to wear
protective gloves.
Drying cloths, protective gloves and vacuum cleaner bags shall be rinsed carefully
with plenty of water.
1HYB800001-30 Rev. A
Page 2
3. Cleaning
A. Insulator with paint-treated plastic outside surface, silicon rubber sheds or porce-
lain insulator.
Rinse the outside surfaces thoroughly with water and let it dry well before the
breaker is opened.
The end and inside surfaces are cleaned with a non fluffy drying cloth soaked with
ethanol.
Cleaned insulators must be touched only with clean protective gloves (plastic or
rubber).
Cover the end surfaces of the insulators with a strong plastic foil to protect from
recontamination.
B. Single parts
Vacuum immediately after disassembly with a vacuum cleaner with a fine dust
filter. Wipe off persistent dust with a non fluffy cloth.
Remove stubbornly adhering dust with a cloth soaked with ethanol.
Cover cleaned details with plastic foil or put in plastic bag.
Details from spaces not filled with SF6 are cleaned with ethanol and then left to
dry in air. Then they are packed in plastic bags.
4. Waste disposal
All the dust as well as the used absorbtion agent is stored in a sealed container and
is disposed off as chemical waste according to the valid provisions. During waste
disposal and handling with decomposition products, it is necessary to wear protective
gloves.
5. Emptying of gas
The breaker is evacuated by means of the gas treatment equipment, that purifies and
compresses the gas, so that it can be reapplied.
Mixed gas - SF6 + N 2 - can only be reapplied if the mixing conditions are under
control.
After the evacuation, the breaker is filled with nitrogen up to atmospheric pressure
and after this evacuated again. In this way the eventual free drifting dust in the
breaker is removed.
Finally the breaker is filled again with dry nitrogen up till atmospheric pressure after
which it is ready for dismounting and transport till the workshop.
NOTE
If work on the circuit-breaker only affects the outside of the breaker, for example
cleaning of the insulators, it is sufficient to empty the breaker down to a pressure of
0.15 MPa abs, normal working pressure.
1HYB800001-31 Rev. A
Page 1
- Up
DO NOT TILT - It is not allowed to tilt the transport unit more than 45 degrees
MORE THAN 45”
- Centre of gravity
Every transport unit must be fixed during the transport. The tying must be so
arranged that the transport units can not move in any direction. Velocity should be
adapted to the road conditions. violent acceleration or retardation can cause damage
to the contents without damaging the packing.
1HYB800001-31 Rev. A
Page 2
Lifting
Before lifting, the symbols on the transport unit (such as centre of gravity, weight
etc.) should be observed. The transport units should be lifted with a lifting machine
provided with forks of slings (see fig. 2). If a crane is utilised slings should be used.
The units may not be rolled or dropped from the conveying or lifting equipment.
The operating mechanisms FSA should be lifted by the lifting devices on top of the
cubicle. Lifting slings should never be used around the operating mechanism (see fig.
3)
Lifting the breakers out of the transport units is only necessary just before erection
(see product informatin, which can be found in the cubicle of the operating
mechanism). If they are going to be stored, see “Storage prior to erection”.
1HYB800001-31 Rev. A
Page 3
Stacking
Transport units with different widths may not be stacked (the pressure may break the
cover of the lower transport units. It should be noted that stacking causes sideways
instability, and therefore the load has to be fixed, i.e. prevented from dropping, rolling
or falling. It is not allowed to stack more than three transport units.
Figure 4 Stacking
1HYB800001-32 Rev. A
Page 1
Circuit breakers intended for outdoor operation are generally delivered in units which
are determined for transport reasons. Intermediate storage of these units should be
avoided. If it is not possible to avoid intermediate storage, they should be stored
indoors or under a roof. They must also be stored above ground level to prevent
water damage. On arrival it is important that plastic sheet are removed in order to
prevent corrosion by condensate water (except for the spare parts).
Storage in a humid climate without proper ventilation may lead to discoloration of the
galvanised surface. This discoloration is commonly known as “white rust” consisting
mainly of zinc oxide and zinc hydroxide and is a result of a chemical process
between the pure zinc on the surface and moisture.
The long term corrosion protection is not influenced, since the iron-zinc layer below
the surface remains unaffected. The presence of white rust is no reason for rejection
of goods.
On arrival, each unit should be checked in the following way :
- delivery is in accordance with order and delivery documents
- any damage in delivery, and material loss
In cases where damages are detected or suspected, the units should be opened and
damages should be photographed. Both damages and shortages should be reported.
All details should be rationally stored so that they are always available. In general, all
material should be stored in an approved storage (note 1), exceptions are given in
the text below. The ambient air should not be heavily contaminated by dust, smoke,
corrosive or combustible gases, vapours or salt, otherwise the equipment has to be
cleaned before erection.
For storage the original transport unit may be used, but the plastic sheeting should
be removed. The coupling joints of the assemblies, as well as all connections, are
fitted with transport covers or protective caps which shall not be removed until
immediately before erection.
Operating mechanism (for circuit breakers)
The operating mechanism should be unpacked on arrival,. If it is not going to be
stored in an approved storage (note 1), the heating elements must be connected and
supplied permanently with power to protect the control equipment from corrosion or
freezing damages.
Circuit Breakers
The breakers should be stored in their original transport unit, where they are well
protected from damages. The units shall be prevented from standing in water. The
breakers may be stored outdoors, except for the EDI-breaker, which should be stored
in an approved store. If the Breakers are stored outdoors they should be covered with
a tarpaulin. (Note 1)
1HYB800001-32 Rev. A
Page 2
The tarpaulin should not be placed directly onto the galvanised surface. An air gap
should be left to prevent condensation. Condensation that may occur should be self-
draining.
For the outdoor breakers the minimum allowed ambient temperature is -300C. For the
indoor breakers the minimum allowed ambient temperature is -50C.
Spare parts
The spare parts shall be stored indoors in an approved storage (note 1), in their
original units. This is in particular valid for rubber parts (sealings etc.), which also
have to be protected against light and sun, in order to prevent them from ageing.
Gaskets can only be stored during limited periods, so avoid storage of these parts.
Structures may be stored outdoors.
Notes 1 :
- roof
- solid ground
- relative humidity less than 50%
- temperature 200C (+/-100C)
1HYB800001-33 Rev. A
Contents :
1. Introduction
2. Thermal and dielectric breaking capacity
3. Chemical reactions in Circuit Breakers
4. Criteria for choice of mixed gas
5. Filling mixed gas
6. Measuring gas mixing proportions
7. Technical data for SF6, CF4 and N 2 gases
8. Safety regulations
8.1 Safety regulations for SF6 gas
8.2 Safety regulations for CF4
8.3 Safety regulations for SF6 and CF 4 gases which
are exposed to arcs
9. Environmental effect.
1HYB800001-33 Rev. A
Page 1
1. Introduction
SF6 gas has become the predominant breaking and insulation media for circuit-
breakers of puffer and Auto-PurrferTM types.
Information on characteristics and regulations for SF6 gas, N2 gas and CF4 gas is
stated in this product information.
2. Dielectric region
Figure A.
Stress on a circuit-breaker at breaking moment
Gas flow
Figure B.
Cooling SF6 arc by cold gas mixture
1HYB800001-33 Rev. A
Page 2
1. Thermal range
At current zero the hot arc channel shall be cooled down quickly to a temperature
which makes it electrically non-conductive, Figure B. Cooling capacity depends on
how quickly the current decreases towards zero, di/dt, and on the rate-of-rise of the
recovery voltage after current zero, du/dt, Figure A.
2. Dielectric range
After current zero the circuit-breaker must, for a short moment, withstand the full top
value of the transient recovery voltage without dielectric breakdown.
Breaking of terminal fault often gives low rate-of-rise of the recovery voltage and is
often a problem in the dielectric range.
SF6 is an electronegative gas of high density with good characteristics in both the
thermal and dielectric ranges.
Mixed gas filling of SF6 and CF6 results in practically unchanged thermal and
dielectric breaking characteristics. A mixed gas filled circuit-breaker with SF6/CF4
often retains its breaking capacity down to the lowest ambient temperature.
heat
CF3-(CF2)N - CF3 ➞ CF2 (1)
heat
2CF2 ➞ C + CF4 (2)
The carbon which is formed according to (2) reacts with fluorine atoms which are
produced according to (3) and form CF4 gas, whereby the carbon is bound and
carbonisation is avoided.
4F + C➞ CF4 (4)
CF4, which is an electronegative gas, is therefore formed when the arc affects the
teflon nozzle and SF6 gas.
Chemical reactions between gas formation and possible moisure residue on surfaces
in breaking units.
heat
SF6 + Cu ➞ SF4 + CuF 2 (8)
heat
3SF6 + W ➞ 3SF4 + WF6 (9)
Degraded gases which can appear in SF6 breakers after a number of years service
are SOF2, CF4, SiF4 and SO2.
The powder which remains in the breaker poles consists of formation of fluorides.
At gas analysis of mixed gas circuit-breakers with SF6/N2 and SF6/CF4 no other
degraded products than the above mentioned have been identified.
SF6/N2 -55 0C 0.36 MPa SF6+0.34 MPa N2=0.7 MPa Reduction one
breaking current step
SF6 /CF4 -55 0C 0.36 MPa SF6+0.34 MPa CF4=0.7 MPa Retains breaking capacity
This table is only for information. It is always the relevant product information for
respective circuit breakers which is valid.
By filling SF6 first a satisfactory gas mixture, without layers of gas, is always
obtained. Otherwise the mixing process takes a long time since it is based on
diffusion and convection. At gas loss, for example due to leakage, refill with correct
mixing proportions and always with SF6 gas first.
The instrument measures the sound velocity of the gas mixture and it is calibrated for
SF6/N2 gas. The instrument shows directly on the display the volume of the SF6 part
If the instrument is used to measure SF 6/CF4 gas mixture, the result shown on the
display must be corrected according to figure C. (Example: if 51% is read on the
instrument the SF6 part is 0% and the CF 4 part 100%)
100
SF6 (%)
In 90
SF6/CF4
80
70
60
50
40
30
20
10 DILO
0
50 60 70 80 90 100 DISPLAY
Figure C.
SF6 part in SF6/CF4 gas as a function of
the shown result on the display of DILO 3-027.
1HYB800001-33 Rev. A
Page 5
Boiling point
at 1.013 bar 0C -63.8 -127.94 -195.8
Density
(1.013 bar 150C)kg/m3 6.25 3.74 1.185
Vapour pressure
at 00C MPa 1.26 - -
Vapour pressure
at 200C MPa 2.3 - -
Critical temperature 0 C 46
8. Safety Regulations
8.1 Safety Regulations for SF6
“SAFETY REGULATIONS FOR SULPHURHEXAFLUORIDE”
HEALTH RISK
INHALATION of very high gas content can cause headache, giddiness and
risk for unconsciousness and suffocation due to lack of oxygen.
PREVENTIVE MEASURES
Good ventilation
Safeguard gas bottles with chains
FIRST AID
Airing
MEASURES AT FIRE
Gas containers near the fire must be removed immediately or cooled with
water.
HEALTH RISK
INHALATION of very high gas content can cause headache, giddiness and
risk for unconsciousness and suffocation due to lack of oxygen.
PREVENTIVE MEASURES
Good ventilation
Safeguard standing gas bottles with chains
1HYB800001-33 Rev. A
Page 7
FIRST AID
Airing
MEASURES AT FIRE
Gas containers near the fire shall be removed immediately or cooled with
water.
8.3 Safety Regulations for SF6 and CF4 gases which are exposed to arc
HEALTH RISK
Air humidity together with degraded products can cause irritation of skin,
eyes, and mucous membrances.
INHALATION of very high gas content can cause headache, giddiness and
risk for unconsciousness and suffocation due to lack of oxygen.
Since the gas has been exposed to high temperatures degraded products,
which cause irritation, have been formed.
PREVENTIVE MEASURES
Good ventilation.
Gas from circuit-breakers can be recovered in gas treatment equipment and
reused.
Fresh air mask or mask with filter against fine dust and gases with acid content.
Plastic or rubber gloves.
Overalls with long sleeves
Vacuum cleaner with filter for fine dust
FIRST AID
Airing
Dust and filters are stored sealed and handled as chemical refuse according
to local regulations.
MEASURES AT FIRE
Gas containers near the fire must be removed immediately or cooled with
water.
9. Environmental Effect
SF6 and CF4 gases can leak out into the surrounding environment due to leakage in
the circuit-breaker.
CF 4 and SF6 are very stable gases and make no detectable contribution to ozone
destruction and photochemical smog, and they have negligible influence on the green
house effect. The latter applies especially when used in circuit-breakers where, from
the global point of view, gas volumes are small.
1HYB800001-35 Rev. A
Page 1
WARNING TEXTS
Warning texts are stated in 5 different degrees of urgency which should be carefully
observed. These are described below :
DANGER indicates an immediate risk situation that can lead to death or serious
personal injury if not avoided.
DANGER
Warning indicates a risk situation that can lead to death or serious personal injury if
not avoided.
Warning
Caution indicates a risk situation that can lead to small or moderate damage.
Caution
Note Note is used when there is danger that can lead to equipment damage only.
1. Safety Regulations
When working on high-voltage circuit-breakers the below-mentioned risks must be
taken into consideration and corresponding safety measures taken.
RISK MEASURE
1. Work next to high-voltage Warning plate placed inside the door to the
operating device
2. Work on ladders and platforms The work shall follow the directions of the Authority
for occupational safety and health. Avoid work in
severe weather conditions which entails a great
deal of climbing for short periods.
3. Work with low-voltage. Do not connect control or heating voltage until all
Both D. C. and A. C. voltage can have been connection work is completed.
drawn on the operating device.
4. Squeezing risk in operating device and Warning plate is placed on the supporting frame.
link system.
No work must be carried out unless the closing and
The spring operated device has energy opening springs are uncharged and the circuit-
stored in the closing spring. The opening breaker in position OFF “O” disconnect voltage to
spring, which is on the mechanism housing of the motor.
pole C1, or on every pole for one-pole
- The operating device must not be operated
operation, has energy stored. The device can
unless it is connected to the circuit-breaker
be activated by heavy vibrations or
and the electric cables are connected. The
unintentional, slight touch on mechanical
circuit-breaker shall be filled with SF6 gas to
latch parts.
a pressure of 0.7 MPa. The closing springs
should for safety reasons be uncharged
during transport and when the circuit-breaker
is off duty.
5. Work on pressurized porcelain insulators. Work close to the insulators of the circuit-breaker,
Normally, the work pressure is up to 0.7 MPa. which entails risk to damage the porcelain, must
Damage in the porcelain can cause risk for not be carried out until the gas pressure has been
the porcelain to break, lowered to 0.125 MPa absolute pressure.
1HYB800001-35 Rev. A
Page 3
2. Unpacking
Place the case hoizontally on a flat surface before opening the cover.
Check that all parts are included in the delivery. Check-off on the accompanying
packing list.
Check that no parts have been damaged during transport; especially the porcelain
insulators.
Information
The information in this document is subject to alteration without prior notice and should not be regarded as an
undertaking from ABB Limited. ABB Limited takes no responsibility for errors that can occur in the documen-
tation.
ABB Limited is not responsible for damage incurred due to the misuse of this document.
The document, or parts thereof, may not be reproduced or copied without prior permission from ABB Limited.
It may not either be imparted to third pary or otherwise be used without authorisation. Infringement hereof will
be subject to action in accordance with applicable laws.
© ABB Limited
1HYB800001-36 Rev. A
Contents
ABB Limited attempts to minimize environmental impact during the entire product’s
service life. Environment aspects are held in focus during technical and product
development. We always try to consider the eco-cycle while the material’s impact on
the environment and possibilities of recycling are observed. Manufacturing processes
are selected that are as gentle as possible on the environment.
When discarding used equipment a great deal of material and the energy content of
the material can, after sorting and cleaning, be recycled. The degree of material that
can be recycled varies depending on the technical resources and experience
available in respective countries.
1.4 SF6-gas
The SF6-gas must be emptied before discarding a circuit-breaker. Care shall be
exercised in accordance with applicable regulations with all handling of SF 6-gas, to
prevent gas leakage. The gas can be taken care of in different ways depending on
the circumstances :
In those cases where the circuit-breaker is filled with mixed gas, the SF6-gas is
separated from the mixture for continued handling as set out above. Alternatively, the
gas mixture can be sent for destruction without being separated.
ABB Limited will willingly take care of the gas when the circuit-breaker is to be
discarded.
1HYB800001-36 Rev. A
Page 2
1.5 Porcelain
Porcelain can, after cleaning, be left for disposal or used for other purposes, for
example, as a filling material.
1.6 Electronics
1.7 Metals
Sort metals according to type and surface finish and leave at an approved recycling
company. After the removal of any paint or other surface treatment the metal can
generally be melted down and used in new products. Many iron, steel and aluminium
parts are large and easy to identify, for example, the frame and mechanism housing.
ABB Limited aims for a reduction in the use of noble metal, or with discharge
environmentally hazardous metals. Recycling of these is extremely important.
Noble metals such as copper and silver are expensive and only occur is small
quantities in the earth’s crust. Copper is primarily used in the current paths, puffer,
contactors and cables. Silver plating of contactors can occur. Some metals can cause
damage if discharged. This applies, among others, to copper, but also to zinc and
nickel which are used sparingly in the form of surface treatment.
1.8 Plastics
Composites found in small quantities in isolators, pipes and cable glands consist of
thermosetting plastic. Thermoplastics can be found in components such as guide
rings, belts bushings and support rings. Thermoplastic in ferrules, nozzles, pipe and
collars contains fluorine and is not suitable for recycling, however, it can be disposed
of without the risk of leaking hazardous substances.
1HYB800001-36 Rev. A
Page 3
Empty oils, grease and the like before discarding and leave at an approved recycling
centre or at a recycling company. Oil waste can be separated into oil, water and
different contamination through the use of gravimetric forces. In many cases the oil
can be reused. Alternatively, the oil’s energy content can be recovered through
combustion in purpose built installations.
1.10 Rubber
Rubber can be left at an approved recycling centre either for disposal or reused for
different purpose.
Contents :
1. General
2. Construction
3. Function
4. Erection
5. Commissioning
6. Troubleshooting
7. Maintenance
8. Spare Parts
11. Appendix
1HYB800001-37 Rev. A
6 Troubleshooting 13
6.1 SF6 gas supply system 13
6.2 Control Circuits 13
7 Inspection intervals 14
7.1 Maintenance concept
7.1.1 Table of parts to be serviced
7.2 Tools, jigs and fixtures and
additional parts 26
7.2.1 Additional parts 26
7.3 Procedures 26
7.3.1 General 26
7.4 Preparations for maintenance 26
1HYB800001-37 Rev. A
Page 1
1. General
1.1 Validity
These operating instructions are applicable for the high voltage circuit breaker type EDF.
Generation
Outdoor design
Breaker construction
1.3 Specifications
Specifications are contained in the order documentation and on the nameplate (Fig. 1/1)
The diagrams contained in these instructions are schematic diagrams and serve to
illustrate functional relationships.
1.4 Masses
The mass of a 3-pole circuit breaker can be obtained from the order documentation
and the shipping documents.
For internal transport purposes see Fig. 1/2.
*) On this flange there is a cover that easily can be exchanged to a safety disc
unit if the customer wishes.
The poles are filled with SF6 gas and connected to header block by means of
pipelines. (Fig. 4/1a, c)
3. Function
3.1 Control and monitoring (Fig. 3/2)
The schematic diagram of the control shows how the switching commands enter the
circuit breaker control circuit, which monitoring elements are installed to detect any
occurring failures, and which signals are thereby triggered.
The control circuit itself can be seen in the order related circuit diagram.
- Monitoring elements :
SF6 gas density :
The density monitor 10112 (temperature - compensated pressure monitor)
monitors the SF6 gas pressure in the breaker poles and gives a ‘low pressure
alarm’ in case of minor gas losses. If the gas density drops to a value below the
blocking pressure curve according to Fig. 5/1, “CLOSE” and “OPEN” operations
are blocked and an alarm signal is given.
- To close the circuit breaker closing coil lever is energised, whereby the closing
spring is released. This moves the moving contact upward, thereby first closing
the arcing contact “g-h”, and then the main current contact “k-l”.
- To open the circuit breaker Trip coil lever is energised, whereby the trip spring
is released. This moves the moving contact downward, thereby first separating
the main current contact “k-l”, and then the arcing contact “g-h”. During this
movement the piston compresses the SF6 gas in the cylinder. The arc between
the contacts increases the compression pressure. In the area of the current
zero a gas flow occurs which extinguishes the arc.
4. Erection
4.1 General
- All adjustments are made in the factory. All moving parts to be coupled are
already positioned correctly and fastened.
- To prevent the absorption of any moisture, the pole columns are filled with
insulating gas Pabs = 150 kPa (=1.5 bar = 22 lbf/1 in2).
- Check SF6 gas pressure by pressing the disc of the check valve inwards with a
pin of approximately f5. A distinct hiss shall then be heard. If there is no
hissing sound the pole has a leak, which must be attended to.
- Place supports 10174 on the prepared foundation. The upper bearing surfaces
for the pole support must be horizontal and must lie in one level. Screw
supports tight to the foundation (Observe MD) (Fig. 2/1).
- The exact location can be obtained from the installation layout plan. During the
erection, make sure that the fixation holes for the earthing connection are
positioned correctly (Fig. 2/1)
- Mount frame 10172 with assembled poles 10171 on supports 10174 with
fasteners 49069, 49622 and 89027. (Observe MD) (Fig. 4/1a)
Be careful! The pole in the middle must not be damaged by Lifting ropes.
Attention !
During mounting of mechanism ensure that the upper joint head of the connecting rod is
inserted into the fork of the actuating lever 10154.
Starting conditions :
Position indicator and spring tension indicator indicate position “b1” and
“Untensioned”. (Fig. 2/1)
- The operating mechanism and the circuit breaker are to be coupled together in
the OPEN position.
- Turn actuating lever on breaker all the way in the direction of the operating
mechanism. For correct position see (Fig. 4/1b).
- However, if the bores of the actuating lever and joint head do not correspond, the
connecting rod length must be corrected.
- This is done by releasing the lower fasteners “g” (Fig. 4/1a), and by lowering
the cubicle enclosure.
- Release locknuts “h” and “k” of the connecting rod (Fig. 4/1b), turn connecting
rod, hold against turning and tighten locknuts (Observe MD).
1HYB800001-37 Rev. A
Page 5
- Adjust connecting rod so it can move freely in the joint heads. Treat cylinderical
pin in the upper coupling with grease G (Mobile 28)
- Lift cubicle enclosure and fasten with the lower fasteners “g”.
- Connect density monitor 10112, cables and possible pressure gauge according
to fig. 2/1, 4/1a, 4/1c.
The high voltage connection fasteners consist of screws M12 (St. 8.8) and
atleast 1 washer 13/28x3 and 1 lockwasher 13.5/28x1.6 on each side of each
bolt (Observe MD)
5. Commissioning
All data which are checked or measured are to be entered in a commissioning record
and preserved for comparisions.
The SF6 gas pressure can be seen on the circuit breaker nameplate.
As the circuit-breaker poles are delivered vacuum processed and filled with SF6 gas
at a transport pressure of 0.150 MPa abs (200C), during commissioning only one
filling of SF6 gas is required, to top up pressure up to the filling pressure given on the
rating plate.
It is appropriate to carry out pressuring directly from an SF6 gas bottle. In order to
avoid risks at the first filling, due to possible transport damages to the porcelain, the
gas bottle with filling equipment shall be placed as far from the circuit-breaker as
possible, and preferably behind some shield. Pole columns are connected to the
header block by pipes. Connect the hose from the gas filling equipment to the SF6
gas filling valve on the header block L10118 (Fig. 4/1c).
● Connect coupling (4) supplied loose with gas filling bag to the non-return
valve on the hose of gas filling device.
● Connect above assembly to the circuit breaker’s gas valve (5).
● Open regulator to fill gas in circuit breaker to rated pressure as per fig. 5/1.
● Allow the pressure to stabilise in the circuit breaker for some time. Check
the pressure and adjust if necessary.
● Dismantle the hose coupling assembly from the gas valve on the circuit breaker.
● Close the valve on the gas cylinder.
● Disconnect regulator with hose from gas cylinder.
Breaker is now ready for functional test as per section 5.3.
When the breaker is to be placed in a climate where the temperature goes below
-300C, the circuit-breaker shall be filled up with “mixed gas” instead of pure SF6-gas.
In order to avoid condensation when the temperature is below -30 0C the SF6-gas is
mixed with N2 (Nitrogen gas).
Selection of gas-mixture :
SF6/N2 25 kA 50 Hz
20 kA 60 Hz
The total filling pressure for mixed gas is stated on the breaker’s rating plate. The
circuit-breaker poles are delivered vacuum processed and filled to the pressure
0.150 MPa abs (20 0). At taking into service the SF6-gas-part is to be filled to 0.36
MPa at 200C first and then the N 2-gas part up to the total filling pressure stated on
the rating plate.
When filling gas after a possible leak, fill with SF6-gas respective N2-gas in proportion
as above. For instance : a leakage to the blocking level 0.6 MPa gives with SF6/N 2
refilling :
1HYB800001-37 Rev. A
Page 7
0.36
SF6-gas ● 0.1 = 0.051 MPa SF6 at 200C
0.7
0.34
N2-gas ● 0.1 = 0.049 MPa N2 at 200C
0.7
In the filling process the dependence of the nominal pressure of temperature must
definitely be taken into account.
In Fig 5/1, use graph 4 for SF6 -gas filling and graph 1 for N2-gas filling.
- the circuit breaker is isolated from the high voltage system and earthed
according to regulations.
- the SF6 gas or mixed gas is at nominal pressure.
- the spring tension indicator of the spring operated mechanism indicates the
position “b2” (Fig. 2/1) “Tensioned”.
The switching times are measured with a time recorder. The diagram of a standard
measuring arrangement is shown in Fig. 5/2a. Every breaker pole has its own
measuring circuit. The time diagrams in Fig 5/2b serve solely for explanation of the
time concepts used.
The closing time “t1” < 60 ms is the time from the instant the command is
issued until the contacts in the arcing chambers touch. It is to be measured for
each breaker pole. The maximum allowable non-simultaneity between the
breaker poles is Ut 1 < 4 ms.
The Opening time “t2” < 35 ms is the time from the instant the command is
issued until the contacts in the arcing chambers separate. It is to be measured
for each breaker pole. The maximum allowable non-simultaneity between the
breaker poles is U t2 3 ms.
The close-open time “t3” < 40 ms is the time form the instant the contacts touch
until they separate in the arcing chamber in a “CLOSE-OPEN” switching
operation. For the measurement the terminals “K1” and “K2” on the close-open
switch “M3” (Fig. 5/2a) are short circuited.
The rapid reclosure can only be tested with the test equipment of the
installation.
1HYB800001-37 Rev. A
Page 8
After the interruption by the OPEN command the circuit breaker should not reclose in
spite of the close command still being present.
Measure resistance or apply voltage and measure the current. When the
thermostat-controlled additional heater is installed, check the adjustment of the
thermostat.
STORAGE YES NO
1 a Complete material is available as per packing list ?
If NO mention the shortages :
b Instruction manual available ?
c G.A. and erection drawing available ?
d Schematic drawing available ?
2 a Operating drives box stored indoor ?
b Accessories box stored indoor ?
c Was the outdoor equipments stored above HFL (Highest flood level ) ?
d Any equipment damaged during re-transportation / unloading at site ?
ERECTION YES NO
1 Is foundation and location of equipment as per G.A. drawing ?
2 STRUCTURE ERECTION
a Is length of the foundation bolts (projecting outside) sufficient to put checknuts ?
b Is there levelling nut available below structure ?
c Is the top side of the structure base plate as per G.A.. Drawing ?
d Is direction of the structure as per G.A. drawing ?
e Is the structure levelled in x , y and z axis as per G.A. drawing
X = Pole to pole distance (Measuring tape)
Y = Structure Height (Water tube level)
Z = Alignment of all the structures in one line (Line thread)
f Tightness of the nuts and checknuts done ?
g Are the foundation bolts filled with mortar ?
h Are the serial nos of all the equipments matching with the serial numbers
mentioned in the packing list ?
1HYB800001-37 Rev. A
Page 10
● Lift the mechanism and fix the 04 mounting bolts with the pole beam.
● Match the Eye-bolt of the mechanism connecting rod with the lever on pole.
● Apply thin layer of grease on the pin before inserting in the eye bolt.
● After insertion of pin, tighen the locking screw with locking washers.
● Spanners
● Cloth
● Cleaning agent
REFILL ALARM
OP. BLOCK –I
OP.BLOCK – II
TIME AT WHICH CALIBRATION DONE : AM / PM
e SF6 GAS PRESSURE FILLED AFTER CALIBRATION OF DENSITY SWITCH
● SF6 gas filled in the breaker : Bar
● Temperature at which gas filled . degree C
● Time at which gas filled AM / PM
f SF6 GAS LEAKAGE TEST : YES NO
● Is Leak detector available?
● If NO , do not proceed further till leak detector is arranged.
● Is the complete SF6 gas system in the breaker (which includes pole,
gas pipes & density switch / monitor ) free from any SF6 gas leakage ?
● If NO , describe leakage found from which joints :
7 COMMISSIONING :
a Connection of density switch cables :
●Density switch cable
closing circuit terminals : &__
trip 1 circuit terminals : &__
trip 2 circuit terminals : &__
b Control coil resistance :
CLOSE COIL : W
TRIP COIL - 1 W
TRIP COIL - 2 W
c Requirment of DC control voltage in ideal condition : dc
Measured control voltage dc
SWITCH “ ON “ AC / DC supply.
d Local operation of the breaker ( electrically) :
Local closing operation OK
Local tripping operation for trip coil 1 OK
Antipumping function OK
* Open command provided directly on terminal number :
e Remote operations :
Close command given on terminal number :
Open command (T1) given on terminal number :
Open command (T2) given on terminal number :
f SPARE CONTACTS OF AUXILIARY SWITCH :
● Position of the breaker : TRIP
● Serial number of contacts found NC :
B ms
C ms
1HYB800001-37 Rev. A
Page 12
B ms
C ms
B ms
C ms
B ms
C ms
B ms
C ms
l Are insulators, operating mechanism, pole beam thoroughly cleaned and free
from dust and dirt?
* If NO , clean it thoroughly with dry cloth , before charging.
If point 1-7 as set out above have been completed, the circuit-breaker
can be commissioned.
1HYB800001-37 Rev. A
Page 13
6 Troubleshooting
Before any activity is started, the circuit breaker has to be isolated form the high-
voltage system and earthed according to regulations. The control and heating
currents are to be interrupted.
7. Inspection intervals
Important checkpoints, acceptable tolerances, certain functional values for
adjustments, and recommended inspection intervals can be found in the following
inspection chart.
In corrosive or polluted air and in climates with a high relative humidity, it can be
necessary to halve the inspection intervals.
Condition of Com-
Explan- circuit- petence
Type of measure Inspection interval
ation breaker require-
during work ments
Explanation:
1) Mech. oper. =Mechanical Close-Open operations.
2) El. oper.= Close-Open operations with electrical load
3) Special demands on resistance inspections for circuit-breakers operated
> 100 Close and Open operations/year.
1HYB800001-37 Rev. A
Page 16
Competence requirements :
a2) Substation personnel with no special training.
b2) Personnel authorised by ABB to carry out assembly, commissioning and
maintenance work.
c2) Personnel authorised by ABB to carry out assembly, commissioning and
maintenance work. In certain cases, with instructions from ABB.
7
1HYB800001-37 Rev. A
Page 17
7
1HYB800001-37 Rev. A
Page 20
1HYB800001-37 Rev. A
Page 21
1HYB800001-37 Rev. A
Page 22
1HYB800001-37 Rev. A
Page 23
1HYB800001-37 Rev. A
Page 24
4
1HYB800001-37 Rev. A
Page 25
7.3 Procedures
7.3.1 General
- Switch circuit breaker to position “b1” (untensioned and OPEN) (Fig. 2/1)
- Open associated high-voltage disconnectors.
- Turn off control, signal, motor and heating voltages
- Earth high-voltage lines on both ends according to local regulations and isolate
from the installation.
- Remove control, signaling and heating lines (disconnect).
- Reduce SF 6 gas pressure for the transport to the servicing room to pabs= 150
kPa (= 1.5 bar=21.8 lbf. in2). Discharge throught dust filter.
7.5 Removal of breaker poles
7.5.1 Dismantling of the SF 6 connecting pipes
- After loosening the fastening bolts of the SF 6 gas supply system the whole
system can be moved longitudinal. The clamp nuts of the check valve are
screwed out so that the groove in the check valve’s thread is visible . Move the
pipe-system side-ways so the stop is in the clamp nut. In this position all the
three check valves are closed and the clamp nuts can be totally loosened at
the same time as the pipe-system is moved further sideways.
- Move breaker poles away to the side. The coupling shaft 10005 (Fig. 4/1a) will
slide out of the coupling bush 10180. Transport to the service room and place
on a mounting block (provided by the customer).
- Place breaker pole on mounting table, Fastening points are the upper flanges
of the post and breaking chamber insulator and the adapter plate 10098.
- Remove fasteners 49756/2 and washer 89026/2 and and take off the cover
10056/1
- Remove fasteners 49756, 49621/2, 89026/2 and carefully lift the flange 10099/
2 with the fixed contact.
- Place the flange on a safe surface and be careful with the O-ring slot.
- Support link gear 10185 on suitable wood base, screw off and pull out as far as
possible.
- Hold operating insulator socket 10042 from turning with open-end wrench WS
28 mm, release locknuts 49695/ 49586 and turn adjusting screw 10041 until it
releases the operating insulator socket 10042 and the linkage joint 10043.
Completely remove link gear 10185. Remove sealing ring 10038/3 and 10038/4.
- Remove fasteners that keep breaking chamber insulator, terminal flange and
post insulator together. Take off the break chamber insulator remove the
moving contact and place on a good surface.
- Withdraw pin 10050 and operating insulator socket 10042 out of operating
insulator 10049.
- Screw set screw 10051 with locknut 49505 out of adjusting ring 10053.
- Drive out flow direction tube base 10054 with disassembly rod and adapter
00104 (Fig. 7/2b). Remove pin 10029.
- Remove screw 49726/1 and washer 89026/1 and dismantle the post insulator
from adapter plate.
- Release screw 49017 and remove desiccant container. Dispose off desiccant
containers according to local regulations.
- Ensure that the sealing surfaces of the insulator, and crank mechanism
housing and O-ring slots in the flanges are not damaged.
1HYB800001-37 Rev. A
Page 28
- Screw off screw 49756 with washer 89006/2 and disassemble the flange and
contact holder.
- Remove hex screws 10057 out of finger cage 10058. Pull off finger cage. The
fingers 10059 will fall out.
- Remove fixed contact pin 10056 with socket srench 00103.
- As general rule, the fixed contact pin 10056 the countersunk screws 10057 and
all fingers 10059 are to be replaced.
7.6.4 Cleaning
- Assemble the reassembled contact 10030 and the terminal flange and
don’t forget to grease the contact surface, marked 3*), fig 7/3 with grease
“P”.
Attention !
- Remove fasteners 49705, 89025 or 49701 and 89154 with shaft guard 10179
or cover 10183 and disassemble completely.
- Push out shaft 10083 and lever 10084 with linkage joint 10085.
- Remove socket head screw 10086 with washers 10088, 89004 and pull out
joint pin 10087.
- Replace following parts :
- O ring 10090
- X ring 10081
- Sealing ring 10182
1HYB800001-37 Rev. A
Page 30
- Attach a new desiccant container to the adapter plate 10098 (Fig. 7/2a)
with screws 49017 (6Nm) and secure with locking agent “B”.
- Determine adjusting dimension “A” between operating insulator socket
10042 and linkage joint 10043 (Fig. 7/2c).
- Attach depth gauge 00109 to upper break chamber insulator flange
10016. Push operating insulator 10049 all the way up. Place straight
edge 00114 against lower flange of insulator and link gear 10185 and
measure dimensions “X” and “Y”.
- Calculation formula for dimension “A”
A = X + Y - 50. (= 1.97 in)
- Adjust compass 00115 to dimension “A”.
Remove depth gauge 00109 and straight edge 00114.
- Installation of fixed contact compl. 10030., See fig. 7/2a.
- Treat the O-ring slot on the upper terminal flange 10099/2 and the two O-
ring with grease “S” before placing the O-ring in the slot.
- Assemble the flange with the reassambled contact, 10030, and centre
the contact in the insulator.
- Use fasteners 49756/2, 89026/2, 49621/2 observe MD = 79 Nm.
- Finally treat the O-ring and the slot on the upper terminal flange with
grease “S” and mount the cover10056/1 screw the washer 49756/2 and
89026/2 (MD 45 Nm)
- Mounting of crank mechanism 10185 (Fig. 7/2a)
- Pull operating insulator 10049 into position “OPEN”
- Treat the O-ring slot in the adaptor plate and O-ring with grease “S” place
the O-ring in the slot.
- Place crank mechanism 10185 at a distance of approx. 50 mm (= 1.97
in) in front of lower flange of post insulator.
- Screw adjusting screw 10041 with hex nuts 49586 and 49695 screwed all
the way back simultaneously into thread of operating insulator socket
10042 and of linkage joint 10043 (only one rotation).
- Screw adjusting screw 10041 into dimension “A” with adjusted compass
00115 and secure on both ends according to (Fig 7/2c) with locking
agent ‘B’ (Observe MD).
- Treat sealing surfaces with grease “S” (fluoro-silicon grease)
- Attach crank mechanism 10185 with fasteners 49621/2, 89026/2 and
secure with locking agent ‘B’. (Observe MD)
- Gas filling
- After that the breaker has been reerected, after revision or repair, it
should be filled with SF6-gas before trail operation.
- Evacuate till a pressure of 1 mbar and continue with pumping at least 1
hour from the moment the pressure of 1 mbar is reached.
- Break off the evacuation and fill the breaker with dry, clean nitrogen up
till atmospheric pressure. Leave the breaker alone for a few hours.
- Evacuate again till a pressure of 1 mbar and fill the breaker with clean SF6
gas up till 0.150 MPa abs. Observe the security precautions for gas filling.
Note: Keep the position of the terminals as it was before the breaker was
opened.
1HYB800001-37 Rev. A
Page 32
- The gas nipple are greased with grease G, Mobil Grease 28, See *), fig. 4/1c.
- Connect the gas system to the breaker poles and screw an all cap nuts up to
the groove. Now the connection is dense, but the check valve is closed. When
all breaker poles are connected in that way. The gas tubes are vacuum-
pumped by the gas filling equipment before connecting to the breaker.
Then the cap nuts are tightened fully while moving the complete tube system to
the side. Tightening torque is 10 Nm.
If the connecting of the gas system to the header block have been dismantled.
They shall be secured with locking agent ‘B’ when reinstalled. Observe the
tightening torque 45 Nm. Fill with SF 6-gas to normal working pressure 0.7 MPa
abs. After conclusion of gas treatment fill the nut and O-ring 10112/c.
8. Spare parts
8.1 General
Quantity
1
1
1
1
1
1HYB800001-37 Rev. A
Page 35
1 2 3
11. Appendix
11.1 Figures
Fig. Designation
1/1 Nameplate
1/2 Tabulated masses
2/1 Circuit breaker
3/1a Breaker Pole (“OPEN” Position)
3/1b Breaker Pole (“CLOSED” position)
3/2 Schematic control diagram
4/1a Circuit breaker, complete
4/1b Connecting rod securement
4/1c SF6 gas line
4/1d Gas filling with SF6
4/2 Transport instructions
5/1 SF6 filling pressure diagram
5/2a Measurement layout for function tests
5/2b Simultaneity monitoring
7/1 Admissible switching cycles for contact overhaul
7/2a Breaker pole, complete
7/2b Tools and overhaul tools
7/2c Length adjustment of moving contact
7/3 Fixed contact
7/4 Moving contact
7/5 Crank mechanism
7/6 Spring stored-energy actuator
1HYB800001-37 Rev. A
Page 38
Fig. 1/1
1HYB800001-37 Rev. A
Page 39
Type EDF
Mass per citruit breaker (net)
kg lb
Fig. 1/2
1HYB800001-37 Rev. A
Page 40
10173 Control cubicle with stored-energy spring operating mechanism and connecting rod
10174 Support
b1 Breaker position “OPEN” and springs untensioned (not ready for swithcing)
b3 Breaker position “CLOSED” and springs tensioned (ready for O-CO Swithcing)
C Earthing connection
Fig. 2/1
1HYB800001-37 Rev. A
Page 42
10017 Cover
10106
10157
10098
Fig. 3/1a,b
1HYB800001-37 Rev. A
Page 44
1) Remote control
10171 10171
10171
S13
Fig. 3/2
1HYB800001-37 Rev. A
Page 46
Nm ft. lbf
13 10
45 33
79 58
190 141
10183
10005
➤
*) Rotation by 1800
Fig. 4/1a
1HYB800001-37 Rev. A
Page 48
10064 Lockwasher
10083 Crankshaft
89224 Washer
c Installation location
d Rubber collar *)
e Clamp *)
h,k Locknuts
MD Torque
Nm ft. lbf
6 4
c=360
Fig. 4/1b
1HYB800001-37 Rev. A
Page 50
L 00111 Washer
L 10112/b Manometer *)
*) At request of customer
Mobil Grease 28
Fig. 4/1c
1HYB800001-37 Rev. A
Page 52
2 Coupling
3 Regulator
4 Coupling
5 Gas Valve
7 Density Switch
8 Gas Valve
9 Pressure Gauge
Fig. 4/1d
1HYB800001-37 Rev. A
Page 54
a Supporting timber
Fig. 4/2
1HYB800001-37 Rev. A
Page 56
Conversion of :
Pabs (kPa) to Pe (gauge) lbf/in2
Pabs - 100 x 0.145 (kPa) = Pe (gauge) lbf/in2
➤
Pabs Pabs
1000
9 130.5 900 1
8 116 800
2
7 101.5 700 3
6 87 600
5 72.5 500
4 58 400 4
3 43.5 300
2 29.0 200
100
0
-30 -20 -5 0 10 20 30 40 50 60 70 80
Pabs t 0C
kPa -30 -20 -5 0 10 20 30 40 50 60 70 80
1 500 580 625 640 670 700 730 760 790 820 850 880
2 490 520 555 570 590 620 650 670 700 730 750 770
3 470 500 540 550 580 600 630 650 680 700 720 750
4 290 300 330 340 350 360 370 380 400 420 430 440
t 0C
Pabs
bar -30 -20 -5 0 10 20 30 40 50 60 70 80
1 5.0 5.8 6.2 6.4 6.7 7.0 7.3 7.6 7.9 8.2 8.5 8.8
2 4.9 5.2 5.6 5.7 5.9 6.2 6.5 6.7 7.0 7.3 7.5 7.7
3 4.7 5.0 5.4 5.5 5.8 6.0 6.3 6.5 6.8 7.0 7.2 7.5
4 2.9 3.0 3.3 3.4 3.5 3.6 3.7 3.8 4.0 4.2 4.3 4.4
Pabs t0 C / F
lbf/in 2 -30/-22 -20/-4 -5/23 0/32 10/50 20/68 30/86 40/104 50/122 60/140 70/158 80/176
1 72.5 84.1 90.7 92.3 97.2 101.5 105.9 110.2 114.5 118.9 123.3 127.6
2 71.1 75.4 80.5 82.7 85.6 89.9 94.3 97.2 101.5 105.9 108.8 111.2
3 68.2 72.5 78.4 79.3 84.1 87.0 91.4 94.3 98.6 101.5 104.4 108.8
4 42.1 43.5 47.9 49.3 50.8 52.2 53.7 55.1 58.0 60.9 62.4 63.8
Fig. 5/1
1HYB800001-37 Rev. A
Page 58
Y1 Coil CLOSE
Q Auxiliary switch
M1 Time recorder
K1 Terminal 1 on M3
K2 Terminal 2 on M3
UM Measurement voltage
US Control Voltage
C CLOSED
O OPEN
I Coil current
t1 Closing time
t2 Opening time
t3 Close-open time
Fig. 5/2b
Fig. 5/2a,b
1HYB800001-37 Rev. A
Page 60
I Breaking current
Nm ft. lbf
6 4
20 15
45 33
79 58
MD=45Nm
Fig. 7/2a
1HYB800001-37 Rev. A
Page 64
00115 Compass
00114 Straightedge
89026/2 Washer
89026/3 Washer
Y Actual dimension from linkage joint in Link ger to outer edge of straightedge (in open position)
mm in
50 1.97
b
10042
10045
Fig. 7/2c
1HYB800001-37 Rev. A
Page 68
89006/2 Washer
MD Torque
Nm ft. lbf
6 4
26 19
49 36
10099
10097
10059
Fig. 7/3
1HYB800001-37 Rev. A
Page 70
Nm ft. lbf
6 4
11 8
79 58
Fig. 7/4
1HYB800001-37 Rev. A
Page 72
Nm ft. lbf
6 4
45 33
110 81
Fig. 7/5
1HYB800001-37 Rev. A
Page 74
A Transmission roller
B Transmission cam
C Locking pawl
D Locking pawl
E Level
F Lever
G Worm wheel
H Worm
Fig. 7/6
1HYB800001-38 Rev. A
Contents :
1. General
2. Construction
3. Function
4. Erection
5. Commissioning
6. Maintenance
7. Spare Parts
8. Appendix
1HYB800001-38 Rev. A
Page 1
Contents Page
1. GENERAL 1
1.1 Validity 1
1.2 Specification 1
1.3 Masses 1
2. CONSTRUCTION 1
2.1 Operating mechanism cubicle 1
2.2 Drive mechanics 1
2.3 Driving units 2
2.4 Electrical components 3
3. FUNCTION 3
3.1 Functions of the basic mechanism 3
3.2 Charging the closing spring 3
3.3 Closing - operation 4
3.4 Opening - operation 5
4. ERECTION 5
4.1 Delivery 5
4.2 Installation 5
5. COMMISSIONING 5
5.1 Function tests 5
5.1.1 Manual operation 5
5.1.2 Motor operation 5
6 MAINTENANCE (Overhaul) 6
6.1 Duty-related overhaul 6
7 SPARE PARTS 7
7.1 Storage instructions 7
7.2 Spare parts list 7
8 APPENDIX 8
8.1 Figures 8
1HYB800001-38 Rev. A
Page 2
1. General
1.1 Validity
1.2 Specifications
Specifications are contained in the order documentation and on the rating plate.
1.3 Masses
The masses (kg/lb) can be obtained from the order documentation and the shipping
documents. For internal transport and assembly see the instructions for erection and
operation of the circuit breaker, Fig. 1/2
2. Construction
The stored-energy spring operating mechanism comprises the following main parts :
In the operating mechanism FSA 1 (outdoor) the electrical components and the
basic mechanism are placed in the operating mechanism cubicle EV 11851.
There is a door with an inspection window for reading the position indicator
EV11825 and the spring charge indicator EV11824 on the operating mechanism
front. The door can be locked with a padlock. When the door is opened the electrical
panel with its electrical components becomes accessible and the hand crank can be
inserted.
The operating mechanism cubicle is designed so that the basic mechanism and the
electrical components are hermetically protected against the effects of the weather.
The outdoor circuit breaker type EDF has the cubicle mounted below the pole
beams of the breaker. Connecting rod projects upwards.
1HYB800001-38 Rev. A
Page 3
- Lever EV 11848 is located on the output shaft and when its rotates it transmits
the rotary movement to the connecting rod.
In the mechanism type FSA 1 the electrical control and monitoring elements
necessary for the control of the circuit breaker are additionally arranged on the
switchgear panel.
If the operating mechanism is to be stored outdoors for periods of longer than four
weeks, the heater should be connected.
1HYB800001-38 Rev. A
Page 4
3. Function
3.1 Function of the basic mechanism (Fig. 7/1)
- The main shaft EV 11815 serves as the drive shaft for charging the closing spring.
- By means of lever EV 11848 the output shaft EV 11816 transmits the closing
or opening movement to the connecting rod, and hence to the circuit breaker.
- The motor EV 11843 with reducer gear EV 11842 charges the operating
mechanism mechanically (tensions the closing spring). The motor limit switch,
EV 11826, opens when the closing spring is tensioned.
- Hand crank EV 11812 (FSA 1) is used to charge the closing springs by hand
(e.g. on power failure).
- On discharging, opening spring EV 11814 release uses the energy to open the
breaker.
- Closing unit EV 11811 holds the closing spring in the charged condition or it
releases it on command electrically via the CLOSE magnet coil or
mechanically (by hand).
- Opening unit EV 11810 holds the opening spring in the charged condition or
releases it on command electrically via the OPEN magnet coil or mechanically
(by hand).
When the engagement lever EV 11837 or the closing coil EV 11839 are actuated by
hand or electrically, the lever 11832 and the blocking hook EV 11834 of the closing
unit release the control disk pawl EV 11820.
By releasing the closing spring EV 11813 the main shaft EV 11815 rotates in the
direction shown on fig. 7/1 and in turn the control disk EV 11820 transmits the
rotational movement to the cam follower EV 11836 and operating lever EV 11835.
The output shaft EV 11816 is thereby rotated and the circuit breaker is closed via
operating lever EV 11848 and connecting rod compl. EV 11780/EV 11822.
Simultaneously, opening spring EV 11814 is charged.
When the output shaft has rotated by 60o, the control disk pawl passes over the cam
follower EV 11836 and then the output shaft is released and can rotate in the
opposite direction.
However, this is not possible as long as holding cam EV 11847 is held by lever EV
11832 and blocking hook EV 11834 of the opening unit. The closing spring EV
11813 is automatically recharged again.
At power failure the closing spring can be recharged by hand with had crank EV
11812 (FSA 1).
In this position the following indications are visible :
- Position indicator : “I” (circuit breaker in closed position)
- Spring charge indicator : “Spring charged”
1HYB800001-38 Rev. A
Page 6
The operating mechanism is ready for another rapid closing operation but the
interlock hook EV 11833 prevents the execution of a closing operation, while the
circuit breaker is closed. Both springs (EV 11813 and EV 11814) remain charged
and both shafts are blocked by the two blocking units (EV 111810 and EV 11811).
4. Erection
4.1 Delivery
Each circuit breaker is delivered with its corrosponding operating mechanism which
is packed separate or already mounted on the circuit breaker pole beams. At
delivery both springs are uncharged and the circuit breaker is in open position.
The operating mechanism must be mounted on the circuit breaker according to the
instruction for erection and operation of the circuit breaker.
5. Commissioning
5.1 Function tests
Function tests are performed after the commissioning work and immediately before
the circuit breaker is taken into service, as well as after overhaul work.
Function tests may only be performed with the circuit breaker disconnected from the
high-voltage system and filled with SF6-gas to 0.7 MPa (abs).
5.1.1 Manual operation
For this purpose hand crank EV 11812 is used for charging the closing spring. When
the closing spring has reached the desired tension, it automatically uncouples the
pull hook (EV 11830) of the main shaft, thereby releasing the hand crank.
During these trial switching operations the position indicators (EV 11824 and EV
11825) and the counter must be tested for proper functioning.
1HYB800001-38 Rev. A
Page 7
The motor should be turned on only after the hand crank has been removed, even
though it is uncoupled automatically when the motor is started.
The charging of the closing springs starts as soon as the motor supply is switched
on. The supply of power to the motor is turned off automatically (by microswitch EV
11826) when the closing spring is adequately charged.
- Proper functioning of the operation mechanism should be tested by several
CLOSE and OPEN switching operations.
- Also a test for correct functioning of the selector switch LOCAL-REMOTE
should be performed.
- Motor running time for charging springs at rated voltage : < 15 seconds.
6. Maintenance
6.1 Duty-related overhaul (Fig. 7/1)
After 2000 CO Switching operations the following parts must be cleaned and
lubricated without being disassembled :
- Cam follower EV 11836 with roller shaft, greased with grease G, (Mobile
Grease 28*)
- Worm gearing EV 11819 (worm and worm wheel), grease G (Mobile Grease 28)
- Rollers of levers EV 11832 of closing and opening units, grease L (Aseol
Sylitea 4-018)
Clean and lubricate the machined surfaces of the following cams :
- Control disk with pawl EV 11820, grease L (Aseol Sylitea 4-108)
- Holding cam EV 11847, grease L (Aseol sylitea 4-108)
Treat the worm surfaces of the following pins or cranks with :
- Crank pin EV 11853, grease L (Aseol sylitea 4-108)
- Spring fixation pin EV 11856, grease L(Aseol sylitea 4-108)
- Spring fixation pin EV 11857, grease L(Aseol sylitea 4-108)
- Crank with switching cams EV 11828, grease L(Aseol sylitea 4-108)
Change the following details of the connection rod if required (Fig. 2/2):
- Rod end joint EV 11858 or EV 11782 (in case of obvious wear)
- Bellows EV11781 when there are cracks in material, leaks.
No work is allowed to be carried out until the closing and opening springs are
discharged, and the circuit breaker is in the OPEN “O” position. The power to the
motor must be disconnected.
*As an alternate to Mobile Grease 28, Molykote Long term 2 plus or Aseol Sylitea 4-
108 may be used.
1HYB800001-38 Rev. A
Page 8
7. Spare parts
For ordering, the following data are essential :
- Order number See order documentation
- Type designation See rating plate
- Serial number See rating plate
- Publication number See spare parts list
- Part number See spare parts list
- Design Outdoor
- Part designation See spare parts list
Reserve parts :
8 Appendix
8.1 Figures
Fig. Title
Fig. 2/1
1HYB800001-38 Rev. A
Page 13
ABB Ltd.
Maneja, Vadodara
Gujarat, (INDIA)
Tel. : +91 265 2642141
Fax : +91 265 2638918, 2638911
visit us at : www.abb.com