Energies 15 07854 v2
Energies 15 07854 v2
Article
Optimal Loss of Load Expectation for Generation Expansion
Planning Considering Fuel Unavailability
Radhanon Diewvilai 1 and Kulyos Audomvongseree 1,2, *
Abstract: In generation expansion planning, reliability level is the key criterion to ensure enough
generation above peak demand in case there are any generation outages. This reliability criterion must
be appropriately optimized to provide a reliable generation system with a minimum generation cost.
Currently, a method to determine an optimal reliability criterion is mainly focused on reserve margin,
an accustomed criterion used by several generation utilities. However, Loss of Load Expectation
(LOLE) is a more suitable reliability criterion for a generation system with a high proportion of
renewable energy since it considers both the probabilistic characteristics of the generation system
and the entire load’s profile. Moreover, it is also correlated with the reserve margin. Considering
the current fuel supply situation, a probabilistic model based on Bayes’ Theorem is also proposed to
incorporate fuel supply unavailability into the probabilistic criterion. This paper proposes a method
for determining the optimal LOLE along with a model that incorporates fuel supply unavailability
into consideration. This method is tested with Thailand’s Power Development Plan 2018 revision 1 to
demonstrate numerical examples. It is found that the optimal LOLE of the test system is 0.7 day/year,
or shifted to 0.55 day/year in the case of considering the fuel supply unavailability.
Citation: Diewvilai, R.;
Keywords: generation expansion planning; reliability criterion; loss of load expectation; reserve
Audomvongseree, K. Optimal Loss of
Load Expectation for Generation
margin; fuel unavailability
Expansion Planning Considering
Fuel Unavailability. Energies 2022, 15,
7854. https://doi.org/10.3390/
en15217854 1. Introduction
1.1. Motivation and Literature Review
Academic Editors: Ameena Al
Sumaiti and Mousa Marzband Generation expansion planning (GEP) is a method for determining the future charac-
teristics of a power system. It is a process used to determine the optimal types of energy
Received: 30 September 2022
technologies, size, and construction time needed to bring new power generation units [1]
Accepted: 19 October 2022
into the electrical power system to meet the demand forecast in the future. Global warm-
Published: 23 October 2022
ing problems, carbon neutrality, and net zero emission targets have been set by several
Publisher’s Note: MDPI stays neutral countries with the goal of reducing greenhouse gas emissions [2]. Thus, high penetration
with regard to jurisdictional claims in of renewable energy sources, especially from solar and wind power, is highly anticipated.
published maps and institutional affil- In order to have the ability to integrate a high level of these variable renewable energy
iations. sources into the power system, complex optimization models must be developed to take
economic, technical, environmental, and other pertinent constraints into consideration as
part of long-term generation expansion planning [3].
During the GEP process, it is necessary to maintain the installed capacity of the system
Copyright: © 2022 by the authors.
at a certain level above the peak demand since any generation unit can be forced into an
Licensee MDPI, Basel, Switzerland.
outage [4] by unexpected problems, e.g., component failure or shortage of fuel supply. The
This article is an open access article
amount of this excess capacity usually results from the level of system reliability criterion
distributed under the terms and
considered in the GEP process. There are two concepts applied to generation expansion
conditions of the Creative Commons
Attribution (CC BY) license (https://
planning, the deterministic method and probabilistic method [4]. For the deterministic
creativecommons.org/licenses/by/
method, reserve margin, a percentage of additional generation over system peak demand,
4.0/). is usually used as the reliability criterion to account for randomly occurring failures [5].
The advantage of the reserve margin is that it is easy to calculate. Its concept of reliability is
also simple and easy to interpret. Thus, the reserve margin is used as the main reliability
criterion for many power utilities, such as 15% for Thailand [6], 22% for South Korea [7],
20–28% for Peninsular Malaysia [8], 15% for Taiwan [9], and 10% to 20% for many utilities in
the USA [10]. The reserve margin is used as a planning constraint in many GEP models that
are tested with national level power systems. Wierzbowski et al. proposed a mixed integer
linear programming (MILP) model for considering power system reserves and tested it
in the Polish power system [11]. Neshat et al. proposed a hybrid model for Iran’s power
system [12]. Koltsaklis et al. proposed an MILP model using Greece’s power system as the
test case [13]. Heuberger et al. proposed an MILP model that was applied to the United
Kingdom’s power system [14]. Chen et al. proposed a model applied to the northwestern
grid of China [15]. Although easy and simple, when determining the reserve margin, only
a single data set comprised of the peak load and its associated total capacity of the system
is considered. Therefore, the behavior of generation units as well as load characteristics
are not considered in the reserve margin calculation. For this reason, reserve margin is not
quite appropriate for use with generation systems that rely on a high level of renewable
energy sources due to their intermittent behavior and limitations.
For the probabilistic method, the forced outage rate (FOR) of generation units, which
accounts for component failure behavior, is usually considered. FOR is used with a load
duration curve (LDC) to calculate system reliability indices, such as Loss of Load Ex-
pectation (LOLE) [5], Expected Energy Not Served (EENS) [5], and Expected Unserved
Energy (EUE) [16]. LOLE is considered a reliability criterion in many power utilities, e.g.,
0.3 days/year for South Korea [7], 1 day/year for Peninsular Malaysia [8], and 0.1 day/year
for power utilities in the USA [10]. They are also considered in many GEP models. However,
due to their non-linear characteristics, these models are usually tested with simplified test
systems or are considered using linearly estimated values instead. Hemmati et al. proposed
a multistage mixed-integer nonlinear programming (MINLP) model, tested on a 2850 MW
test system [17]. They also considered LOLE in an MINLP model in microgrids [18].
Sirikum et al. proposed an MINLP model tested with a 1600 MW scaled-down version
of Thailand’s generation system [19]. Opathella et al. proposed an MILP model with a
linear approximation of LOLE as a constraint [20]. Aghaei et al. proposed a multi-period,
multi-objective generation expansion planning (MMGEP) model using the Z-method to
evaluate LOLE [21]. Hanna et al. proposed a microgrid investment planning model with
sequential Monte Carlo simulation to accurately evaluate non-linear reliability indices [22].
EENS has also been considered in several recent GEP models. Oree et al. used EENS to
determine unmet demand costs [23]. Hamidpour et al. consider minimization of EENS
as one of the objective functions of the proposed generation and transmission expansion
planning [24]. Abushamah et al. consider an expected energy not supplied cost for reliabil-
ity evaluation [25]. An indirect approach is also introduced to incorporate LOLE into GEP.
For example, Abdalla et al. proposed an algorithm that uses adjustable reserve margin
as a reliability criterion in the MILP model [26,27]. Firstly, the LOLE of the GEP results is
calculated and compared to the LOLE criterion. If the LOLE result is not acceptable, the
reserve margin constraint is adjusted and the GEP is repeated iteratively until the LOLE
result is acceptable.
Since the probabilistic nature of generation components and entire load models are
taken into account, the probabilistic method can provide more appropriate reliability
criteria than the deterministic method, especially for power systems that rely on a high
proportion of renewable energy. For example, LOLE and LOEE are considered as reliability
constraints in an optimization method to create an optimal design and energy management
of the hybrid systems, including the photovoltaic panels, wind turbines, and fuel cells [28].
Apart from the selection of the system reliability criterion, either reserve margin or
LOLE, setting up the value of the criterion is also important. Too high of a reliability level
leads to over-investment, resulting in excessive power generation costs, which are then
passed through the electricity tariff structure. However, under-investment leads to the
Energies 2022, 15, 7854 3 of 17
opposite situation [5], in which, although the cost of electricity can be lower, the level of
reliability of the system might not be acceptable.
To determine optimal reliability criteria, a customer interruption cost is introduced
and combined with the power generation cost to create the total system cost as a function of
reliability as described in [29]. The customer’s interruption cost is a customer cost caused by
failures in the electricity supply system [30]. This cost can be computed from EENS and the
Interrupted Energy Assessment Rate (IEAR). With this concept, the total cost of the power
system at different reliability criteria can be evaluated and compared, as demonstrated in
Figure 1. Consequently, the optimal reliability index is the one that provides the minimum
total system cost. This concept is used in several publications. For example, Billinton used
this concept to determine the optimal reserve margin of a 240 MW reliability test system
with a 185 MW peak load [29]. The Brattle Group also used this concept to determine the
optimal reserve margin of a wholesale electric market of the Electric Reliability Council
of Texas (ERCOT) in 2014 and 2018 [31,32]. Energy and Environmental Economics, Inc.
used this concept to determine the optimal planning reserve margin for the El Paso Electric
Company in 2015 [33].
Although the concept mentioned above is used in several publications, the optimal
reliability criterion discussed in many publications is reserve margin. In addition, the
objective function of the aforementioned problem is to minimize the total system cost. This
total cost is the sum of the utilities’ investment cost and the customer’s interruption cost.
It is not only the cost that a utility actually pays. Thus, sometimes, it is not so convincing
for some power utilities to include this cost in their calculation. With these concerns in
mind, the concept of reliability improvement’s benefit, which is another perspective but
equivalent when determining the optimal reliability level, is considered in this paper. In
addition, LOLE, which is a more appropriate reliability criterion, is also focused. Although
reserve margin and LOLE are different criteria, the GEP result obtained from using LOLE as
the planning criterion can provide a minimum reserve margin as an outcome or vice versa.
For example, Abdalla et al. chose to adjust the minimum reserve margin in the robust GEP
model to obtain the power system with acceptable LOLE [26,27]. However, it should be
noted that this relationship is based on the characteristics of a given generation system,
since different power systems having the same LOLE can have a different minimum reserve
margin. Moreover, if the minimum reserve margin is used as the planning criterion, the
maximum LOLE output might not be the same value as the LOLE criterion used in the first
GEP since the maximum LOLE and the minimum reserve margin might not occur in the
same year.
In GEP, fuel supply is typically assumed to be always available in order to reduce the
complexity of the problem. Only the future price of each fuel, reflecting the future market
situation, is forecast. However, apart from the market situation, international conflicts can
also lead to fuel shortages or unavailability [34]. As conventional generation units need
a continuous fuel supply, fuel unavailability can cause interruption to these generation
units. The scale of this interruption could affect the reliability of the power generation
system. Thus, it might be necessary to consider fuel supply availability in generation
Energies 2022, 15, 7854 4 of 17
expansion planning if the generation system relies heavily on any specific fuel, especially
in Thailand where natural gas accounts for more than 55% of the fuel mix. This can be done
by adjusting the probabilistic reliability criterion with the probability of fuel unavailability,
using a concept based on Bayes’ Theorem.
N
LOLE = ∑ pi t LDC (Oi ) (2)
j =1
Energies 2022, 15, 7854 5 of 17
where:
N is the number of states of COPT;
pi is the individual probability of outage capacity state j;
t LDC (Oi ) is the duration of the load loss due to the outage capacity Oi (h).
Figure 3. Concept of optimal reliability criteria determination from the total benefit of a power system.
The CIC is calculated from the net present value of the multiplication of EENS and
IEAR for every year in the generation planning period, as shown in (4).
N IEARy × EENSy
CIC = ∑ (1 + r ) y
(4)
y =1
where:
N is the number of years in the generation planning period;
IEARy is the interrupted energy assessment rate of year y (THB/MWh);
EENSy is the expected energy not supplied of year y (THB);
r is the discount rate (%);
where:
LOLEall−avail is the LOLE of a generation system in which all fuels are available;
LOLEunavail ( f ) is the LOLE of a generation system in which only the fuel f are unavailable;
Punavail ( f ) is the probability of unavailability of the fuel f .
• Reliability constraint.
In this study, LOLE is used as the reliability criterion for generation expansion planning
during the optimal LOLE evaluation process. The value of LOLE is varied to find the
optimal LOLE. The reserve margin is also used as a reliability criterion during the reserve
margin determination process. The value of the reserve margin also varied to match with
the optimal LOLE.
• Carbon dioxide emission constraint.
According to PDP2018r1, a carbon dioxide emission constraint is provided in average
kilograms of carbon dioxide emission per kilowatt-hour of electricity. The average carbon
dioxide emission constraint used in this study is shown in Figure 6, and the carbon diox-
ide emission factor of each fuel is provided in Appendix G. The constraint is gradually
decreased to reduce the greenhouse gas emissions from the power generation system.
since the value of reserve margin is subjective, especially the dependable factor. Thus, in
this study, LOLE is introduced as the planning criterion instead.
Figure 9. Total benefit associated with LOLE criterion of the case study.
From Figure 9, it can be seen that the optimal LOLE for the case study is 0.7 day/year.
With this optimal LOLE as the reliability criterion, a GEP is carried out using data from the
Energies 2022, 15, 7854 11 of 17
case study and a 700 MW natural gas unit as the candidate unit. Additional generation capac-
ity and reliability indices of the generation expansion plan are shown in Figures 10 and 11.
Please note that this GEP will be referred to as the LOLE 0.7 day/year case.
Figure 10. Additional generation capacity of the PDP2018r1 and the case of LOLE 0.7 day/year.
Figure 11. Reliability indices of the generation expansion plan with LOLE < 0.7 day/year case.
From Figure 10, it can be seen that 7700 MW of additional capacity needs to be added
to fulfill the less than 0.7 day/year reliability criterion and other planning constraints.
This additional capacity is almost the same as the 6900 MW of additional capacity of the
original PDP2018r1. However, compared to the original plan, the additional capacity of
the LOLE 0.7 day/year case can be delayed by several years since the planning constraints
can still be fulfilled by the generation system in 2030 and 2031. Furthermore, as seen in
Figure 11, the LOLE index of the LOLE 0.7 day/year case is maintained within the reliability
criterion. It can also be seen that the trends of LOLE and the reserve margin indices are not
perfectly negatively correlated since the LOLE index is affected by the generation system
characteristics, unlike the reserve margin index. Therefore, the minimum reserve margin
index might not occur in the same year as the maximum LOLE index.
Figure 12. Reliability indices of generation expansion plan with LOLE < 0.7 day/years.
Considering Figure 13, it can be concluded that the LOLE criterion of the system with
fuel supply unavailability consideration needs to be adjusted to maintain the equivalent
level of system reliability. For example, with both western and eastern natural gas networks
unavailable, a LOLE criterion of 0.55 day/year should be selected to maintain the reliability
level equivalent to a LOLE criterion of 0.7 day/year without consideration of fuel supply
unavailability, as shown in the black dashed line.
4. Conclusions
This paper proposes a method for evaluating and identifying the optimal LOLE for
generation expansion planning using the concept of power system net benefit. The relation-
ship between the reserve margin and the LOLE is also explained and used to evaluate the
equivalent reserve margin criterion for any specific LOLE value. Lastly, the impact of fuel
supply unavailability on the LOLE is demonstrated, based on Bayes’ Theorem.
In this paper, the LOLE is selected as the reliability criterion since it is a probabilistic
index which considers both generation system characteristics and the overall load model,
unlike the reserve margin, whose value is determined by only peak time period and also
highly dependent on deterministic assumptions such as dependable factor or capacity
credit. Thus, the LOLE is more suitable as the reliability criterion than the reserve margin
is. With the method described in Section 2.2, power system net benefit can be evaluated
by comparing the customer’s interruption cost and the utility’s investment cost in the
generation system planned by considering the LOLE criterion and the base generation
Energies 2022, 15, 7854 13 of 17
system. The net benefit of each generation system with different LOLE criteria is then
compared to determine the maximum point, which is identified as the optimal level for the
LOLE criterion. The proposed method is tested with Thailand’s PDP2018r1. It is found that
the optimal LOLE of Thailand’s modified PDP2018r1 system is 0.7 day/year. Moreover,
with the result discussed in Section 3.3, LOLE can also be represented by an equivalent
reserve margin.
Lastly, since the LOLE is a probabilistic index and the probabilities of fuel supply
unavailability are independent from each other, the impact of fuel supply unavailability can
be evaluated using Bayes’ Theorem. The impact of eastern and western natural gas supply
unavailability on the LOLE of the case study is being evaluated. It is found that if fuel
supply is not reliable, it might be necessary to adjust the LOLE criterion of the generation
system to maintain the same level of generation system reliability.
Author Contributions: Conceptualization, R.D. and K.A.; methodology, R.D. and K.A.; software,
R.D.; validation, K.A.; formal analysis, R.D.; investigation, K.A.; resources, R.D. and K.A.; data cura-
tion, R.D.; writing—original draft preparation, R.D.; writing—review and editing, K.A.; visualization,
R.D.; supervision, K.A. All authors have read and agreed to the published version of the manuscript.
Funding: This research received no external funding. The APC will be partially funded by Energy
Research Institute, Chulalongkorn University.
Institutional Review Board Statement: No applicable.
Informed Consent Statement: No applicable.
Data Availability Statement: Data is contained within the Appendix A, Appendix B, Appendix C,
Appendix D, Appendix E, Appendix F and Appendix G.
Conflicts of Interest: The authors declare no conflict of interest.
FOR
Fuel Type Number (Unit) Total Capacity (MW) Lifetime (Years) Heat Rate (Btu/kWh)
(%)
Lignite 7 2180.0 30–39 10,600 5.00
Bituminous 14 2406.6 21–30 8300–9100 5.00–7.00
Eastern natural gas 20 13,217.0 21–35 6800–9500 4.00–7.00
Western natural gas 11 7647.0 20–26 6800–9400 4.00–6.00
Other natural gas 76 7537.7 21–27 6800–8400 4.00–7.00
Import coal 3 1473.0 30 9100 6.00
Diesel 7 60.7 25–30 8300–10,400 7.00–10.00
Fuel oil 2 320.0 21–30 8300–10,400 7.00–10.00
Hydro 17 2926.8 50 - 3.58–6.76
Import hydro 4 2104.6 25–50 - 3.58–4.00
PHS 1 500.0 50 - 2.86
Renewable Energy - 5417.0 - - -
FOR
Fuel Type Number (Unit) Total Capacity (MW) Lifetime (Years) Heat Rate (Btu/kWh)
(%)
Natural Gas Infinite 100 25 6284 4.0
Natural Gas Infinite 700 25 6284 4.0
Table A9. Availability and unavailability of natural gas sources in the western gas network.
From the fact that Thailand’s western gas network is not sufficient to supply the desig-
nated power plants if at least one gas source is unavailable, the probability of unavailability
of the western gas source can be calculated from
Table A10. Availability and unavailability of major natural gas sources in the eastern gas network.
From the fact that Thailand’s eastern gas network is not sufficient to supply the
designated power plants if two or more major gas sources are unavailable, the probability
of unavailability of the eastern gas source can be calculated from
where
P0 = (0.997319 × 0.988588 × 0.997903 × 0.998990) = 0.982876
P1 = (0.002642 + 0.011346 + 0.002065 + 0.000994) = 0.017047
References
1. Koltsaklis, N.E.; Dagoumas, A.S. State-of-the-art generation expansion planning: A review. Appl. Energy 2018, 230, 563–589. [CrossRef]
2. Diewvilai, R.; Audomvongseree, K. Possible Pathways toward Carbon Neutrality in Thailand’s Electricity Sector by 2050 through
the Introduction of H2 Blending in Natural Gas and Solar PV with BESS. Energies 2022, 15, 3979. [CrossRef]
3. Diewvilai, R.; Audomvongseree, K. Generation expansion planning with energy storage systems considering renewable energy
generation profiles and full-year hourly power balance constraints. Energies 2021, 14, 5733. [CrossRef]
4. Chongphipatmongkol, T.; Audomvongseree, K. Determination of reserve margin based on specified loss of load expecta-
tion. In Proceedings of the ECTI-CON 2018–15th International Conference on Electrical Engineering/Electronics, Computer,
Telecommunications and Information Technology, Chiang Rai, Thailand, 18–21 July 2018; pp. 644–647. [CrossRef]
5. Billinton, R.; Allan, R. Reliability Evaluation of Power Systems; Pitman Advanced Publishing Program: London, UK, 1984;
ISBN 0273084852.
6. Ministry of Energy. Thailand’s Power Development Plan (PDP) 2018. Available online: http://www.eppo.go.th/images/
POLICY/PDF/PDP2018.pdf (accessed on 16 January 2022).
7. Korea Power Exchange. The 7th Basic Plan for Long-Term Electricity Supply and Demand (2015–2019). Available online:
https://www.kpx.or.kr/eng/selectBbsNttView.do?key=328&bbsNo=199&nttNo=14547 (accessed on 31 August 2021).
8. Tenaga, S. Energy Commission Peninsular Malaysia Electricity Supply Industry Outlook 2019; Suruhanjaya Tenaga: Putrajaya,
Malaysia, 2019.
9. Yu, H.H.; Chang, K.H.; Hsu, H.W.; Cuckler, R. A Monte Carlo simulation-based decision support system for reliability analysis of
Taiwan’s power system: Framework and empirical study. Energy 2019, 178, 252–262. [CrossRef]
Energies 2022, 15, 7854 17 of 17
10. North American Electric Reliability Corporation (NERC) 2021 Long-Term Reliability Assessment December. Available online:
https://www.nerc.com/pa/RAPA/ra/ReliabilityAssessmentsDL/NERC_LTRA_2021.pdf (accessed on 12 June 2022).
11. Wierzbowski, M.; Lyzwa, W.; Musial, I. MILP model for long-term energy mix planning with consideration of power system
reserves. Appl. Energy 2016, 169, 93–111. [CrossRef]
12. Neshat, N.; Amin-Naseri, M.R. Cleaner power generation through market-driven generation expansion planning: An agent-based
hybrid framework of game theory and Particle Swarm Optimization. J. Clean. Prod. 2015, 105, 206–217. [CrossRef]
13. Koltsaklis, N.E.; Georgiadis, M.C. A multi-period, multi-regional generation expansion planning model incorporating unit
commitment constraints. Appl. Energy 2015, 158, 310–331. [CrossRef]
14. Heuberger, C.F.; Rubin, E.S.; Staffell, I.; Shah, N.; Mac Dowell, N. Power capacity expansion planning considering endogenous
technology cost learning. Appl. Energy 2017, 204, 831–845. [CrossRef]
15. Chen, X.; Lv, J.; McElroy, M.B.; Han, X.; Nielsen, C.P.; Wen, J. Power system capacity expansion under higher penetration of
renewables considering flexibility constraints and low carbon policies. IEEE Trans. Power Syst. 2018, 33, 6240–6253. [CrossRef]
16. Fockens, S.; van Wijk, A.J.M.; Turkenburg, W.C.; Singh, C. A concise method for calculating expected unserved energy in
generating system reliability analysis. IEEE Trans. Power Syst. 1991, 6, 1085–1091. [CrossRef]
17. Hemmati, R.; Saboori, H.; Jirdehi, M.A. Multistage generation expansion planning incorporating large scale energy storage
systems and environmental pollution. Renew. Energy 2016, 97, 636–645. [CrossRef]
18. Hemmati, R.; Saboori, H.; Siano, P. Coordinated short-term scheduling and long-term expansion planning in microgrids
incorporating renewable energy resources and energy storage systems. Energy 2017, 134, 699–708. [CrossRef]
19. Sirikum, J.; Techanitisawad, A.; Kachitvichyanukul, V. A new efficient GA-Benders’ decomposition method: For power generation
expansion planning with emission controls. IEEE Trans. Power Syst. 2007, 22, 1092–1100. [CrossRef]
20. Opathella, C.; Elkasrawy, A.; Adel Mohamed, A.; Venkatesh, B. MILP formulation for generation and storage asset sizing and
sitting for reliability constrained system planning. Int. J. Electr. Power Energy Syst. 2020, 116, 105529. [CrossRef]
21. Aghaei, J.; Akbari, M.A.; Roosta, A.; Baharvandi, A. Multiobjective generation expansion planning considering power system
adequacy. Electr. Power Syst. Res. 2013, 102, 8–19. [CrossRef]
22. Hanna, R.; Disfani, V.R.; Haghi, H.V.; Victor, D.G.; Kleissl, J. Improving estimates for reliability and cost in microgrid investment
planning models. J. Renew. Sustain. Energy 2019, 11, 45302. [CrossRef]
23. Oree, V.; Sayed Hassen, S.Z.; Fleming, P.J. A multi-objective framework for long-term generation expansion planning with
variable renewables. Appl. Energy 2019, 253, 113589. [CrossRef]
24. Hamidpour, H.; Pirouzi, S.; Safaee, S.; Norouzi, M.; Lehtonen, M. Multi-objective resilient-constrained generation and transmission
expansion planning against natural disasters. Int. J. Electr. Power Energy Syst. 2021, 132, 107193. [CrossRef]
25. Abushamah, H.A.S.; Haghifam, M.R.; Bolandi, T.G. A novel approach for distributed generation expansion planning considering
its added value compared with centralized generation expansion. Sustain. Energy Grids Netw. 2021, 25, 100417. [CrossRef]
26. Abdalla, O.H.; SMIEEE, L.; Adma, M.A.A.; Ahmed, A.S. Two-stage robust generation expansion planning considering long- and
short-term uncertainties of high share wind energy. Electr. Power Syst. Res. 2020, 189, 106618. [CrossRef]
27. Abdalla, O.H.; Abu Adma, M.A.; Ahmed, A.S. Generation expansion planning under correlated uncertainty of mass penetration
renewable energy sources. IET Energy Syst. Integr. 2020, 2, 282–288. [CrossRef]
28. Hadidian Moghaddam, M.J.; Kalam, A.; Nowdeh, S.A.; Ahmadi, A.; Babanezhad, M.; Saha, S. Optimal sizing and energy
management of stand-alone hybrid photovoltaic/wind system based on hydrogen storage considering LOEE and LOLE reliability
indices using flower pollination algorithm. Renew. Energy 2019, 135, 1412–1434. [CrossRef]
29. Billinton, R. Evaluation of reliability worth in an electric power system. Reliab. Eng. Syst. Saf. 1994, 46, 15–23. [CrossRef]
30. Billinton, R.; Wangdee, W. Approximate methods for event-based customer interruption cost evaluation. IEEE Trans. Power Syst.
2005, 20, 1103–1110. [CrossRef]
31. Newell, S.; Spees, K.; Pfeifenberger, J.; Karkatsouli, I.; Wintermantel, N.; Carden, K. Estimating the Economically Optimal Planning
Reserve Margin in ERCOT; The Brattle Group: Boston, MA, USA, 2014.
32. Newell, S.; Carroll, R.; Kaluzhny, A.; Spees, K.; Carden, K.; Wintermantel, N.; Krasny, A. Estimation of the Market Equilibrium and
Economically Optimal Reserve Margins for the ERCOT Region; The Brattle Group: Boston, MA, USA, 2018.
33. Energy and Environmental Economics. Estimating the Economically Optimal Planning Reserve Margin. Available online:
https://www.epelectric.com/files/html/PRM_Report.pdf (accessed on 12 June 2022).
34. Amaro, S. 3 Charts Show Europe’s Unprecedented NAtural Gas Crisis. Available online: https://www.cnbc.com/2022/08/01/3-charts-
show-europes-unprecedented-natural-gas-crisis-.html (accessed on 31 August 2022).
35. Ministry of Energy. Thailand’s Power Development Plan (PDP) 2018 Rev. 1. Available online: https://policy.asiapacificenergy.
org/node/4347/portal (accessed on 31 August 2021).
36. Wang, S.; Zheng, N.; Bothwell, C.D.; Xu, Q.; Kasina, S.; Hobbs, B.F. Crediting Variable Renewable Energy and Energy Storage in
Capacity Markets: Effects of Unit Commitment and Storage Operation. IEEE Trans. Power Syst. 2022, 37, 617–628. [CrossRef]
37. Junlakarn, S.; Diewvilai, R.; Audomvongseree, K. Stochastic Modeling of Renewable Energy Sources for Capacity Credit
Evaluation. Energies 2022, 15, 5103. [CrossRef]
38. Naksrisuk, C.; Audomvongseree, K. Dependable capacity evaluation of wind power and solar power generation systems. ECTI
Trans. Electr. Eng. Electron. Commun. 2013, 11, 58–66.