Detailed Calculations
Detailed Calculations
Substituting 21.043 for C/V in the formulas for Class B (1:2 1/2:5):
ROOF BEAM
18000-1451-1347-1,990-3600-1760-954-810-1390-1375-313-262=2,748 sqm
LINTEL BEAMS
D6=0.60(3)=1.8+ 0.30=2.1(.30)=0.69
TOTAL = 6.66m³
Concrete floor topping for 200mm x 200mm Ceramic Floor tiles - T&B (20x20 Homogenous Tiles)
T&B 1
T&B 3
Concrete floor topping for 600mm x 600mm Ceramic Floor tiles (60x60 Homogeneous Tiles)
Laundry & Kitchen = 37.30 sqm. /0.36 sqm. = 103.61 pcs. say 105pcs.
Living & Dining = 37.50 sqm. /0.36 sqm. = 104.16 pcs. say 105pcs.
From the drawings, there are 16 pieces of steel reinforcing bars per footing. Therefore:
Total Number of Bar for 15 Footing = 16 × 15 = 240 Pieces
No. of F/L Bars Required = 240/7 = 34.29; say 35 pcs ⌀16mm × 6.00m = 331.28 kg
From the drawings, there are 16 pieces of steel reinforcing bars per footing. Therefore:
Total Number of Bar for 10 Footing = 16 × 10 = 160 Pieces
No. of F/L Bars Required = 160/9 = 17.78; say 18 pcs ⌀12mm × 6.00m = 95.904 kg
From the drawings, there are 8 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 80m
Plus 10% Allowance for Wastage and Splicing = 8m
Total Length of Beam + Allowance = 88m
Total Number of Bar for the total length of FTB = 8 × 88 = 704 pcs
No. of F/L Bars Required = 704/8 = 88; say 90 pcs ⌀12mm × 6.00m = 479.17 kg
Column C-1
Column C-2
Slab Rebars
Wall Footing
From the drawings, there are 3 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 20.93m
Plus 10% Allowance for Wastage and Splicing = 2.093m
Total Length of Beam + Allowance = 23.023m
Total Number of Bar for the total length of FTB = 3 × 23.023 = 69.069 ; say 70 pcs
No. of F/L Bars Required = 70/6 = 11.66; say 12 pcs ⌀16mm × 6.00m = 113.58 kg
Roof Beams
From the drawings, there are 8 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 78.90m
Plus 10% Allowance for Wastage and Splicing = 7.89m
Total Length of Beam + Allowance = 86.79m
Total Number of Bar for the total length of FTB = 8 × 86.79 = 694.32 ; say 695 pcs
No. of F/L Bars Required = 695/6 = 115.83; say 116 pcs ⌀16mm × 6.00m = 1097.95 kg
Horizontal Bars
Wall A
Height of the wall = 3.5/.8 =4.375 say 5pcs.
Length of the wall = 46.58 x 5 = 232.9m
232.9(1.10)
=42.70 ; say 43pcs.
6.00 m
Wall B
Vertical Bars
Wall A
3.5/.8 = 4.375 say 5pcs.
Wall B
4/.8 = 5pcs.
4(13) = 52
501.6(1.2)
= 100.32 ; say 101pcs. = 537.74kg
6.00 m
STEEL TIES
Pieces
C-1: 15 Pcs - 0.30m by 0.30m
C-2: 10 Pcs - 0.20m by 0.20m
Height
C-1: 4.8m
C-2: 4.8m
Size of Tie Bar
C-1: ⌀10mm @ .20m OC
C-2: ⌀10mm @ .20m OC
Number of Ties
C-1: 4.8/.20 = 24; say 25 Ties
C-2: 4.8/.20 = 24; say 25 Ties
CHB WALLS
No. of CHB required = 9.275 x 13 = 120.57; say 121 pcs.(2) = 242 pcs.
Area of Wall = 2 x 4 = 8 m²