Method Statement of Hacking Works On RC Wall and Rectification Works
Objective
To implement hacking and rectification works on reinforcement concrete wall
Preparatory by contractor before hacking works
1. Submit the proposed method statement hacking work and rectification work to
Authority for approval.
2. Submit request for inspection of structural member’s client / clients representative
Prior to hacking and rectification works
3. Prepare and implement a sequential hacking area on plan specific to the site and
Approved by a competent structural engineer. Specifically, the plan should consider
The rate on area to hack and positioning of temporary supports (when needed) in
In the plan.
Hacking Works
1. Hacking work implemented at level overhead
2. Before start the works, make sure mark the area to be hack at structure.
3. Temporary support or propping should be installed when needed to support
Others structure and prevent crack effect on concrete while hacking works.
4. Plant, machinery and equipment that have high loading not to be unloaded on floor
While hacking works
5. All existing structure (concrete removal) must be dismantled carefully using
Equipment as applicable to prevent crack effect on concrete
6. The reinforcement shall be remained while the demolishing work is commencing.
Once the concrete has broken away, the reinforcement shall be cut off and rebar
Works must follow as original detailing before concrete works is doing.
7. Protection of the rebar: Prime immediately after cleaning. Apply a continuous coat
of active rich primer/appropriate corrosion protection system before continue
Reinforcement work and recast – in place concrete.
Safety Measures
1. Risk assessment shall be carried out to identify hazards associated he demolition
Process, assess such hazards and take reasonably practicable steps to eliminate or
Control the risks arising from those hazards.
2. Workers shall possess valid work permit, SOC and in proper attire
3. Personal protective equipment shall be provided to workers prior to the start of
work