Guideline 0.2 Commissioning Process For Existing Systems and Assemblies 2015
Guideline 0.2 Commissioning Process For Existing Systems and Assemblies 2015
Commissioning Process
for Existing Systems and
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Assemblies
ASHRAE Guidelines are scheduled to be updated on a five-year cycle; the date following the Guideline number is the year
of ASHRAE approval. The latest edition of an ASHRAE Guideline may be purchased on the ASHRAE website
(www.ashrae.org) or from ASHRAE Customer Service, 1791 Tullie Circle, NE, Atlanta, GA 30329-2305. E-mail:
[email protected]. Fax: 678-539-2129. Telephone: 404-636-8400 (worldwide) or toll free 1-800-527-4723 (for orders in
US and Canada). For reprint permission, go to www.ashrae.org/permissions.
Includes real-world examples that illustrate application of the Cx Process to various facility,
system, or assembly types. Requires Microsoft Word®.
Copyrighted material licensed to University of Toronto by Thomson Scientific, Inc. (www.techstreet.com).
ASHRAE Guideline Project Committee 1.2
Cognizant TC: 7.9, Building Commissioning
SPLS Liaison: Donald M. Brundage
K. William Dean,* Chair Richard B. Casault* David F. Moser*
Thomas E. Cappellin,* Vice-Chair David E. Claridge* Keshwar B. Ramjattan*
Scott L. Gordon* Charles E. Dorgan* Reinhard G. Seidl*
J. Robert Atkins, Jr.* Gerald J. Kettler* Holly R. Townes*
James W. Bochat* Natascha S. Milesi Ferretti* Markham R. Wheeler Jr.*
Barry B. Bridges* Mark F. Miller* Ronald J. Wilkinson*
* Denotes members of voting status when the document was approved for publication
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Waller S. Clements Arsen K. Melikov James K. Vallort, CO
John F. Dunlap Mark P. Modera
James W. Earley, Jr. Cyrus H. Nasseri
SPECIAL NOTE
This Guideline was developed under the auspices of ASHRAE. ASHRAE Guidelines are developed under a review process, identifying a Guideline
for the design, testing, application, or evaluation of a specific product, concept, or practice. As a Guideline it is not definitive but encompasses
areas where there may be a variety of approaches, none of which must be precisely correct. ASHRAE Guidelines are written to assist professionals
in the area of concern and expertise of ASHRAE’s Technical Committees and Task Groups.
ASHRAE Guidelines are prepared by Project Committees appointed specifically for the purpose of writing Guidelines. The Project Committee
Chair and Vice-Chair must be members of ASHRAE; while other committee members may or may not be ASHRAE members, all must be technically
qualified in the subject area of the Guideline.
Development of ASHRAE Guidelines follows procedures similar to those for ASHRAE Standards except that (a) committee balance is desired
but not required, (b) an effort is made to achieve consensus but consensus is not required, (c) Guidelines are not appealable, and (d) Guidelines
are not submitted to ANSI for approval.
The Senior Manager of Standards of ASHRAE should be contacted for
a. interpretation of the contents of this Guideline,
b. participation in the next review of the Guideline,
c. offering constructive criticism for improving the Guideline, or
d. permission to reprint portions of the Guideline.
DISCLAIMER
No further reproduction or distribution is permitted.
ASHRAE uses its best efforts to promulgate Standards and Guidelines for the benefit of the public in light of available information and accepted
industry practices. However, ASHRAE does not guarantee, certify, or assure the safety or performance of any products, components, or systems
tested, installed, or operated in accordance with ASHRAE’s Standards or Guidelines or that any tests conducted under its Standards or Guidelines
will be nonhazardous or free from risk.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Energy Audit, and a Building Tune-up ................................................................................................................ 39
Informative Annex D: Documentation Matrix for Commissioning Process for Existing Buildings and Assemblies................... 42
Informative Annex E: Request for Qualifications and Team Selection ..................................................................................... 43
Informative Annex F: Roles and Responsibilities...................................................................................................................... 45
Informative Annex G: Existing-Building Commissioning Plans ................................................................................................. 47
Informative Annex H: Existing-Building Commissioning Process Program Plan for Multiple Facilities..................................... 48
Informative Annex I: Current Facility Requirements Workshop ................................................................................................ 50
Informative Annex J: Current Facility Requirements................................................................................................................. 53
Informative Annex K: Existing-Building Documentation and Records ...................................................................................... 56
Informative Annex L: Existing-Building Commissioning Process Report .................................................................................. 57
Informative Annex L1: Assessment Report .............................................................................................................................. 58
Informative Annex L2: Investigation Report .............................................................................................................................. 60
Informative Annex L3: Implementation Report ......................................................................................................................... 62
Informative Annex L4: Measurement and Verification Report .................................................................................................. 63
Informative Annex L5: Training ................................................................................................................................................. 64
Informative Annex L6: Lessons-Learned Workshop ................................................................................................................. 68
Informative Annex M: Systems Manual .................................................................................................................................... 69
Informative Annex M1: Facility Guide ....................................................................................................................................... 71
Informative Annex N: Ongoing Commissioning Report ............................................................................................................ 73
Informative Annex O: Existing-Building Commissioning Process Resources .......................................................................... 74
No further reproduction or distribution is permitted.
NOTE
Approved addenda, errata, or interpretations for this guideline can be downloaded free of charge from the ASHRAE
Web site at www.ashrae.org/technology.
© 2015 ASHRAE
1791 Tullie Circle NE · Atlanta, GA 30329 · www.ashrae.org · All rights reserved.
ASHRAE is a registered trademark of the American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
Copyrighted material licensed to University of Toronto by Thomson Scientific, Inc. (www.techstreet.com).
(This foreword is not part of this guideline. It is merely The process places an emphasis on planning and on doc-
informative and does not contain requirements necessary umentation of the CFR early on, with updates throughout as
for conformance to the guideline.) needed. Owners adopt the EBCx to achieve their stated objec-
tives and criteria as defined in the CFR. The CFR must appro-
FOREWORD priately describe these criteria as understood at the beginning
The Commissioning (Cx) Process for existing systems and of the process and must be modified as new information is
assemblies is an organized, quality-oriented process for plan- uncovered.
ning, assessing, investigating, implementing, verifying, and The Assessment, Investigation, and Implementation
documenting that improves the performance of facilities, sys- Phases are critical to making a difference in a facility, but the
tems, and assemblies to meet defined operational require- most overlooked phase is the OCx Phase, which is used for ver-
ments and criteria for the facility over time. ifying and sustaining the actual performance of the facility over
time. If the Owner does not continue to verify system perfor-
The Existing-Building Commissioning Process mance improvements, those benefits are likely to deteriorate or
The Existing-Building Commissioning (EBCx) Process is disappear in future years. The development of facility staff
used by Owners and/or other facility decision makers to opti- training modules, including documents on how the building
mize the operation of their facilities and systems for their spe- works (facility guide), are critical to maintaining long term
cific Current Facility Requirements (CFR). The process is performance in anticipation of the inevitable staff turn-over.
used to plan facility operation programs and goals and then The Cx Process as presented herein allows the Owner to
compare existing conditions and operations to those goals. reduce the life-cycle cost of the facility. Following this inte-
This evaluation allows the Owner to determine if any of the grated process should result in a fully functional facility, with
existing conditions require or warrant further attention. The complete documentation of its systems and assemblies, and
process is also used to identify the causes of existing problems trained operating and maintenance personnel.
and shortfalls in achieving the CFR and to determine methods
for resolving those problems. Most importantly, the process EBCx Process Supporting Technical Guidelines
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
provides the Owner with a logical decision-making approach ASHRAE Guideline 0.2 presents details on the Cx Process for
to evaluate, compare, prioritize, and implement recommenda- existing systems and assemblies without focusing on specific
tions for making their facilities operate as efficiently and systems or assemblies. Supporting technical guidelines are
effectively as is economically feasible given the Owner’s spe- being developed to provide specific and detailed information
cific requirements and resources. When physical changes to on how to implement the Cx Process for each major facility
the facility are required as a consequence of the EBCx Pro- system or assembly. However, the EBCx can be implemented
cess, all such modifications must meet applicable codes per- successfully without the supporting technical guidelines.
taining to the work being performed. Additionally, following Supporting technical guidelines use a common content
the process allows Owners to maintain the benefits of these organization that is closely coordinated with Guideline 0.2 to
implemented recommendations over time. avoid repeating Cx Process information that is conveyed in
The EBCx Process differs from the Cx Process for new this guideline. This common content organization, with focus
buildings in that the Cx Team for existing buildings is selected on system-specific information, forms a set of documents that
and charged with evaluating existing-building systems and can be employed together or in any combination to accommo-
assemblies to determine their ability to meet the Owner’s date varying Owner requirements.
CFR, which may differ from the original design.
This guideline details a process that can be applied to any Annexes
type of building, system, or assembly. The EBCx Process con- Annexes are included with this guideline to assist users in
sists of distinct phases with specific objectives to be achieved applying the Cx Process for existing systems and assemblies
during each phase in order to identify and correct operational and to aid in the development of the supporting technical
and functional issues that prevent the building systems and guidelines. Most of the annexes include examples located
assemblies from performing as currently required. The process online at www.ashrae.org/G02-2015. The examples are
involves the following phases: Planning, Assessment, Investi- based on specific project experience and are presented as a
gation, Implementation, Hand-Off, and Ongoing Commission- representative sample of current practice, which may not fol-
ing (OCx). This guideline describes the responsibilities of the low all of the procedures presented in this guideline. They
Cx Team and the documents and reports needed to provide a illustrate application of the Cx Process to various facility,
No further reproduction or distribution is permitted.
uniform, integrated, and consistent approach for maintaining, system, or assembly types. They are not intended to promote
operating, and managing assets to meet the Owner’s and other specific formats for the various deliverables related to the Cx
stakeholders’ ongoing requirements. Process but to help illustrate how the guideline can be put
The process detailed in this guideline is presented as lin- into practice.
ear. In reality, the process probably will be iterative and inter-
active, where many tasks and even some phases are performed History of Cx Process Guidelines
more than once as needed for the specific facility and systems. Development of guidelines for the Cx Process began formally
The documents used and created in this guideline are living in 1982 when ASHRAE formed a committee to document best
documents that will need to be updated throughout the EBCx practices to achieve facilities that performed according to the
Process. needs of the Owner and other stakeholders. ASHRAE published
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
line to detail the EBCx, along with supporting technical ing and/or its systems and assemblies. The process focuses on
requirements guidelines for different building systems. This planning, investigating, implementing, verifying, and docu-
resulted in both ASHRAE Guideline 0.2, The Commissioning menting that the facility and/or its systems and assemblies are
Process for Existing Systems and Assemblies, as well as an operated and maintained to meet the CFR, with a program in
expansion of the commissioning guideline series. place to maintain the enhancements for the remaining life of
the facility.
1. PURPOSE
facility guide (FG): a basic building systems description and
1.1 The purpose of this guideline is to describe the proce- operating plan with general procedures and confirmed facility
dures, methods, documentation, requirements, and physical operating conditions, setpoints, schedules, and operating pro-
activities of the Commissioning (Cx) Process for existing cedures to properly operate the facility.
buildings, systems, and assemblies using the principles devel-
oped in ASHRAE Guideline 0, The Commissioning Process. functional performance test protocol: a written collection of
tests that, when executed in the test process, allow verification
2. SCOPE of the performance of a system or assembly.
2.1 This guideline applies to existing buildings, systems, and issues and resolution log: a formal and ongoing record of
assemblies. problems or concerns and their resolution that have been
raised by members of the Cx Team during the course of the
3. DEFINITIONS Cx Process.
acceptance: a formal action taken by a person with appropri- Measurement and Verification (M&V) Plan: a plan for gath-
ate authority (which may or may not be contractually defined) ering relevant data over time to evaluate performance and
to declare that some aspect of the project meets defined benefits.
requirements, thus permitting subsequent activities to pro-
Multiple-Facility Program Plan: a strategic plan for enhanc-
ceed.
ing multiple facilities.
commissioning (Cx): see Commissioning (Cx) Process.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
4.1 Section 4 provide an executive summary of the Existing- ensuring that improvements remain in place, as appropriate,
Building Commissioning (EBCx) Process with sufficient over time, through training, documentation, and putting
information to allow users to determine the value of using the mechanisms in place to regularly check the performance and
process to enhance the value of their assets, increase produc- the improvements.
tivity, and reduce operating costs, including energy and main-
tenance costs. 4.6 Table 1 summarizes the EBCx Process phases and lists
the major activities and deliverables in each phase. The
4.2 This guideline builds on the quality principles of the objectives of each phase are as follows.
Commissioning (Cx) Process that were developed for new
buildings as described in Guideline 0-2013, The Commission- 4.6.1 The objectives of the Multiple-Facility Planning
ing Process. Key components of this process include the fol- Phase are to clearly define the expectations of the EBCx Pro-
lowing. gram and establish processes and procedures necessary to
successfully implement the program across a group of build-
4.2.1 Use a team.
ings, systems, or assemblies. The decisions made here will be
4.2.2 Involve stakeholders of and in the facility. based on the defined goals and specific facility types to be
4.2.3 Develop a conceptual plan for multiple facilities and/ included in the program. The final objective of the phase is to
or projects. develop a master or strategic EBCx Program Plan to be used
4.2.4 Determine functional needs and requirements of the as a guideline for the execution of the program across the
facility. selected facilities.
4.2.5 Document performance of current and required sys- 4.6.2 The objectives of the Assessment Phase are to estab-
tems and assemblies. lish the CFR or ensure that an existing CFR includes all nec-
essary information, to assess the facility’s suitability for an
4.2.6 Make obvious low-cost repairs.
EBCx Plan, and to develop a course of action to execute the
4.2.7 Identify, analyze, and recommend improvements. EBCx Plan.
4.2.8 Implement approved recommendations and improve-
4.6.3 The objectives of the Investigation Phase are to
No further reproduction or distribution is permitted.
ments.
understand and document existing conditions and perfor-
4.2.9 Measure and verify performance and benefits. mance to identify improvements that bring the facility into
4.2.10 Identify persistence of benefits and improvements. compliance with the CFR.
4.2.11 Produce a functional systems manual for facility 4.6.4 The objective of the Implementation Phase is to exe-
operations. cute the recommendations selected from the Investigation
4.2.12 Provide training or retraining to operations and Reports. Verify performance meets the CFR. Report the
maintenance (O&M) staff and occupants. results of implementation.
4.2.13 Develop a lifetime Ongoing Commissioning (OCx) 4.6.5 The objectives of the Hand-Off Phase are to provide
program. the completed documents from the EBCx to the Owner, pro-
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
(Section 8) • Implement Capital Projects (8.3) • Updated CFR
• Update EBCx Team (8.4) • Updated EBCx Report, including the
• Incorporate Informal Training (8.5) addition of the Implementation Report
• Update EBCx Plan (8.6) • Updated systems manual material
• Implement Recommendations (8.7)
• Verify Completed Recommendations and Performance (8.8)
• Update the EBCx Documentation (8.9)
• Obtain Owner Acceptance and Decision to Proceed (8.11)
Hand-Off • Develop OCx Plan (9.2) • EBCx Report, including the addition of
(Section 9) • Assemble Systems Manual (9.3) the Lessons-Learned Report
• Train Facility Personnel (9.4) • Systems manual, including facility
• Verify Training Effectiveness (9.5) guide
• Conduct Lessons-Learned Workshop (9.6) • OCx Plan
• Finalize EBCx Report (9.7)
• Provide Project Documents to Owner (9.8)
• Obtain Owner Acceptance and Decision to Proceed (9.10)
Ongoing • Assemble the OCx Team (10.2) • Updated OCx Plan
Commissioning • Update the OCx Plan (10.3) • Updated CFR
(OCx) • Verify Achievement of CFR (10.4) • Updated systems manual
(Section 10) • Investigate Unacceptable Performance or Outcome (10.5) • OCx Report (made periodically)
• Implement Recommendations (10.6)
• Update Systems Manual (10.7)
• Update Facility Personnel Training (10.8)
• Write/Deliver OCx Report (10.9)
• Obtain Owners Acceptance (10.11) No further reproduction or distribution is permitted.
vide training to the Owner’s personnel, and to incorporate les- 4.7 Table 1 and this guideline present the process as occur-
sons learned from the Cx Process into the day-to-day O&M ring in a linear fashion. In reality, the process is often iterative
procedures in the facility. and interactive where many tasks and even some phases are
4.6.6 The overall objective of the OCx Program is to ensure performed more than once, as needed, for the specific facility
that the benefits obtained from the EBCx Plan and any other and systems.
building improvements are sustained over time and improved 4.8 The complete list of deliverables in Table 1 may not be
if possible. OCx involves performing critical elements of the required or desired due to factors of project size, complexity,
process, repeatedly over a series of cycles, with periods typi- funding, time, etc. The decision regarding which deliverables
cally lasting from months to years. to provide is performed by the EBCx Team, as they have the
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
single report that documents the measures implemented, les-
sons learned, changes made to the systems, a report on the 5.2.1.1 The success of the EBCx Program will depend
improvements realized, and the facility guide (FG). greatly on the decisions made during the development of the
program mission, goals, objectives, and procedures. As a
4.9 The application of this guideline will depend on the CFR;
result, the individuals chosen to participate in the program
how the original facility was designed, built, and modified;
development are essential to the success of the program. The
the condition of the present systems and equipment; and the
team selection should begin with establishing a Commission-
current operational requirements. The process described in
ing Authority (CxA), with experience in applying the Cx Pro-
this guideline is written in a generic (non-system-specific)
cess to existing buildings, to lead and facilitate the Cx Team.
manner so as to be applicable to most situations, and so must
This person will be responsible for the overall development of
be adapted to each facility as needed.
the EBCx Program Plan. The EBCx Program team leader or
4.10 This guideline describes the Cx Process for existing sys- CxA may be an in-house person who is familiar with the facil-
tems and assemblies and is supplemented by companion tech- ities and systems under consideration or may be an outside
nical guidelines. Each supporting technical guideline describes entity with experience in the EBCx Process. The existing-
specific and detailed information to properly implement the Cx building program team leader will then work with the Owner
Process for existing systems and assemblies for a specific facility to identify the necessary team members to aid in the develop-
system or assembly. ment of the overall EBCx Program Plan. Proper selection of
the CxA is key to the success of the project. Annex E includes
5. MULTIPLE-FACILITY PLANNING examples of Requests of Qualifications (RFQ) for selecting a
5.1 Introduction CxA with the full breadth of skills and experience necessary
5.1.1 The Multiple-Facility Planning Phase is intended for for the particular commissioning project.
Owners considering employing the EBCx Process on multi- 5.2.1.2 The remaining team members should include a
ple facilities. This approach may also be applied to single combination of engineering and management facilities, key
facilities that need to be addressed in stages. This section is unit or functional managers, engineers and architects (espe-
meant to help Owners establish the goals, objectives, and exe- cially those in project planning and programming for capital
No further reproduction or distribution is permitted.
cution strategy of an EBCx Program to be implemented projects), financial management, maintenance personnel, and/
across a portfolio of buildings. Those Owners or other deci- or key occupants of the types of facilities under consideration.
sion makers who decide to apply the EBCx Process to a sin- The members chosen should have specific knowledge of the
gle facility may proceed directly to Section 6, “Assessment.” operational requirements and status of the buildings and infra-
The same process can be applied to a single large facility, structure as well as an understanding of the overall financial
such as a large corporate, public, or private building (includ- goals and restrictions that will be placed on the program. To
ing large residential complexes) in phases. When funds are assist in setting priorities, the key occupants on the team
restricted, the process may even apply to a small facility, such should have an understanding of the specific challenges
as a combined grade-school building in a small community or within their facility types as well as what functions may be
to a small hospital. This section concludes with the comple- affected by the EBCx Process.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
level of discussion will provide the members with enough
understanding to allow them to provide meaningful input for process and gain experience with the teams executing the
the overall program plan and for setting goals and priorities. projects.
5.2.4.3 Determine a method for ranking the order of the
5.2.2.1.2 Program Goals. Discuss and define the over-
facilities in which the EBCx Program will be applied. The
all goals and the mission of the EBCx Program and document
order may be determined by factors other than the empirical
in an EBCx Program mission statement. The goals of the pro-
evaluation criteria used to rank the facilities. Other possible
gram may be centered on outcomes such as the improvement
methods for prioritizing the order in which buildings are
of energy performance, occupant comfort, productivity,
scheduled for EBCx may include the following:
extending the life of facilities, or a combination of desired
outcomes. It is important to define the mission of the EBCx a. Highest return for the effort, such as a facility with high
Program early in the overall program development. Define opportunity for reduction in energy or operational cost.
specific goals to develop a means to achieve the desired out- b. Highest productivity return to the organization, such as for
come. Establish benchmarks and methods for measuring suc- a large data center.
cess. This discussion can be used to establish a mission c. Facilities most critical to the organization’s mission.
statement for the multiple-facility program. The final mission d. Selecting less complicated candidates first to refine the
statement should be concise and unambiguous in defining the process before undertaking more complicated projects.
purpose and expectations of the program.
5.2.2.1.3 Facility Identification. Identify what facili- 5.2.4.4 The discussion of ranking metrics will also lead to
ties will be included in the program. Discuss and generally a determination of what data and materials will need to be
assess the overall portfolio of facilities under consideration gathered and analyzed. Determine who will gather the neces-
and determine the most appropriate way to group the facilities sary data to complete the ranking analysis.
by categories, such as space use. Develop a plan for bench- 5.2.5 Measurement and Verification (M&V)
marking the performance of the buildings around the metrics 5.2.5.1 Discuss the manner in which the benefits of the
to be used for evaluation. Metrics may include occupant den- program will be quantified. The EBCx Program will result in
No further reproduction or distribution is permitted.
sity (staff and client/guest); income or profit per unit area or benefits that can be both measured and verified. The EBCx
facility; environmental quality/satisfaction; use effectiveness; Program Planning Team will need to discuss the level of
fire/life safety compliance with current codes; maintenance/ detail that will be required when documenting the benefits
service needs or cost; annual net cost per unit area; annual obtained.
energy use per unit area, including demand charges; intensity 5.2.5.2 In some cases, Owner and/or contractual require-
of contribution toward meeting the organization’s mission, ments may dictate the use of and compliance with specific
and other criteria appropriate for the overall facility. M&V protocols. If a specific M&V protocol is required, the
5.2.2.1.4 Exclusions. The discussion may also be used team will need to discuss and understand the requirements of
to determine what facilities or facility types may be excluded the protocol to be used, who will be responsible for execution,
from further consideration. and what options may be applicable based on the building
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
the program will not be available for their normal duties for
program is measured. List the types of facilities and systems
certain periods. The type and quantity of outside resources
included, the benchmarking methods and metrics used to rank
may also be dictated by the required expertise for the systems
the facilities, and the resources required to implement the pro-
to be included in the program. In addition, the type and quan-
gram.
tity of resources may be different for different building types
and/or what systems will be evaluated. 5.3.2 The EBCx Program goals and objectives document
should be based on the input gathered from the Owner and
5.2.7.2 Budget. The required personnel resources (inter-
EBCx Program Planning Team. Once completed, the docu-
nal or external) will have a cost impact on the program. When
ment should be reviewed by all planning team members to
using internal resources, they may require additional equip-
verify the document accurately represents the expectations of
ment and training to complete the tasks associated with the
the team. The final approved document will be used as the
EBCx. When using outside resources, the costs associated
guideline for how the program will be executed and the
with individual tasks must be estimated to establish what
results judged.
level of funding will be required. The sequence of funding
needs to be addressed. Set a budget for the program using 5.3.3 Based on the information gathered, document the ini-
either in-house or contracted resources. tial budget and schedule for the program. Include initial gen-
eral estimates for the overall cost and timeframe for the EBCx
5.2.7.3 The use of modeling software programs for evalu-
Program for the buildings under consideration. It should be
ating initial and/or predicted facility performance can be use-
understood that these are rough estimates as they are prelimi-
ful in identifying opportunities for improvement as well as
nary. More accurate estimates of costs and benefits will be
quantifying the expected cost benefits, but can also require
established during the Assessment Phase for each facility.
significant cost to employ.
After a few facilities have been completed, the program plan
5.2.8 Expected Benefits. Discuss the expected benefits of can be updated with more accurate information and the pro-
the program, such as energy efficiency, energy efficiency gram reevaluated. This is especially true when the facilities
through reduced energy demand, productivity enhancements, are similar but located throughout the country or world.
occupant comfort, code compliance, and other benefits that
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
m. EBCx Program Planning Team (name, affiliation,
and title) 6.2 Define Owner’s EBCx Goals and Objectives
6.2.1 The Owner must be willing and able to assist the
5.5.2 The development of an EBCx Plan for each of the pri- EBCx Team in defining the goals and objectives of the EBCx
oritized individual facilities is discussed in the following sec- Plan in real, measurable terms for meeting the current needs
tions of this guideline. and requirements for the facility. The Owner’s role is crucial
5.6 Planning Phase Deliverables for the team to determine the appropriate methods and steps
5.6.1 EBCx Program Plan to address the Owner’s specific needs and for allowing deci-
sion makers to logically evaluate the findings.
5.7 Obtain Owner Acceptance and Decision to Proceed
6.2.2 The goals and objectives should address the benefits
5.7.1 The Owner reviews the EBCx Program Plan and related to issues such as comfort, health, safety, maintenance,
either accepts it in total or makes comments. operations, control, energy, sustainability, sales, profits, satis-
5.7.2 If the EBCx Program Plan is acceptable to the Owner, faction, aesthetics, productivity, code compliance, etc.These
then the team will continue the process for the recommended goals and objectives will be used to bring focus to the EBCx
facility as described in Section 6. Plan going forward. If the overall goals and objectives of the
5.7.3 If the EBCx Program Plan is not acceptable, the process are clearly defined, this will have an impact on the
EBCx Program Planning Team should be assembled to dis- approach taken to the types of systems included and the level
cuss and if possible resolve the issues raised by the Owner of testing conducted.
and resubmit the plan for the Owner’s review. 6.2.3 Conduct an EBCx Planning Meeting. Assemble
key decision makers to develop an understanding of the
6. ASSESSMENT EBCx. The meeting should begin with an overview descrip-
6.1 Introduction tion of the EBCx and the impacts this could have on the oper-
6.1.1 The Assessment Phase consists of preparatory activi- ation of the facility. Once the process has been described, the
ties of the EBCx Process in which Current Facility Require- discussion should focus on what the specific process goals
No further reproduction or distribution is permitted.
ments (CFR) and an Existing-Building Commissioning and objectives will be and what systems and assemblies will
(EBCx) Plan are developed and defined for a single facility, be included.
and an assessment of the facility is performed. If the EBCx 6.2.3.1 If EBCx Program goals and objectives were
Process is being deployed for multiple facilities, then the defined during a Multiple-Facility Planning Phase meeting
Multiple-Facility Planning Phase must first be completed as (Section 5), those global objectives that are applicable to the
described in Section 5. The purpose of the Assessment Phase specific building under investigation should be discussed here
is to gain enough of an understanding about the individual or may be updated for the specific facility being commis-
facility to develop an initial scope, schedule, budget, and gen- sioned.
eral approach for the Investigation Phase as well as an esti- 6.2.3.2 Once the goals and objectives have been dis-
mate of potential opportunities to improve the facility cussed, the discussion should then move toward what level of
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
members to achieve the stated goals of the project. The CxA
6.2.4 Document the overall EBCx Plan goals and objec- plays a vital role in ensuring that the roles and responsibilities
tives agreed on during the EBCx planning meeting. The docu- are properly defined, well communicated, and continually
ment should include the specific building systems and met by the team members.
assemblies to be included and the expected outcome. The
6.4 Develop CFR
document should also define what impacts the process will
have on the facility operations with regard to such issues as 6.4.1 A cornerstone of the EBCx Plan is the establishment
staff resources, facility access, potential system interruptions, of a document defining the CFR. Owners, users, and occu-
etc. The document should define the established rules of pants have specific requirements for their facilities to support
engagement for coordinating the activities required with min- their mission. When a building is originally constructed, the
imal disruption to facility operations. This document should specific requirements are defined based on the expected use
be sent to all stakeholders involved in the development to of the facility. After occupancy, the specific functions of the
ensure agreement with the results. facility or individual spaces may evolve away from their orig-
inal use. Examples of changes that can occur over time
6.3 Select the Initial EBCx Team include remodeling or repurposing of spaces and changes in
6.3.1 Form the initial EBCx Team to oversee, implement, operation of systems.
and accomplish the EBCx Plan activities. The members of 6.4.2 Developing a CFR that reflect the present needs and
this team may vary throughout the process based on the sys- requirements of the Owner, the users or occupants, service
tems and assemblies being commissioned and the issues iden- and operating units, and if appropriate, the community, is an
tified during the process. The initial team will consist of the essential task for effectively and efficiently developing the
Owner or Owner’s representative, the Commissioning EBCx Plan goals and objectives. Having an effective and effi-
Authority (CxA), and other appropriate members based on cient means to gather and document the CFR early reduces
the goals of the process and the systems and assemblies to be the risk of discovering important needs of the facility after
included. substantial work has been completed.
6.3.2 The CxA will be responsible for leading the team 6.4.3 The CFR defines the manner in which a building is
No further reproduction or distribution is permitted.
throughout the entire process. This may be an in-house person actually used, current operational needs, and potential future
who is familiar with the facilities and systems under consider- requirements for the facility. The requirements defined within
ation or may be an outside entity with experience in the EBCx the CFR must be obtained from all levels of the facility staff,
Process. If the former, the person should become familiar occupants, users (including customers, clients, and visitors),
with the EBCx Process. service contractors, and management.
6.3.3 The EBCx Plan contains logical milestones at which 6.4.4 The CFR should include information from existing
the team must determine the next course of action. Since this sources, EBCx Program Plan requirements (as appropriate to
process requires team members with various skill sets for the the building), the information developed during the EBCx
systems, assemblies, and issues under consideration at differ- Team meetings, data gathered during the initial walk-through,
ent times throughout the process, the Owner must commit and conclusions from the CFR workshop(s).
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
oping the CFR.
a. Scope and activities of the Cx Process
6.4.6 The document needs to include an overview of the 1. Specific systems, assemblies, components, and opera-
facility use and general information regarding the specific tions on which to focus
environmental, functional, and operational conditions that
must be maintained in order to support the mission. The CFR 2. Specific issues to address
should identify any known issues with the building or build- 3. Known issues to investigate
ing systems and assemblies that need to be addressed to sup- 4. Known issues to correct immediately
port the overall facility mission. This may include projects b. Estimates of schedule and budget
under consideration in planning or design by the Owner’s c. Expected benefits of the Cx Process
capital project program. d. Team members’ roles and responsibilities for subsequent
6.4.7 Once defined, the CFR provides the criteria from phases
which scope, acceptance, and operational decisions are evalu- e. Investigation Phase and verification requirements
ated. The CFR document should define specific, measurable 1. Known areas of performance that do not meet the CFR,
targets wherever possible, such as achieving a specific carbon and a plan to bring the performance into compliance
footprint. However, there may be some instances where the
2. Any system testing that may require interruptions of
information is more conceptual in nature, such as improving
facility operations
sustainability.
3. M&V requirements and approach
6.4.8 Measurable targets may include baseline require-
4. Approach to ensuring persistence of benefits
ments for the facility that will be used as a metric for deter-
mining how well the building systems and assemblies are 5. Methodology and intensity of data gathering
performing. The EBCx Plan will be used to identify areas of 6. Field measurement and testing approach
performance that do not meet the CFR, develop a plan to f. Hand-Off Phase activities
bring the performance into compliance, and implement the 1. Training requirements and Training Plan
solutions agreed on. 2. Approach for developing the systems manual and
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
on-site investigations might commence. The schedule should IV. Facility Operations
also set milestones and target dates. The initial budget should 1. Facility guide, including operating plan; building and
include a defined amount for the known activities to occur in equipment operating schedules, setpoints, and ranges;
the process as well as an estimate or range of costs for the systems operation control sequences, limitations,
unknown aspects of the process (such as implementation) emergency shut-down actions
based on previous experience. 2. Janitorial and cleaning plans and procedures
6.5.6 The scope of the EBCx Plan will vary from one facil- 3. Maintenance plans, procedures, checklists, and
ity to another and from one phase to another within a facility records
as more information is obtained in each phase. This uncer- 4. Maintenance schedules
tainty will most likely result in an iterative process wherein an 5. Maintenance record keeping
initial scope of work and budget is authorized and then subse- 6. Utility measurement and reporting
quent data that is gathered indicates that scope changes are
required. Once the changes to the scope and budget are modi- V. Training
fied, the additional data gathering may warrant further scope 1. Training plans and materials
and budget changes. 2. Training application and troubleshooting
6.5.7 Establish the format, style, content outline, and loca- 3. Training records
tion for the documents that are assembled and created as part
VI. Commissioning (Cx) Process Report
of the EBCx Plan for the facility. This shall be noted in the
EBCx Plan. Determine the level of access stakeholders will 1. Cx Plan
have to the content and who will be responsible for updating 2. Testing reports
the content. Engage information technology experts when 3. Verification forms—completed
electronic media formats and storage are selected to assist and 4. Functional performance forms—completed
advise on issues such as backup storage of information, pass- 5. Issue logs and item resolution
word protection and access levels, wireless access, and
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
d. Building, systems, and assembly information only for in a good understanding of the building systems and assem-
equipment/system changes during EBCx blies, their state and condition, and the operational parameters
e. Facility guide currently in place. It is important that this information be well
f. Utility measurement and reporting if the EBCx’s focus is documented as it provides the initial comparison of building
on utilities performance against the criteria defined in the CFR. This
baseline information also serves as part of the M&V used to
g. Training plans and records
measure benefits and performance obtained through the
h. EBCx final report
EBCx Process. In cases where specific M&V protocols are
6.7 Perform Assessment required, care should be taken to adhere to acceptable meth-
6.7.1 The purpose of the assessment is to understand ods for gathering and documenting baseline conditions.
enough about the facility to develop an initial scope, sched- 6.7.3 Even though the assessment may conclude that fur-
ule, and budget for the EBCx, as well as to identify potential ther full investigation of the systems and assemblies may not
improvements that arise from the EBCx. It is not a full evalu- be warranted, training, facility documentation, and OCx may
ation but rather a cursory data gathering and brief walk- still be needed to meet the CFR for a well-functioning facility.
through of the facility, resulting in sufficient information to 6.7.4 Issues and Resolution Log. Create and maintain an
develop the EBCx Plan and assess the benefits of proceeding issues and resolution log containing detailed descriptions of
with the process. This assessment may include the following the findings and recommendations from the initial assess-
activities, which will be performed in more detail during the ment. This log is maintained through the entire EBCx Process
Investigation Phase: and should reference the CFR with respect to identified
issues.
a. Determine availability of existing documents and gather
those easily obtained that are needed for the systems man- 6.7.4.1 The following information should be considered
ual. for inclusion in the issues and resolution log:
b. Identify missing documentation that will impede the pro- a. Issues
cess.
1. Unique numeric or alphanumeric identifier for the issue
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
of the recommendation the CFR
5. Method used to document implementation of the rec- c. Results obtained from benchmarking analysis and any
ommendation, including type of M&V postimplemen- established baselines
tation data gathered d. Current operating parameters for building systems
e. Hand-Off e. Benefits anticipated by this process, such as enhancing
1. Method of training operators occupant functional needs and reducing energy, mainte-
2. Method of maintaining ongoing performance of the nance, and/or operational costs
recommendation f. Immediate improvements conducted during this phase and
their benefits
3. Identification of any changes to the CFR
g. Assessment of whether or not the process can help the
6.7.4.2 On a periodic basis, at least for each EBCx Team facility meet the Owner’s objectives
meeting, an updated issues and resolution log should be gen- h. Estimates of costs, benefits, and duration for implement-
erated with a review of outstanding issues and new recom- ing measures to correct each nonconforming CFR item (as
mendations to enhance the facility. known at this time); includes the measures implemented
6.7.4.3 In subsequent phases, resolution of the issue may during the Assessment Phase
identify other issues or require further investigation. New rec- i. Initial time schedules for the major milestones in the pro-
ommendations may be identified. cess
6.7.4.4 Throughout the EBCx Process, keep the issues j. Initial budgets for the process, broken out by major mile-
and resolution log updated with current information related to stones where known
each issue. k. Training requirements
6.7.5 Correction of some issues and the identification of l. Systems manual outline and FG outline
opportunities may require revising the CFR. Other issues may m. Initial approach for M&V and any initial baselines gath-
not be corrected until a later phase of the process. Update the ered
CFR as required. n. Initial approach to ensure persistence of benefits
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
was developed and the Owner decides not to proceed, the contractors
Owner and team should refer back to the EBCx Program Plan f. Users and occupants
to determine the next facility to be assessed and begin the 7.3 Conduct Investigation Planning Meeting
Assessment Phase on that facility. Submit an updated priori-
7.3.1 The Investigation Phase planning meeting should
tized list of facilities for the Owner’s review.
provide an overview of the EBCx Plan and review findings
7. INVESTIGATION from the Assessment Phase. This is an opportunity to bring
new team members up to speed with the EBCx activities and
7.1 Introduction to provide a refresher to existing members if considerable
7.1.1 The Investigation Phase consists of the detailed site time has passed since their last involvement. This meeting is
investigation, which compares the actual building conditions also the time to review the EBCx goals and objectives, spe-
and system performance with the Current Facility Require- cific tasks to be accomplished during the Investigation Phase,
ments (CFR). On a technical level, the Investigation Phase roles and responsibilities, schedules, milestones, and budgets
reveals existing conditions in the building, evaluates the need so that everyone understands their roles and how their tasks
for change, and identifies requirements for additional sys- impact other team members and the overall process.
tems, assemblies, or additions. The benefits and economics of 7.3.2 This meeting should accomplish several objectives.
each change are documented with a tentative timeline for 7.3.2.1 Review the CFR. If the CFR is older than one
implementation. Some issues that are discovered during the year, or if there are known changes since the CFR was devel-
Investigation Phase can be corrected with minimal time and oped, verify that the conditions on which the CFR was based
effort, do not require additional evaluation, and can be docu- are still valid. If the needs and requirements have changed
mented immediately. This phase concludes with the comple- since the initial CFR was prepared, update the CFR. This ver-
tion of the Investigation Report, which identifies scope and ification will document the current use and occupancy levels
benefits of recommended facility modifications and improve- to determine if additional tasks are required, such as a new
ments as well as the improvements already implemented dur- functional use in the building or new safety codes.
ing the Investigation.
7.3.2.2 If there are sufficient changes to the CFR and
No further reproduction or distribution is permitted.
7.1.2 The objective of the Investigation Phase is to under- additional assessment activities are warranted, conduct addi-
stand and document existing conditions and performance to tional assessment.
identify improvements that bring the facility into compliance
7.3.2.3 Update the CFR with any new information related
with the CFR.
to facility requirements. Note changes to the following items
7.1.3 Main Activities in the updated CFR:
7.1.3.1 Update the Existing Buildings Commissioning
a. Functional activities or users
(EBCx) Team.
b. New goals and expectations
7.1.3.2 Conduct investigation planning meeting. c. Space utilization
7.1.3.3 Review facility documentation. d. Occupancy and activity level
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
the site investigation and testing increases acceptance of the building systems surveys.
process, increases staff awareness of how to identify perfor- 7.4.4 Review Documents. Categorize and review existing
mance issues, and provides an understanding of how issues documents and develop a means of adding documents as the
identified affect overall building performance. This knowl- investigation proceeds.
edge increases the ability of the O&M staff to maintain per-
sistence of the benefits obtained from the EBCx and 7.4.4.1 A detailed review and analysis of documents
encourages continued identification of performance enhance- assists in creating the framework for each team’s investigation,
ments during the OCx Phase. as well as which investigational methods are appropriate.
7.3.2.7 Discuss measurement and verification (M&V) 7.4.4.2 Detailed review may reveal information about the
requirements for the project. This discussion should focus on probable original basis of design, existing record design, and
baseline testing that may be required. In cases where specific the current operational procedures. Attempt to determine
M&V protocols are required, this may have an impact on the deviations between the current operations, original facility/
manner in which testing is conducted. systems design, and CFR.
7.3.2.8 Discuss Training. The Investigation Phase repre- 7.4.4.3 Goals of this detailed review may include items
sents a unique opportunity for informal training of the facility such as the following:
O&M Staff. Provide training to familiarize the O&M staff on
the EBCx Process and their roles, responsibilities, and expec- a. Understanding potential problem areas to investigate
tations. Informal training through participation in the investi- b. Understanding the design of building systems, assemblies,
gation process composes much of the training achieved during and controls related to the scope of the EBCx Process,
the Investigation Phase. including, for example, architectural floor plans, locations
7.3.2.9 Convey schedules, milestones, budgets, and other of structural components, and various mechanical, plumb-
items defined during the Assessment Phase to team members. ing, fire, life safety, indoor air quality (IAQ), laboratory,
7.3.3 Meeting Notes. Document decisions and significant and electrical systems and assemblies No further reproduction or distribution is permitted.
discussions for meeting participant review and for inclusion c. Creating a list of specific equipment and assemblies to
in the Investigation Report (see Section 7.5). evaluate during the site investigation based on the scope
of the project
7.4 Review Facility Documentation
d. Gathering relevant information on the equipment and
7.4.1 Assemble Existing Documents. Building documenta-
assemblies to be commissioned
tion gathered and reviewed during the Assessment Phase now
goes through a more detailed review process. Attempt to find 7.4.4.4 Review will almost always include the following:
documents or information noted as “not gathered” or “miss-
ing” during the Assessment Phase that is required for the a. Interactions between building systems, subsystems, and
investigation activities. Documents include a wide variety of assemblies—for example, building envelope elements that
information for a given building: maintenance records, utility may influence HVAC system performance
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
potential for improvement. Typically, the investigation does
not thoroughly address every system and assembly in the 7.5.1.6.3 Test procedures should be documented in test
facility. Conduct the following activities and include related forms that include the following:
information in the Investigation Plan. a. Purpose of the test
7.5.1.1 Describe the equipment, systems, and assemblies b. Participants required for the test
that will be included in the investigation, the level to which c. Schedule for testing
each of these items will be investigated, and the activities that d. Precautions, including potential risks and disruptions
will be conducted during the investigation. e. List of tools and/or equipment (ladders, test meters,
7.5.1.2 Determine if any tests are required or known prior gauges, sensors) required, means of access (keys, security
to the site investigations. Develop a list of presite visit tests codes), safety procedures (asbestos, specialty gases), and
and prepare a written description of the intended tests. This site protocols (sign-in, gowning, ID checks)
should identify who will do the tests and when they will be f. Accuracy and calibration of instrumentation
completed. g. Prerequisites for the test
7.5.1.2.1 Identify any changes in the operational state h. Step-by-step instructions for conducting the test. For each
of existing systems planned as part of the tests, and identify step of the test, include the following:
potential risks and disruptions. Changes in the operation of 1. Parameters and physical quantities to be measured
existing systems or assemblies may also result in risk to the 2. Baseline information and measurements that need to
Owner’s process. In the case of a critical facility or hospital, be recorded for the M&V approach
for example, conduct a risk assessment with the Owner and 3. Expected performance and range of acceptable results
key personnel to ensure that systems or assemblies are not 4. Observed performance and if it is acceptable or not
taken out of operation without approval. (pass/fail). (This information is recorded during the
7.5.1.3 Describe the interviews to be conducted with test.)
facility stakeholders to augment direct investigation of sys- 5. Back-out and return to normal procedures
tems and assemblies. Identify which stakeholders are to be
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
7.6 Perform Site Investigation and Testing
sensus on the EBCx Plan goals. This series of discussions
7.6.1 Carry out physical inspections and tests to evaluate
may reveal new, relevant information that was not previously
condition and performance as detailed in the approved EBCx
included within the CFR. This new information should be
investigation plan, and record observations and data. The abil-
evaluated to determine if it is potentially relevant to the cur-
ity to meet the CFR may be gauged by observation, testing of
rent CFR. If it is not, it may be incorporated into a separate
components without interference in their operations, and by
analysis for prioritization at a later date. If the new informa-
changing their operational state to produce a comparison
tion is deemed to be significant to the current CFR, the infor-
between desired and actual conditions and results.
mation should be presented to the stakeholders in order to
7.6.2 It is important not to draw final conclusions until the evaluate and update the CFR.
entire site investigation process is completed. Interim possible
7.6.6.1 Discussions with facility staff may also reveal rel-
root causes of likely problems should be listed and analyzed
evant information about operational strategies such as proce-
by comparing measured test data, observations, discussions
dures, processes, and policies that would assist in achieving
with users and occupants, facility operating data, record docu-
the CFR. Evaluate the following subjects:
ments and other information resources to the expected or
desired conditions, data, or CFR. Development of hypotheses a. Operator knowledge of proper building maintenance pro-
based on initial, gathered, or measured data or information cedures and preventative maintenance programs
may be very useful in determining additional information and b. Condition and performance of components, equipment,
data required to either confirm or reject the hypothesis. systems, and assemblies included in the investigation
7.6.3 Implement and document immediate improvements c. Deferred maintenance impact on annual building opera-
to the operation of the facility to eliminate obvious issues so tions and maintenance cost budgets
they do not mask underlying major issues, especially as they 7.6.7 Performance evaluation may include active and pas-
relate to achieving the CFR. sive testing. Execute the tests and repeat as necessary to
7.6.4 The EBCx Team needs to meet at regular intervals obtain conclusive information about the performance of sys-
during execution to monitor progress and to discuss intermedi- tems. The test results may highlight differences between
No further reproduction or distribution is permitted.
ate results and findings. The frequency will depend on the actual performance and expected performance in record docu-
complexity of the project and the number of subteams ments, or perceived performance as relayed by building ten-
involved. In many cases, this may be a short daily meeting, ants or operators. Test procedures and forms developed earlier
followed by longer meetings as determined by team members. in the process when creating the investigation plan should be
7.6.5 The two elements of physical site investigation are used when conducting active and passive testing.
condition evaluation and performance evaluation. Condition 7.6.7.1 Active tests involve placing systems and assemblies
evaluation includes an assessment of the installed condition into particular operating states to observe their response. This
of the equipment, systems, and assemblies, such as appear- typically involves physical interactions on site and changes
ance, physical damage, deterioration of condition, upgraded such as turning power on or off, opening or closing assemblies,
features, and change of use. Performance evaluation includes placing components under load and then unloading them, etc.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
lenges. On completion, test records are formatted as specified 7.7.2 Review information gathered from any previous com-
in the test procedures. This may involve configuration of missioning activities to increase understanding of issues that
fairly large electronic data files from recording equipment. affect the building’s condition and performance.
The CxA reviews these records and performs any analysis 7.7.3 Update the issues and resolution log with identified
required to provide executive level information to the Owner issues and related recommendations.
and EBCx Team so that the ability of systems to meet the
7.7.4 Analyze costs and benefits of recommendations.
CFR is presented in nontechnical terms.
7.7.4.1 Develop initial pricing estimates for implement-
7.6.7.3 The use of automated data collection and record-
ing recommendations. Base estimates on the experience of
ing systems is extremely valuable for trending parameters,
cost estimators or on contractor pricing obtained with prelim-
understanding actual sequences of events, and compiling
inary performance specifications that are less detailed than
large quantities and varieties of data from sensors, devices,
construction documents.
and equipment. It is important that such data collection sys-
tems, whether permanently installed or temporary/portable, 7.7.4.2 Develop estimates for the economic benefits
be accurate and synchronized. related to implementing recommendations.
7.6.7.4 Some testing may be deferred for seasonal rea- 7.7.4.3 Note that the benefit value of an investment may
sons, due to equipment change-out, movement of occupants, not be directly convertible into an economic equivalent. Other
or other reason. Keep a list of deferred testing and investiga- considerations include environmental quality, litigation aver-
tion to remind the team of what may need to be completed sion, productivity, etc. Nevertheless, methods exist for deter-
after the bulk of the investigation is finished. mining the level of comfort for occupants, such as occupant
comfort surveys. Comfort isn't addressed in Annex C1. These
7.6.8 The evaluation procedures should start at the compo- can be obtained at low cost and executed before changes are
nent level and proceed in increasing levels of interdependence made, as part of the establishment of a baseline, and after
through equipment, systems, and complete facilities. While it changes are made, to gauge effectiveness of measures taken.
is difficult to define exactly what constitutes these levels, the
7.7.4.4 Assess the financial viability of recommenda-
complexity of a system is often proportional to the number of
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
break-out of alternative products, services, and recommenda- tive based on the Owner’s investment criteria
tions for implementation. The Owner can then select options d. Recommendations that would not result in a substantial
that best meet the objectives desired and choose the method benefit
of implementation. Each approach will have costs and bene- e. Recommendations that the Owner has indicated would
fits that may be compared by performing analyses based on never be implemented due to Owner preference
the Owner’s criteria or desired analysis approach. These f. Deferred investigation
might range from simple payback calculations to life-cycle
Note that recommendations not selected by the Owner for
cost analysis.
implementation may affect the extent to which the CFR is met.
7.7.5.5 The CxA advises the Owner on benefits and short-
7.8 Update EBCx Report with Investigation Report
falls of recommendations listed and assists in narrowing the
scope of the project by selecting specific approaches for more 7.8.1 At the end of a review period during which the previ-
detailed information gathering or by removing approaches ous steps may be repeated iteratively a number of times, cre-
deemed inappropriate or undesirable by the Owner. ate an Investigation Report. The report contains the largest
number of approaches that meet the CFR criteria and initial
7.7.5.6 The list serves as a tool that is updated through a
budgetary requirements. The Investigation Report informs the
refinement period during which approaches are evaluated,
Owner’s staff about the scope and viability of possible correc-
refined, and removed, and during which new approaches can
tive actions. The report also includes calculations and field
be added. This refinement period may include several itera-
investigation results. The report contains all major elements
tions through the Assessment and Investigation Phases.
developed during the investigation process, including the fol-
7.7.5.7 Typical information to include in the list of find- lowing.
ings and recommendations includes the following from the 7.8.1.1 Documentation of changes implemented during
issues and resolution log: the Assessment and Investigation Phases.
a. Issues 7.8.1.2 List of findings and recommendations.
1. Unique numeric or alphanumeric identifier for the 7.8.1.3 Calculations and supporting documentation
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
8.3 Implement Capital Projects
tives, scope, and budget of the work; or other activities.
8.3.1 Typically, most recommendations fit within the EBCx
7.10.2 If the Investigation Report is acceptable to the
Process as described in this guideline. However, some recom-
Owner, then the Team will continue the process as described
mendations may more accurately be categorized as capital
in the EBCx Plan for the Implementation Phase.
projects due to their higher costs, longer implementation
7.10.3 If the Investigation Report is not acceptable, the times, or intensive design requirements. Capital projects are
Investigation Phase team should be assembled to discuss and, normally selected and procured by the Owner, and most of
if possible, resolve the issues raised by the Owner and resub- these projects require processes outside the scope of the
mit the Investigation Report for the Owner’s review. If the EBCx Process. In some cases, these capital projects affect the
Owner decides not to proceed with the Implementation Phase EBCx Plan. These recommendations should be handled as
for the specific facility just assessed, the CFR, EBCx Plan, described herein.
and Assessment and Investigation Phase reports should be
filed for future reference and the process stopped for this 8.3.2 Capital projects are normally conducted outside the
facility. If an EBCx Program Plan was developed for multiple EBCx Plan and do not affect the EBCx Plan or its completion.
facilities, the Owner and team should refer back to the Pro- 8.3.2.1 It is important that continuity be maintained
gram Plan to determine the next facility to be assessed and between the EBCx Plan and the commissioning of the capital
begin the Assessment Phase for that facility. projects. It is recommended that the Owner utilize the same
Commissioning Authority (CxA) for the capital projects as
8. IMPLEMENTATION they do for the EBCx Plan so that the responsibility of
8.1 Introduction achieving the performance promised remains with the EBCx
Team. This also helps ensure that changes to the building
8.1.1 During the Implementation Phase, the Owner decides systems integrate well with the EBCx system improvements.
which Investigation Report recommendations to implement.
The selected recommendations are implemented and evalu- 8.3.2.2 These capital projects should be managed as sepa-
ated to verify that they achieve the expected benefits and sat- rate projects and commissioned in accordance with ASHRAE
isfy the Current Facility Requirements (CFR). Guideline 0. The EBCx Plan continues independently of the
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
8.4.3.1 Coordinate and schedule participation of the 8.6 Update the EBCx Plan
Owner’s representatives for activities in implementation. 8.6.1 The EBCx Plan is updated to include the details
Owner’s representatives’ participation may vary from one needed to address implementation and verification of the
activity to another, both in number and in the specific individ- selected recommendations. The following elements should be
uals. It is necessary for Owner’s representatives to participate addressed as described below:
in EBCx Team meetings, review the Cx Process and reports,
discuss changes to the CFR, and participate in staff and occu- a. Implementation Plan
pant training. Owner’s representatives also participate in b. Implementation Verification Plan
reviewing submittals and developing contracts with designers c. Training Plan
and contractors needed to implement recommendations. d. Measurement and verification (M&V) Plan
Owner’s representatives may also participate in implementing
recommendations and witness testing. 8.6.2 Create Implementation Plan
8.4.3.2 The O&M Staff should be included in the develop- 8.6.2.1 The EBCx Plan includes an Implementation Plan.
ment and review of the implementation plan of all recommen- This plan includes the details of roles and responsibilities of
dations. Some recommendations can be self-implemented by EBCx Team members, including identification of new team
the Owner’s in-house staff. This level of involvement will members. It establishes lines of communication between new
ensure that the staff understands the recommendations and team members and the Owner. In addition, a review and
what level of coordination and planning is important to ensure update of defined levels of authority for team members as
the recommendations achieve the desired results. This could approved by the Owner may be needed at this point. It also
include involving the staff in the development of the verifica- includes the details of the implementation of recommenda-
tion testing procedures. tions. For each recommendation selected by the Owner, the
Implementation Plan includes the following:
8.4.3.3 The CxA should coordinate the activities of con-
tractors’ and designers’ forces with those of the Owner’s staff a. Participants in the implementation and their roles and
for all activities in the EBCx Plan. responsibilities
b. Schedule of implementation coordinated with occupants,
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
executed to ensure that corrections and improvements were prior to commencing actual implementation of the recom-
successfully implemented such that systems meet the CFR. mendations, the EBCx Team should conduct a kick-off meet-
This means the focus of tests and their description of ing with the Owner’s representative and any selected outside
expected system responses may change, and the inclusion of providers and/or contractors. The purpose of the meeting is to
pass/fail parameters may also be included to indicate where review the roles of each party, resolve any misunderstandings,
systems need to undergo additional corrections before being finalize the schedule, and ensure the updated EBCx Plan is as
found acceptable. complete as needed by the Owner. During the meeting the fol-
8.6.3.2.3 Update the physical inspection and test pro- lowing should take place.
cedures developed in the Investigation Phase and prepare 8.7.3.1 Review the updated EBCx Plan. In addition,
documentation required to verify that the recommendation review the specific roles and responsibilities of contractors or
installation and performance meets the CFR. consultants and the Owner’s in-house staff to clarify who will
8.6.3.2.4 These verification procedures should include implement recommendations and who will verify.
a quality-assurance component and subsystem and system- 8.7.3.2 Review any needs for M&V baseline develop-
level performance tests and physical inspections. The level of ment to ensure the defined baseline data are in place prior to
effort and resources required will vary for each different rec- making changes.
ommendation.
8.7.4 Conduct Site Visits for Verification. Periodically,
8.6.3.3 The Owner reviews and accepts the Implementa-
appropriate EBCx Team members should visit the job site to
tion Verification Plan prior to verification activities being per-
verify installation of the recommendations. These visits pro-
formed.
vide an opportunity to identify issues early in the implemen-
8.6.4 Update Training Plan. Update the formal Training tation that may not be able to be resolved later or cost more to
Plan to include any changes made as a result of Implementa- resolve later. Distribute site visit reports through agreed-on
tion Phase activities. Ensure that the training addresses all of communication channels. Any observed deviations from the
the implemented measures and changes to the operating pro- plan(s) should be reported and recorded as part of the issues
cedure. and resolution log.
No further reproduction or distribution is permitted.
8.6.5 Update M&V Plan. The M&V Plan must be updated 8.7.5 Update Issues and Resolution Log. Update the issues
based on the known scope of work for improvement measures and resolution log. As issues arise during the Implementation
to be implemented. The M&V Plan should include the details Process, document the issues and track their status and resolu-
for baseline and performance period testing that will be tion on the already established issues and resolution log. See
required for quantifying the performance and benefits of the Section 6 for items to include in this log.
process. In cases where specific M&V protocols are required,
the M&V Plan should include the specific means and meth- 8.8 Verify Completed Recommendations and Performance
ods necessary to comply with the requirements of the chosen 8.8.1 Conduct the verification testing once installation is
protocol option. If necessary, add specific M&V procedures complete as required in the updated EBCx Plan and devel-
required to verify the final benchmark or goal. The Owner oped in the Implementation Verification Plan.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
8.9.1 Update the CFR to include any changes that occurred cable.
during the Implementation Phase. 8.9.4 In the EBCx Report, list the specific CFR items that
8.9.2 Update the EBCx Plan on completion of deferred and were to be addressed through EBCx (from the EBCx Plan),
seasonal tests. This update includes deferred and seasonal test and the level to which those CFR items were achieved by the
procedures and results. end of the Implementation Phase. For any CFR items that
8.9.3 Update the EBCx Report to include the Implementa- were not fully achieved, describe why those items were not
tion Report along with an executive summary that includes achieved and include recommended next steps. This should
which recommendations were implemented and their bene- supplement the verification documentation discussed in Sec-
fits, plus important future work. Many of these documents are tion 8.9.3.8.
also in the systems manual for the facility. The Implementa- 8.9.5 The systems manual is updated to include any new
tion Report includes the following. information for components, assemblies, and systems that
8.9.3.1 Updated list of findings and recommendations, have been modified or installed as part of the implementation
including an update to the benefit analysis. The final imple- process. Update the facility guide (FG) to include any
mented recommendations may differ from the original rec- changes to operating procedures that occurred during the
ommendations due to conditions uncovered during the Implementation Phase.
implementation process. 8.10 Implementation Phase Deliverables
8.9.3.2 Updated persistence strategy for each recommen- 8.10.1 Updated EBCx Plan
dation.
8.10.2 Updated EBCx Report, including the addition of the
8.9.3.3 If capital projects were performed as part of the Implementation Report
overall process, incorporate the Cx Report into the Implemen-
8.10.3 Updated systems manual materials
tation Report.
8.9.3.4 List of implementation recommendations that 8.11 Obtain Owner Acceptance and Decision to Proceed
should be carried out in the future. 8.11.1 Decide if the selected recommendations have been
No further reproduction or distribution is permitted.
8.9.3.5 Test Documentation. Test procedures, documen- completed to the Owner’s satisfaction.
tation, and results. This includes the original test procedures 8.11.2 If any new discoveries are made during Implementa-
and data forms, plus data such as photos, computerized docu- tion activities, the Owner decides, based on EBCx Team rec-
mentation, and other records of the tests. Both the final ommendations, if additional investigation work is required.
accepted test and earlier tests that failed to meet the specified This iterative process is integral to EBCx. If a discovery dur-
criteria are included. Once deferred/seasonal testing is com- ing implementation requires additional investigation, the pro-
pleted, the report is updated to include the deferred testing cess for this specific discovery begins at the Investigation
results. Provide a complete set of test procedures and blank Phase. If the Owner chooses not to proceed with further
data forms, etc., for future use for each implemented recom- investigation at this time, the item will be documented in the
mendation. information transferred at hand-off.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
and process recommendations are documented while the changes in the CFR, FG, and systems/assemblies.
information is fresh in the minds of team members. 9.2.1.8 Monitoring and evaluating system performance
regularly to verify compliance with the CFR and against pre-
9. HAND-OFF viously established benchmarks. For example, through review
9.1 Introduction of occupant satisfaction surveys, trend logs, complaint logs,
9.1.1 The Hand-Off Phase is the transition between the service tickets, and utility use. See Section 7 for further guid-
Existing-Building Commissioning (EBCx) Team and person- ance.
nel responsible for operating and maintaining the facility over 9.2.1.9 Describing procedures necessary to maintain the
the remainder of its life cycle. During the Hand-Off Phase, persistence of building performance.
the EBCx Team works to ensure that the required documenta- 9.2.1.10 Ongoing training of O&M personnel and occu-
tion in the EBCx Report has been completed and is consistent pants on the current CFR and the current systems/assemblies.
with the EBCx Program (if one exists) and the EBCx Plan. 9.2.1.11 Defining the process and procedures necessary
The Ongoing Commissioning (OCx) Plan is developed, the for satisfying the measurement and verification (M&V)
systems manual is updated and completed, and the key deliv- requirements.
erables are provided to the Owner. The systems manual and
9.3 Assemble Systems Manual
the OCx Plan are used in conjunction with the training of
facility operations and maintenance (O&M) personnel and 9.3.1 The systems manual is assembled to incorporate
occupants to ensure the persistence of the benefits. changes to assemblies and systems that occurred during com-
missioning (Cx). Documentation generated during and after the
9.1.2 Objectives. The objectives of the Hand-Off Phase are
Implementation Phase is incorporated into the systems manual.
to provide the completed documents from the EBCx to the
Owner, provide training to the Owner’s personnel, and to 9.3.2 The FG is updated to reflect changes to assemblies
incorporate lessons learned from the Cx Process into the day- and systems.
to-day O&M procedures in the facility. 9.3.3 Training documentation is added to the systems man-
ual as training is performed.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
training documentation typically includes the Training Plan,
training syllabus, training attendance records, and training 9.8.2 Provide for distribution of the M&V Reports to be
materials provided during O&M and occupant training. submitted for approval. The document should be reviewed
9.4.8 Ideally, the training sessions would be video recorded with the Owner and operations staff to ensure that the
so future O&M personnel and occupants can be trained with- required instrumentation and data collection remain in place
out having to recreate the training session. through the M&V performance period in accordance with the
M&V Plan.
9.4.9 Compile all of the training documentation into the
systems manual at the conclusion of training. 9.8.3 The information in these deliverables should be used
and kept updated throughout the life of the facility as
9.5 Verify Training Effectiveness described in Section 10, “Ongoing Commissioning.”
9.5.1 Verify the effectiveness of training within a reason-
9.9 Hand-Off Phase Deliverables
able period of the completion of each training program.
Example training verification methodologies are provided in 9.9.1 EBCx Report, including addition of the Lessons-
Annex L5. The intent of this testing is to verify that the train- Learned Report.
ees were provided with the pertinent information and can 9.9.2 Systems manual.
demonstrate their ability to operate and maintain the facility 9.9.3 OCx Plan.
to meet the CFR and ensure persistence of benefits. The
attendee sign-in sheets should be reviewed to verify that the 9.10 Obtain Owner Acceptance and Decision to Proceed
training has been delivered to all necessary personnel. 9.10.1 The Owner reviews the deliverables and any unre-
solved issues from this phase and either accepts them in total
9.6 Conduct Lessons-Learned Workshop
or makes comments.
9.6.1 Conduct a lessons-learned workshop after the com-
9.10.2 If the EBCx Report, OCx Plan, and systems manual
pletion of the training and the update of the systems manual.
are acceptable to the Owner, then the process will continue as
The lessons-learned workshop typically includes all of the
described in Section 10.
key participants and stakeholders of the Cx Process. Example
No further reproduction or distribution is permitted.
approaches to the lessons-learned workshop are provided in 9.10.3 If the EBCx Report, OCx Plan, or systems manual
Annex L6. are unacceptable, assemble the Hand-Off Phase team to dis-
cuss and, if possible, resolve the issues raised by the Owner
9.6.2 The lessons-learned workshop provides a forum for
and resubmit the plan for the Owner’s review.
the EBCx Team to discuss issues impacting the O&M of the
facility and to discuss knowledge gained during the imple- 9.10.4 If the Owner decides not to proceed with the OCx
mentation of the measures. The discussion should examine Phase for the specific facility just commissioned, the EBCx
both the execution of the Cx Process and the methods and Report and all phase reports should be filed for future refer-
issues found that affect facility operation. The intent of the ence and the process stopped for this facility.
discussion is to determine improvements in both the Cx Pro- 9.10.5 For multiple facilities, refer to the EBCx Program
cess and facility operations. Make recommendations to sup- Plan to determine the next facility to be assessed and begin
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
10.3.2 The scope of activities in the OCx Plan needs to be
Plan and any other building improvements are sustained over reviewed. This includes determining that assigned resources
time and improved where possible. OCx involves performing have the time and skills needed for each activity.
critical elements of the process repeatedly over a series of
10.3.3 The frequency of activities in the OCx Plan needs to
cycles with periods typically lasting from months to years.
be defined and reviewed by the OCx Team.
10.1.3 Main activities.
10.3.4 The OCx Plan should clearly define any remaining
10.1.4 Assemble the OCx Team. scope items from the EBCx Report, including deferred
10.1.5 Update the OCx Plan. inspections and testing, recommendations that have not yet
10.1.6 Verify achievement of CFR. been implemented, and completion status of capital projects.
10.1.7 Investigate unacceptable performance or outcome. 10.3.5 Update the CFR
10.1.8 Implement recommendations. 10.3.5.1 Review and update the CFR. For facilities that
underwent a new-building Cx Process, the CFR is the evolu-
10.1.9 Update systems manual.
tion of the Owner’s Project Requirements (OPR) established
10.1.10 Update facility personnel training. during the original Cx Process. If the facility use has changed
10.1.11 Write/deliver OCx Report. from the original design, or if a CFR does not exist, refer to
10.1.12 Obtain Owner’s acceptance. Section 6 of this guideline for information about developing
the CFR document.
10.2 Assemble the OCx Team
10.3.5.2 Review the CFR document at regular intervals to
10.2.1 The organizational structure of the OCx Team will
ensure information still reflects the status of the facility and
vary from facility to facility and from time to time. For each
its requirements. Any required updates should be made based
facility, the capabilities of the internal facility staff, service
on recommendations in the OCx Report.
contractors, and the nature of the relationship with external
professionals, commissioning contractors, and Cx Process 10.3.5.3 Changes to the CFR may also have an impact on
providers are unique. Further, over time, people move in and verification requirements for the OCx Plan and the Imple-
mentation Verification Plan.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
to identify a solution. Identify the root cause of the unaccept-
Report.
able performance. This may include condition assessment,
testing, and analysis of the results to determine the extent of 10.7.2 The FG section of the systems manual should be
the unacceptable performance or degree of deviation from updated with key performance parameters and facility operat-
desired results. Section 7 of this guideline addresses the ing procedures whenever they are changed. Establish moni-
investigation methodology. toring procedures to compare facility performance against the
baseline at frequent intervals.
10.5.2 If the diagnosis shows that unacceptable perfor-
10.7.3 Changes to the CFR will eventually arise due to
mance is due to a major changes in the CFR, the associated
changes in occupancy, use, remodeling, etc. Document the
parameters should be modified to reflect this change and the
impact of these changes in the systems manual and FG.
performance measured against the new baseline. Ensure that
the underlying issues are identified and that any needed 10.8 Update Facility Personnel Training
updates to the CFR are made. Update the facility guide (FG) 10.8.1 Facility personnel training requirements will con-
for inclusion in the OCx Report. tinue to evolve due to facility changes, operational changes,
10.5.3 Maintain the issues and resolution log to track and and staff turnover. O&M staff training should be updated at
record issues. The issues and resolution log used during this regular intervals to ensure the procedures required to maintain
phase can be similar to the issues and resolution log used in building performance are maintained. Needs for additional
previous phases. See Section 6 for items to consider for inclu- training may also arise due to changes to regulatory factors,
sion in the issues and resolution log. facility equipment, or overall facility function. The OCx
Team should regularly review the performance of building
10.5.4 Once findings and recommendations are identified,
staff to identify any needs for updated training. All operator-
they are listed on the issues and resolution log, including any
error items identified during fault correction as lessons
estimated costs and associated benefits that the action will
learned should be discussed with the staff to ensure the prob-
provide. Recommendations should include methods to main-
lems do not reoccur.
tain the benefits of the performance and improvements made
during the EBCx. 10.8.2 The training conducted during OCx should build on
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
ducted based on changes to the facility, staff turnover, or the annual report for the building. This allows a periodic
lessons learned opportunity to revise the program for the following year, with
e. Any updated acceptable performance parameters activities additions and reductions. The acceptance should
f. Any improvement recommendations accompanied by esti- acknowledge successful compliance with all activities and
mated costs deliverables in the OCx Plan. The acceptance should also pro-
g. The level to which the specific CFR items have been vide tracking for resolution of existing issues and identify any
achieved needs for conflict resolution.
10.9.2 The OCx Report should include the current results 10.11.2 If the OCx Report is acceptable to the Owner, then
of the M&V Plan. If the OCx Program requires compliance the team will continue the process into the next cycle.
with a specific M&V protocol, the material in the OCx Report 10.11.3 If the OCx Report is unacceptable to the Owner,
should be consistent with the requirements of the M&V Plan determine what the issues are and take corrective action
and be produced and submitted under separate cover. before resubmitting the OCx Report.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
air-conditioning, and refrigeration (HVAC&R) will be devel- Process Program
oped by ASHRAE. ASHRAE’s various technical committees The recommended format of the technical guidelines
will be encouraged to develop guidelines for specific topics, should follow the same format used in Guideline 0.2. The fol-
such as kitchen hoods, fire and smoke control, laboratories, lowing material presents the general organization to be used
data centers, etc. in the development of technical guidelines. To maintain con-
Technical guidelines are developed to assist the Cx Team sistent numbering between all documents, it is acceptable to
and Owner in efficiently and successfully using the EBCx denote a section, subsection, or annex as “not applicable to
Process for various systems, assemblies, functional needs, this guideline,” “no additional information for this section or
and operations and maintenance (O&M) of a particular build- paragraph,” etc. This denotation should be explained in both
ing or facility. the foreword and in Section 4, “Process Overview,” of each
It is desired that each technical guideline for a specific technical supporting guideline that is developed to support the
system or assembly in an existing building utilize the princi- general EBCx Process. The following is an example of sug-
ples and procedures of the EBCx Process described in Guide- gested wording:
line 0.2 and not redefine a new process with respect to the Throughout this guideline, various sections, subsections, and
topic (e.g., lighting or other system and assemblies) in the annexes may be marked as “not applicable to this guideline.”
supporting technical guideline. The purpose of this designation is to maintain uniformity of sec-
The objective of both Guideline 0.2 and the technical tion, subsection, and annex labeling throughout all Existing-
guidelines is to provide information on implementing a cost- Building Commissioning Process guidelines in support of
effective enhancement process for all existing buildings in Guideline 0.2.
order to increase the value of existing assets though efficient
use of energy, effective O&M, and increasing the unit pro- TECHNICAL GUIDELINE FORMAT
ductivity of in-place assets. This includes the ultimate sus- The following is an outline format to be used in the develop-
tainability objective—achieving these goals without major ment of technical guidelines in support of the EBCx Process
rehab or replacement of existing facilities. The technical developed in ASHRAE Guideline 0.2. Some sections or para-
No further reproduction or distribution is permitted.
guidelines are not intended to be a detailed user’s guide but graphs may not require procedures or documents for that
rather to provide resource guidance and information on phase or activity for the particular system or technology.
where to find detailed solutions to issues and problems in These can be noted as “not required.” The listed paragraph
existing buildings. Guidelines on the EBCx Process imple- titles come from Guideline 0.2 and are intended to provide a
mentation plan, development of Current Facility Require- framework to produce a thorough guideline.
ments (CFR), construction checklists, statistical or other In the following sections, normal text provides the
quality tools, and other detailed requirements for implement- reader guidance as to the type of information that would be
ing the EBCx Process are included in Guideline 0.2, with added to that section specific to the facility under consider-
only appropriate and limited additions in the technical sup- ation; example text is shown in small type; and variable text
porting guidelines to support the general quality process. is shown in brackets and italics.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
5.6 Planning Phase Deliverables
months, or other requirement]. However, these high-cost or high-
5.7 Owner Acceptance and Decision to Proceed
payback projects will typically be transferred from the Existing-
Building Commissioning (EBCx) Process to the Owner’s capital Section 6, Assessment Phase
planning and implementation staff or group. This transfer recog- 6.1 Introduction
nizes the difference between EBCx and rehabilitation or remod-
6.2 Define Owner’s EBCx Goals and Objectives
eling projects and retains the focus on a short-term EBCx Process
6.3 Select the Initial EBCx Team
that is not confused with projects that may extend for five, ten, or
6.4 Develop Current Facility Requirements
fifteen years awaiting implementation.
6.5 Develop the EBCx Plan
Section 1, Purpose 6.6 Establish the Systems Manual Outline
6.7 Perform Assessment
The following paragraph should be used as the general pur-
6.8 Initiate EBCx Report with Assessment Report
pose for each technical guideline: 6.9 Assessment Phase Deliverables
The purpose of this supporting technical guideline is to describe 6.10 Obtain Owner Acceptance and Decision to
the technical requirements for the application of the Existing- Proceed
Building Commissioning (EBCx) Process described in
ASHRAE Guideline 0.2 to [insert the specific topic or technol- Section 7, Investigation Phase
ogy, i.e. lighting, envelope, HVAC&R] that will allow the user to 7.1 Introduction
develop appropriate Current Facility Requirements (CFR) and 7.2 Update EBCx Team
implement changes, upgrades, or capital projects that will 7.3 Conduct Investigation Planning Meeting
achieve the Owner’s CFR for [specific technology]. 7.4 Review Facility Documentation
7.5 Update EBCx Plan
Section 2, Scope 7.6 Perform Site Investigation and Testing
The following should be used as the general scope for each 7.7 Perform Issues and Opportunities Analysis
technical guideline: 7.8 Update EBCx Report with Investigation Report
7.9 Investigation Phase Deliverables
The procedures, methods, and documentation requirements in
7.10 Obtain Owner Acceptance and Decision to Proceed
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
10.7 Update Systems Manual in Annex A if this approach is used. To enhance the value of
10.8 Update Facility Personnel Training the annex, one or more additional examples may be provided
10.9 Write/Deliver OCx Report for facilities not related to the building in Annex A. To be in
10.10 OCx Phase Deliverables compliance with Guideline 0.2, the list and numbering of
10.11 Obtain Owner Acceptance annexes must be as shown in Table A-1.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
List requirements and recommendations that relate to the example system described in Annex A.
H Existing-Building Commissioning Process Program Plan for [insert system title] System in Multiple Facilities
List requirements and recommendations that relate to the example system described in Annex A.
I Current Facility Requirements Workshop for [insert system title] System
List requirements and recommendations that relate to the example system described in Annex A.
J Current Facility Requirements Relating to [insert system title] System
List requirements and recommendations that relate to the example system described in Annex A.
K Existing-Building Documentation and Records Relating to [insert system title] System
Relate to the example system described in Annex A.
L Existing-Building Commissioning Process Report Relating to [insert system title] System
Provide documentation and records that relate to the example system described in Annex A. (This is an overview of the report.
The sub-annexes contain each element of the report.)
L1 Assessment Report Relating to [insert system title] System
Relate an example of all reports to the example facility described in Annex A.
L2 Investigation Report Relating to [insert system title] System
Relate an example of all reports to the example facility described in Annex A.
L3 Implementation Report Relating to [insert system title] System
Relate an example of all reports to the example facility described in Annex A.
L4 Measurement and Verification Report Relating to [insert system title] System
May be omitted for nonoperating systems if not required.
L5 Training Related to [insert system title] System
List requirements and recommendations that relate to the example system described in Annex A.
L6 Lessons-Learned Workshop Relating to [insert system title] System
No further reproduction or distribution is permitted.
INFORMATIVE ANNEX B
FLOWCHARTS FOR THE COMMISSIONING
PROCESS FOR EXISTING BUILDINGS
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
FIGURE B-1 Section 5—Multiple-facility planning flowchart.
FIGURE B-2 Section 6—Assessment Phase flowchart. No further reproduction or distribution is permitted.
35
FIGURE B-4 Section 8—Implementation Phase flowchart.
FIGURE B-3 Section 7—Investigation Phase flowchart.
36
Copyrighted material licensed to University of Toronto by Thomson Scientific, Inc. (www.techstreet.com).
(This annex is not part of this guideline. It is merely infor- procedures to quickly highlight performance problems and
mative and does not contain requirements necessary for guide operators in returning the systems to their correct oper-
conformance to the guideline.) ation.
An important aspect of Cx is the training provided to the
INFORMATIVE ANNEX C1 operators and system users. The creation of a training module
COST AND BENEFITS OF THE COMMISSIONING for each important system and assembly provides a learning
PROCESS FOR SYSTEMS IN legacy that remains long after the initial students have left.
EXISTING BUILDINGS AND ASSEMBLIES For complex assemblies, it can show the interdependence of
This annex provides an example of how to implement part of systems so that informed decisions are made for operation,
Guideline 0.2. It is not intended to be a comprehensive repre- maintenance, and modification. It also captures aspects of the
sentation or a best-practice example. Practitioners applying design intent so that future users will understand why certain
the Existing-Building Commissioning (EBCx) Process decisions were made and the limitations that were accepted at
should follow Guideline 0.2 and applicable commissioning the time.
(Cx) technical guidelines tailored to their specific projects.
One of the biggest obstacles to commissioning existing COSTS OF COMMISSIONING
buildings and assemblies is the lack of understanding of the Commissioning of existing buildings costs on average $0.30/
benefits of Cx. This annex will begin to quantify some of the ft2 ($3.23/m2) and has a simple payback of 1.1 years based
costs and benefits associated with the Cx Process for existing on a study of 643 buildings covering 100 million ft2 (9.3 mil-
buildings and assemblies in an effort to answer the question lion m2) by 37 commissioning providers1. In this meta-anal-
“Why should I commission this building?” ysis of Cx costs, energy-intensive industries such as health
The impetus for considering a Cx project is often predi- care and research had faster paybacks than schools and office
cated by a required change in performance, operating cost, or buildings. This study primarily focused on energy-related Cx
system function and is often associated with a special funding projects. The study suggests that there are economies of
opportunity.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
scale for costs related to commissioning. Buildings fewer
than 50,000 ft2 (4625 m2) had costs as great as $3.00/ft2
BENEFITS OF COMMISSIONING ($32.29/m2), while buildings in excess of 1 million ft2
Commissioning provides an ability to verify the existing (93,000 m2) had costs below $0.25/ft2 ($2.69/m2).
operation parameters and compare them to “as required” con- When Cx is performed for nonenergy reasons, the eco-
ditions.This is important if a facility changes Owners or occu- nomics will be related to the change in use, productivity
pants and there is a need to confirm that it can accommodate gains, improved comfort, or risk avoidance parameters devel-
its intended use. oped by the Owner and manager.
Once the systems and assemblies are documented as part Costs of Cx will depend on the team selected and the
of the Cx Process, they can be optimized for the current or amount of in-house capability that an Owner has at their dis-
revised uses. posal. Commissioning Teams can comprise in-house groups,
Commissioning of safety systems is very common and is outside contractors, or a combination of the two. It is impor-
often a regulated mandatory requirement for elevators, fire tant that everyone’s involvement be accounted for to ensure
alarms, and similar equipment or systems. When Cx princi- that adequate resources are made available at the start of a Cx
ples are applied to unregulated systems and assemblies, a project.
similar safety benefit can be realize by ensuring that all sys- The cost of commissioning existing buildings is also
tems are fully operational. spread over the various phases of work. The Planning and
Many buildings contain back-up systems that are Investigation Phases generally make up about 69% of the
intended to operate in the event of a principal system failure. total cost, and implementation accounts for 27%. The balance
Those systems are intended to mitigate the risk related to the of the initial costs (4%) covers the verification, tracking, and
failure of a related system or a similar rare event. If the sys- reporting required2. Costs related to the Ongoing Commis-
tem is not regularly inspected or commissioned, there is no sioning Phase depend on the level of M&V established to
assurance that the equipment will operate as intended when monitor performance. Often those costs become an integral
needed. This can then create a cascade failure of other sys- part of normal operations and maintenance (O&M) costs.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
b. Level 2—Energy survey and analysis mentation to diagnose and fix breakdowns quickly will the
c. Level 3—Detailed analysis of capital-intensive modifica- building be kept in good working order. One-line schematic
tions diagrams of HVAC air and water; diagrams that show loca-
Energy audits are appealing to Owners and operators tions of VAV boxes, reheat coils, and other small devices; and
because they appear to lead directly to savings. Properly con- inconspicuous local markings (for example, on ceiling tiles)
ducted, EBCx also creates fast savings through real-time cor- make O&M much easier.
rection of low-cost/no-cost malfunctions, though the benefits The EBCx Process also adds trend logging, real-time
of EBCx extend well beyond short-term savings. Unfortu- energy analysis, and/or automated fault detection and diagno-
nately, because building Owners and operators have become sis (FDD) for fast correction of failures. The transition to an
so accustomed to the idea of the energy audit since its intro- Ongoing Commissioning (OCx) Process provided by EBCx
duction thirty years ago, the EBCx Process is being forced allows the building equipment to monitor itself and provides
into that mold. savings into the future in addition to the fast payback of the
energy audit and the quick fixes of the building tune-up. Table
1. ASHRAE. 2011. Procedures for Commercial Building Energy C2-1 shows a summary of the differences between EBCx, an
Audits. Atlanta: ASHRAE. energy audit, and a building tune-up.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
specifications, O&M manuals, specifications.
and maintenance records.
Perform diagnostic monitoring — — —
and establish trend logs to
document building performance
for several weeks.
Visually inspect systems for Visually inspect systems for — —
correct installation and operation. correct installation and operation.
Perform simple repairs required — — Perform simple repairs required
to keep equipment operating, to keep equipment operating.
reduce energy use, and allow
more accurate data gathering
such as trend logging.
Perform functional tests. Perform functional tests. — —
Identify potential modifications — Identify potential modifications —
that will reduce energy use and/ that will reduce energy use and/or
or cost (includes a description of cost (includes a description of the
the measure, estimated energy measure, estimated energy
savings, cost estimate, and savings, cost estimate, and simple
simple payback). payback).
Perform an engineering and — Perform an engineering and —
economic analysis of potential economic analysis of potential
modifications. modifications.
Prepare a rank-ordered list of — Prepare a rank-ordered list of Implement improved
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
including the Lessons Learned analysis process and results.
Report.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
FIGURE D-1 EBCx documentation matrix.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
GENERAL APPROACH lio in order to help prioritize buildings with which to
This section discusses a typical approach for preparing an begin the Investigation and Implementation Phases of
RFQ for EBCx. complete EBCx projects. In these cases, which are
obviously the most resource and time intensive, out-
a. The following items are typically in the RFQ: sourcing the process to a third party may be the best
1. Qualifications for the CxA and all of their subcontrac- approach.
tors
2. Requests for work samples from the CxA on previous TEAM COMPOSITION SELECTION
EBCx projects, with a particular emphasis on projects The following discussion gives Owners guidance as to which
having a similar scope approach provides the appropriate level of resources to com-
3. Selection criteria for the project plete different types and scopes of projects. Regardless of the
4. Goals for improving building performance or operation type of project or the makeup of the EBCx Team, there is
5. Building systems that are to be commissioned great benefit and value to involving building operations staff,
6. Level and breadth of assessment and investigation, and they should always be a significant contributor to the
including measurement and verification (M&V) EBCx Team. Refer to Annex F for more information for the
requirements roles and responsibilities for all members of the EBCx Pro-
7. Description of systems with known issues, problems, cess. This information will provide further insight into the
or opportunities issues to be discussed as part of putting together the team.
Various approaches can be used to establish an EBCx
8. What building information and documentation exists
Team. The make-up will depend on the available resources
and how it will be made available to the CxA
and expertise of the building Owner’s staff. For example, the
9. Expectations/deliverables for each phase of the proj- efforts and resources differ greatly depending on the scope.
ect/process Below are some scope examples and possible team composi-
10. Anticipated timeline for each phase tions:
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
consultant to perform the analysis needed for a solid c. Review samples of work to see if what will be provided is
business case to secure funding. This scenario gives the equivalent or desired level and scope of process, con-
the Owner and operators confidence in pursuing par- tent, and documentation.
ticular opportunities based on reliable numbers. d. Include the participation of building operators and other
2. Implementation. The Owner’s staff often has the capa- appropriate company personnel in at least the submittal
bility and resources to implement some of the recom- reviews.
mendations; however, the Owner may require special e. Meet in person with consultants and the personnel who
trades and consultants for some of the implementation will be on-site doing the work.
or may not have time to implement any recommenda-
tions. EXAMPLES
3. Ongoing Commissioning (OCx). This combination Examples of RFQs from actual projects can be found at
approach may need to include all of the team mem- www.ashrae.org/G02-2015. These examples were created
bers, resources, and tools necessary to properly plan prior to the development of Guideline 0.2 and may not align
and discuss the persistence and OCx Process phases exactly with the previously outlined sections. However, they
in a multidisciplinary project. should help illustrate the overall structure and intent of an RFQ.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
OWNER k. Coordinate system and assembly testing. Verify the results
a. Include a statement regarding EBCx responsibilities and and include a summary of deficiencies.
scope in the request for services. l. Supervise the EBCx Team members in completion of
b. Assist the EBCx Team in defining the goals and objectives tests. The test data will be part of the EBCx Report.
of the EBCx Plan. m. Verify implementation of the selected recommendations.
n. Assemble or receive and review the systems manual as
c. Develop and commit to the Current Facility Requirements
submitted or revised. Verify that it achieves the CFR.
(CFR) for the facility and its use.
Insert systems descriptions as provided by the project pro-
d. Review and approve any changes made to the CFR.
fessionals in the systems manual.
e. Assign O&M personnel and schedule them to participate in
o. Periodically review record drawings for accuracy with
the various meetings and observations/inspections. Review
respect to the installed systems. Request revisions to
and approve the Multiple-Facility Planning, Assessment,
achieve accuracy.
Investigation, Implementation, Hand-Off, and Ongoing
p. Verify that the systems manual and all other design and
Commissioning (OCx) Phase reports, plans, and other doc-
construction records have been updated to include all
umentation.
modifications made during the various project phases.
f. Review the identified recommendations and select recom-
q. Repeat implementing of tests to accommodate seasonal
mendations for implementation.
tests or to correct any performance deficiencies.
g. Implement the selected recommendations.
r. Coordinate and lead the training session. This session will
h. Assign O&M personnel for training sessions.
be attended by the Owner's O&M personnel, the project
i. Review and comment on the CxA’s EBCx Reports.
professionals, the contractors, and the CxA as required.
j. Review and comment on the CxA’s testing reports.
s. Review proposed contractor/installer-provided training pro-
k. Review and accept the EBCx Report. gram to verify that the CFR is achieved.
t. Prepare the final EBCx Report.
COMMISSIONING AUTHORITY
No further reproduction or distribution is permitted.
a. Participate in all phases of the EBCx Process, including a. Prepare instructions and/or contract documents where
regular EBCx Team meetings. required, including the integration of the EBCx Process
b. Participate in the system testing process and meetings. requirements and activities provided by the CxA.
c. Review and comment on procedures for testing systems. b. Respond to EBCx Team design submission review com-
d. Participate in testing of equipment and assemblies. ments and other issues in a timely manner.
e. Assist in the identification and selection of recommenda- c. Specify and verify that the O&M of the systems and assem-
tions for implementation. blies has been adequately detailed in the contract docu-
f. Review, accept, and keep systems manual updated. ments.
g. Attend Owner training sessions. d. Review and incorporate as appropriate the CxA’s comments
h. Participate in the OCx Process. from submittal reviews.
e. Participate in the O&M personnel and occupant training ses-
CONTRACTORS OR IMPLEMENTATION TEAM
sion. Participate in other training as detailed in the train-
a. Include costs for EBCx Process activities in the contract ing program.
price or budgets. f. Review and accept record documents and systems manual
b. Include EBCx Process requirements and activities in each as required by project documents.
purchase order or subcontract written. g. Review and comment on the final EBCx Report.
c. Obtain cooperation and participation of all subcontrac- h. Recommend final acceptance of the systems to the
tors and manufacturers. Owner.
d. Attend the pre-implementation and EBCx Team meet-
ings. MANUFACTURERS/SUPPLIERS
e. Include EBCx Process milestones in the project schedule.
f. Implement the training program as detailed in the project a. Provide all information required for the O&M of the system
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
documents. or assembly as part of the initial submittal.
g. Provide submittals to the Owner, project professionals, b. Provide the requirements to maintain the warranty as part
and the CxA. of the initial submittal.
h. Notify the CxA when systems and assemblies are ready c. Coordinate and accomplish factory tests as detailed in the
for testing. contract and project documents.
i. Demonstrate the performance of assemblies and/or operation d. Provide training as detailed in the training program contained
of systems to the Owner and CxA. in the project documents.
j. Continuously maintain the record drawings and systems e. Demonstrate operation and performance of the system or
manual and submit as detailed in the contract documents. assembly as detailed in the project documents.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
research centers). c. To increase sales of frozen foods by 17%
c. Organizations with one or more buildings at many loca- d. To increase tests scores by 7% and reduce absentees by
tions (e.g., school districts, state governments, hotels, res- 50%
taurants, retail, REITs, military, and GSA). Many of these e. To enhance utilization of all assets by 10% (reduce either
will have local and organization strategic plans or pro- underused space or equipment or incorrect location func-
grams for enhancing all existing facilities. tions)
An organization should have an understanding of the The introduction should give a general overview of the
needs and benefits of the EBCx Process before simply imple- EBCx Program and describe goals, expectations, and support
menting one building at a time without any known expecta- to justify the program. It should also identify roles and
tions or an overall planned approach. They should not merely responsibilities for each EBCx Process team member for
trust the in-house professionals or third–party professionals to each facility.
adequately manage a multibuilding EBCx Program without a Program Goals and Objectives
strategic approach or plan.
This section should clearly state the overall and specific
The purpose and scope of the EBCx Program should
expectations, objectives, and goals for the program. These
match the organization’s expectations and strategic plans.
should be clearly stated and include the means by which suc-
There will continue to be organizations that will only focus on
cess will be measured. There will usually be specific goals and
reducing energy use in their existing buildings. This is worth-
objectives for each individual facility. This is an expansion of
while, but the EBCx Process has proven to achieve much
requirements to support the mission. For example, if the mis-
larger needs of organizations and the underlying enhancement
sion was to increase occupant satisfaction by 12%, then goals
of an organization’s assets.
may include identifying facility operations and design features
With a well-conceived strategic plan, the organization that impact occupant satisfaction; objectives may include
can achieve an asset management program that will lead to retaining employees and increasing productivity; and expecta-
enhancing all of their facilities. The utility of the EBCx Pro- tions may include improving profits and employee satisfaction
No further reproduction or distribution is permitted.
cess is more than providing energy savings. The results from transfers to improved customer satisfaction.
operations and maintenance (O&M) costs and benefits are
usually equal to or greater than the energy cost reductions. Building Identification and Ranking
Benefits related to enhancing the performance of the Building identification and ranking will be used to secure
building to meet the functional use, including productivity funding and to determine the order in which facilities will be
(sales, profits, education enhancement, occupant satisfaction, scheduled for the EBCx Process within an organization’s pro-
customer satisfaction, enhanced use of space and facilities, gram. It is assumed that neither all buildings nor a large build-
etc.) can be many times greater than the energy reduction ing will be economically scheduled for the EBCx Process at
when a sound plan is developed to address functional needs of one time. Priority may be assigned in order of building use,
the organization related to each of their facilities or buildings. cost to operate, functional contribution to the organization,
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
doors, walls, foundation, insulation, daylighting, etc.) them. Some Owners allocate all or a proportion of their
4. Supporting infrastructure (parking lots, power reliabil- staff and technician time for successful implementation of
ity, etc.) the assessment and evaluation phase at each building to be
allocated to training budgets. Proper training has proven to
EBCx Process Resources be a major benefit to the long-term operational and mainte-
This section should discuss the resources that are anticipated nance cost reduction achieved by the EBCx Process.
to be required to implement the EBCx Program for all the
facilities and for each system within the building. The Execution Schedule
resource list should include funding, internal staff, disruption This section should define the overall EBCx Process timeline
cost (hopefully minor compared to the benefits of the pro- schedule for each building or portion of a building. The report
gram), and contract needs to assess, investigate, and imple- and report responsibility for program progress and implemen-
ment the program. The listed resources need to describe the tation should be identified in the strategic plan. There may be
effort and involvement of management and indirectly related a requirement to identify the financial responsibility for fund-
costs, people, and other resources. ing the program. This should include all preparatory training
Evaluation of Success and resource queuing as well as the order and schedule of
building level execution. The schedule should reflect the
The means and methods that will be used to judge success established prioritization for building categories and individ-
and evaluate various aspects of the program should be clearly ual buildings.
stated in this section. For energy, this is generally related to
cost. However, this may require measurement and verification
EXAMPLE
of a specific system or installed equipment. For others, like
lighting, it can be calculated. For daylighting, it may include An example of an EBCx Program Plan from an actual project
energy reduction and an evaluation of the functional use (e.g., can be found at www.ashrae.org/G02-2015. This example
effect on occupant productivity and satisfaction). This section was created prior to the development of Guideline 0.2 and
should describe the means of measurement and verification of may not align exactly with the previously outlined sections.
No further reproduction or distribution is permitted.
the benefits for various anticipated modification or change to However, it should help illustrate the overall structure and
buildings and systems. This description should include the intent of an EBCx Program Plan.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
tal, fire chief, stockholders, tax payers, neighboring busi- very simple changes can be made to meet needs defined dur-
nesses). ing the CFR workshop. Other needs that cannot be achieved
The workshop uses the Nominal Group Technique (NGT) with the available funds or reasonable modifications to the
to effectively determine the facility’s needs to meet the func- facility. This results in many EBCx Process projects failing to
tional and productivity requirements, as well as to determine receive funding or never being proposed because the scope of
the related Owner’s needs for improved sustainability, reduced the task may be so broad that establishing a plan is over-
energy costs, and achieving environmental or carbon goals. whelming. A workshop or similar NGT helps the Owner
Other methods are available to determine the CFR for a overcome this negative inertia by developing a list of require-
specific building; however, the CFR workshop is the recom- ments and having participants rank them in order of impor-
mended method. Other methods include the following: tance. The EBCx Team and Owner’s representative will then
use these rankings to select which issues to address.
a. One or two members representing the Owner develop the
Owners should not be discouraged if the workshop
CFR using a predefined organizational CFR developed in
results need to be reviewed multiple times as the investigation
the multiphase or multiple-facility strategic plan for all
and implementation proceed. Throughout the EBCx Process,
buildings.
the CFR may be subject to change. Therefore, it is probable
b. Brainstorming sessions (not as effective as NGT in most
that additional workshop meetings will be needed as CFR
cases).
items are added, deleted, or modified and rankings changed.
c. Charrettes may be used by the Owner’s professional staff,
The CFR workshop will be only one resource for devel-
following the NGT workshop, as a problem-solving exer-
oping the CFR. Other sources include prior evaluations of the
cise for design development of the implementation
facility by inside staff and consultants. Some of these may
requirement defined during the Investigation Phase. Cha-
rettes tend to be leader-result-orientated and take more include mandatory surveys or inspections. Capital projects
time than the NGT workshop. Prior development of the may have been identified or be in progress. The operating
CFR using the NGT will make the charrette much more staff may have active work orders, or a list of needs or work
orders on hold. Service and preventive maintenance logs and
No further reproduction or distribution is permitted.
effective.
reports are good resources. The CFR workshop facilitates
The CFR is the heart of the EBCx Process. The work- bringing all stakeholders together to discuss their mutual
shop guidance for the CFR differs from that in Annex I of needs and develop a ranking of their best combined needs and
Guidelines 0 and 1.1 in that the goal is to establish a format requirements for a successful and functional facility.
for developing users’ and other’s needs with the existing
building’s layout and operations rather than establishing the DEVELOPING THE CFR
Owner’s Project Requirements (OPR), which form the basis There are four steps in developing the CFR:
of the design team’s requirements reflected in the Basis of
Design (BoD) for new buildings. The EBCx Process shifts a. Conduct the CFR workshop.
the emphasis from new buildings to changes to an existing b. Document the CFR (report).
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
individual to respond with as many answers and ideas as After several iterations and reviews of the CFR by the project
he or she can. and design teams, the requirements must be approved to pro-
c. Record individual responses in a round-robin fashion—no vide the design team adequate direction for their design. It is
discussion at this point, just record the responses on a flip- important to distinguish development of the CFR from the
chart, overhead, chalkboard, or multicomputer link to all traditional role of the architect in the planning or program-
participants. ming process. The CFR defines the criteria required for suc-
d. Review all responses, consolidate similar ones, and clarify cess, whereas the architect’s document may only address
so all in the group have the same understanding of all specific space size and occupant flow requirements. Where
responses. the CFR may state that the functional use of the facility is X,
e. Have individuals rank the responses in order of impor- Y, and Z, the architect’s document may specify the locations
tance (1 through 5). of, the size of, and the flow of people through X, Y, and Z.
f. Determine a group ranking from individual rankings.
g. A rediscussion of the top 10 items—and any responses SUMMARY
ranked most important—is desired, followed by a second The CFR workshop is one means to provide consistency in
round of individual and group combined rating/ranking. the implementation of the Cx Process from project to project.
The questions asked during this workshop must be broad It should be a topic addressed in the lessons-learned work-
in nature, elicit discussion, result in a variety of viewpoints, shop during the Hand-Off Phase. Other techniques for devel-
and must not leave the workshop. The questions should not oping the CFR, such as interviews and surveys, do not allow
focus on such items as “at what temperature are you comfort- interaction between the user groups. Further, it has been
able?” but should be broader, such as “how do you define shown that the results or answers are biased by the beliefs of
comfort?” or “how will you measure the cost success of this the expert who develops the questions for the interviews or
project?” (versus a broader question, such as “how will you surveys. Frequently when such techniques are used, the ques-
determine if this was a successful project?”) tions can be analyzed and the conclusions predetermined,
Example questions include the following: regardless of whether or not the interviews or surveys are
No further reproduction or distribution is permitted.
completed.
a. How do you define comfort in an ideal building?
b. What are the functional needs for this building? MEASUREMENT AND VERIFICATION
c. How will you determine the success of the EBCx Process? Many facilities will require making measurements and verify-
d. How are measurement and data requirements to determine ing current operational and equipment performance. This
the current conditions in this building? includes all buildings and assemblies. For mechanical sys-
e. What are functional needs that are missing in this build- tems, there are established measurement and verification
ing? (M&V) standards and guidelines. When there is a need to
f. How do you define “ideal indoor air quality” in a building? establish baseline performance for the equipment and/or sys-
g. What are key productivity measures for this building? tems, the accuracy of the results will be greatly affected by
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
ifications to the facility and those systems and assemblies that This section should be used to define any specific require-
are underperforming. ments of the facility occupants and users that are necessary to
As the EBCx Process proceeds through the different meet the overall mission requirements. These may be current
phases, the CFR may require updating or amending. This may facility features that must be maintained or those that need to
occur, for example, as the budget and costs change. No be added to support facility operation.
changes to the CFR will occur without the Owner’s written • Private-office occupants will be able to adjust the temperature
approval. For example, the CFR may require that new win- setpoints in the offices.
dows be impact rated certified to Category 5 hurricane level. • The ground floor (southwest quadrant) will be converted to a
If the window replacement bid exceeded the budget, the CFR
cafeteria for users and occupants of the building.
could be changed (and approved by the Owner) to design
non-impact-rated windows with provisions for field-installed Owner-Directed Requirements
protection during a hurricane.
This section should define any directives given that need to be
Developing the CFR includes contributions from all the addressed by the EBCx Process. This is an interactive process
stakeholders that use, occupy, operate, and maintain the facil-
to generate information between all of the stakeholders.
ity. The CFR will contain both technical and nontechnical
requirements (e.g., technical requirement: replace roof with an • The existing windows shall be replaced with impact-rated
R-30 roofing assembly; nontechnical requirement: comply windows in a 150 mph zone.
with LEED for existing buildings at Gold level). The CFR • The roof shall be replaced with a green roof with minimum
contains specific and measurable requirements (e.g., instead of R-35 insulation.
“the light level in offices will be adequate,” the CFR may read, • The fire alarm system shall be manufactured by Notifier.
“the light level in offices will be 40 fc measured at 30 in. • The building shall be equipped with a sprinkler system.
above the floor level”). The CFR must be concise, clear, cor-
rect, and complete to reduce the risk for any misinterpretation. Specific Facility Requirements
Some of the more general requirements for the CFR are This section should define specific functional requirements
listed below. These CFR requirements may expand or con- for each area of the facility and space use variation. This will
No further reproduction or distribution is permitted.
tract following focused discussions with the Owner. include parameters such as functional uses, space needs,
Suggested CFR content is as follows: occupancy requirements, systems or assemblies replacement,
and comfort requirements (e.g., space temperature and
a. User/occupant requirements
humidity for occupant comfort). This may also include spe-
b. Owner-directed requirements
c. Specific facility requirements, such as environmental and cific parameters for critical environments, such as tolerances
energy goals, level of systems control, and/or sustainabil- for minimum lighting levels, temperature variation, ventila-
ity certification tion rates, room pressurization, noise levels, etc. All varia-
d. Training requirements tions in occupancy schedules should be defined along with
e. Sustainability requirements any subsequent changes in operational parameters.
f. Equipment and systems maintainability requirements • Indoor lighting requirements: Offices 45 fc at 30 in. AFF.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
noise sources requiring mitigation, spaces such as classrooms • Adequately sized doors/access panels shall be provided for
that require low background noise, and short reverberation equipment replacement.
times.
Capabilities of Operators and Maintenance Team
• Other Owner requirements.
This section should define the capabilities of the operations
For example, natural ventilation, operable windows, day-
and maintenance (O&M) team, including their experience,
light.
training in specific systems and assemblies, level of educa-
Training Requirements tion, etc.
This section should define the expectations for the core com- • The HVAC chillers will be maintained by an outside vendor.
petency level of the facility personnel responsible for operat- • The Owner’s fire-alarm technicians have been factory trained
ing the facility. This will serve as an evaluating metric to and certified in Notifier systems.
determine any training requirements necessary to achieve the • All of the Owner’s technicians have obtained craft certifica-
required competency level at all necessary levels of the facil- tion from technical institutes.
ity staff.
Regulatory Requirements
• Factory or on-site training for the Owner, whether Owner
staff, contracted staff, or users/occupants, shall include a This section should define specific regulatory requirements
description and overview of systems, not just the components placed on the operation of the facility and what impacts this
and equipment that compose each system. may have on the manner in which the facility, systems, and
• Training should include general orientation and reviews of assemblies are operated, monitored, and maintained. The spe-
the written O&M instructions, relevant health and safety cific requirements may vary throughout the facility based on
issues or concerns, operation in all possible modes, preven- different functional requirements of specific areas of the facil-
tive maintenance, and common troubleshooting problems and ity. Examples would be references to specific environmental
solutions.
health and safety standards, such as College of American
Pathologists (CAP) and Clinical Laboratory Improvement
• Training shall be performed for the following building sys-
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
• Temperature changes throughout each floor shall not vary by List discount rate, period of study, escalate rate criteria
more that 4°F. for energy, etc.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
lists with nameplate information, dates of installation, and v. Recent changes documentation
submittals (cut sheets) w. Recent additions documentation
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
This is a brief description of the project. The executive sum- Lessons-Learned Report
mary should be concise and should not be more than one page Developed in the Hand-Off Phase. See Annex L6.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
would be added to that section specific to the facility under • The rear-entry door adjacent to the loading-dock area was
consideration, and example text is shown in small type. propped open, and the card reader was not operational. A
work order was submitted to repair the card reader.
ASSESSMENT REPORT OUTLINE
Summary Table
Executive Summary
Discuss any issues that were corrected during the assessment
This is a brief description of the work conducted during the inspection such as safety, security, or operational.
Assessment Phase and the overall results of the assessment,
including the initial EBCx Process scope, CFR, schedule, and a. Building and/or location
budget. The summary should include the implementation of b. Affected system
any Owner-authorized improvements and benefits anticipated c. Opportunity or corrected issue description
by the assessment process, such as enhancing occupant func- d. Related CFR and how it is being met or not met
tional needs, reducing energy, maintenance, and/or opera- e. Estimated implementation cost
tional costs. f. Qualitative benefits (e.g., energy savings, improved occu-
The Executive Summary should be concise and should pant comfort)
not be more than one page in length if possible. It should con- g. Quantitative benefits (e.g., energy cost savings)
clude with an overall recommendation for how to proceed and
h. Estimated utility incentives
next steps.
i. Estimated simple payback period or other financial metric
General Description of Facility j. Estimated energy reduction
Briefly describe the facility, including use, size, and number k. Estimated duration for implementing the opportunity
of floors; year constructed; and general overall condition. The l. Responsible party
description should include the current operating schedule and m. Next steps
a general overview of the systems that are included within the
Existing Building Documentation
EBCx program.
List the available building documentation that could be help-
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
INVESTIGATION OUTLINE the objectives of the Cx project (such as improved occu-
pant comfort) that would be realized by implementing the
The following is an example outline for an Investigation recommendation. Provide quantitative estimates wherever
Report and includes recommendations for content to include possible. Briefly describe the calculation method used to
in each section. estimate the results.
Executive Summary d. Costs. Provide the estimated costs associated with imple-
menting the recommendation, and discuss how the costs
This is a brief description of the work conducted during the
were estimated.
Investigation Phase and the overall results of the investiga-
tion. The executive summary should be concise and not more e. Cost/Benefit Analysis. Include a quantitative cost/benefit
than one page in length if possible. This summary is also a analysis of each recommendation. Examples of factors to
good opportunity to briefly restate the goals of the project, consider include energy, demand, carbon, liability, worker
including what systems or assemblies were being commis- productivity, indoor environmental quality, regulatory
sioned and why and the general approach to the investigation. issues, health, sales, and impact on other systems.
Include an overall summary of the benefits, costs, and f. Detailed Implementation Method. Discuss the specific
analysis associated with the recommendations. If the number steps for implementing the recommendation, including
of recommendations is large, consider summarizing the over- suggestions for who will do the work, interactions and
all costs and benefits related to the recommendations rather synergies with any other recommendations, and any
than including a recommendation summary table in this sec- important factors to consider, such as long lead times for
tion. Also include any recommendations for prioritization of any hardware/equipment.
implementation where appropriate. g. Implementation Verification Plan. Describe how imple-
The executive summary should conclude with an overall mentation of each recommendation will be verified. Meth-
recommendation for how to proceed and next steps. ods could include trend data/data logger analysis,
functional testing, photos, and screenshots.
Project Overview
h. Measurement and Verification (M&V). If an M&V Plan
No further reproduction or distribution is permitted.
In this section, include such information as the following: has been developed, describe how the gathered baseline
a. General building characteristics data complies with it and discuss any postimplementation
data that will be required for meeting the requirements of
1. Building type, size, and location
the plan.
2. Gross and conditioned floor area
i. Maintaining Persistence of Benefits. Provide a discus-
3. Number of floors sion of strategies that could be routinely conducted to
4. General envelope, lighting, and HVAC system descrip- ensure ongoing persistence of benefits. Identify who would
tions implement the strategies, and describe any documentation,
5. Occupancy schedules and equipment operating sched- signage, or other devices that should be implemented to
ules assist in ensuring that the changes stay in place over time.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
mentation. an Investigation Report.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Plan) and the level to which those CFR items were achieved Records of site visits and any significant reports and meeting
by the end of the Implementation Phase. For any CFR items minutes generated throughout the process.
that were not fully achieved, describe why those items were
not achieved and include recommended next steps. This Verification Documentation
should supplement the information in the “Verification Docu- Evaluations of the performance of the systems at the time of
mentation” section of the Implementation Report. test completion and the ability of the system to meet the CFR.
Identify any systems or assemblies that do not meet the CFR.
IMPLEMENTATION REPORT OUTLINE
The Implementation Report includes the following sections. Measurement and Verification (M&V) Documentation
Include documentation of any completed M&V activities.
Executive Summary
This should include the results of any and all testing con-
The executive summary includes which recommendations were ducted as part of the M&V requirements. Provide a complete
implemented and their benefits, plus important future work. set of test procedures and blank data forms, etc., for future use
for each implemented recommendation.
Updated List of Findings and Recommendations
Includes an update to the benefit analysis. The final imple- Training Documentation
mented recommendations may differ from the original recom- Provide information on any training that occurred during
mendations due to conditions uncovered during the implementation and verification, including who attended,
implementation process. Include an updated persistence strategy dates, length of time, training subjects, training materials, and
for each recommendation. trainer, where applicable.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
M&V Scope The actual measured quantities should be compared with
levels expected (or guaranteed). Any variances from the
This section should define what portions of the EBCx project
expected values should be quantified for each portion of the
are being tracked through the M&V Plan.
EBCx project being tracked separately through the M&V
The EBCx Process can be applied to several building sys-
Plan. The overall measured benefits should also be totaled
tems as well as to operations and maintenance (O&M) prac-
and tabulated.
tices. The M&V process can focus on specific portions of the
EBCx project or may employ different approaches to quantify M&V Acceptance and Approval
the benefits of different aspects of the project. The scope of The means of acceptance and approval of the M&V results
work should describe what portions of the EBCx project are must be agreed upon in advance between the Owner and those
being tracked. This may require that a list of component responsible for the M&V program. The terms agreed upon
improvement measures be kept, or it may be defined by build- must define what level of performance is required to meet the
ing system, project goal, or a combination of each. expectations of the M&V program. This section should make
M&V Methodology a determination as to whether the actual measured benefits
This section should include a brief description of the general meet or exceed the levels predicted. In the event of a savings
approach to quantifying the benefits obtained from the EBCx shortfall, the report should clearly define any identified rea-
project. This will define the specific M&V methods applied sons for the shortfall and any proposed remediation methods.
to each portion of the EBCx project scope. The M&V Plan
EXAMPLE
developed and agreed to by the Owner should be included to
define the details of specific methods and protocols to be fol- An example M&V Report from an actual project can be
lowed. found at www.ashrae.org/G02-2015. This example was cre-
ated prior to the development of Guideline 0.2 and may not
Baseline Data align exactly with the previously outlined sections. However,
This section should define the baseline data against which the it should help illustrate the overall structure and intent of an
No further reproduction or distribution is permitted.
results were measured. The baseline data will be required for M&V Report.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Prior to assessing the specific training needs of the project, missioning existing buildings.
some form of orientation to the EBCx Process should take If O&M is outsourced, the training approach and needs
place. Training should include a description of the Owner’s may differ from the approach described above.
purpose and how training aligns with the CFR. If the trainees Staff and tenant training is optional but, at the very least,
weren’t part of the initial CFR workshop, then an executive a high level of awareness of the EBCx project should be pro-
summary can help them to understand EBCx and how it’s vided, as these projects will most likely take place in the
appropriate to the building. building while it is occupied. Staff and tenants may be aware
A determination will need to be made whether or not an that something is happening, so training for regular staff
individual training manual is needed. Review the benefits could parallel training of maintenance staff to keep them
with the building manager and maintenance staff if the Train- apprised of how EBCx will affect them and how they can help
ing Plan is part of in the process.
a. a stand alone package/document, Training mainly occurs in the Hand-Off Phase, but there
b. the CFR, or are many opportunities and associated benefits with beginning
c. an existing or new systems manual. in the Assessment and Investigation Phases of the process. This
approach will vary from building to building. Training needs
Whatever shape the training manual takes, the final prod-
and opportunities will arise sooner rather than later. It is typi-
uct (or individual parts) should be visible and accessible to all
cally wise to involve O&M staff early so that the process will
appropriate current and future personnel. Other building docu-
be understood by these individuals. They may then be tasked/
ments, policies, and perhaps the building automation system
asked to assist in the Assessment, Investigation, and Implemen-
(BAS) should point to this document when issues occur related
tation Phases as a formal part of the training curriculum.
to the systems that were improved through the EBCx project.
Assessment of individual staff members’ current exper-
TRAINING PLAN tise could also be a component of early discussions, as the
training program will need to be focused and customized to
The scope of the Training Plan and manual should be suited to
suit the O&M staff’s aptitude.
the needs of each project. If the project is of a smaller scale,
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
ment are listed as follows. For each EBCx project, some train- the training should ensure that the benefits of all improve-
ing agendas will be very similar, while others will different ments to the building will be sustained through the efforts of
greatly. the building operators, maintenance personnel, and their suc-
a. Describe the project and list the building and its location cessors by way of adequate documentation, verification, and
(on agenda documentation). Owner acceptance of training.
b. Identify senior staff.
c. Recommended training regime. TRAINING ATTENDANCE DOCUMENTATION,
AND VERIFICATION
1. Trainees, their number, and which area they represent
2. Instructors, their company, and qualifications Record individual trainers and trainees after each session,
indicating the system or individual components being taught.
3. Level of detail
Verification of the training through a documentation proce-
4. Description of system operation dure should be included in the training manual or systems
5. Owner representative approval of agenda manual as determined by the Cx Plan. Verification (participa-
d. How is the improvement aligned with the CFR? tion) may use paper documentation and/or video documenta-
e. Describe the purpose of the system or component being tion, depending on the value of each method and the needs of
commissioned. the Owner and operating staff.
f. Quantified benefits where required or where critical. Training for all appropriate building operators (as
g. Will the improvement require verification and if so to selected by the EBCx Team) should be recorded and
what level? approved by operators and staff for each individual improve-
h. Service and maintenance requirements. ment and kept in the appropriate manual. The training verifi-
i. System interactions. cation shall include a checklist of items covered, name of
j. Recording of trends on BAS. trainer, name of building operator, dates of training, etc. Any
k. Reporting structure on persistence of benefits, frequency, recommendations on follow-up training or seasonal items
and who will receive such reports. should also be included, with similar verification of any sub-
No further reproduction or distribution is permitted.
l. Review any pertinent documentation (drawings and speci- sequent training added to the manual.
fications). Final documentation of the training attendance and veri-
m. Is a protocol required if improvements are discovered or fication should be stored and distributed as previously agreed
when the benefits start to slide back to the precommis- during the Cx Plan discussions. One example may be that two
sioned state? hard copies of the training or systems manual and one elec-
n. Review any safety and health issues related to improve- tronic copy of the entire document on CD or DVD be deliv-
ments. ered by the CxA to the building Owner at the end of the
o. System recovery procedures after service interruptions. Hand-Off Phase. Individual copies for more senior operators
p. A procedure should also be written to address anomalies may also be included. This could take place during the les-
or alarms identified by the building operator (or others) as sons-learned workshop.
Purpose: This form is used to evaluate each training session. Based on this evaluation, later sessions can be improved. This form will be
completed by the CxA and one D-I-R employee in the training after each session.
Every attendee fills out one copy of this form. Mark questions that are not applicable with “N/A.”
4. Do you understand the various types and purpose of these components/systems? 1 2 3 4 5 N/A
6. Do you know how the components/systems operate under all normal modes? 1 2 3 4 5 N/A
7. How well do you understand the importance of meeting the design intent for the systems 1 2 3 4 5 N/A
covered?
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
8. Are you able to efficiently find the relevant information in the systems manual to operate 1 2 3 4 5 N/A
and maintain the systems/components you were trained for in this session?
9. Do you know how to perform the needed maintenance on the equipment and/or do you 1 2 3 4 5 N/A
know to obtain the information you need?
10. Do you know how to obtain updated technical service information for the components/ 1 2 3 4 5 N/A
systems?
Explain why any questions received very low or very high ratings from you:
What topics would you desire to be covered that were absent from this training session?
You may provide other comments concerning anything about this training session (e.g., information prior to training, content, etc.):
TRAINING EVALUATION AND ACCEPTANCE that they can apply the lessons to their work. At least four
strategies can be use to evaluate the effectiveness of the train-
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
address any training needs particular to new discoveries iden-
work. Including observations related to training effectiveness tified by the O&M staff.
as part of the OCx Process can provide insight into the effec-
tiveness of the training.
EXAMPLE
Depending on the size and scope of the project, the
Owner’s or Owner’s representative’s acceptance will again An example EBCx Training Plan from an actual project can
require discussion as to the level of formality required to be found at www.ashrae.org/G02-2015. This example was
determine that the training requirements of the Cx Plan have created prior to the development of Guideline 0.2 and may
been met. In some cases, acceptance may be determined by not align exactly with the previously outlined sections. How-
participating in witnessing some on-site instructions, while ever, it should help illustrate the overall structure and intent of
other more critical systems may require filling out forms ask- an EBCx Training Plan.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
ipants would stay focused on the Cx project efforts and resist iii. Recommendations for future projects
the temptation to include ancillary issues that would diminish f. List of documents for distribution before the workshop
the effectiveness of the workshop’s efforts to bring closure to
1. All issues and resolution logs and open items
the Cx project.
Discussion participants must include all members of the 2. Multiple-Facility Program Plan (if there is one)
EBCx Team; typically these members would include facility 3. CFR
Owner’s representatives, facility operations personnel, repre- 4. EBCx Plan
sentatives of people whose work will be affected by the new 5. Systems manual
conditions brought about through the Cx Process, and ven- 6. EBCx Report
dors whose equipment and systems were used to modify and
g. Outline and format of workshop report
upgrade the working environment within the facility. Partici-
pants are not limited to the EBCx Team members. If someone 1. General description of project scope
observing the Cx Process outside the EBCx Team has reason- 2. List of systems included in the project
able observations, those people should be included in the dis- 3. Summary of validation and testing procedures
cussion. 4. Summary of successes and failures by system
The Commissioning Authority (CxA) must provide an 5. List and description of open items and further required
agenda that guides the meeting and outlines the topics that actions
will be discussed. The agenda should allow for free discus-
6. Recommendations for future projects
sion of all points of interest in the Cx Process, as well as the
freedom to comment on the impact of the changes brought 7. Plans and schedules for future meetings if required
about through the Cx Process. This agenda would be assem- 8. List of attendees
bled in part from the issues and resolution logs created during 9. Distribution list
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
nation with O&M personnel in developing standard formats building maintenance systems are developed and changes to
and divisions (shops) is undertaken to simplify future systems the systems occur.
manual development. The systems manual contains the following sections in
It is the intent that the systems manual be assembled in the order of availability and use.
electronic format to facilitate access and reduce storage
Executive Summary
requirements. The electronic format will also reduce the pos-
sibility of loss of information. For systems manuals assem- The executive summary contains an overview of the building
bled in hard copy format, the larger documents, such as design, construction, and operational requirements. This
record drawings, specifications, submittals, and O&M docu- information is intended to provide general guidance on the
ments, can be stored in secure locations, with these locations intended O&M of the building in conformance to the OPR.
referenced in the systems manual. The design team and their contact information is also
Also included in the systems manual is the develop- provided to facilitate information transfer on original designs
ment of periodic maintenance and information for insertion and maintenance and optimization.
into a computerized maintenance management system (CMMS),
Facility Design and Construction
including equipment make and model information, checking
requirements, maintenance requirements, and troubleshooting a. OPR/CFR. Insert a final copy of OPR/CFR developed
items. during the Cx Process. This provides the O&M staff and
The Commissioning Authority (CxA) shall be responsible future Owner information on the intent for the design and
for verifying the development of the systems manual. use of the building.
The entity responsible for developing the systems manual b. BoD. Insert a final copy of BoD document if one is avail-
shall include all items involved in the project and capture the able or developed during the Cx Process. This provides
system and assembly data in either an electronic or printed ver- the O&M staff and future Owner information on the origi-
sion. In addition, printed operations, service, maintenance, spare nal design of the building.
parts list, and repair manuals may be provided. This entity c. Construction Record Documents. Insert final specifica-
(Owner, contractor, design professional, other) shall have the tions and insert or describe locations of record drawings.
No further reproduction or distribution is permitted.
skills of design, construction, and operations required to Digitized systems manuals can also contain copies of the
develop a comprehensive systems manual. record documents. This process minimizes the loss of
The required details for a full systems manual are these documents.
enhanced in each of the technical Cx Process guidelines. The Building, Systems, and Assemblies Information
systems manual will have multiple sections depending on the
number of systems focused on during the Cx Process. a. Specifications. Insert a final copy of facility design speci-
The systems manual contains information related to the fications.
OPR/CFR and documentation of building design and con- b. Approved Submittals. Insert final copy of specific
struction, along with operational requirements, maintenance approved submittals by specification section sequence,
information, training and testing documentation for the use of including a copy of final approved and commissioned
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
4. Insert a copy of routine building operations mainte- installation.
nance requirements. 3. Insert copies of installers’ and CxA’s completed vali-
5. Insert a copy of emergency shutdown procedures and dation checklists. This provides a record of installation
locations of applicable controls. checks and observations for future reference.
6. See Annex M1 for more content that could be included 4. Insert copies of installers’ and CxA’s completed func-
in the facility guide. tional performance checklists of assemblies, equip-
Note: The following items (b) through (f) should be ment, and integrated system. This provides a record of
added to the systems manual when required by the OPR/CFR performance checks and observations for future refer-
or where available. ence.
d. Cx Progress Reports. Insert a copy of all Cx progress
b. Maintenance Procedures, Checklists, and Records. reports.
Insert procedures, forms, and checklists for facility O&M.
e. Issues and Resolution Logs. Insert a copy of all issues
Include updating requirements. Describe inspections and
testing required on a routine basis and standard forms and resolution logs with resolution or status of each item.
required. This provides a record of problems and issues found and
c. Maintenance Schedules. Include recommended mainte- resolved during the design and construction process for
nance schedules for systems and equipment along with future reference.
update requirements. f. Item Resolution and Open Items. Insert a list of any
d. Utility Measurement and Reporting. Include descrip- open items and seasonal or additional testing required.
tion of utility metering and monitoring systems. Provide
document formats and procedures for tracking utility use SUMMARY
and reporting this information to meet the Owner’s and The systems manual is an expansion of what traditionally has
jurisdictional requirements. been referred to as an “O&M manual.” The systems manual
e. OCx Operational and Maintenance Record Keeping. should contain much more information and be arranged to be
Include OCx and optimization procedures and documen- more functional in both training and operation of the building.
No further reproduction or distribution is permitted.
tation to monitor and improve the performance of facility The arrangement recommended here centers around capturing
systems. the documents normally produced during the design and con-
f. Janitorial and Cleaning Plans and Procedures. Insert a struction, remodeling, or Cx of a building. All of these docu-
copy of facility cleaning and janitorial plan with proce- ments are important to operating and maintaining the building.
dures and intended chemicals and equipment. While all of the recommended documents should be included,
it is understood that based on the Owner’s needs for the build-
Training
ing, all of the documents or sections may not be required.
a. Training Plans and Materials. Include instructions and However, in all cases, the maximum number of available doc-
procedures for the use of appropriate sections of the sys- uments should be captured or developed and included in the
tems manual for training for building O&M. Include systems manual.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
information related to the systems and assemblies that require
design, construction, and operational requirements. The infor-
regular attention during building operation and incorporating
mation is intended to provide general guidance on the intended
it into a usable information resource with indexes and cross
operation of the building in conformance with the Current
references. This information is edited and organized to focus
Facility Requirements (CFR).
on key systems (HVAC, plumbing, electrical, vertical transpor-
tation, fire alarm, security, etc.) in the building. Coordination Facility Operations Instructions
with facility and maintenance personnel in developing build-
ing standard formats, level of detail, systems included, and a. Operating Plan. Insert a copy of the completed facility
reporting procedures is necessary to ensure the guide is useful operating plan with explanations of the intended use and
for maintaining the long-term best operation of the facility. The operation of the facility.
FG is usually located in the operations section of the systems b. Building and Equipment Operating Schedules, Set-
manual, but it can be developed independently if needed. points, and Ranges. Insert a copy of setpoints of all
Annex M of this guideline includes a more complete descrip- equipment with normal operational adjustments. Include
tion of the systems manual. the setpoint normal intended ranges and limitations.
The guide should be provided separately from the sys- c. Sequences of Operation and Limitations. Insert a copy
tems manual in a location where operations and maintenance of the sequences of operation for appropriate operating
(O&M) personnel are able to quickly refer to it when rou- equipment in language and a format that is understandable
tinely reviewing system operation. Parts of the guide may also to the property managers or to other groups using the
be appropriate to present in other formats so that those work- guide. This would not be the controls submittal drawings
ing on equipment can refer to important concepts and param- but a written description of the sequences and the intent of
eters without opening or reaching for a book. Examples each sequence. It should include relevant sequence/system
include laminated schematics with sequences on the walls of interaction as well as graphics or schematics.
equipment rooms, parameters in text on the computer screen d. Start-Up and Shutdown Actions. Insert a copy of rou-
of a controls system, and phenolic labels or permanent writ- tine system start-up and shutdown procedures and loca-
ing of key parameters on equipment access doors. The FG tions of applicable controls and shutoffs.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
No further reproduction or distribution is permitted.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
performance identified during the period. estimated costs and associated benefits that the action will
d. Document all corrective actions taken and lessons learned. provide. Include both quantitative and qualitative benefits.
e. Document improvement recommendations with associ- Discuss how benefits were quantified. Identify by whom and
ated costs and benefits. how corrections were and will be implemented.
f. Report on updates to facility training programs and train-
ing conducted based on changes to the facility or staff Implemented Corrective Actions
turnover. Document corrective actions implemented that do not require
Owner approval. Include the estimated costs and associated
ONGOING COMMISSIONING REPORT OUTLINE benefits that the action will provide. Include both quantitative
The following is an example outline for an OCx Report and and qualitative benefits. Discuss how benefits were quanti-
recommendations for content to include in each section. fied. Identify by whom and how corrections were and will be
implemented. Examples of such actions are control system
Executive Summary
setpoint changes or releasing control system overrides.
This is a brief description of the work conducted during the
OCx Phase and the overall results of the process. The execu- Updates to Documents
tive summary should be concise and should not be more than Note other documents such as the CFR and systems manual.
one page in length if possible. Highlight important significant updates and attach as appro-
Include an overall summary of operating deficiencies dis- priate.
covered, their consequences, and recommendations imple-
mented or proposed to resolve the deficiencies. Provide an EXAMPLE
overview of why the recommendations will help to maintain
the persistence of building performance and the benefits. The An example OCx Report from an actual project can be found
next steps should be listed. at www.ashrae.org/G02-2015. This example was created
prior to the development of Guideline 0.2 and may not align
Performance Parameters exactly with the previously outlined sections. However, it
No further reproduction or distribution is permitted.
Note if performance parameters have changed significantly should help illustrate the overall structure and intent of an
due to major changes in occupancy, use, remodeling, etc. OCx Report.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Resource Name Author (Year)
EBCx Guides
Best Practices in Commissioning Existing Buildings BCA (2008)
A Guide to Building Commissioning PNNL and PECI for the DOE (2011)
A Retrocommissioning Guide for Building Owners PECI for the EPA (2007)
EBCx Studies
Building Commissioning: A Golden Opportunity for Reducing Energy Costs and LBNL (2009)
Greenhouse-gas Emissions
A Report of Cost-Effective Commissioning of Existing and Low Energy Buildings PECI, Texas A&M University and
Natural Resources Canada (2010)
Energy Efficiency Guide for Existing Commercial Buildings: Technical ASHRAE (2011)
Implementation
Guidelines for Verifying Savings from Commissioning Existing Buildings CCC (2012)
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Energy Information Handbook LBNL (2011)
California Commissioning Collaborative Information, tools, case studies, and guides on EBCx.
National Environmental Balance Bureau (NEBB) Offers commissioning-related certifications, procedural standards,
specifications, seminars, and publications.
United States Department of Energy Conducts research and develops publications related to EBCx.
LinkedIn sites (CCC, BCA) Active professional networks for the California Commissioning
Collaborative and the Building Commissioning Association.
ASHRAE is concerned with the impact of its members’ activities on both the indoor and outdoor environment.
ASHRAE’s members will strive to minimize any possible deleterious effect on the indoor and outdoor environment of
the systems and components in their responsibility while maximizing the beneficial effects these systems provide,
consistent with accepted Standards and the practical state of the art.
ASHRAE’s short-range goal is to ensure that the systems and components within its scope do not impact the
indoor and outdoor environment to a greater extent than specified by the Standards and Guidelines as established by
itself and other responsible bodies.
As an ongoing goal, ASHRAE will, through its Standards Committee and extensive Technical Committee structure,
continue to generate up-to-date Standards and Guidelines where appropriate and adopt, recommend, and promote
those new and revised Standards developed by other responsible organizations.
Through its Handbook, appropriate chapters will contain up-to-date Standards and design considerations as the
material is systematically revised.
ASHRAE will take the lead with respect to dissemination of environmental information of its primary interest and
will seek out and disseminate information from other responsible organizations that is pertinent, as guides to updating
Standards and Guidelines.
The effects of the design and selection of equipment and systems will be considered within the scope of the
system’s intended use and expected misuse. The disposal of hazardous materials, if any, will also be considered.
ASHRAE’s primary concern for environmental impact will be at the site where equipment within ASHRAE’s scope
operates. However, energy source selection and the possible environmental impact due to the energy source and
energy transportation will be considered where possible. Recommendations concerning energy source selection
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
should be made by its members.
About ASHRAE
ASHRAE, founded in 1894, is a global society advancing human well-being through sustainable technology for the
built environment. The Society and its members focus on building systems, energy efficiency, indoor air quality,
refrigeration, and sustainability. Through research, Standards writing, publishing, certification and continuing
education, ASHRAE shapes tomorrow’s built environment today.
To stay current with this and other ASHRAE Standards and Guidelines, visit www.ashrae.org/standards.
This copy downloaded on 2016-10-13 11:35:41 -0500 by authorized user University of Toronto User.
Visit the ASHRAE Bookstore
ASHRAE offers its Standards and Guidelines in print, as immediately downloadable PDFs, on CD-ROM, and via
ASHRAE Digital Collections, which provides online access with automatic updates as well as historical versions of
publications. Selected Standards and Guidelines are also offered in redline versions that indicate the changes made
between the active Standard or Guideline and its previous edition. For more information, visit the Standards and
Guidelines section of the ASHRAE Bookstore at www.ashrae.org/bookstore.
To ensure that you have all of the approved addenda, errata, and interpretations for this
Guideline, visit www.ashrae.org/standards to download them free of charge.
Addenda, errata, and interpretations for ASHRAE Standards and Guidelines are no longer
distributed with copies of the Standards and Guidelines. ASHRAE provides these addenda,
errata, and interpretations only in electronic form to promote more sustainable use of
resources.
No further reproduction or distribution is permitted.