Pile Group: Number & Spacing of Piles in A Group
Pile Group: Number & Spacing of Piles in A Group
Pile Group
Number & Spacing of Piles in a Group
Very rarely are structures founded on single piles. Normally,
there will be a minimum of three piles under a column or a
foundation element because of alignment problems and
inadvertent eccentricities.
1 2
1
10/30/2019
Number & Spacing of Piles in a Group … Cont’d Typical Arrangements of Piles in Groups
When piles are cast-in-situ, the soils adjacent to the piles are not
stressed to that extent and as such smaller spicing are permitted.
If the displacement of soil compacts the soil in between the piles as in
the case of loose sandy soils, the piles may be placed at closer
intervals.
But if the piles are driven into saturated clay or silty soils, the
displaced soil will not compact the soil between the piles. As a result
the soil between the piles may move upwards and in this process lift
the pile cap. Greater spacing between piles is required in soils of this
type to avoid lifting of piles.
Generally, the spacing for point bearing piles, such as piles
founded on rock, can be much less than for friction piles since the
high-point-bearing stresses and the superposition effect of overlap of
the point stresses will most likely not overstress the underlying
material nor cause excessive settlements.
7 8
2
10/30/2019
* This holds true for driven piles in loose sand. Otherwise, the spacing has to be > 3. 9 10
Empirical Formula
11 12
This equation is limited to rectangular groups with identifiable values of n1 x n2.
3
10/30/2019
Driven Group Piles in Sand & Gravel Bored Pile Groups in Sand & Gravel
If piles are driven into loose sand and gravel, the soil around the piles
to a radius of at least three times the pile diameter is compacted. The
efficiency of the pile group becomes greater than unity. There will always be a general loosening of the soil during boring and
It is normally assumed that the efficiency falls to unity when the then too when the boring has to be done below the water table.
spacing is increased to five or six diameters.
Since present knowledge is not sufficient to evaluate the efficiency for Since bored piles do not compact the soil between the piles, the
different spacing of piles, it is conservative to assume an efficiency efficiency factor will never be greater than unity.
factor of unity for all practical purposes. We may, therefore, write
For practical purposes, the efficiency may be taken as 2/3-3/4.
The procedure explained above is not applicable if the pile tips rest on
compressible soil such as silts or clays. The carrying capacity of pile
groups under these conditions is governed by the shear strength and
compressibility of the soil, rather than by the "efficiency” of the
group within the sand or gravel stratum.
13 14
4
10/30/2019
17 18
5
10/30/2019
Settlement of Single Pile in Cohesionless Soils Settlement of Single Pile in Cohesionless … Cont’d
21 22
Settlement of Single Pile in Cohesionless … Cont’d Settlement of Single Pile in Cohesionless … Cont’d
23 24
6
10/30/2019
25 26
27 28
7
10/30/2019
vo ' '
For normally consolidated clay, e Cc log
vo '
29 30
Example 1.9
Check the adequacy of the 3x3 pile group with regard to settlement criterion.
•Spacing and diameter of piles are 0.6 and 0.2 m respectively
•DL=600 KN & LL= 400 KN
•Allowable settlement= 75 mm
31