New Building Handover Report
New Building Handover Report
Contents
Inspection details 3
Accessibility 6
Summary 7
Significant items 8
Additional comments 29
Conclusion 32
If you have any queries with this report or require further information, please do not hesitate to contact
the person who carried out the inspection.
Inspection details Page 3
Inspection details
Property Address: Footscray Area
Client
Name: Private
Consultant
Main building – wall construction: Concrete Panels, External light weight walling system, External
cladding, Metal Sheeting
PAINT IN PARTICULAR WILL REQUIRE CAREFUL & DETAILED CHECKING & REPAIRS, FROM THE WALLS,
TIMBER WINDOW TRIMS, SKIRTINGS, CEILINGS, ETC.
Accessibility Page 6
Accessibility
Areas Inspected
The inspection covered the Readily Accessible Areas of the property. Please note obstructions and limitations to
accessible areas for inspection are to be expected in any inspection.
- Building interior
- Part exterior and balcony area
The inspection does not include areas which are inaccessible due to obstructions, or where access cannot be
gained due to unsafe conditions.
- Flooring
- Plaster Installation is a HIGH obstruction in this particular property.
Obstructions increase the risk of undetected defects, please see the overall risk rating for undetected defects.
Inaccessible Areas
The following areas were inaccessible:
- Not Applicable
Any areas which are inaccessible at the time of inspection present a high risk for undetected building defects. The
client is strongly advised to make arrangements to access inaccessible areas urgently.
Summary Page 7
Summary
SUMMARY INFORMATION: The summary below is used to give a brief overview of observations made in each
inspection area. The items listed in the summary are noted in detail under the applicable sub headings within the
body of the report. The summary is NEVER to be relied upon as a comprehensive report and the client MUST read
the entire report and not rely solely on this summary. If there is a discrepancy between the information provided in
this summary and that contained within the body of the Report, the information in the body of the Report shall
override this summary. (See definitions & information below the summary to help understand the report)
Significant items
Safety Hazard
Non Compliant
Significant items Page 9
It was noted on inspection that sealant is missing, inadequate and/or not completed to a
tradesmens like finish.
This may include floor edges, kitchen benches/splashbacks, vanities, cabinetry/plaster
junctions, bath edges and shower floor/wall corners, etc.
Particular care should be considered to all wet area adjoining surface joints & junctions
Ensuite
Significant items Page 11
Significant items Page 12
All AREAS to the entire property should be checked CAREFULLY to identify any further paint
and plaster defects to the entire property, as these defects are in other areas of the property.
I HIGHLY RECOMMEND that the painter inspects ALL rooms and ALL areas of the building
carefully to all the timber work including the skirting, architraves and doors.
I HIGHLY RECOMMEND that the painter inspects ALL rooms and ALL areas of the building
carefully to all the walls and ceilings as the paint does not meet the Australian Standards and
Standards and Tolerances.
All plaster work and plaster patching along with all the sanding and preparation to all the
areas for repair to the plaster and timber work will require to be completed first and then the
paint work.
The paint work is inconsistent with orange peal in some areas and smooth in others or chips,
scratches, runs and or imperfections.
With out treating this home with a detailed overall inspection by the painter to the sanding,
patching to the timber work and plaster work to the walls and ceilings in areas required to
building , the paint job will not be a level 4 finish.
Areas were identified where the surface finish of the painting was found to be defective. This
includes areas of minor blemishes, missing painting, over-painting, paint runs, sags , lack of
paint and/or wrinkling of paint finish.
Paint irregularities will be apparent in different light conditions and are often hidden from view
in low light conditions.
During New Construction Inspections, any irregularity in the paint finish surface is considered
a detraction from the area`s overall appearance, and is therefore considered to be a minor
defect.
An allowance is made for critical light conditions for a Level 4 finish, which is the default level
for plaster surfaces. Additional painting requirements have been marked up in ONLY some
areas as a guide.
Significant items Page 13
These finishes should be sanded back, filled, levelled and painted as applicable. The painting
contractor should be appointed to perform the necessary works prior to final handover.
-----------------------------------------
Guide To Standards and Tolerances 2015.
---------------------------------------------------------
13 VBA | GUIDE TO STANDARDS AND TOLERANCES 2015
Generally, variations in the surface colour, texture and finish of walls, ceilings, floors and
roofs, and variations in glass and similar transparent materials are to be viewed where
possible from a normal viewing position. A normal viewing position is looking at a distance of
1.5 m or greater (600 mm for appliances and fixtures) with the surface or material being
illuminated by ‘non-critical light’1 .Non-critical light means the light that strikes the surface is
diffused and is not glancing or parallel to that surface.
It was identified that the cleanliness and degree of finish for fixtures and fittings is
substandard. Fittings and fixtures including sinks and bathtubs are required to be as new
prior to handover. Evidence of damage marks scuffs and dirt need to be removed where
present.
The Building Commission’s, Guide to Standards and Tolerances clause 18.09 Cleaning,
states- ‘Owners are entitled to expect that the building site and works are clean and tidy on
completion. Building works are defective where windows are not clean, floors are not swept,
mopped or vacuumed as appropriate, tiles, sinks, basins, troughs, baths, etc. are not
cleaned and shelving, drawers and cupboards ready for use.’
Once the cleaners have properly completed all of this work, all of the glazing, mirrors,
cupboards, baths, shower bases, shower screens, floor coverings, walls, stairs, garage floor,
fixtures and fitting etc, should all be thoroughly checked again for any scratches and damage
which may have occurred, prior to handover proceeding.
Significant items Page 17
Significant items Page 18
It is observed that some of the cabinet doors are not aligned and / or have inconsistent gaps
between the doors.
The Building Commissions, Guide to Standards and Tolerances clause 8.04 Internal Door
Clearances, states- ‘The installation of doors is defective if within three months of
completion, clearances between door leaves and frames and between adjacent door leaves
are not uniform and within 1mm. A clearance between door leaves or between a door leaf
and the frame is defective if it is less than 2mm or greater than 5mm in width’
The gaps around these doors must be adjusted to comply with this tolerance.
Ensuite
Bathroom
Significant items Page 20
BlueScope Steel, the manufacturer of colorbond steel state on their web site that
–‘BlueScope steel does not recommend the use of touch up paints on Colorbond steel’ and
that ‘Our recommendation is not to touch up. Minor scratching will not affect the life of the
sheet and is rarely obvious to a casual observer. Should damage be substantial, replace the
sheet.
We particularly recommend against the use of spray cans, as these can result in
overspraying of surrounding areas. The problem might not be immediately obvious, but since
overspray paint weathers at a different rate to the oven dried paint on Colorbond steel you’ll
eventually be left with an unsightly blemish on the sheet’.
All finished surfaces must be clean and free of defects at hand over to comply with the
Standards and Tolerances guide.
The photos attached are just a guide to the type of repairs required and are NOT all the
defects related to this topic on the property.
All areas to the entire property should be checked carefully to identify any further defects of
the same type.
It is identified that damage or faults affecting tiles, appliances and / or fittings supplied as part
of the building contract have occurred. Where this is due to the builder`s workmanship or
damage occurring during construction it is considered a defect with respect to Standards
and Tolerances - 18.02.
Where grouting is missing or incomplete, the area is not sealed against water penetration,
increasing the likelihood of water damage to flooring and other associated building elements.
Also
Areas where the tile grout does not finish to the cushion on cushion edge tiles and / or flush
with square edge tiles (except for tooling) is considered a defect with reference to AS3958.1.
Adequate repair to grouting for all the above defects and must be applied to the affected
area prior to final handover.
Grouting is defective if it is not carried out in accordance with the requirements of Clause
5.7 of AS 3958.1.
Joints are defective if they are not, as far as is practicable, of consistent width and can be
seen from a normal viewing position.
Finished grout is defective if it is not uniform in colour, smooth, without voids, pinholes or low
spots.
a) The top surface of the grout may be tooled to provide a contoured depression
of no deeper than 1 mm for up to 6 mm wide joint and up to 2 mm for a 6-10 mm wide joint
(clause 5.7(e) of AS 3958.1).
b) Joint widths for floor tiles should not exceed 3 mm for pressed tiles and 6 mm for
extruded tiles (clause 4.6(c)(i) of AS 3958.1).
c) Joint widths for wall tiles should not exceed 1.5 mm for pressed tiles and 6 mm for
extruded tiles (clause 5.4.6(c)(ii) of AS 3958.1).
d) Joint alignment should be consistent throughout the installation within a tolerance of 4 mm
in 2 m8 (clause 5.4.6(d) of AS 3958.1).
Grout is defective if it becomes loose within 24 months of handover.
DOMESTIC BUILDING CONTRACTS ACT 1995, Act No. 91/1995, Part 2 - Provisions that
apply to all Domestic Building Contracts.
The following warranties about the work to be carried out under a domestic building contract
are part of every domestic building contract -
(A) the builder warrants that the work will be carried out in a proper and workman like manner
and in accordance with the plans and specifications set out in the contract.
(D) the builder warrants that the work will be carried out with reasonable care and skill and
will be completed by the date (or within the period) specified by the contract.
ALSO
All these photos are added in to demonstrate DEFECTIVE / SUB STANDARD and/or
INCOMPLETE WORKS and they are all required to be rectified as they are ALL not
satisfactory for Handover as per the DOMESTIC BUILDING CONTRACT ACT 1995 as stated
above.
Significant items Page 26
Substandard Workmanship
Incomplete
Incomplete 4.10
In Addition :
The main bedroom has a step in the wall, which has made the bedroom wall very
unappealing, particularly once the bed goes into location as the step is located in the middle
of the room where the bed will sit.
The plans DO NOT have this step in the wall and my client has made it clear that this is not
acceptable and insists on the wall to be flat and consistent.
Significant items Page 28
Incomplete 4.11
Additional comments
There are no additional comments
This report contains a list of a number of defects that in our judgement require rectification.
Observations Page 32
1. Purpose
The purpose of our inspection is to identify any defects in the finishes and the quality of those
finishes presented by the builder at the stage of works nominated on the front of this report.
This report contains a schedule of building defects that in the writer’s judgement do not
reach an acceptable standard of quality, level of building practice, or have not been built in a
proper workmanlike manner relative to the Building Code of Australia, the relevant Australian
Standards or the acceptable standards and tolerances as set down by the Building Control
Commission.
2. Scope
Our engagement is confined to that of a Building Consultant and not that of a Building
Surveyor as defined in the Building Act, of 1993. We therefore have not checked and make
no comment on the structural integrity of the building, nor have we checked the title
boundaries, location of any easements, boundary setbacks, room dimensions, height
limitations and or datum’s, glazing, alpine and bush-fire code compliance, or any other
requirements that is the responsibility of the Relevant Building Surveyor, unless otherwise
specifically noted within this report.
Special Notes.
Conclusion
Building consultant's summary
There are a number of defects listed in this report which will require attention to rectify and comply with
Australian Standards.
The quality of the finishes to the new apartment appear to be in good quality and finishes, with repairs in
order to get the home to the finishes that meet the Australian Standards as detailed in this report.
Definitions Page 33
SERVICE As requested by the Client, the inspection carried out by the Building Consultant (“the Consultant”) was a
‘Standard Property Report’.
PURPOSE OF INSPECTION The purpose of this inspection is to provide advice to the Client regarding the
condition of the Building and Site at the time of inspection.
SCOPE OF INSPECTION This Report only covers and deals with any evidence of: Major Defects in the condition of
Primary Elements including Structural Damage and Conditions Conducive to Structural Damage; any Major Defect in
the condition of Secondary Elements and Finishing Elements; collective (but not individual) Minor Defects; and any
Serious Safety Hazard discernible at the time of inspection. The inspection is limited to the Readily Accessible Areas
of the Building and Site (see Note below) and is based on a visual examination of surface work (excluding furniture
and stored items), and the carrying out of Tests.
Note. With strata and company title properties, the inspection was limited to the interior and the immediate exterior
of the particular residence inspected. Common property was not inspected.
ACCEPTANCE CRITERIA The building was compared with a building that was constructed in accordance with the
generally accepted practice at the time of construction and which has been maintained such that there has been no
significant loss of strength and serviceability.
Unless noted in “Special Conditions or Instructions”, the Report assumes that the existing use of the building will
continue.
This Report only records the observations and conclusions of the Consultant about the readily observable state of
the property at the time of inspection. The Report therefore cannot deal with:
(a) possible concealment of defects, including but not limited to, defects concealed by lack of accessibility,
obstructions such as furniture, wall linings and floor coverings, or by applied finishes such as render and paint; and
(b) undetectable or latent defects, including but not limited to, defects that may not be apparent at the time of
inspection due to seasonal changes, recent or prevailing weather conditions, and whether or not services have been
used some time prior to the inspection being carried out.
These matters outlined above in (a) & (b) are excluded from consideration in this Report.
If the Client has any doubt about the purpose, scope and acceptance criteria on which the Report was based
please discuss your concerns with the Consultant on receipt of the Report.
The Client acknowledges that, unless stated otherwise, the Client as a matter of urgency should implement any
recommendation or advice given in this Report.
LIMITATIONS
The Client acknowledges:
1. ‘Visual only’ inspections are not recommended. A visual only inspection may be of limited use to the Client. In
addition to a visual inspection, to thoroughly inspect the Readily Accessible Areas of the property requires the
Consultant to carry out when ever necessary appropriate Tests.
2. This Report does not include the inspection and assessment of items or matters outside the scope of the
requested inspection and report. Other items or matters may be the subject of a Special-Purpose Inspection Report,
which is adequately specified (see Exclusions below).
Terms and conditions Page 34
3. This Report does not include the inspection and assessment of items or matters that do not fall within the
Consultant’s direct expertise.
4. The inspection only covered the Readily Accessible Areas of the property. The inspection did not include areas,
which were inaccessible, not readily accessible or obstructed at the time of inspection. Obstructions are defined as
any condition or physical limitation which inhibits or prevents inspection and may include – but are not limited to –
roofing, fixed ceilings, wall linings, floor coverings, fixtures, fittings, furniture, clothes, stored articles/materials,
thermal insulation, sarking, pipe/duct work, builder’s debris, vegetation, pavements or earth.
5. Australian Standard AS4349.0-2007 Inspection of Buildings, Part 0: General Requirements recognises that a
property report is not a warranty or an insurance policy against problems developing with the building in the future.
6. This Report was produced for the use of the Client. The Consultant is not liable for any reliance placed on this
report by any third party.
EXCLUSIONS
The Client acknowledges that this Report does not cover or deal with:
Any of the above matters may be the subject of a special-purpose inspection report, which is adequately specified
and undertaken by an appropriately qualified inspector.