Installation Guidelines
Installation Guidelines
1
Deciding the site-specific design and layout of system components
The scale of storage tank required and specific layout of the system components used is unique for each
particular site. Factors to consider in the selection of tank size and site layout include:
• Topography and relative elevations of buildings and key site locations.
• Condition of existing roofing structures.
• Distance between buildings and key site locations.
• Location of and access to other sources of water for future connection.
• Location of and access to drainage channels for overflow.
• Surface area of existing roofing structures to be utilised.
• Layout of buildings and key site locations.
• Annual rainfall distribution of the specific implementation location.
• Water use requirements of the school or clinic.
This step required the input of an experienced engineer to guide the implementing contractor. Once
final decisions regarding system design, tank size and site layout have been made and communicated to
the implementing contractor, the contractor should follow the following steps alongside normal
construction practices to implement the provided design.
2
• Securely attach the gutter brackets to the fascia board using fixtures rated for long-term
external use. Brackets should be installed at appropriate spacings roughly 1m apart.
• Aluminium or galvanized steel are recommended materials for the gutter brackets.
• Clip the guttering securely into the mounting brackets and ensure the entire gutter is flat and
securely attached, reinforce with additional brackets it required.
• Ensure proper sealing between joins where guttering sections meet, this can be achieved using
commercially available joints or liberal application of silicone sealant.
• Ensure downpipes are well connected and sealed with PVC cement and/or silicone sealant as
appropriate.
• Ensure end caps are well secured and sealed with silicone sealant.
• Ensure the end of the roof sheet is overhanging the guttering in all locations.
• Test the system by pouring a large amount of water on the furthest location from the downpipe
and observing for any leaks or areas in which water does not flow freely towards the downpipe.
• Test all locations along the length of the building to ensure water flows freely from the roof to
the gutter in all locations.
• If roof slow is low and water runs back up past the gutter on the underside of the roof sheet in
some locations this can be amended by slightly bending down the end of the roof sheet or with
the application of a single bead of silicone sealant on the underside of the roof sheet, 5mm in
from the edge to promote the deposition of water in this area and break the surface tension
drawing water back up the underside of the roof sheet.
3
• Ensure downpipes are well connected and sealed with PVC cement and/or silicone sealant as
appropriate.
• Test the system by pouring a large amount of water into the downpipe and observing for any
leaks or areas in which water does not flow freely.
4
STEP 5: Construction of tank stand and storage tank
• Ensure that the elevation of the inlet of the tank will allow for adequate continuous fall from the
top of the first flush mechanism to ensure sufficient flow of water from the collection system to
the storage tank. Adjust the foundation height and depth accordingly based on specific site
conditions.
• Ensure hardcore base well compacted.
• Install formwork for slab concrete.
• Slab levelling with lean concrete 1:3:6 according to drawing.
• Install rebar (reinforcement steel) for the slab.
• Install formwork for wall of storage tank according to drawing.
• Ensure overall formwork is strong and according to size before being cast.
• Cast in place for concrete must be 1:2:3 according the drawing.
• Ensure the inlet pipe to the storage tank is straight with a continuous fall towards the tank.
• Ensure the inlet pipe has a minimum slope of 0.5% (preferably 2%, the greater the slope the
better) is maintained throughout the inlet pipe.
• Ensure the inlet pipe is sufficiently supported to ensure it does not move or warp over time,
accounting for the weight of water when the pipe is full.
• Ensure the installation of the outlet, overflow pipes and box controls according to the drawing