Detailed Calculations

The document provides calculations for estimating concrete and rebar quantities needed for various structural elements of a building project. It calculates concrete volumes and rebar quantities for columns, footings, slabs, stairs, beams, and more. Formulas are used to determine bag quantities of cement, sand and gravel needed based on the estimated concrete volumes. Total estimated concrete volumes are provided along with rebar quantities and sizes required for footings and tie beams.

Uploaded by

Kyle Hipolito
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
228 views15 pages

Detailed Calculations

The document provides calculations for estimating concrete and rebar quantities needed for various structural elements of a building project. It calculates concrete volumes and rebar quantities for columns, footings, slabs, stairs, beams, and more. Formulas are used to determine bag quantities of cement, sand and gravel needed based on the estimated concrete volumes. Total estimated concrete volumes are provided along with rebar quantities and sizes required for footings and tie beams.

Uploaded by

Kyle Hipolito
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 15

Concrete Mix (Columns)

Length of One Column (C1) = 4.00m + .40m + .40m = 4.80m


Total Length of 15 Columns (C1) = 15 × 4.80m = 72.00m
Total Length of 15 Columns (C1) = 10 × 4.80m = 48.00m
Total Length of 25 Columns (C1 & C2) = 25 × 4.80m = 120.00m

Concrete Volume of 15 Columns (C1) = 72.00m × .30m × .30m = 6.48m


Concrete Volume of 10 Columns (C2) = 48.00m × .20m × .20m = 1.92m
C1 + C2 = 6.48m³ + 1.92m³ = 8.40m³
Plus: 5% Allowance for Wastage = 0.42m³
Total Estimated Concrete Volume (C/V) = 8.82m³

Substituting 8.82 for C/V in the formulas for Class A (1:2:4):


8.82 × 7.85 = 69.08; say 70 Bags Cement
8.82 × 0.42 = 3.7044; say 4 Cubic Meters Sand
8.82 × 0.84 = 7.4088; say 8 Cubic Meters Gravel

Concrete Mix (Footings)


Volume of One Footing (F1) = 1 × 1 × 0.25 = 0.25m³
Total Volume of 15 Footing (F1) = 0.25 × 15 = 3.75m³
Volume of One Footing (F2) = 0.80 × 0.80 × 0.25 = 0.16m³
Total Volume of 10 Footing (F2) = 0.25 × 15 = 1.60m³
Total Volume of 25 Footing = F1 + F2 = 3.75 + 1.60 = 5.35m³

Plus: 10% Allowance for Wastage = 0.535m³


Total Estimated Concrete Volume (C/V) = 5.885m³

Substituting 5.885 for C/V in the formulas for Class A (1:2:4):


5.885 × 7.85 = 46.19; say 42 Bags Cement
5.885 × 0.42 = 2.47; say 3 Cubic Meters Sand
5.885 × 0.84 = 4.94; say 5 Cubic Meters Gravel
FTB = Volume × Quantity = in cubic meter

FTB 1A = 0.301392m³ × 3 = 0.90 m³


FTB 1B = 0.301392m³ × 3 = 0.81 m³
FTB 1C = 0.301392m³ × 3 = 0.80 m³
FTB 1D = 0.301392m³ × 5 = 0.84 m³
FTB 1E = 0.301392m³ × 1 = 0.33 m³
FTB 1F = 0.301392m³× 2 = 0.58 m³
FTB 1G = 0.301392m³ × 2 = 0.56 m³
FTB 1H = 0.301392m³ × 2 = 0.35 m³
FTB1I = 0.301392m³ × 2 = 0.69 m³
FTB1J = 0.34713m³ × 1 = 0.35 m³
FTB1K = 0.1691655m³ × 1 = 0.17 m³
FTB1L = 0.322686m³ × 1 = 0.32 m³
FTB1M = 0.258888m³ × 1 = 0.26 m³
FTB1N = 0.4055625m³ × 1 = 0.41 m³
FTB1O = 0.27008625m³ × 1 = 0.27 m³

Concrete Volume of FTB = 7.64 m³

Plus: 10% Allowance for Wastage = 0.764 m³


Total Estimated Concrete Volume (C/V) = 8.404 m³

Substituting 8.404 for C/V in the formulas for Class A (1:2:4):

8.404 × 7.85 = 65.8714; say 66 Bags Cement


8.404 × 0.42 = 3.52968; say 4 Cubic Meters Sand
8.404 × 0.84 = 7.05936; say 8 Cubic Meters Gravel

Slab = Volume × Quantity = in cubic meter

S1A = 2.3762908m³ × 1 = 2.38 m³


S1B = 2.1469736m³ × 1 = 2.15 m³
S1C = 1.4524532m³ × 1 = 1.45 m³
S1D = 1.0107807m³ × 1 = 1.01 m³
S1E = 1.0529061m³ × 1 = 1.05 m³
S1F = 1.0542332m³× 1 = 1.05 m³
S1G = 3.7120454m³ × 1 = 3.71 m³
S1H = 1.4060491m³ × 1 = 1.41 m³
S1I = 1.4532506m³ × 1 = 1.45 m³
S1J = 2.4486903m³ × 1 = 2.45 m³
S1K = 0.7441415m³ × 1 = 0.74 m³
S1L = 0.2747492m³ × 1 = 0.27 m³
Concrete Volume of Slab = 19.13 m³

Plus: 10% Allowance for Wastage = 1.913 m³


Total Estimated Concrete Volume (C/V) = 21.043 m³

Substituting 21.043 for C/V in the formulas for Class B (1:2 1/2:5):

21.043 × 6.49 = 136.56907; say 137 Bags Cement


21.043 × 0.44 = 9.25892; say 10 Cubic Meters Sand
21.043 × 0.87 = 18.30741; say 19 Cubic Meters Gravel

Wall Footing = Volume × Quantity = in cubic meter

WF1A = 0.157008m³ × 2 = 0.31 m³


WF1B = 0.255256m³ × 1 = 0.26 m³
WF1C = 0.10964m³ × 1 = 0.11 m³
WF1D = 0.189824m³ × 1 = 0.19 m³
WF1E = 0.219832m³ × 1 = 0.22 m³
WF1F = 0.27968m³× 1 = 0.28 m³
WF1G = 0.463392m³ × 1 = 0.46 m³

Concrete Volume of Wall Footing = 1.09 m³

Plus: 10% Allowance for Wastage = 0.109 m³


Total Estimated Concrete Volume (C/V) = 1.199 m³

Substituting 1.199 for C/V in the formulas for Class A (1:2:4):

1.199 × 7.85 = 9.41215; say 10 Bags Cement


1.199 × 0.42 = 0.50358; say 1 Cubic Meters Sand
1.199 × 0.84 = 1.00716; say 2 Cubic Meters Gravel

Concrete Stairs (Porch)

Concrete Stairs = (L × W × D) × Number of Steps = in cubic meter


Concrete Volume of Concrete Stairs = (4.30 × 0.30 × 0.172) × 4 = 0.88752m³
Concrete Stairs as a Cube = (L × W × D) = (4.30 × 1.20 × .825) = 4.257m³
Getting the Exact Measurement = 4.257 - 0.88752 = 3.36948m³
= 3.36948/2 = 1.68474m³
= 1.68474 + 0.88752 = 2.57226
Concrete Volume of Concrete Stairs = 2.57226m³

Plus: 0.5% Allowance for Wastage = 0.128613 m³


Total Estimated Concrete Volume (C/V) = 2.700873 m³
Substituting 2.700873 for C/V in the formulas for Class A (1:2:4):

2.700873 × 7.85 = 21.20185305; say 22 Bags Cement


2.700873 × 0.42 = 1.13436666; say 2 Cubic Meters Sand
2.700873 × 0.84 = 2.26873332; say 3 Cubic Meters Gravel

CONCRETE STAIRS (BACK)

Concrete Stairs = (L × W × D) × Number of Steps = in cubic meter


Concrete Volume of Concrete Stairs = (1.5 × 0.30 × 0.172) × 4 = 0.306m³

Concrete Stairs as a Cube = (L × W × D) = (1.5 × 1.20 × .825) = 1.485m³

Getting the Exact Measurement = 1.485 - 0.306 = 1.179m³


= 1.179/2 = 0.5895m³
= 0.5895 + 0.306 = 0.8955

Plus: 0.5% Allowance for Wastage = 0.0153 m³


Total Estimated Concrete Volume (C/V) =0.9108 m³

Substituting 0.9108 for C/V in the formulas for Class A (1:2:4):

0.9108 × 7.85 = 7.14978; say 8 Bags Cement


0.9108 × 0.42 = 0.382536; say 1 Cubic Meters Sand
0.9108 × 0.84 = 0.765072; say 1 Cubic Meters Gravel

Total Cubic meter of Concrete Stairs (Porch & Back)

TotalPORCH + TotalBACK = 2.700873 m³ + 0.9108 m³ = 3.611673 m³

Total Square meter of Concrete Stairs (Porch & Back)

TotalPORCH + TotalBACK = 5.16 sqm + 1.8 sqm = 6.96sqm

STRUCTURAL STEEL AND OTHER METALS


TotalTRUSS + TotalPURLINS = P73,935 + P58,800 = P132,735
Concrete Mix (Roof Beam)

Concrete Volume of Roof Beam = 8.00m³

Plus: 10% Allowance for Wastage = 0.8 m³


Total Estimated Concrete Volume (C/V) = 8.80 m³

Substituting 8.80 for C/V in the formulas for Class A (1:2:4):


8.80 × 7.85 = 69.08; say 70 Bags Cement
8.808 × 0.42 = 3.696 say 4 Cubic Meters Sand
8.80 × 0.84 = 7.392; say 8 Cubic Meters Gravel

ROOF BEAM

18000-1451-1347-1,990-3600-1760-954-810-1390-1375-313-262=2,748 sqm

LINTEL BEAMS

D1=2.7 + 0.30 =3(.30) =.90


D2=2.7(2)=5.4 + 0.30=5.7(.30)=1.71

D3=3.6+ 0.30 =3.9(.30)=1.17


D4=2.7+ 0.30= 3(.30)=0.90
D5=0.80(5) = 4+ 0.30 = 4.3(.30)=1.29

D6=0.60(3)=1.8+ 0.30=2.1(.30)=0.69

TOTAL = 6.66m³

Concrete floor topping for 200mm x 200mm Ceramic Floor tiles - T&B (20x20 Homogenous Tiles)

T&B 1

Total sq.m. = 3.62 sq.m.


Area of Tiles = 0.04 sq.m.
Total no. of tiles= 3.62sqm/0.04 = 91 pcs.
Plus: 5% Allowance for Wastage = 4.55 pcs
Total Tiles = 95.55; say 96 tiles
T&B 2

Total sq.m. = 2.95 sq.m.


Area of Tiles = 0.04 sq.m.
Total no. of tiles= 2.95sqm/0.04 = 74 pcs.
Plus: 5% Allowance for Wastage = 3.70 pcs
Total Tiles = 77.70; say 78 tiles

T&B 3

Total sq.m. = 3.00 sq.m.


Area of Tiles = 0.04 sq.m.
Total no. of tiles= 3.00sqm/0.04 = 75 pcs.
Plus: 5% Allowance for Wastage = 3.75 pcs.
Total Tiles = 78.75; say 79 tiles

Total SQM of all T&B = 9.57 sqm

Concrete floor topping for 600mm x 600mm Ceramic Floor tiles (60x60 Homogeneous Tiles)

Bedroom 1 = 17.80 sqm. / 0.36 sqm. = 49.4 pcs. say 50 pcs.

Bedroom 2 = 10 sqm. / 0.36 sqm. = 27.7 pcs. say 30 pcs.

Bedroom 3 = 14.06 sqm. / 0.36 sqm. = 38 pcs. say 40pcs.

Bedroom 4&5 = 10.50 sqm. /0.36 sqm. = 29 pcs. say 30pcs.

Laundry & Kitchen = 37.30 sqm. /0.36 sqm. = 103.61 pcs. say 105pcs.

Living & Dining = 37.50 sqm. /0.36 sqm. = 104.16 pcs. say 105pcs.

Total floor sqm = 43.20 sqm

Total = 360 pcs.

Plus: 5% Allowance for Wastage = 18 pcs


Total Tiles = 378 tiles
REBARS

Footings Rebar for F-1 1.00m by 1.00m

From the drawings, there are 16 pieces of steel reinforcing bars per footing. Therefore:
Total Number of Bar for 15 Footing = 16 × 15 = 240 Pieces

No. of F/L Bars Required = 240/7 = 34.29; say 35 pcs ⌀16mm × 6.00m = 331.28 kg

Footings Rebar for F-2 0.80m by 0.80m

From the drawings, there are 16 pieces of steel reinforcing bars per footing. Therefore:
Total Number of Bar for 10 Footing = 16 × 10 = 160 Pieces

No. of F/L Bars Required = 160/9 = 17.78; say 18 pcs ⌀12mm × 6.00m = 95.904 kg

Total Kilogram of Rebars for Footings = 331.28 + 95.904 = 427.184 kg


Total Piece of Rebars for Footings = 35 + 18

Footing Tie Beam 0.15m by 0.30m

From the drawings, there are 8 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 80m
Plus 10% Allowance for Wastage and Splicing = 8m
Total Length of Beam + Allowance = 88m
Total Number of Bar for the total length of FTB = 8 × 88 = 704 pcs

No. of F/L Bars Required = 704/8 = 88; say 90 pcs ⌀12mm × 6.00m = 479.17 kg

Column C-1

No. of Column = 15 Columns


C-1 = 10 Pcs⌀16mm
Height of C-1 = 4.80m
4.80 + 0.35 = 5.15m
5.15 × 10 =51.5m
51.5 × 15 Columns = 772.5m
772.5
×1.10=141.625 say 142 pcs. ⌀16mm × 6.00m Bars = 1344.05 kg
6

Column C-2

No. of Column = 10 Columns


C-2 = 4 Pcs⌀16mm
Height of C-1 = 4.80m
4.80 + 0.35 = 5.15m
5.15 × 4 = 20.6m
20.6 × 10 Columns = 206m
206
× 1.10=37.77 say 38 pcs. ⌀16mm × 6.00m Bars = 359.67 kg
6

Total Kilogram of Rebars for Column = 1344.05 + 359.67 = 1703.72 kg

Slab Rebars

Total Length of Slabs = 57.8094m


Plus 10% Allowance for Wastage and Splicing (Length) = 5.78094m
Total Length of Slab + Allowance = 63.69034; say 64 Pcs. ⌀12mm × 6.00m = 340.74 kg

Total Width of Slabs = 55.5299m


Plus 10% Allowance for Wastage and Splicing (Length) =5.55299m
Total Length of Slab + Allowance = 61.08; say 62 Pcs. ⌀12mm × 6.00m = 330.10 kg
Total Kilogram = 340.74 + 330.10 = 670.84 kg.

Wall Footing

From the drawings, there are 3 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 20.93m
Plus 10% Allowance for Wastage and Splicing = 2.093m
Total Length of Beam + Allowance = 23.023m
Total Number of Bar for the total length of FTB = 3 × 23.023 = 69.069 ; say 70 pcs

No. of F/L Bars Required = 70/6 = 11.66; say 12 pcs ⌀16mm × 6.00m = 113.58 kg

Roof Beams

From the drawings, there are 8 pieces of steel reinforcing bars per FTB. Therefore:
Total Length of FTB = 78.90m
Plus 10% Allowance for Wastage and Splicing = 7.89m
Total Length of Beam + Allowance = 86.79m
Total Number of Bar for the total length of FTB = 8 × 86.79 = 694.32 ; say 695 pcs

No. of F/L Bars Required = 695/6 = 115.83; say 116 pcs ⌀16mm × 6.00m = 1097.95 kg

MASONRY WORKS REBARS

Horizontal Bars

Wall A
Height of the wall = 3.5/.8 =4.375 say 5pcs.
Length of the wall = 46.58 x 5 = 232.9m
232.9(1.10)
=42.70 ; say 43pcs.
6.00 m
Wall B

Height of the wall = 4 /.8 = 5pcs.


Length of the wall = 37.45 x 5 = 187.25m
187.25(1.10)
=34.38 ; say 35pcs.
6.00 m
Total no. of Horizontal Rebars = 78 pcs.= 415.28kg

Vertical Bars

Wall A
3.5/.8 = 4.375 say 5pcs.

3.5 (15) = 52.5

Wall B
4/.8 = 5pcs.

4(13) = 52

Total no. of vertical bars = 10 pcs.

104.5 (4.8) = 501.6m

501.6(1.2)
= 100.32 ; say 101pcs. = 537.74kg
6.00 m

Total kg of rebars = 953.02kg

STEEL TIES

Pieces
C-1: 15 Pcs - 0.30m by 0.30m
C-2: 10 Pcs - 0.20m by 0.20m

Height
C-1: 4.8m
C-2: 4.8m
Size of Tie Bar
C-1: ⌀10mm @ .20m OC
C-2: ⌀10mm @ .20m OC

Number of Ties
C-1: 4.8/.20 = 24; say 25 Ties
C-2: 4.8/.20 = 24; say 25 Ties

Number of Ties multiplied by No. of Columns


C-1: 15 × 25 = 375 Pcs
C-2: 10 × 25 = 250 Pcs

Pieces ties that can be cut


C-1: 5 Ties
C-2: 6 Ties

No. of Full - Length Bars Required


C-1: 375/5 = 75 pcs of ⌀10mm × 6.00m
C-2: 250/6 = 41.67 pcs; say 42 pcs of ⌀10mm × 6.00m

CHB WALLS

BEDROOM 3 (CHB for wall 1) (exterior wall)

Area of Wall = 4.6 x 3.5 = 16.1 m²

Less (Door) = 2.7 x 2.4 = 6.48 m²

Net CHB wall area = 16.1 - 6.48 m² = 9.62 m²

No. of CHB required = 9.62 x 13 = 125.06; say 126 pcs.

(CHB for wall 2&3) (exterior wall)

Area of Wall = 2.65 x 3.5 = 9.275 m²

No. of CHB required = 9.275 x 13 = 120.57; say 121 pcs.(2) = 242 pcs.

(CHB for wall 4) (interior wall)

Area of Wall = 4.7 x 3.5 = 16.45 m²

Less (Door) = 0.8 x 2.10 = 1.68 m²

Net CHB wall area = 16.45 - 1.68 m² = 14.77 m²

No. of CHB required = 14.77 x 13 = 192.01; say 192 pcs.

BEDROOM 4 (CHB for wall 1) (exterior wall)


Area of Wall = 2.7 x 3.5 = 9.45 m²

Less (window) = 1.5 x 1.2 = 1.8 m²

Net CHB wall area = 9.45 - 1.8 m² = 7.65 m²

No. of CHB required = 7.65 x 13 = 99.45; say 100 pcs.

(CHB for wall 2) (interior wall)

Area of Wall = 2.7 x 3.5 = 9.45 m²

Less (door) = 2.7 x 2.4 = 6.48 m²

Net CHB wall area = 9.45 - 6.48 m² = 2.97 m²

No. of CHB required = 2.97 x 13 = 38.61; say 39 pcs.

(CHB for wall 3) (interior wall)

Area of Wall = 3.5 x 3.5 = 12.25 m²

No. of CHB required = 12.25 x 13 = 159.25; say 160 pcs.

BEDROOM 5 (CHB for wall 1) (exterior wall)

Area of Wall = 2.7 x 3.5 = 9.45 m²

Less (window) = 1.5 x 1.2 = 1.8 m²

Net CHB wall area = 9.45 - 1.8 m² = 7.65 m²

No. of CHB required = 7.65 x 13 = 99.45; say 100 pcs.

(CHB for wall 2) (interior wall)

Area of Wall = 2.7 x 3.5 = 9.45 m²

Less (door) = 2.7 x 2.4 = 6.48 m²

Net CHB wall area = 9.45 - 6.48 m² = 2.97 m²

No. of CHB required = 2.97 x 13 = 38.61; say 39 pcs.

(CHB for wall 3) (interior wall)

Area of Wall = 3.4 x 4 = 13.6 m²


No. of CHB required = 13.6 x 13 = 176.8; say 177 pcs.

KITCHEN (CHB for wall 1) (exterior wall)

Area of Wall = 2.7 x 4 = 10.8 m²

Less (Window) = 2.7 x 4 = 1.8 m²

Net CHB wall area = 10.8 - 1.8 m² = 9 m²

No. of CHB required = 9 x 13 = 117; say 117 pcs.

(CHB for wall 2) (exterior wall)

Area of Wall = 1.4 x 4 = 5.6 m²

No. of CHB required = 5.6 x 13 = 72.8; say 73 pcs.

T&B 2 (CHB for wall 1) (interior wall)

Area of Wall = 2.2 x 4 = 8.8 m²

No. of CHB required = 8.8 x 13 = 114.4; say 115 pcs.

(CHB for wall 2) (exterior wall)

Area of Wall = 1.4 x 4 = 5.6 m²

Less (Window) = 0.6 x 0.5 = 0.3 m²

Net CHB wall area = 5.6 - 0.3 m² = 5.3 m²

No. of CHB required = 5.3 x 13 = 68.9; say 69 pcs.

(CHB for wall 3) (interior wall)

Area of Wall = 1.4 x 4 = 5.6 m²

Less (door) = 0.6 x 2.1 = 1.26 m²

Net CHB wall area = 5.6 - 1.26 m² = 4.34 m²

No. of CHB required = 4.34 x 13 = 56.42; say 57 pcs.


(CHB for wall 4) (interior wall)

Area of Wall = 2 x 4 = 8 m²

No. of CHB required = 8 x 13 = 104; say 104 pcs.

T&B 3 (CHB for wall 1) (exterior wall)

Area of Wall = 1.3 x 4 = 5.2 m²

Less (Window) = 0.6 x 0.5 = 0.3 m²

Net CHB wall area = 5.2 - 0.3 m² = 4.9 m²

No. of CHB required = 4.9 x 13 = 63.7; say 64 pcs.

(CHB for wall 2) (interior wall)

Area of Wall = 1.5 x 4 = 6 m²

Less (door) = 0.6 x 2.1 = 1.26 m²

Net CHB wall area = 6 - 1.26 m² = 5.26 m²

No. of CHB required = 5.26 x 13 = 68.38; say 69 pcs.

LAUNDRY (CHB for wall 1) (exterior wall)

Area of Wall = 5.1 x 4 = 20.4 m²

BR 1 & T&B 1 (CHB for wall 1) (interior wall)

Area of Wall = 4.45 x 4 = 17.8 m²

No. of CHB required = 17.8 x 13 = 231.4; say 232 pcs.

(CHB for wall 2) (exterior wall)

Area of Wall = 4.45 x 3.5 = 15.575 m²

Less (window) = 2.7 x 2.4 = 6.48 m²

Net CHB wall area = 15.575 - 6.48 m² = 9.091 m²

No. of CHB required = 9.01 x 13 = 118.233; say 119 pcs.


T&B 1 (CHB for wall 1) (interior wall)

Area of Wall = 2.6 x 3.5 = 9.1 m²

No. of CHB required = 9.1 x 13 = 118.3; say 119 pcs.

(CHB for wall 2) (interior wall)

Area of Wall = 1.45 x 3.5 = 5.075 m²

Less (door) = 0.6 x 2.10 = 1.26 m²

Net CHB wall area = 5.075 - 1.26 m² = 3.815 m²

No. of CHB required = 3.815 x 13 = 49.59; say 50 pcs.

(CHB for wall 3) (interior wall)

Area of Wall = 4.5 x 3.5 = 15.75 m²

Less (door) = 0.8 x 2.10 = 1.68 m²

Net CHB wall area = 15.75 - 1.68 m² = 14.07 m²

No. of CHB required = 14.07 x 13 = 182.91; say 183 pcs.

BEDROOM 2 (CHB for wall 1) (exterior wall)

Area of Wall = 2.83 x 3.5 = 9.9 m²

Less (door) = 1.5 x 1.2 = 1.8 m²

Net CHB wall area = 9.9 - 1.8 m² = 8.1 m²

No. of CHB required = 8.1 x 13 = 105.3; say 106 pcs.

(CHB for wall 2) (interior wall)

Area of Wall = 2.83 x 3.5 = 9.9 m²

Less (door) = 0.80 x 2.10 = 1.68 m²

Net CHB wall area = 9.9 - 1.68 m² = 8.22 m²


No. of CHB required = 8.22 x 13 = 106.8; say 107 pcs.

(CHB for wall 3) (interior wall)

Area of Wall = 4.5 x 3.5 = 15.75 m²

No. of CHB required = 15.75 x 13 = 204.75; say 205 pcs.

DINING/LIVING (CHB for wall 1) (exterior wall)

Area of Wall = 5.7 x 4 = 22.8 m²

Less (window) = 3.6 x 2.4 = 8.64 m²

Net CHB wall area = 22.8 - 8.64 m² = 14.16 m²

No. of CHB required = 14.16 x 13 = 184.08; say 185 pcs.

(CHB for wall 2) (exterior wall)

Area of Wall = 4.9 x 4 = 19.6 m²

Less (window) = 2.7 x 2.4 = 6.48 m²

Net CHB wall area = 19.6 - 6.48 m² = 13.12 m²

No. of CHB required = 13.12 x 13 = 170.56; say 171 pcs.