Bar Bending Schedule Kerala Overseer PSC
Bar Bending Schedule Kerala Overseer PSC
COSTING
BAR BENDING SCHEDULE
Unit weight of bar Genral formula
weight/m of bar =d²/162
Density of reinforcement=7850kg/m³
5 Bent up 2*9d
(45⁰ both 2(0.42D) L+18d+0.84D
side)
6 24d 2*(L₁-(2*clear
cover))+2*(L₂-
stirrup (2*clear
cover))+24d
Number of stirrup= (span/spacing)+1
For 1 bag of cement quantity of water required = 22..5L
1 Bag of cement = 50 kg=34.5 L=0.035m³
1m³ cement=30 bag=1440 kg
GRADE OF CONCRETE QUANTITY OF WATER REQUIRED PER
BAG OF CEMENT
M5 60L
M7.5 45L
M10 34L
M15 32L
M20 30L
QUANTITY CALCULATION
PCC(PLAIN CEMENT CONCTERE 40mm aggregate)
M₅=1:5:10
M₇.₅=1:4:8
M₁₀=1:3:6
M₁₅=1:2:4
M₂ₒ=1:1.5:3
M₂₅=1:1:2
=205.2/50
=4.1 bag
Q)For preparing 10 m ³ of 1:4:8 cement concrete, the required sand would be?
1:4
1:5 0.15 m ³ sand for 10 m²
1:6