Check List Form (Bored Pile)

The document provides inspection details for bored pile construction including measuring pile positions, drilling logs, and test results. It documents the process of drilling and constructing bored pile 11 at pier 4 of the Ayeyarwaddy bridge project.

Uploaded by

Kaung Khant Ko
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views24 pages

Check List Form (Bored Pile)

The document provides inspection details for bored pile construction including measuring pile positions, drilling logs, and test results. It documents the process of drilling and constructing bored pile 11 at pier 4 of the Ayeyarwaddy bridge project.

Uploaded by

Kaung Khant Ko
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 24

(MOC/DOB/BP/Survey-F-1)

DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
MEASURING AND CHECKING OF PILE POSITION

PROJECT NAME :
PROJECT TEAM :
PROJECT LOCATION :
CONTRACTOR NAME :
PIER/ABUTMENT No. :

BM
__Thayet Side

CL
Aung Lan Side
5 4 3 2 1

( D /S) ( U /S)
10 9 8 7 6

15 14 13 12 11

Benchmark(BM) Position: N= m,E= m, Z= m


River Bed Within
Distance
Measured Casing RL* Water Level
Pile No. Design Measured Difference Level Allowable Remarks
Date
(ft or m) mm (ft or m) Tolerance

Allowable Tolerence: Displacement from Designed Pile Diameter ( <100mm )


Allowable Tolerence: Pile Inclination ( <1/100 )
*RL- Reduced Level

SURVEYOR: INSPECTED BY: CHECKED BY: APPROVED BY:


(_______/______/______)
(MOC/DOB/BP/F-2)

DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
CAST IN PLACE BORED PILE DRILLING LOG

PROJECT NAME : Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM : Construction (Unit-3)
PROJECT LOCATION : Thayet,Magway
CONTRACTOR NAME : DESIGNATION :Quality Control Manual for Bridge Foundation(JICA)
PIER/ABUTMENT No. : RP-4 PILE No. : BP-11

ELEVATIONS(ft or m) CASING INFORMATION DIIMENSION(ft or m) DRILLING METHODS


Reference : Casing(Tb/Pc): Soil Auger Dia:
Survey Record Temporary 1.5m Drilling Type: Cast in Place Bored Pile
Ground Surface : 6.756m Soil Pile Length:
Type: Steel 44m Bucket(Type/ Size): Soil 1.5m
Water Table: Outer Dia:(mm) 1670 Rock Auger Dia: Auger Size:
Pile Top : 16.014m Thickness(mm) 10 Rock Socker Length: Drilling Machine: 2DR-010
Cap Base : 14.214m Top Elev:(mm) 16349 Consd Pile Length: Base Crane: Casagrande 2Z 123

Msda Top Rock : Bot: Elev:(mm) -150 PILE BOTTOM INSPECTION CLEANOUT METHOD
Msda Avg: Pile Bot: Length (m) 14.5 Visual ⃞ Tape/Probe ✓ Bucket ✓ Airlift ⃞ Pump ⃞
DRILLING SLURRY Record 5 Depth to the bottom of finished Other
Type Brand Manufacture shaft(m): 1. 46.94m_ Meet Cleanout Specifications? Yes_✓__ No____
3 2. 46.90m
Grade A TK Local 3. 47.00m Meet Alingment Specifications? Yes_✓__ No____
4. 46.95m
TEST RESULTS OF SLURRY PROPERTIES 1 5 2 TYPE OF CONSTRUCTION
5. 46.90m
Density(g/cm3) Viscosity(sec/L) Sand Content(%) pH Dry ⃞ Wet ✓
4
1.07 41.59 0.9 a
Measured b
Temporary cPermanent
Slurry meets Specification of ACI 336.1? Yes___ No___ Avg: Pile Bottom Elevation(m): 46.938m d
Construction

Symbols
Start Finished Sounding Elevation for Soils
Date Soil and Material Description Remark
hr:min(AM/PM) hr:min(AM/PM) ft or m ft or m and
Rocks
23.12.2021 10:15 AM 11:15 AM 7m Stand Pipe Driving
23.12.2021 4:50 PM 5:15 PM 12 m Greyish Brown SAND some Silt
24.12.2021 8:00 AM 8:50 AM 15.5 m Greyish Brown SAND some Silt
24.12.2022 10:00 AM 10:30 AM 19.5 m Greyish Brown SAND some Silt
24.12.2023 10:48 AM 11:18 AM 23.5 m Greyish Brown SAND some Gravel
24.12.2024 1:30 PM 2:00 PM 27.8 m Greyish Brown SAND some Silt some Gravel
24.12.2025 2:15 PM 2:48 PM 31.7 m Grey SAND some Silt trace Gravel
24.12.2023 3:05 PM 3:45 PM 35.8 m Grey SAND some Silt trace Gravel
24.12.2024 4:05 PM 4:45 PM 39.8 m Grey SAND some Silt trace Gravel
24.12.2025 5:11 PM 5:52 PM 43.5 m Grey SAND some Gravel some Silt
24.12.2023 6:10 PM 6:45 PM 44.3 m Grey SAND some Gravel some Silt
24.12.2024 7:26 PM 7:50 PM 46.5 m Grey SAND some Gravel some Silt
24.12.2025 7:53 PM 8:05 PM 47.1 m Grey SAND some Gravel some Silt
24.12.2025 8:45 PM 8:50 PM 47.8 m Grey SAND some Gravel some Silt

Remarks: 1. Record and describe all materials encountered during pile excavation. (Water table information, obstruction encountered,
equipment used and equipment breakdowns)
2. Used additional sheet if necessary.

INSPECTED BY: CHECKED BY: APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊန္ၾ
အငယ္တန္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) တံ တားဦးစီးဌာန
(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊန္ၾ
အငယ္တန္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) တံ တားဦးစီးဌာန
(ေဌးေအာင္) ၫႊန္ၾ
ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တံ တားဦးစီးဌာန
(ေဌးေအာင္) ၫႊန္ၾ
ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တံ တားဦးစီးဌာန
(MOC/DOB/BP/F-3)
DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
DRILLING DEPTH VS. TIME GRAPH

PROJECT NAME : Ayeyarwaddy Bridge (Thayet-Aunglan) PROJECT TEAM :


PROJECT LOCATION : Construction (Unit-3) CONTRACTOR NAME:
PIER No./PILE No. :RP-4 DATE:23/12/2021,24/12/2021 TIME(START/FINISH)10:15AM/8:50PM

Time(hr)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Remarks
Depth(m)
3
6
9
12
15
18
21
24
27
30
33
36
39
42
45
48
51
54
57
60
Type Brand Manufacture Density(g/cm3) Viscosity(sec/L) Sand Content(%) pH
Slurry Information: Test Results of Slurry
Properties:

INSPECTED BY: CHECKED BY: APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊန္ၾ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) တံ တားဦးစီးဌာန
(______/_______ /_______)
(ေဌးေအာင္) ၫႊန္ၾ
ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တံ တားဦးစီးဌာန
(MOC/DOB/BP/F-4)
DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
CHECKING OF REINFORCEMENT CAGE INSTALLATION

PROJECT NAME : Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM : Construction (Unit-3)
PROJECT LOCATION: Thayet,Magway
CONTRACTOR NAME :
PIER/ABUTMENT No. :RP-4 PILE No.:BP-11

1st Reinforcement Cage ( 13.7 )m long


Diameter As Per Design Checked By Lapping
Main Bar ( 32 )mm ( 27 ) Nos ( 27 ) Nos ( 1.0 ) m
Stirrup ( 10 ) mm ( 61 ) Nos ( 61 ) Nos ( 0.3 ) m
Welding Condition meets specification: Yes_✓____ No_______
Welding Length 27Nosx75mmx2Six2Ply x3Place

2nd Reinforcement Cage ( 12 )m long


Diameter As Per Design Checked By Lapping
Main Bar ( 32 )mm ( 27 ) Nos ( 27 ) Nos ( 1.0 ) m
Stirrup ( 10 ) mm ( 40 ) Nos ( 40 ) Nos ( 0.3 ) m
Welding Condition meets specification: Yes_✓____ No_______
Welding Length 27Nosx75mmx2Six2Ply x3Place

3rd Reinforcement Cage ( 12 )m long


Diameter As Per Design Checked By Lapping
Main Bar ( 32 )mm ( 54 ) Nos ( 54 ) Nos ( 1.0 ) m
Stirrup ( 10 ) mm ( 73 ) Nos ( 73 ) Nos ( 0.3 ) m
Welding Condition meets specification: Yes_✓____ No_______
Welding Length 27Nosx75mmx2Six2Ply x3Place

4th Reinforcement Cage ( 12 )m long


Diameter As Per Design Checked By Lapping
Main Bar ( 32 )mm ( 54 ) Nos ( 54 ) Nos ( 1.0 ) m
Stirrup ( 10 ) mm ( 81 ) Nos ( 81 ) Nos ( 0.3 ) m
Welding Condition meets specification: Yes_✓____ No_______
Welding Length 54Nosx75mmx2Six2Ply x3Place
Total Length of Steel Cage ( 45.7 )m
Thin Sheet Length ( 18.0 )m
Corrosion Painting at final cage top portion: Yes_____ No___✓______
NOTES -------------------------------------------------------------------------------------------------

INSPECTED BY: CHECKED BY: APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊန္ၾ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) တံ တားဦးစီးဌာန
(_______/_______/_______)
(ေဌးေအာင္) ၫႊန္ၾ
ကားေရးမွဴး(ၿမိဳ႕ျပ)
တံ တားဦးစီးဌာန
(MOC/DOB/BP/F-6)
DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
CAST IN PLACE BORED PILE CONCRETING RECORD

PROJECT NAME : Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM : Construction (Unit-3)
PROJECT LOCATION: Thayet,Magway
CONTRACTOR NAME:
PIER/ABUTMENT No. : RP-4 PILE No. : BP-11

Pile Top Elevation :16.014m Pile Diameter: 1.5m Rebar Cage Top Elevation:16.014m
Pile Bottom Elevation :(-)29.786m Pile Length : 44m Rebar Design Elevation :16.014m
Pile Cap Bottom Elevation:14.214m Depth to Water Table: Depth to Slurry:
Design Concrete Compressive Strength (Cylinder/Cube): Rebar Cage Centered Within Specification:
____35__MPa / ______psi Yes ✓ No ⃞
Placement Method: Concrete Volume m3
Termie ✓ Free Fall ⃞ Volume in stand pipe :
Concrete Pouring Date Time Volume in thin sheet : 31.81
Start 25/12/2021 7:05 AM Volume in the rest portion : 49.13
End 25/12/2021 2:45 PM Total estimated volume (TEV): 80.94
Pile Completion time (including Total volume delivered (TVD): 83.00
casing removal) Difference Volume (TVD-TEV): (+)2.06

Sr. Arrival Concrete Start Finish Tremie Depth To NOTES*


Truck
No. Time Volume Time Time Depth Concrete

AM/PM No. m³ hr:min hr:min m m

46.9
1 7:00 AM 2 12 7:05AM 7:55AM 45.4 5.5

2 8:00 AM 2 12.0 8:05AM 9:15AM 36.52 13.2

3 9:20 AM 3 15 9:25AM 10:48AM 27.64 22.9

4 10:53 AM 3 16.5 10:55AM 12:13PM 18.76 32

5 12:15 PM 3 19.5 12:18PM 2:10PM 6.92 46

6 2:15 PM 2 8.0 2:18PM 2:45PM 47.2

Total Concrete Volume Delivered 83m³ *NOTES - (delays, additives, breaching, casing removal, bucket number)

APPROVED BY:
INSPECTED BY: CHECKED BY:
(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊန္ၾ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) တံ တားဦးစီးဌာန
(______/ ______/ _____)
(ေဌးေအာင္) ၫႊန္ၾ
ကားေရးမွဴ း(ၿမိဳ႕ျပ)
တံ တားဦးစီးဌာန
(MOC/DOB/BP/F-8)

DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
CAST IN PLACE BORED PILE CONCRETE VOLUME

PROJECT NAME : Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM: Construction (Unit-3)
PROJECT LOCATION: Thayet,Magway
CONTRACTOR NAME:
PIER/ABUTMENT No. :RP-4 PILE No. :BP-11 PILE DIAMETER: 1.5m
CONCRETE CURVE

Prior to concreting a plot should be made showing the theorectical concrete surface (by depth or elev.) vs theorectical concrete volume
placed. During concreting, the actual concrete surface vs the actual concrete volume placed is then plotted.

PILE TOP

48
DEPTH/ELEVATION(m)

40

30

20

10

0 10 20 30 40 50 60 70 80 90
PILE BOTTOM CONCRETE VOLUME (m ) 3

NOTES: _______________________________________________________________________

INSPECTED BY: CHECKED BY: APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) န္ၾကားေရးမွဴး(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃)
တံ တားဦးစီးဌာန
(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္)
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃)

(____/____/______)
3.65

(ေဌးေအာင္) ၫႊ
န္ၾကားေရးမွဴး(ၿမိဳ႕ျပ)

တံ တားဦးစီးဌာန
(MOC/DOB/BP/F-9)
DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION INSPECTION CHECK LIST
CAST IN PLACE BORED PILE INSPECTION REPORT

PROJECT NAME: Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM: Construction (Unit-3)
PROJECT LOCATION: Thayet,Magway
CONTRACTOR NAME:
PIER/ABUTMENT No. : RP-4 PILE No. : BP-11

Date/Time REINFORCEMENT
Started Finished Elev.(Top): ______16.014m___________
Excavation
23/12/2021 10:15AM_24/12/2021 8:50PM_ Elev.(Bot): ______(-29.786m)____
Pile Bottom Inspection __________________________________
CASING INFORMATION
Started Finised
Concreting
25/12/2021 7:05AM_ 25/12/2021 2:45PM_ Top Elev.: _16.349 m________

As Built
Measurement Cap Base Elev.: __14.214m_____
Design Measurement
Top Elevation (m): 16.014m_ 16.014m_
Bottom Elevation (m): (-)29.786m (-)29.786m
Pile Diameter (m): 1.5m 1.5m
Rock Socket Diameter (m) (if
_______________ _______________
applicable)
Pile Length * (m) 45.8m 45.8m
*Was Pile Length approved? Yes ✓ No ⃞ River Bed Elev.: 8.214m
Concrete Volume 83.0m 3
(or) Ground Water Elev.
Concrete Mixed Design Casing Bot Elev.: _(-)0.15m____
Cylinder/35MPa Cylinder/35MPa
(Cylinder /Cube)(Mpa or psi)
Concrete Placement Method: Tremie ✓ Free Fall ⃞

Bottom Of Pile Cleanliness Meets Specification?


Yes ✓ No ⃞

Proper Reinforcement Installation :___✓____________________


Soil Description of Bottom of Pile :Greyish SAND Some Clay trace Silt
COMMENTS (Obstructions Encountered ,etc. );
____________________________________________________
____________________________________________________ Pile Bot Elev.: __(-)29.786m_____

INSPECTED BY: CHECKED BY : APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) န္ၾကားေရးမွဴ း(ၿ
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) မိဳ႕ျပ)
တံ တားဦးစီးဌာန
(ကို ကို ထက္ႏို င္)
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃)

(____/____/______)
(MOC/DOB/BP/GPR)

DEPARTMENT OF BRIDGE
BORED PILE CONSTRUCTION
GENERAL PROGRESS PHOTO REPORT

PROJECT NAME: Ayeyarwaddy Bridge (Thayet-Aunglan)


PROJECT TEAM: Construction (Unit-3)
PROJECT LOCATION: Thayet,Magway
CONTRACTOR NAME:
PIER No./SPAN No. ; RP-4 WORK ITEM: CONTRACT No.:

Driving Stand Pipe Drilling Bored Pile

Rebar Check Installing Steel Cage

Installing Steel Cage Pouring Concrete

RECORDED BY: CHECKED BY: APPROVED BY:


(ကို ကို ထက္ႏို င္) (လႊမ္းေဝသက္) (ေဌးေအာင္) ၫႊ
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ) ဦးစီးအရာရွိ(ၿမိဳ႕ျပ) န္ၾကားေရးမွဴး(ၿ
တည္ေဆာက္ေရးအဖြဲ႕(၃) တည္ေဆာက္ေရးအဖြဲ႕(၃) မိဳ႕ျပ)
တံ တားဦးစီးဌာန
(ကို ကို ထက္ႏို င္)
အငယ္တ န္းအင္ဂ်င္နီယာ(၂)(ၿမိဳ႕ျပ)
တည္ေဆာက္ေရးအဖြဲ႕(၃)

(_____/_____/_____)

You might also like