34.5kV OHL Installation Works

The document is a bill of quantities (BOQ) for 34.5kV overhead power line installation works. It includes 14 line items with quantities, unit rates, and total rates for various activities such as erecting pole sections, installing guy wires and pole accessories, earthing poles, stringing conductors and optical ground wire, installing junction boxes, laying underground cable, installing reclosers, and terminating cables. The total estimated cost for all the works is 20,701,500 Saudi Riyals.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
396 views1 page

34.5kV OHL Installation Works

The document is a bill of quantities (BOQ) for 34.5kV overhead power line installation works. It includes 14 line items with quantities, unit rates, and total rates for various activities such as erecting pole sections, installing guy wires and pole accessories, earthing poles, stringing conductors and optical ground wire, installing junction boxes, laying underground cable, installing reclosers, and terminating cables. The total estimated cost for all the works is 20,701,500 Saudi Riyals.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

BOQ for 34.

5kV OHPL INSTALLATION WORKS


Unit Rate Total Rate
Sl No. Activity UOM Qty Remarks
(SAR) (SAR)

Erection of Top pole section with bottom embedded section including loading from
1 store, transportation and unloading at site as per Saudi Aramco Standards, Nos 1,671 3000 5,013,000
Specifications and in line with IFC drawing and Site Engineer instruction

Erection of Guy wire along with Fixing of all accessories for Overhead Pole including
2 loading from store, transportation and unloading at site as per Saudi Aramco Nos 541 500 270,500
Standards, Specifications and in line with IFC drawing and Site Engineer instruction

Installation of pole accessories to the pole section including loading from store,
3 transportation and unloading at site as per Saudi Aramco Standards, Specifications Nos 1,671 2000 3,342,000
and in line with IFC drawing and Site Engineer instruction

Earthing of Electical Poles including installation of grounding rods and conductors


4 from equipment as required by National Electrical Code and in accordance with Saudi Nos 1,671 1000 1,671,000
Aramco Engineering Standard SAES-P-104 and SAES-P-111

Paying out, tensioning, binding of ACSR Merlin Conductors and tightening of stays, Tensioner,Puller,Pilot wire,
5 Circuit- Kms 126 40000 5,040,000
Stringing of conductors -3phase (Circuit Length- 126 km) conductor rullers by L&T

Tensioner,Puller,Pilot wire,
6 Strining of 48F OPGW conductors (Circuit Length- 126 km) Kms 126 20000 2,520,000
OPGW rullers by L&T

7 Installation of OPGW Junction boxes including all civil works Nos 25 5000 125,000

If Pre-Installation Test,Post
8 48F OPGW splicing and connection to Junction Boxes Nos 50 12000 600,000 Test require then rate will
be increased

9 Installation automatic recloser along the 34.5kV OHPL Nos 15 5000 75,000
Laying of 3Cx400sqmm, 34.5kV underground power cable at road crossing and insider
10 M 1,800 500 900,000
substation (including thru HDD duct)
11 Laying of underground FO cable (UGNMFOC) M 1,800 500 900,000
12 Auto / Tie-in Re-closures & LBS with Control Box incl. Pole & Stringing Sets 50 2500 125,000

Termination of 3X400sqmm, 34.5kV Power Cable and connection to 34.5kV OH Power All tools and accessories
13 Sets 20 5000 100,000
Line provided by L&T

14 Testing of 3Cx400sqmm, 34.5kV Power Cable Sets 10 2000 20,000


20701500 SAR