SAUDI ARAMCO ID/PID - Rev 1- 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Low Voltage Cable and Wire SATIP-P-104-01 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW
Cable and Conduit Seal To be reviewed and approved prior to electrical work at
1.1
Installation Procedures
SAIC-P-3004 SAIC-P-3004 RH1 R1 job site
RECEIVING
2.0
INSPECTION
Cable Storage, Handling,
2.1 and Preservation SAIC-P-3201 SAIC-P-3201 W2 S Weekly Inspection by Contractor QC
Visual Inspection
SAIC-P-3202 UL / NEC Cable
Cable Reel
SAIC-P-3203 NEC / SASO / IEC Unjacketed Wire
2.2 Material Receiving See Remarks See Remarks H1 W1 SAIC-P-3204 IEC Armored Cable
Visual Inspection
SAIC-P-3205 IEC Unarmored Cable
SATR-P-3201 Power & Control Cable Test
Cable Material Receving SATR-P-3202 Building Wire Test
2.3 Continuity and Insulation See Remarks See Remarks H1 W2 Continuity (Volt-Ohm meter) and insulation resistance
Testing (On Cable Reel) (Megger) testing. SA to witness 1 of every 10 LV cable
reel tests.
Cable accessories include cable pulling lubricant; cable
gland connector fittings, hot and cold shrink insulation
tubing; electrical tape; cable straps and ties; crimp wire
connectors; cable termination kits; bulk terminal blocks
Cable Accessories
and points; bulk electrical nuts, bolts and washers;
2.4 Material Receiving SAIC-P-3206 SAIC-P-3206 H1 W2 crimping tools & dies; weather-proof cable and duct seal,
Visual Inspection
hazardous location damming fiber and cement.
Notify SA PID by RFI on initial receipt of each listed
accessory (by type and/or manufacturer).
Page 1 of 3
11/27/2005 3:13 PM
SAUDI ARAMCO ID/PID - Rev 1- 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Low Voltage Cable and Wire SATIP-P-104-01 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.0 INSTALLATION
SAIC-P-3207 Power & Control Cable
Cable Pulling SAIC-P-3208 Building Wire (Circuit)
3.1
Visual Inspection
See Remarks See Remarks H1 W2 SA PID shall be notified on start of this activity for each
process system, and plant area.
Direct Buried Also See SATIP-Q-001 for additional test and inspection
Cable Trench activities for road crossings.
3.2
Visual Inspection
SAIC-P-3333 SAIC-P-3333 H1 W1 See SATIP-A-114 for additional direct buried earthwork
(Before Cable Laying) QA/QC activities, requirements, and coordination.
SAIC-P-3207 Power & Control Cable
Below Grade Cable Laying
SAIC-P-3333 Identification and Backfilling
3.3 and Warning Marker Installation See Remarks See Remarks H1 W1 Hold points for all direct buried LV cables prior to
Visual Inspection
backfilling of cable and safety warning markers.
SAIC-P-3207 Power & Control Cable
SAIC-P-3208 Building Wire (Circuit)
Cable dressing and termination work (inside cabinet)
shall not proceed unitl all cable glands, cable route and
Cable Gland Installation, Cable cable dressing in tray has been inspected by Contractor
3.4 Dressing, Cable Identification and See Remarks See Remarks H1 W2 QC.
Termination Visual Inspection
SA PID shall be notified on termination of first ten circuits
of each voltage service level. SA PID shall be notified
on start of this activity for each process system and plant
area.
4.0 PRE-COMMISSIONING
SATR-P-3203 Power & Control Cable Test
Cable Continuity SATR-P-3204 Building Wire Test
4.1 and Insulation Testing See Remarks See Remarks H1 W2 Continuity (Volt-Ohm meter) and insulation resistance
(Installed Cable) (Megger) testing. SA to witness 1 of every 10 LV cable
tests.
Page 2 of 3
11/27/2005 3:13 PM
SAUDI ARAMCO ID/PID - Rev 1- 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Low Voltage Cable and Wire SATIP-P-104-01 1-Oct-05 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SATR-P-3205 Power & Control Cable Torque Test
SATR-P-3206 Building Wire Torque Test
Cable Termination
4.2
Torque Testing
See Remarks See Remarks H2 W2 Contractor QC Inspector to witness torque testing on
100% of all power terminations. SA PID to witness 1 of
every 10 LV power cable termination torque tests.
Cable / Conduit Hold point for cement pouring (after cable pulling and
4.3
Hazardous Location Sealing
SAIC-P-3209 SAIC-P-3209 H1 H1 fiber dam installation)
SAIC-P-3207 Power & Control Cable
Cable / Circuit
4.4
Final Visual Inspection
See Remarks See Remarks H1 H1 SAIC-P-3208 Building Wire (Circuit)
Hold point for energization of each power circuit.
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative
4
in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 Sample Review of Documents S Surveillance