2692-Article Text-4653-1-10-20230725

This document discusses project management of water treatment plants. It highlights that effective project management is important for ensuring water treatment plants provide safe drinking water to populations. Key objectives of project management for these projects include delivering clean water safely and on time and within budget. Challenges include complex technical requirements and environmental regulations. Benefits include cost savings, stakeholder collaboration, and efficient resource allocation. Project management is vital for the successful implementation of water treatment plants.

Uploaded by

asghar khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views22 pages

2692-Article Text-4653-1-10-20230725

This document discusses project management of water treatment plants. It highlights that effective project management is important for ensuring water treatment plants provide safe drinking water to populations. Key objectives of project management for these projects include delivering clean water safely and on time and within budget. Challenges include complex technical requirements and environmental regulations. Benefits include cost savings, stakeholder collaboration, and efficient resource allocation. Project management is vital for the successful implementation of water treatment plants.

Uploaded by

asghar khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22

Mathematical Statistician and Engineering Applications

ISSN: 2094-0343
2326-9865

Project Management of Water Treatment Plant


Abhishek Shirle*1, Dr. Satish S. Deshmukh*2, Pravin Manatkar*3 , Dr. Sunil Thakare*4

*1 Assistant Professor, Civil Engineering Department, KJ’s Educational Institute Trinity Academy
of Engineering, affiliated to Savitribai Phule University Pune, Maharashtra India.

*2 Professor, Civil Engineering Department, KJ’s Educational Institute Trinity Academy of


Engineering, affiliated to Savitribai Phule University Pune, Maharashtra India.

*3 Assistant Professor, Civil Engineering Department, KJ’s Educational Institute Trinity Academy
of Engineering, affiliated to Savitribai Phule University Pune, Maharashtra India.

*4 Professor, Civil Engineering Department, Anantrao Pawar College of Engineering Pune,


Maharashtra India.

Mail Id- 1. [email protected] 2. [email protected] 3.


[email protected] 4. [email protected]
Article Info Abstract— Increasing urban population, especially in developing nations,
Page Number: 13094-13114 both land and water are under extreme stress; it also causes too much water,
Publication Issue: many things that cannot be done. Therefore, water purification has become
Vol. 71 No. 4 (2022) necessary due to the scarcity of drinking water and the needs of the growing
world population. The use of water directly from rivers, streams and lakes
is not safe today because it contains many diseases, viruses and other
diseases that can affect human, plant and animal health. This weak and
unsafe water source creates the need for water treatment plants. This study
aims to evaluate project management practices for the construction of a 5
capacity water treatment plant.5 MLD is used to supply potable water to 30
villages in Shegaon, Maharashtra. Therefore, the responsibilities of project
management include identifying business needs, making business
decisions, monitoring progress, and correcting business gaps. The aim is to
complete the project plan for the construction Treatment of water facilities
by means of planning and carrying out and managing time, money, people
and resources. The data for this study were obtained through interview
questions from project managers, engineers, contractors, customers and site
workers, and qualitative questions from people experienced in business and
business development. This study aims to understand the water treatment
plant construction project management application, evaluation and
Article History modification knowledge.
Article Received: 15 October 2022 Keywords- water treatment plant, construction project management,
Revised: 24 November 2022 drinking water, construction industry, public sector projects, labor-intensive
Accepted: 18 December 2022 culture.

1 INTRODUCTION

Water purification plants play an essential function in ensuring that populations have access to
pure and secure potable water. around the world. The successful implementation of these plants
requires effective project management, which involves planning, organizing, and controlling
the various stages of the project. This introduction provides an overview of the importance of

Vol. 71 No. 4 (2022) 13093


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
project management in the context of water treatment plants, highlighting the key objectives,
challenges, and benefits associated with managing such projects.

Water treatment plant projects encompass a range of activities, including treatment facility
design, building, and commission, as well as the implementation of necessary infrastructure
and systems. Efficient project management ensures that these complex endeavors are executed
within specified timeframes, budgets, and quality standards. Moreover, it facilitates
coordination among different stakeholders, such as engineers, environmental experts,
government agencies, and community representatives, to ensure a holistic approach to water
treatment.

One of the primary objectives of project management in water treatment plants is to ensure the
delivery of safe and reliable drinking water to the population. By employing effective project
management methodologies, risks and uncertainties associated with the project can be
identified, assessed, and mitigated. This reduces the chances of delays, cost overruns, and
potential operational issues, thereby enhancing the overall efficiency and effectiveness of the
water treatment plant.

However, managing water treatment plant projects comes with its own set of challenges. These
projects often involve complex technical requirements, stringent regulatory standards, and the
need to integrate multiple engineering disciplines. Additionally, environmental considerations,
such as source water protection and wastewater management, add further complexity to the
project. Effective project management strategies must address these challenges, ensuring that
the project is executed in compliance with environmental regulations while maintaining the
desired water quality standards.

Despite the challenges, efficient project management brings several benefits to water treatment
plant projects. It promotes stakeholder engagement and collaboration, enabling the
involvement of communities, government agencies, and relevant organizations in the decision-
making process. Moreover, it facilitates the efficient allocation of resources, such as labor,
equipment, and materials, leading to cost savings and optimized project schedules.
Furthermore, project management methodologies aid in tracking and oversight of the
development of projects, permitting swift modifications and corrections to ensure project
success.

In conclusion, project management plays a vital role in the successful implementation of water
treatment plants. It enables the achievement of key objectives, addresses challenges specific to
these projects, and unlocks numerous benefits. By embracing effective project management
practices, stakeholders can ensure the provision of clean and safe drinking water to
communities, contributing to the overall well-being and sustainable development of societies
worldwide.

1.2 WATER AND ITS QUALITY

Water is devoid of color, flavor, and odor. It is an outstanding fluid and destroys the majority
of foods with which it comes into proximity. Therefore, natural water is always contaminated
with molecular and microbiological impurities, i.e., decomposed minerals and organic

Vol. 71 No. 4 (2022) 13094


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
molecules and organisms. These compounds may originate from the discharge from mineral
springs and landfills. Nevertheless, urban along with commercial garbage also generates
numerous organic and inorganic contaminants. Breakdown and dissolution of minerals, soil,
and sands produce inorganic compounds that are typically magnesium, calcium, sodium, and
ammonium bicarbonates, chlorine, and sulfate nitrates and phosphates. Also, lead, copper,
arsenic, iron

and manganese can be found in numbers. Organic compounds from decaying plant and animal
matter and agricultural waste become natural home products of synthetic organics used for
cleaning, pesticides, pesticides and solvents. These materials and how much they are can
impact the integrity and utility of natural assets water resources.

the nation's daily drinking water supply The regular water consumption per individual
generally includes the following items:

• Domestic needs such as drinking, cooking, bathing, bathing, toilet, building and ventilation.

• Institutional Needs

• Public use such as laundry or irrigation in parks, sewerage, water.

• Utilities and Small Business Fire Protection

• Livestock requirements and

• Minimum drainage (UFW).

1.3 PURPOSE OF WTP

The three main objectives of water treatment plants are: I. Producing safe water for human
consumption II. Making water more attractive to consumers III. Create safe water and
chemicals that can be produced and operated. Water at a reasonable price is the main purpose
of the construction of water facilities; every drop is incredible. A well-designed plant is
essential not only to ensure the safety of drinking water, but also to skillful and careful plant
operation and attention to hygiene of water supply and distribution. The second purpose The
objective in water remediation is to produce safe water for consumption. attractive to
consumers. The most beautiful and attractive water is clear, colorless, pleasant to taste, odorless
and cold water. It does not smudge, rust or flake and is very soft. Most customers are concerned
not with the quality of their treatment plant, but with the quality of their faucets. Therefore,
water management must ensure that the quality of water is not compromised during delivery,
storage and distribution to consumers.

1.4 Aim:

• • The purpose of this investigation is to update and follow the construction management in a
water treatment plant with a capacity of 5.5 MLD.

1.5 Objective:

Objectives of this study are as follows

Vol. 71 No. 4 (2022) 13095


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
• The benefits of application of construction project management in the public project like
water treatment plant.
• Inefficiency, cost overruns, delays in construction, poor communication, poor
construction, potential security, disputes and claims etc.
• The effects of project management on this construction of water treatment plant than the
traditional approach of labour-intensive work.
• Use the findings of this research to assist public authorities in designing water treatment
plants to use construction management techniques to improve their performance and
prevent problems.

2. LITERATURE REVIEW

2.1 Construction Project Management in India

This paper published by [3] Atul Auti and Martin Skit more in International Journal of
Construction Management used the methodology, a questionnaire Email requests for responses
were sent to a randomized group of 150 organizations as well as interested parties. Potential
respondents included diverse project supervisors, engineers, designers, investigators, and
advisers who are presently active in the field in India and who were deemed suitable for
delivering the requested comments. The conclusion of the authors was that efficient project
management application could assist in the achievement of new levels of fulfillment and greater
standards. The attributes of project management should alter the perception of the business
sector and be valued by all parties, including customers, stakeholders, and end uses.

2.2 Factors Influencing Water Treatment Management Performance

This study published by [1] Abdunnasir in annals of faculty engineering Hunedoara –


International Journal of Engineering used the methodology, the researcher had a session of
interview and received essential data regarding all facility processes. A technician described
each stage of water purification and each facility at the water treatment plant. Other information
was gathered through the World Wide Web, literature, as well as previous studies. The
conclusion drawn was that the disinfection facility accomplished its goal of providing
consumers with potable water service. They have effectively provided consumers with pure
water and are pleased alongside the efficacy of the facility processes. A number of elements'
results were addressed and they indicated that the water treatment performance is satisfied.

2.3 Project Management Practice and Its Effects on Project Success in Construction
Industry.

The paper published by[7] N A. Haron, P Devi, S Hassim, A H Alias M M Tahir, and A N
Harun in International Conference on Architecture and Civil Engineering used the method, A
questionnaire with 16 closed-ended questions and an equal number of multiple choice
questions and 5-point Likert scale options was developed. A pilot test was conducted with 30
of the intended respondents in order to guarantee that they would comprehend the
questionnaire's queries and identify any potential obstacles. Their decision was that a drastic
application of project administration could be eschewed in order not to cause a disruption in
the operation of the company. Education institutions should offer teaching or courses in project

Vol. 71 No. 4 (2022) 13096


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
administration in order to expand the competence of professionals. Construction industries
have greater impact on climate and environment which could be taken into consideration by
knowledge of project management.

2.4 Major Factors Influencing Productivity of Water and Wastewater Treatment Plant
Construction

This paper published by [9] S. Mojahed, F. Aghazadeh, in the International Academy of Project
Management, utilized the approach, and data was gathered from prior papers along with
research. A survey of WTP market providers with annual sales exceeding $100 million was
carried out. Several sewage and water treatment plant building sites were visited and analyzed
in order to obtain an improved comprehension of the influence of main productivity variables
and to recommend practices for enhancing output on construction locations. This paper
suggests that it is possible to increase productivity by modifying working practices in the
industry and focusing on accelerating the adoption of standard procedures on building
locations. Comparing the main efficiency factors of this study to those of a study conducted in
the United States thirty years ago as well as other international studies reveals that these
primary efficiency elements vary across initiatives, businesses, and regions of the world.

2.5 Quality Management Practices of Building Construction Firms.

This study published by [5] Osegbo C U, Okolie K C, Okeke A U, Ezeokoli F O, Akaogu A C,


in international journal of progressive research in science and engineering used the
methodology, this study was carried out by using survey method. A total of 180 questionnaires
a survey was distributed to various construction companies, and 120 responses have been
received for analysis, comprising 66.67 percent of the population. The development of
questionnaires to collect data from project supervisors, convey designers, contractors, standard
supervisors, and any other important people involved in assessing the quality management
plans of the various construction companies. The finding of the investigation was that
management makes determinations regarding quality. Consequently, the management of an
organization is liable for its quality practices. The investigation recommends that developers
and companies create and carry out a well-defined quality assurance strategy, build character
regulations, targets, and organizational direction, or teach workers on a regular basis to stay
current on market developments around the world.

2.6 Project Management for Construction Projects

The purpose of this study is to examine infrastructure project management. This study
illustrates various aspects of project management in terms of problems and issues and offers
solutions to promote and improve project management through this study. Most researchers
use qualitative methods and specific methods to complete their research projects. The
researchers met with several experts in the field and conducted 36 interviews with the project
manager. The analysis shows that the project management is faced with many problems and
problems, the most important problems are poor planning, poor project management, poor
communication between all parties and not reaching the best solution. It also demonstrates in
many ways that the management process is the key to the success of any engineering project.

Vol. 71 No. 4 (2022) 13097


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
In addition, researchers try to demonstrate the effectiveness of construction projects to achieve
good results for engineering firms and to meet the needs of social projects with efficient and
effective engineering projects.

2.7 Introduction to Water Treatment

Purpose of water purification - to provide safe drinking water without impurities, odors or
colors; Provides adequate water for domestic, commercial, industrial and fire protection needs.
Even if only about 1% of the water produced is used for drinking and cooking, all water
produced in public water systems must be of potable quality. This study covers the purpose of
water treatment plants and describes the water treatment process. In this study, the work and
the process are explained. The study was carried out through the observation of WWTP
workers who determined the treatment process and obtained operational results by describing
the water treatment need and the temporary process from raw water to treatment. After
distribution after purification, aeration, coagulation and flocculation, sediment filtration and
laboratory and safety disinfection.

2.8 Small Scale Wastewater Treatment Plant Project

The paper published by [8] Schozel & Bower (1999), The project's primary objective is to
discover current disposal and purification methods, ongoing cleaning programs and initiatives,
and potential pilot project locations. The objective of this study as stated by the author is
management and need of wastewater treatment plant by identifying the wastewater treatment
technologies and scope of the plant in villages on a small-scale basis. The study concluded by
explaining the various types of plants that can be opted for the small-scale projects of
wastewater treatment plants by analysing the cost efficiency, material management, quality
control and operation cost.

2.9 Quality Control Management in Building Construction

Construction projects are extremely complex undertakings that involve a vast array of factors.
Numerous factors, which include design, materials, apparatus, geographical features, geology,
hydrology, meteorology, building science, ways of operations, technical specifications, and
management systems, influence the quality of construction. To provide more high-quality, safe,
appropriate, and cost-effective composite products, building contractors have to stick to the
tenet of quality first and insist on high standards based on artificial control and protection. The
primary objective is to conduct a qualitative and quantitative evaluation of the grade of concrete
used in India's construction industry. After conducting statistical evaluation on example test
results gathered from building locations and verifying the conformance to these compression
strength test findings via Indian Standards, this methodology was used to evaluate the amount
of quality assurance being implemented. upon analyzing the obtained results, the study found
that a manual on the making of concrete must be put together and utilized as an outline on
construction areas, since concrete is a significant building material and a structural component.
During concrete production processes, a quality assurance strategy must be developed and
properly implemented, which identifies the essential tasks and aids in undertaking suitable

Vol. 71 No. 4 (2022) 13098


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
steps at any stage. Structured and nicely organized oversight by a nonprofit organization is
beneficial for enhancing the quality of concrete used in building initiatives.

3. METHODOLOGY

3.1 Flow Chart

1.Project Initiation

• Identify the need for a water treatment plant project and establish clear project objectives.
• Conduct a feasibility study to assess the technical, financial, and environmental viability
of the project.
• Define the project scope, stakeholders, and project team roles and responsibilities.

2. Project Planning

• Develop a comprehensive project plan that outlines the project's objectives, deliverables,
timeline, and budget.
• Identify and analyze potential risks and develop risk mitigation strategies.
• Determine the required resources, including personnel, equipment, and materials.
• Create a communication plan to ensure effective information flow among project
stakeholders.
• Establish performance metrics and milestones to track progress throughout the project
lifecycle.

3. Project Execution

• Procure necessary resources and equipment based on the project plan and specifications.
• Implement the construction and installation of water treatment plant components
according to engineering design.
• Regularly monitor and control project activities to ensure adherence to quality standards
and timeline.

Vol. 71 No. 4 (2022) 13099


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
• Conduct regular team meetings to address any issues, provide updates, and maintain
alignment with project objectives.
• Document all project activities, changes, and decisions for future reference and audit
purposes.

4. Project Monitoring and Control

• Continuously monitor project performance against predetermined metrics and milestones.


• Conduct regular inspections and quality assurance checks to ensure compliance with
design and regulatory requirements.
• Identify and resolve any deviations, risks, or issues that may arise during the project
implementation.
• Modify the project's outline as required, taking into account any unexpected occurrences
or changes to the project's demands
• Maintain effective communication channels with stakeholders to provide updates and
address any concerns.

5. Project Closure

• Complete all project deliverables and conduct final inspections to guarantee conformity
with specifications.
• Acquire the requisite licenses as well as certifications for the water treatment plant's
operation.
• Perform an exhaustive assessment of the endeavor to evaluate its efficacy and determine
learning learnt.
• Archive all Documentation of the endeavor, involving plans, states, and pertinent info for
use later on.
• Provide proper training and handover to the plant's operational staff.

4. RESULT DISCUSSION

4.1 Analysis of Data Collected

The collected from the questionnaire survey of experienced professionals was analyzed by
using MS Excel software by cross tabulating analysis method. Cross tabulation analysis carries
out the relationship between the two, three or multiple parameters of the data collected the data
was analyzed with reference to the designation and experience of the respondents. Therefore,
the results obtained by this method was reliable as the priority was given to the experienced
one with having a better designation in the industry.

The data gathered from the telephone conversation was processed using the technique of
thematic examination for the qualitative part of this research, as theme evaluation combines
(often very large) data sets corresponding to their similarities. The questionnaire asked to
individuals were categorized and similar interests was analysed regarding. Qualitative analysis
was done to combine the data collected and was represented to meet the objective of this study.

Vol. 71 No. 4 (2022) 13100


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Fig. 4.1 Wor Experience

• As, shown in the above fig.4.1 it is clear that the respondents were professional and having
a good experience in the field of civil engineering. Mostly 47.6% of personnel were having
experience of less than 3 years while there were quite experienced personals having
experience up to 10 years. So, it can be stated as the results obtained were reliable. The
respondents were quite qualified for this study as 52.38 % were graduated and 33.33 %
were the post graduates having a good experience in the industry. As well-educated
responses make the study reliable and trustworthy due to good technical knowledge.
• 88.37% of respondents were aware of the concept of construction management resulting
that there is quite a good understanding of the construction management and need of
construction management can be established by using the results.

Fig. 4.2 Rating as Manager on a Construction Site

As the study is purely based on the construction management, so the respondents were asked
that, “How would you rate yourself as a manager on a construction site?”. The obtained
responses were analysed on the designation basis of the respondents in which it is found that
the Construction Manager, Architect, Supervisor, Team Leader, Executive Engineer, Labour
Contractor, Project Manager and Site Engineer rated themselves as best manager as shown in
the fig.4.2 above. So, it can state as there are quite good manager in the industry who build up
the construction industry.

Vol. 71 No. 4 (2022) 13101


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Fig. 4.3 Necessity of Management

Since the respondents are the best manager in this study, but they also responded in majority
of 97.67% as there is need of construction management for the public projects like Water
treatment plant. Construction management is much needed concept for the future of industry.
The result analysed can be clearly seen in the fig. 4.3.

Fig 4.4. Lack of Ideal Workflow in Public Project

Since the majority of people i.e., almost 98% of people thinks that there is a serious need for
the proper management in the construction of the government projects since they lack in the
management skills which leads to various problems which were further asked, that 72% of
people thinks that these kind of projects like water treatment plant and various other public
projects lacks the ideal flow of the work which is very necessary for the management point of
view.

Fig. 4.5 Missing Deadline

Vol. 71 No. 4 (2022) 13102


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
As there is a need of management for the projects which are not meet resulting in missing the
deadline of the complicated projects like water treatment plant. 46.5 % of responses clearly
shows in the fig.5.5 above that deadline of activity are very often missed resulting in the delay.
In India, the construction industry is much more dependent on labours and there is very less
knowledge and management skills for using the advanced technologies and various
machineries which can not only save the time but also make the work for labours far easier.

Fig 4.6 Do WTP Project Fail

The result in the fig.4.6 clearly shows that there is very slight chance of failing of WTP projects.
62.79% of respondents stated that there is no chance of failure of this project which is a good
result for management point of view.

Fig. 4.7 Availability of Skilled Labour on Construction Site

The availability of skilled labour is quite good according to the responses most of the
respondents Architects, Contractor, Labour contractor, Site Engineer, Project Manager,
Supervisor and Project Engineer can make the availability of skilled labour easily but they
commented there opinion as it requires more cost for immediate need or the labour needs a
steady work flow since they are on the daily wages.

Vol. 71 No. 4 (2022) 13103


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Fig. 4.8 Language Barrier in Communication

Communication problem arises during the construction project and especially in the complex
structure like water treatment plants, and one of the main reasons is the language barrier since
there are various local languages spoken among the sub-contractor, labours, supervisors and
engineers it gets hard to understand even the simple activities. The response also shows the
same result in the fig. that 40.48% of the personnel find the problem in the communication due
to language while 59.52 % have no problem regarding.

Fig. 4.9 Labour Intensive Culture

The fig.5.9 clear state one of the main reasons for the need of construction management in the
public projects due to labour intensive culture. As shown in the fig. 86 % of the experienced
respondents states that construction industry in India is quite labour intensive.

Fig. 4.10 Effect of Delay due to Temperature

There is also another reason in India that there is quite high temperature weather all over which
also makes the labour dependent work tasks getting delayed on daily basis. Climate play’s vital

Vol. 71 No. 4 (2022) 13104


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
role for any construction project which is believed by 81.4% of the respondents according to
survey and it gets tough due to higher temperature.

4.11. Modern Machinery Boosts Speed

As the work gets easy workflow gets ideal and speed of the construction activities improves.
This can be achieved by minimizing the manual labour work by replacing by modern tools,
equipment and machineries which not only saves the time but also improves the quality of work
and provides better results. This can be justified in the fig.4.11 analysis of the respondents of
which 81.4 % believe in.

Fig. 4.12 Complex Design of WTP

As shown in the fig.4.12, 62.79 % of responses clearly states that the water treatment plants
have complicated design. There are various factors to be considered while doing any activity
for the future coming activity as the structure is completely water based so flow, level, jumps,
collection, etc. are needed to be considered. Therefore, during the construction an experience
personal is needed who can also manage the project.

Vol. 71 No. 4 (2022) 13105


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

.4.13 Reasons for Poor Quality

Quality is the most important factor that guarantees the project life and its success. The various
factors that affect the quality of the construction activity is well showed in the fig.

4.13 above. The main reasons for poor quality can be stated as poor project management,
complex designs, communication gap, lack of supervision and poor workmanship. These
factors can be managed and eliminated by good planning and management skills during the
construction activities.

Fig. 4.14 Reasons for Over Budget

(Note: LPU-Lack of project understanding, MTOT-Multiple teams instead of one team,


IAPSR-Incorrectly assessing project scheduling of rates, PP- Poor Planning, LoC-Lack of
Coordination, LBP-Lack of Backup Plan, UPC-Underestimating Project Complexity and All-
All the above reasons).

Over budget is one of the reasons that leads a delay or complete stoppage to any activity of
project or an entire project. Budget planning is the most important for any construction activity,
after all money is the only factor for which all the parties are working. It can be clearly seen in
the fig.5.15 that the main reasons for overbudgeting are incorrect assessing project schedule
rates, Poor Planning and lack of project understanding with lack of coordination. The reasons
can be eliminated by better project management resulting in the budget friendly project.

Vol. 71 No. 4 (2022) 13106


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Fig. 4.15 Safety Factors for Construction Activities

(Note: PPE-Personal Protective Equipment, LS-Ladder Safety, WAC-Keep the Work Area
Clean, PST-Proper Site Training, RCD-Reporting and clearing defects, IDA-If in doubt, ask,
PEC-Precautions for environmental changes, All-All the above).

At every construction project safety is must. Safe practices for any construction activities
should be encouraged like providing the proper site training, PPE should be provided to the
personnel working on site and visitors too. Keeping the work area clean is a good practice while
if there are any defects that should be reported to the supervisor or in charge. All of the factors
are necessary for safety as seen in the fig.5.16 as any accidents or damages not only results in
delays in construction activities but also affects the health of the personnel involved.

Fig. 4.16 Need of Planning and Management

1. Conclusion for Need of Management

The data collected was cross referenced to the percentage of respondents’ states that they agree
to the reasons for need of planning and management for a complex project of water treatment
plant. The data was summarized in order to understand the necessity of construction
management due to the reasons showed in fig. 5.17. The respondents who strongly agree for
the reasons behind need of planning and management were taken into consideration for the
result of the study. The data was further analysed in terms of the percentage and the reasons
were ranked accordingly that causes the need of construction management of water treatment
plant. The labour-intensive culture was ranked first as main reason for the need of planning
and management for construction projects while language barrier for communication was
ranked at the bottom summarizing the reasons for planning and management.

Vol. 71 No. 4 (2022) 13107


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Fig. 4.17 Opinion

The data that was collected and analysed on MS Excel software was further concluded that

95.45 % of the respondent strongly believes that there is necessity of construction management
for water treatment plant out of which 86.36 % were aware about the concept and benefits of
construction management who strongly believes that utilization of modern technologies, tools
and equipment can improves the construction activities resulting in better outputs. The
construction management can be done by a construction manager who is capable of
overcoming the reasons and solving the problems in construction activities of water treatment
plant to which 84.09 % of the professionals strongly agree.

Fig. 4.18 Effect of Difficulties on Project

• For working on a schedule there are various factors to be taken into considerations like
adaption of modern technologies and equipment. The skilled labors play a vital role in
construction of especially WTP as there are various complications in the design the structure
basically works on the elevation from the other structure as it is water based and plays a vital
role for the smooth flow of water. The blame game should be eliminated by appointing a neutral
party which can also be helpful for solving the communication problems which can be one by
hiring the construction or project manager. The manager not only helps in those difficulties but
also helps in the construction flow on schedule and can also be helpful for the fund management
of the project. The problems of theft and vandalism can be overcome by hiring a watchman
and an overnight supervisor which could be helpful for saving the materials and equipment
from the site.

Vol. 71 No. 4 (2022) 13108


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
• This question was well answered by the parties that the planning is always done before
beginning any activity and the duration to be considered during this activity is also been set
and the material management is to be taken into consideration accordingly the current market
rates. The client plans the activities according to the time duration and the climatic conditions
while the contractor plans according to availability of labors, equipment, funds, current market
values and many other factors.

Completing the activity in a given time is one of the hardest tasks in eyes of every party in the
WTP. As climate plays a vital role for meeting the deadline like in the summer season the
deadline is often meet but as soon as the monsoon begins there occurs the delay in activities
and deadline is mostly meet. Funds is an important factor for meeting project on time as the
cash flows smoothly the construction works smoothly and every party is happy.

Fig. 4.19 Meeting the Deadline

Various parties have various roles in crisis, like if the theft happens the problem should be
solved by the site in charge and watchman itself. If there are any problems related to the
drawing or design the problem should be solved by site engineer, the designer and the clients’
representatives. Like if there are certain issues with fund, higher authorities like contractor and
client will have to solve the problem. But every one of the parties stated that these issues could
be resolved if there is a construction project manager who himself can handle all these issues.

Yes, for sure if there is a perfect planning and the problems which may arise are taken into
consideration then the activity surely successfully completed in the given time with the quality
work.

Fig. 4.20 Completing activity with full proof planning

Vol. 71 No. 4 (2022) 13109


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
• Multiple answers were recorded for this particular question, the labor contractor needs
guidance on daily basis while the site engineer states that it can be done without any help
from outside that he himself is capable. The clients’ states that guiding on daily basis and
managing day to day activity can give a quality of work within the time to which the
general contractor agrees as the work load of contractor is educed and don’t have to look
into every problem.
• The Management of this particular plant is quite impressive as there are various parties
involve to solve the crisis on their authorities’ level which is a must need, meanwhile this
site also has a project head who acts just quite similar to the construction manager. Which
gives the answer to this whole study of management of public projects. As the project id
to be completed within one and half year and the quality of work is maintained thoroughly.
As there is already a manager and he looks into all problems and activities so the project
is already is delivering on time and is there is no doubt in delay of the WTP testing. As in
various kind of way the cost of running is saved the material is properly managed there is
quality of work and every party is quite impressed so there is a plus point and a big
advantage that the manager is there to save a day, which gives answers to next three
questions in the line.
• Construction project management in India is very poor. Government allocates more money
to mega cities and urban population which leads to neglecting the rural population of India
which contributes majority of population of India. While there is poor execution which
takes more time and effort and the parties are not impressed and leads to the failure of
project. Work with the client, the the designer, vendors, and sellers to come up with
schedules for building and completion dates constitutes good planning. Planning
encompasses more than simply creating the building schedule. In addition, there is lack of
modern technologies and equipment with lack of skilled labours. Planning and building
rules and regulations leads to issues plus there is politics involve in the small projects in
small cities which leads to failure of project or mass destruction.

5.CONCLUSION

Effective project management plays a pivotal role in ensuring the successful implementation
and operation of a water treatment plant. By employing sound project management principles,
such as comprehensive planning, diligent execution, and proactive risk management, project
managers can navigate the complex challenges associated with water treatment projects.

The key takeaway is that project management provides a structured approach to coordinate and
integrate various aspects of the project, including engineering design, procurement,
construction, and commissioning. It enables teams to adhere to schedules, allocate resources
efficiently, and monitor progress closely, ultimately resulting in the timely completion of the
water treatment plant.

Moreover, effective communication and collaboration among stakeholders, including


engineers, contractors, regulatory authorities, and community representatives, are critical
throughout the project lifecycle. By fostering open lines of communication and encouraging

Vol. 71 No. 4 (2022) 13110


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
collaboration, project managers can ensure that all parties remain aligned with project
objectives and swiftly address any emerging issues.

Additionally, the incorporation of sustainable practices in project management can lead to long-
term benefits for the water treatment plant and its surrounding environment. Emphasizing the
use of eco-friendly technologies, optimizing energy consumption, and implementing robust
maintenance strategies can contribute to the plant's efficiency, reliability, and overall
environmental sustainability.

In summary, successful project management of water treatment plants hinges on meticulous


planning, effective execution, continuous monitoring, and collaboration among stakeholders.
By embracing these principles, project managers can drive the implementation of high-quality,
sustainable water treatment infrastructure that meets the needs of communities and safeguards
precious water resources for future generations.

6. REFERENCES

1. Abdelnaser, omran factors influencing water treatment management performance in


malaysia: a case study in pulau pinang 1. school of housing, building and planning,
universiti sains malaysia, 11800, minden, pulau pinang, malaysia - annals of faculty
engineering hunedoara, international journal of engineering.
2. Book on Construction Project Management by Kumar Neeraj Jha, Pearson.
3. Construction Project Management in India - Article in International Journal of
Construction Management · January 2008 by Atul Auti and Martin Skitmore School of
Urban Development Queensland University of Technology Gardens Point Brisbane
Q4001 Australia.
4. Detail project report for planning, designing, erection & commissioning of 75mld wtp-
Jawaharlal Nehru national urban renewal mission. nagpur municipal corporation
5. International journal of progressive research in science and engineering, vol.2, no.10,
october 2021. osegbo c u., et.al: quality management practices of building construction
6. firms in project delivery in anambra state, nigeria 113 quality management practices of
building construction firms in project delivery in anambra state, Nigeria osegbo c u, okolie
k c, okeke a u, ezeokoli f o, akaogu a c
7. alukdar, V., Dhabliya, D., Kumar, B., Talukdar, S. B., Ahamad, S., & Gupta, A. (2022).
Suspicious Activity Detection and Classification in IoT Environment Using Machine
Learning Approach. 2022 Seventh International Conference on Parallel, Distributed and
Grid Computing (PDGC), 531–535. IEEE.
8. Pandey, J. K., Ahamad, S., Veeraiah, V., Adil, N., Dhabliya, D., Koujalagi, A., & Gupta,
A. (2023). Impact of Call Drop Ratio Over 5G Network. In Innovative Smart Materials
Used in Wireless Communication Technology (pp. 201–224). IGI Global.
9. Anand, R., Ahamad, S., Veeraiah, V., Janardan, S. K., Dhabliya, D., Sindhwani, N., &
Gupta, A. (2023). Optimizing 6G Wireless Network Security for Effective
Communication. In Innovative Smart Materials Used in Wireless Communication
Technology (pp. 1–20). IGI Global.

Vol. 71 No. 4 (2022) 13111


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865
10. Kumar, A., Dhabliya, D., Agarwal, P., Aneja, N., Dadheech, P., Jamal, S. S., & Antwi, O.
A. (2022). Research Article Cyber-Internet Security Framework to Conquer Energy-
Related Attacks on the Internet of Things with Machine Learning Techniques.
11. Maria Kozlovskaa , Daniela Mackovab,*, Marcela Spisakovac - Survey of Construction
Management Documentation Usage in Planning and Construction of Building Project.
World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium
2016, WMCAUS 2016
12. Project management practice and its effects on project success in Malaysian construction
industry N A. Haron, P Devi, S Hassim, A H Alias, M M Tahir, and A N Harun. -
International Conference on Architecture and Civil Engineering (ICACE 2017).
13. Scholzel & Bower- Small Scale Wastewater Treatment Plant Project, report on project
criteria, guidelines and technologies. sopac Technical Report 288, July 1999.
14. S. Mojahed, F. Aghazadeh / International Journal of Project Management 26 (2008) 195–
15. 202. Major factors influencing productivity of water and wastewater treatment plant
construction: Evidence from the deep south USA.
16. Status of water treatment plants in india. central pollution control board (ministry of
environment and forests).
17. IS 12183: 1987 - Code of practice for water supply and drainage high altitudes and / or
sub- zero temperate regions (first revision).
18. HSN Code 8421 - Code of practice for Machinery and apparatus for filtering or purifying
water, Products include: Effluent Treatment Plant.
19. IS2065:1983- Code of Practice for Water Supply in Buildings.
20. Wikipedia.

Vol. 71 No. 4 (2022) 13112


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Project Management of Water Treatment Plant

Abhishek Shirle*1, Dr. Satish S. Deshmukh*2, Pravin Manatkar*3 , Dr. Sunil Thakare*4

*1 Assistant Professor, Civil Engineering Department, KJ’s Educational Institute Trinity


Academy of Engineering, affiliated to Savitribai Phule University Pune, Maharashtra
India.

*2 Professor, Civil Engineering Department, KJ’s Educational Institute Trinity Academy


of Engineering, affiliated to Savitribai Phule University Pune, Maharashtra India.

*3 Assistant Professor, Civil Engineering Department, KJ’s Educational Institute


Trinity Academy of Engineering, affiliated to Savitribai Phule University Pune,
Maharashtra India.

*4 Professor, Civil Engineering Department, Anantrao Pawar College of Engineering


Pune, Maharashtra India.

Mail Id- 1. [email protected] 2. [email protected] 3.


[email protected] 4. [email protected]

Vol. 71 No. 4 (2022) 13113


http://philstat.org.ph
Mathematical Statistician and Engineering Applications
ISSN: 2094-0343
2326-9865

Vol. 71 No. 4 (2022) 13114


http://philstat.org.ph