0% found this document useful (0 votes)
710 views1 page

Template Certificate of Final Completion

This certificate of final completion certifies that a contractor has completed a project for a company according to their service order and agreement. It establishes the date of final completion and notes that the contractor's obligations and the company's rights under their agreement are still in effect. Representatives from both the company and contractor have signed to acknowledge completion and acceptance of the project.

Uploaded by

ozy3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
710 views1 page

Template Certificate of Final Completion

This certificate of final completion certifies that a contractor has completed a project for a company according to their service order and agreement. It establishes the date of final completion and notes that the contractor's obligations and the company's rights under their agreement are still in effect. Representatives from both the company and contractor have signed to acknowledge completion and acceptance of the project.

Uploaded by

ozy3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CERTIFICATE OF FINAL COMPLETION

Company
Contractor
Service Order #
Project ID
Date of Final Completion

Final inspection of the Work has been conducted and Company is reasonably satisfied that Final
Completion has been achieved in accordance with the Service Order and the terms of the Master
Construction Services Agreement referred to in the Service Order. The Date of Final Completion is as
indicated above.

The issuance of this Certificate does not reduce or exclude Company’s rights or Contractor’s
obligations under the Master Construction Services Agreement and the Service Order.

All capitalised terms shall have the same meaning as defined in the Master Construction Services
Agreement.

Xenith IG Approvers
Company’s Representative Executive Approval
Signature: Signature:
Name: Name:
Position / Title: Position / Title:
Date: Date:

********

Contractor acknowledges and accepts the above Certificate of Final Completion.

Contractor’s Representative:

Name:
Title:
Date: