1 INTRODUCTION
Water purification plants play an essential function in ensuring that populations have access to
pure and secure potable water. around the world. The successful implementation of these plants
requires effective project management, which involves planning, organizing, and controlling
the various stages of the project. This introduction provides an overview of the importance of
Water treatment plant projects encompass a range of activities, including treatment facility
design, building, and commission, as well as the implementation of necessary infrastructure
and systems. Efficient project management ensures that these complex endeavors are executed
within specified timeframes, budgets, and quality standards. Moreover, it facilitates
coordination among different stakeholders, such as engineers, environmental experts,
government agencies, and community representatives, to ensure a holistic approach to water
treatment.
One of the primary objectives of project management in water treatment plants is to ensure the
delivery of safe and reliable drinking water to the population. By employing effective project
management methodologies, risks and uncertainties associated with the project can be
identified, assessed, and mitigated. This reduces the chances of delays, cost overruns, and
potential operational issues, thereby enhancing the overall efficiency and effectiveness of the
water treatment plant.
However, managing water treatment plant projects comes with its own set of challenges. These
projects often involve complex technical requirements, stringent regulatory standards, and the
need to integrate multiple engineering disciplines. Additionally, environmental considerations,
such as source water protection and wastewater management, add further complexity to the
project. Effective project management strategies must address these challenges, ensuring that
the project is executed in compliance with environmental regulations while maintaining the
desired water quality standards.
Despite the challenges, efficient project management brings several benefits to water treatment
plant projects. It promotes stakeholder engagement and collaboration, enabling the
involvement of communities, government agencies, and relevant organizations in the decision-
making process. Moreover, it facilitates the efficient allocation of resources, such as labor,
equipment, and materials, leading to cost savings and optimized project schedules.
Furthermore, project management methodologies aid in tracking and oversight of the
development of projects, permitting swift modifications and corrections to ensure project
success.
In conclusion, project management plays a vital role in the successful implementation of water
treatment plants. It enables the achievement of key objectives, addresses challenges specific to
these projects, and unlocks numerous benefits. By embracing effective project management
practices, stakeholders can ensure the provision of clean and safe drinking water to
communities, contributing to the overall well-being and sustainable development of societies
worldwide.
Water is devoid of color, flavor, and odor. It is an outstanding fluid and destroys the majority
of foods with which it comes into proximity. Therefore, natural water is always contaminated
with molecular and microbiological impurities, i.e., decomposed minerals and organic
and manganese can be found in numbers. Organic compounds from decaying plant and animal
matter and agricultural waste become natural home products of synthetic organics used for
cleaning, pesticides, pesticides and solvents. These materials and how much they are can
impact the integrity and utility of natural assets water resources.
the nation's daily drinking water supply The regular water consumption per individual
generally includes the following items:
• Domestic needs such as drinking, cooking, bathing, bathing, toilet, building and ventilation.
• Institutional Needs
The three main objectives of water treatment plants are: I. Producing safe water for human
consumption II. Making water more attractive to consumers III. Create safe water and
chemicals that can be produced and operated. Water at a reasonable price is the main purpose
of the construction of water facilities; every drop is incredible. A well-designed plant is
essential not only to ensure the safety of drinking water, but also to skillful and careful plant
operation and attention to hygiene of water supply and distribution. The second purpose The
objective in water remediation is to produce safe water for consumption. attractive to
consumers. The most beautiful and attractive water is clear, colorless, pleasant to taste, odorless
and cold water. It does not smudge, rust or flake and is very soft. Most customers are concerned
not with the quality of their treatment plant, but with the quality of their faucets. Therefore,
water management must ensure that the quality of water is not compromised during delivery,
storage and distribution to consumers.
1.4 Aim:
• • The purpose of this investigation is to update and follow the construction management in a
water treatment plant with a capacity of 5.5 MLD.
1.5 Objective:
2. LITERATURE REVIEW
This paper published by [3] Atul Auti and Martin Skit more in International Journal of
Construction Management used the methodology, a questionnaire Email requests for responses
were sent to a randomized group of 150 organizations as well as interested parties. Potential
respondents included diverse project supervisors, engineers, designers, investigators, and
advisers who are presently active in the field in India and who were deemed suitable for
delivering the requested comments. The conclusion of the authors was that efficient project
management application could assist in the achievement of new levels of fulfillment and greater
standards. The attributes of project management should alter the perception of the business
sector and be valued by all parties, including customers, stakeholders, and end uses.
2.3 Project Management Practice and Its Effects on Project Success in Construction
Industry.
The paper published by[7] N A. Haron, P Devi, S Hassim, A H Alias M M Tahir, and A N
Harun in International Conference on Architecture and Civil Engineering used the method, A
questionnaire with 16 closed-ended questions and an equal number of multiple choice
questions and 5-point Likert scale options was developed. A pilot test was conducted with 30
of the intended respondents in order to guarantee that they would comprehend the
questionnaire's queries and identify any potential obstacles. Their decision was that a drastic
application of project administration could be eschewed in order not to cause a disruption in
the operation of the company. Education institutions should offer teaching or courses in project
2.4 Major Factors Influencing Productivity of Water and Wastewater Treatment Plant
Construction
This paper published by [9] S. Mojahed, F. Aghazadeh, in the International Academy of Project
Management, utilized the approach, and data was gathered from prior papers along with
research. A survey of WTP market providers with annual sales exceeding $100 million was
carried out. Several sewage and water treatment plant building sites were visited and analyzed
in order to obtain an improved comprehension of the influence of main productivity variables
and to recommend practices for enhancing output on construction locations. This paper
suggests that it is possible to increase productivity by modifying working practices in the
industry and focusing on accelerating the adoption of standard procedures on building
locations. Comparing the main efficiency factors of this study to those of a study conducted in
the United States thirty years ago as well as other international studies reveals that these
primary efficiency elements vary across initiatives, businesses, and regions of the world.
The purpose of this study is to examine infrastructure project management. This study
illustrates various aspects of project management in terms of problems and issues and offers
solutions to promote and improve project management through this study. Most researchers
use qualitative methods and specific methods to complete their research projects. The
researchers met with several experts in the field and conducted 36 interviews with the project
manager. The analysis shows that the project management is faced with many problems and
problems, the most important problems are poor planning, poor project management, poor
communication between all parties and not reaching the best solution. It also demonstrates in
many ways that the management process is the key to the success of any engineering project.
Purpose of water purification - to provide safe drinking water without impurities, odors or
colors; Provides adequate water for domestic, commercial, industrial and fire protection needs.
Even if only about 1% of the water produced is used for drinking and cooking, all water
produced in public water systems must be of potable quality. This study covers the purpose of
water treatment plants and describes the water treatment process. In this study, the work and
the process are explained. The study was carried out through the observation of WWTP
workers who determined the treatment process and obtained operational results by describing
the water treatment need and the temporary process from raw water to treatment. After
distribution after purification, aeration, coagulation and flocculation, sediment filtration and
laboratory and safety disinfection.
The paper published by [8] Schozel & Bower (1999), The project's primary objective is to
discover current disposal and purification methods, ongoing cleaning programs and initiatives,
and potential pilot project locations. The objective of this study as stated by the author is
management and need of wastewater treatment plant by identifying the wastewater treatment
technologies and scope of the plant in villages on a small-scale basis. The study concluded by
explaining the various types of plants that can be opted for the small-scale projects of
wastewater treatment plants by analysing the cost efficiency, material management, quality
control and operation cost.
Construction projects are extremely complex undertakings that involve a vast array of factors.
Numerous factors, which include design, materials, apparatus, geographical features, geology,
hydrology, meteorology, building science, ways of operations, technical specifications, and
management systems, influence the quality of construction. To provide more high-quality, safe,
appropriate, and cost-effective composite products, building contractors have to stick to the
tenet of quality first and insist on high standards based on artificial control and protection. The
primary objective is to conduct a qualitative and quantitative evaluation of the grade of concrete
used in India's construction industry. After conducting statistical evaluation on example test
results gathered from building locations and verifying the conformance to these compression
strength test findings via Indian Standards, this methodology was used to evaluate the amount
of quality assurance being implemented. upon analyzing the obtained results, the study found
that a manual on the making of concrete must be put together and utilized as an outline on
construction areas, since concrete is a significant building material and a structural component.
During concrete production processes, a quality assurance strategy must be developed and
properly implemented, which identifies the essential tasks and aids in undertaking suitable
3. METHODOLOGY
1.Project Initiation
• Identify the need for a water treatment plant project and establish clear project objectives.
• Conduct a feasibility study to assess the technical, financial, and environmental viability
of the project.
• Define the project scope, stakeholders, and project team roles and responsibilities.
2. Project Planning
• Develop a comprehensive project plan that outlines the project's objectives, deliverables,
timeline, and budget.
• Identify and analyze potential risks and develop risk mitigation strategies.
• Determine the required resources, including personnel, equipment, and materials.
• Create a communication plan to ensure effective information flow among project
stakeholders.
• Establish performance metrics and milestones to track progress throughout the project
lifecycle.
3. Project Execution
• Procure necessary resources and equipment based on the project plan and specifications.
• Implement the construction and installation of water treatment plant components
according to engineering design.
• Regularly monitor and control project activities to ensure adherence to quality standards
and timeline.
5. Project Closure
• Complete all project deliverables and conduct final inspections to guarantee conformity
with specifications.
• Acquire the requisite licenses as well as certifications for the water treatment plant's
operation.
• Perform an exhaustive assessment of the endeavor to evaluate its efficacy and determine
learning learnt.
• Archive all Documentation of the endeavor, involving plans, states, and pertinent info for
use later on.
• Provide proper training and handover to the plant's operational staff.
4. RESULT DISCUSSION
The collected from the questionnaire survey of experienced professionals was analyzed by
using MS Excel software by cross tabulating analysis method. Cross tabulation analysis carries
out the relationship between the two, three or multiple parameters of the data collected the data
was analyzed with reference to the designation and experience of the respondents. Therefore,
the results obtained by this method was reliable as the priority was given to the experienced
one with having a better designation in the industry.
The data gathered from the telephone conversation was processed using the technique of
thematic examination for the qualitative part of this research, as theme evaluation combines
(often very large) data sets corresponding to their similarities. The questionnaire asked to
individuals were categorized and similar interests was analysed regarding. Qualitative analysis
was done to combine the data collected and was represented to meet the objective of this study.
• As, shown in the above fig.4.1 it is clear that the respondents were professional and having
a good experience in the field of civil engineering. Mostly 47.6% of personnel were having
experience of less than 3 years while there were quite experienced personals having
experience up to 10 years. So, it can be stated as the results obtained were reliable. The
respondents were quite qualified for this study as 52.38 % were graduated and 33.33 %
were the post graduates having a good experience in the industry. As well-educated
responses make the study reliable and trustworthy due to good technical knowledge.
• 88.37% of respondents were aware of the concept of construction management resulting
that there is quite a good understanding of the construction management and need of
construction management can be established by using the results.
As the study is purely based on the construction management, so the respondents were asked
that, “How would you rate yourself as a manager on a construction site?”. The obtained
responses were analysed on the designation basis of the respondents in which it is found that
the Construction Manager, Architect, Supervisor, Team Leader, Executive Engineer, Labour
Contractor, Project Manager and Site Engineer rated themselves as best manager as shown in
the fig.4.2 above. So, it can state as there are quite good manager in the industry who build up
the construction industry.
Since the respondents are the best manager in this study, but they also responded in majority
of 97.67% as there is need of construction management for the public projects like Water
treatment plant. Construction management is much needed concept for the future of industry.
The result analysed can be clearly seen in the fig. 4.3.
Since the majority of people i.e., almost 98% of people thinks that there is a serious need for
the proper management in the construction of the government projects since they lack in the
management skills which leads to various problems which were further asked, that 72% of
people thinks that these kind of projects like water treatment plant and various other public
projects lacks the ideal flow of the work which is very necessary for the management point of
view.
The result in the fig.4.6 clearly shows that there is very slight chance of failing of WTP projects.
62.79% of respondents stated that there is no chance of failure of this project which is a good
result for management point of view.
The availability of skilled labour is quite good according to the responses most of the
respondents Architects, Contractor, Labour contractor, Site Engineer, Project Manager,
Supervisor and Project Engineer can make the availability of skilled labour easily but they
commented there opinion as it requires more cost for immediate need or the labour needs a
steady work flow since they are on the daily wages.
Communication problem arises during the construction project and especially in the complex
structure like water treatment plants, and one of the main reasons is the language barrier since
there are various local languages spoken among the sub-contractor, labours, supervisors and
engineers it gets hard to understand even the simple activities. The response also shows the
same result in the fig. that 40.48% of the personnel find the problem in the communication due
to language while 59.52 % have no problem regarding.
The fig.5.9 clear state one of the main reasons for the need of construction management in the
public projects due to labour intensive culture. As shown in the fig. 86 % of the experienced
respondents states that construction industry in India is quite labour intensive.
There is also another reason in India that there is quite high temperature weather all over which
also makes the labour dependent work tasks getting delayed on daily basis. Climate play’s vital
As the work gets easy workflow gets ideal and speed of the construction activities improves.
This can be achieved by minimizing the manual labour work by replacing by modern tools,
equipment and machineries which not only saves the time but also improves the quality of work
and provides better results. This can be justified in the fig.4.11 analysis of the respondents of
which 81.4 % believe in.
As shown in the fig.4.12, 62.79 % of responses clearly states that the water treatment plants
have complicated design. There are various factors to be considered while doing any activity
for the future coming activity as the structure is completely water based so flow, level, jumps,
collection, etc. are needed to be considered. Therefore, during the construction an experience
personal is needed who can also manage the project.
Quality is the most important factor that guarantees the project life and its success. The various
factors that affect the quality of the construction activity is well showed in the fig.
4.13 above. The main reasons for poor quality can be stated as poor project management,
complex designs, communication gap, lack of supervision and poor workmanship. These
factors can be managed and eliminated by good planning and management skills during the
construction activities.
Over budget is one of the reasons that leads a delay or complete stoppage to any activity of
project or an entire project. Budget planning is the most important for any construction activity,
after all money is the only factor for which all the parties are working. It can be clearly seen in
the fig.5.15 that the main reasons for overbudgeting are incorrect assessing project schedule
rates, Poor Planning and lack of project understanding with lack of coordination. The reasons
can be eliminated by better project management resulting in the budget friendly project.
(Note: PPE-Personal Protective Equipment, LS-Ladder Safety, WAC-Keep the Work Area
Clean, PST-Proper Site Training, RCD-Reporting and clearing defects, IDA-If in doubt, ask,
PEC-Precautions for environmental changes, All-All the above).
At every construction project safety is must. Safe practices for any construction activities
should be encouraged like providing the proper site training, PPE should be provided to the
personnel working on site and visitors too. Keeping the work area clean is a good practice while
if there are any defects that should be reported to the supervisor or in charge. All of the factors
are necessary for safety as seen in the fig.5.16 as any accidents or damages not only results in
delays in construction activities but also affects the health of the personnel involved.
The data collected was cross referenced to the percentage of respondents’ states that they agree
to the reasons for need of planning and management for a complex project of water treatment
plant. The data was summarized in order to understand the necessity of construction
management due to the reasons showed in fig. 5.17. The respondents who strongly agree for
the reasons behind need of planning and management were taken into consideration for the
result of the study. The data was further analysed in terms of the percentage and the reasons
were ranked accordingly that causes the need of construction management of water treatment
plant. The labour-intensive culture was ranked first as main reason for the need of planning
and management for construction projects while language barrier for communication was
ranked at the bottom summarizing the reasons for planning and management.
The data that was collected and analysed on MS Excel software was further concluded that
95.45 % of the respondent strongly believes that there is necessity of construction management
for water treatment plant out of which 86.36 % were aware about the concept and benefits of
construction management who strongly believes that utilization of modern technologies, tools
and equipment can improves the construction activities resulting in better outputs. The
construction management can be done by a construction manager who is capable of
overcoming the reasons and solving the problems in construction activities of water treatment
plant to which 84.09 % of the professionals strongly agree.
• For working on a schedule there are various factors to be taken into considerations like
adaption of modern technologies and equipment. The skilled labors play a vital role in
construction of especially WTP as there are various complications in the design the structure
basically works on the elevation from the other structure as it is water based and plays a vital
role for the smooth flow of water. The blame game should be eliminated by appointing a neutral
party which can also be helpful for solving the communication problems which can be one by
hiring the construction or project manager. The manager not only helps in those difficulties but
also helps in the construction flow on schedule and can also be helpful for the fund management
of the project. The problems of theft and vandalism can be overcome by hiring a watchman
and an overnight supervisor which could be helpful for saving the materials and equipment
from the site.
Completing the activity in a given time is one of the hardest tasks in eyes of every party in the
WTP. As climate plays a vital role for meeting the deadline like in the summer season the
deadline is often meet but as soon as the monsoon begins there occurs the delay in activities
and deadline is mostly meet. Funds is an important factor for meeting project on time as the
cash flows smoothly the construction works smoothly and every party is happy.
Various parties have various roles in crisis, like if the theft happens the problem should be
solved by the site in charge and watchman itself. If there are any problems related to the
drawing or design the problem should be solved by site engineer, the designer and the clients’
representatives. Like if there are certain issues with fund, higher authorities like contractor and
client will have to solve the problem. But every one of the parties stated that these issues could
be resolved if there is a construction project manager who himself can handle all these issues.
Yes, for sure if there is a perfect planning and the problems which may arise are taken into
consideration then the activity surely successfully completed in the given time with the quality
work.
5.CONCLUSION
Effective project management plays a pivotal role in ensuring the successful implementation
and operation of a water treatment plant. By employing sound project management principles,
such as comprehensive planning, diligent execution, and proactive risk management, project
managers can navigate the complex challenges associated with water treatment projects.
The key takeaway is that project management provides a structured approach to coordinate and
integrate various aspects of the project, including engineering design, procurement,
construction, and commissioning. It enables teams to adhere to schedules, allocate resources
efficiently, and monitor progress closely, ultimately resulting in the timely completion of the
water treatment plant.
Additionally, the incorporation of sustainable practices in project management can lead to long-
term benefits for the water treatment plant and its surrounding environment. Emphasizing the
use of eco-friendly technologies, optimizing energy consumption, and implementing robust
maintenance strategies can contribute to the plant's efficiency, reliability, and overall
environmental sustainability.