Delhi Mumbai Award Status Mar 23

The document provides a status update as of March 31st, 2023 for the Delhi-Mumbai Expressway project. It summarizes that the Delhi to Vadodara section is under construction, with 90km completed in Haryana and the rest in various stages of completion in Rajasthan. The Vadodara to Mumbai section is also currently under construction in various packages. The spur to JNPT port has been awarded but work has yet to commence.

Uploaded by

Manoj Doshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
655 views11 pages

Delhi Mumbai Award Status Mar 23

The document provides a status update as of March 31st, 2023 for the Delhi-Mumbai Expressway project. It summarizes that the Delhi to Vadodara section is under construction, with 90km completed in Haryana and the rest in various stages of completion in Rajasthan. The Vadodara to Mumbai section is also currently under construction in various packages. The spur to JNPT port has been awarded but work has yet to commence.

Uploaded by

Manoj Doshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Delhi – Mumbai Expressway – Monthly Progress Report

Status as of March 31st, 2023


(Length in km)
Key Plan (Status as of March 31st, 2023)

Delhi - Vadodara Section (Including Delhi-Faridabad-Sohna)

Vadodara – Mumbai (Virar) Section

Spur to JNPT
Delhi – Mumbai Expressway Package Level Status (as of March 31st, 2023)

Chainage Date of Target Physical


Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Dineshchandra R.
1 Haryana Pkg 1 0.000 9.000 9 Under Construction 31-Jul-20 11-Jan-22 12-Jan-24 Agrawal Infracon Pvt. 48%
Ltd.
M/s Dineshchandra R.
2 Haryana Pkg 2 9.000 33.000 25 Under Construction 30-Jul-20 10-Aug-21 11-Aug-23 Agrawal Infracon Pvt. 59%
Ltd.
M/s Dineshchandra R.
3 Haryana Pkg 3 33.000 59.063 26 Under Construction 07-Aug-20 14-May-21 15-May-23 Agrawal Infracon Pvt. 99%
Ltd.
Jewar Awarded - Work to M/s APCO Infratech Pvt.
s4 Uttar Pradesh 0 30 31 01-Aug-22 - - -
Connectivity Commence Ltd.

Delhi – Faridabad - Sohna Total 90


M/s APCO Infratech Pvt.
1 Haryana Pkg 1 0.000 18.460 18 Completed 05-Mar-19 13-Sep-19 Completed 100%
Ltd.
M/s APCO Infratech Pvt.
2 Haryana Pkg 2 18.460 46.960 29 Completed 05-Mar-19 13-Sep-19 Completed 100%
Ltd.
M/s Centrodorstroy India
3 Haryana Pkg 3 46.960 78.760 32 Completed 28-May-19 05-Sep-19 Completed 100%
Pvt. Ltd
M/s H.G. Infra
4 Rajasthan Pkg 4 78.760 115.660 37 Completed 09-Mar-19 10-Dec-19 Completed 100%
Engineering Limited
M/s KCC Buildcon Pvt.
5 Rajasthan Pkg 5 115.660 151.800 36 Completed 09-Mar-19 10-Dec-19 Completed 100%
Ltd.
M/s KCC Buildcon Pvt.
6 Rajasthan Pkg 6 151.800 182.960 31 Completed 09-Mar-19 20-Nov-19 Completed 100%
Ltd.
M/s Gawar Constructions
7 Rajasthan Pkg 7 182.960 214.220 31 Completed 28-May-19 07-Feb-20 Completed 100%
Ltd.
M/s H.G. Infra
8 Rajasthan Pkg 8 214.220 247.270 33 Completed 11-Feb-20 07-Nov-20 Completed 100%
Engineering Limited
M/s H.G. Infra
9 Rajasthan Pkg 9 247.270 292.910 46 Under Construction 26-Feb-20 18-Dec-20 Completed 98%
Engineering Limited
M/s Dhaya Maju
Infrastructure (Asia ) Sdn.
10 Rajasthan Pkg 10 292.910 319.360 26 Under Construction 30-Jun-20 22-May-21 31-Mar-24 Berhad - Crescent EPC 53%
Projects & Technical
Services Ltd.
11 Rajasthan Pkg 11 319.360 330.990 12 Under Construction 19-Jun-20 22-May-21 31-Dec-23 M/s Larsen & Toubro Ltd. 90%

M/s G R Infraprojects
12 Rajasthan Pkg 12 330.990 359.130 28 Under Construction 18-Jun-20 01-Apr-21 31-Dec-23 66%
Limited
M/s CDS Infra Projects
13 Rajasthan Pkg 13 359.130 388.380 29 Under Construction 18-Jun-20 25-Mar-21 31-Dec-23 69%
Limited
M/s Dhaya Maju
Infrastructure (Asia ) Sdn.
14 Rajasthan Pkg 14 388.380 418.960 31 Under Construction 30-Jun-20 24-May-21 31-Mar-24 Berhad - Crescent EPC 55%
Projects & Technical
Services Ltd.
M/s Dilip Buildcon Ltd –
15 Rajasthan Pkg 15 418.960 427.260 8 Under Construction 22-Dec-20 06-Jul-21 31-Mar-24 M/s Altis Holding 23%
Corporation
Chainage Date of Target Physical
Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Dineshchandra R.
16 Rajasthan Pkg 16 427.260 452.390 25 Under Construction 08-Jul-20 05-Jan-21 31-Dec-23 Agrawal Infracon Pvt. 81%
Ltd.
M/s JiangXi Construction
Madhya Engineering (Group)
17 Pkg 17 452.390 484.390 32 Under Construction 11-Feb-20 08-Oct-20 30-Apr-23 94%
Pradesh Corporation Ltd. - MKC
Infrastructure Ltd. (JV)
Madhya M/s G R Infraprojects
18 Pkg 18 484.390 517.390 33 Completed 01-Oct-19 07-Feb-20 Completed 100%
Pradesh Limited
M/s JiangXi Construction
Madhya Engineering (Group)
19 Pkg 19 517.390 546.890 30 Under Construction 11-Feb-20 05-Nov-20 30-Apr-23 92%
Pradesh Corporation Ltd. - MKC
Infrastructure Ltd. (JV)
Madhya
20 Pkg 20 546.890 572.190 25 Under Construction 08-Mar-19 06-Dec-19 Completed M/s GHV (India) Pvt Ltd. 100%
Pradesh
Madhya M/s G R Infraprojects
21 Pkg 21 572.190 602.390 30 Completed 28-May-19 10-Dec-19 Completed 99%
Pradesh Limited
Madhya
22 Pkg 22 602.390 627.390 25 Completed 19-Jun-20 20-Nov-20 Completed M/s Larsen & Toubro Ltd. 100%
Pradesh
Madhya M/s G R Infraprojects
23 Pkg 23 627.390 652.690 25 Under Construction 07-Aug-19 29-May-20 Completed 99%
Pradesh Limited
Madhya M/s G R Infraprojects
24 Pkg 24 652.690 673.740 21 Completed 07-Aug-19 05-Mar-20 Completed 100%
Pradesh Limited
Madhya M/s G R Infraprojects
25 Pkg 25 673.740 696.890 23 Under Construction 07-Aug-19 05-Mar-20 Completed 99%
Pradesh Limited
M/s Atlas Construction
26 Gujarat Pkg 26 696.890 726.390 30 Under Construction 11-Nov-21 02-May-22 30-Jun-24 12%
Pvt. Ltd. - NKC (JV)

27 Gujarat Pkg 27 726.390 755.390 29 Under Construction 30-Jul-21 15-Feb-22 30-Jun-24 M/s GHV (India) Pvt Ltd 28%

28 Gujarat Pkg 28 755.390 780.890 26 Under Construction 27-May-21 16-Nov-21 30-Jun-24 M/s GHV (India) Pvt Ltd 32%

M/s PNC Infratech Pvt.


29 Gujarat Pkg 29 780.890 803.390 23 Under Construction 23-Jul-20 16-Apr-21 30-Jun-24 97%
Ltd.
M/s Patel Infrastructure
30 Gujarat Pkg 30 803.390 824.890 22 Under Construction 05-Oct-20 08-Sep-21 30-Jun-24 52%
Limited
M/s PNC Infratech Pvt.
31 Gujarat Pkg 31 824.890 844.350 19 Under Construction 23-Jul-20 18-May-21 30-Jun-24 80%
Ltd.

Delhi – Vadodara Total 845


M/s IRB Infrastructure
1 Gujarat Pkg 1 355.000 378.740 24 Completed 20-Mar-18 18-Jan-19 Completed 100%
Developers Ltd.
M/s IRCON International
2 Gujarat Pkg 2 323.000 355.000 32 Under Construction 28-Mar-18 31-Jan-19 31-May-23 99%
Limited
M/s Patel Infrastructure
3 Gujarat Pkg 3 292.000 323.000 31 Under Construction 28-Mar-18 08-Mar-19 31-May-23 96%
Limited
M/s Ashoka Buildcon
4 Gujarat Pkg 4 279.000 292.000 13 Under Construction 28-Mar-18 10-Dec-18 31-May-23 97%
Limited
Chainage Date of Target Physical
Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Sadbhav
5 Gujarat Pkg 5 254.430 279.000 25 Under Construction 28-Mar-18 01-Nov-19 30-Jun-24 27%
Engineering Pvt. Ltd.
M/s G R Infraprojects
6 Gujarat Pkg 6 217.500 254.430 37 Under Construction 30-Jul-20 10-Dec-21 30-Jun-24 35%
Limited
M/s IRB Infrastructure
7 Gujarat Pkg 7 190.000 217.500 28 Under Construction 31-Jul-20 10-Dec-21 30-Jun-24 28%
Developers Ltd.
Awarded - Work to M/s Roadway Solutions
8 Gujarat Pkg 8 154.600 190.000 35 27-May-21 - 30-Jun-24 -
Commence India Infra Ltd.
Awarded - Work to M/s Roadway Solutions
9 Gujarat Pkg 9 128.000 154.600 27 30-Jul-21 - 30-Jun-24 -
Commence India Infra Ltd.
M/s Roadway Solutions
10 Gujarat Pkg 10 103.400 128.000 25 Under Construction 30-Mar-21 21-Mar-22 30-Jun-24 7%
India Infra Ltd.
M/s RKC Infrabuilt
11 Maharashtra Pkg 11 77.000 103.400 26 Under Construction 15-Oct-20 28-May-22 30-Jun-24 26%
Private Ltd.

12 Maharashtra Pkg 12 50.700 77.000 26 Under Construction 15-Oct-20 22-Mar-22 30-Jun-24 M/s Montecarlo Limited 25%

Pkg 13 26.582 50.700 24


13 Maharashtra Under Construction 15-Oct-20 22-Mar-22 30-Jun-24 M/s G R Infraprojects Ltd. 28%
Pkg 13 (Spur
0.000 3.000 3
to JNPT)

Vadodara – Virar Total 355 -

Pkg 14 (Spur M/s IRCON International


1 Maharashtra 3.000 20.200 17 Under Construction 30-Nov-21 10-Nov-22 30-Jun-24 5%
to JNPT) Limited

Pkg 15 (Spur M/s Agroh Infrastructre &


2 Maharashtra 20.200 43.000 23 Under Construction 30-Nov-21 10-Nov-22 30-Jun-24 4%
to JNPT) Developer Pvt. Ltd.

Pkg 16 (Spur M/s Shivalaya


3 Maharashtra 43.000 69.700 27 Under Construction 29-Oct-21 01-Nov-22 30-Jun-24 10%
to JNPT) Construction Ltd.

Pkg 17 (Spur M/s IRCON International


4 Maharashtra 69.700 79.780 10 Under Construction 24-Dec-21 19-Jan-23 30-Jun-24 1%
to JNPT) Limited

Pkg 18 (Spur Bids to be Invited


5 Maharashtra 79.780 94.290 18 - - - - -
to JNPT) shortly

Virar – JNPT Total 91

Delhi - Mumbai Total 1386 -


Photographs

Delhi – Dausa – Lalsot section was inaugurated by Hon’ble Prime Minister on 12th Feb, 2023

Completed expressway near Sohna, Haryana


Interchange near Dausa, Rajasthan

Wayside amenities near Dausa, Rajasthan


8 laning and road marking completed near Vadodara, Gujarat

Clover Interchange near Bharuch, Gujarat


Animal Underpass constriction near Sawai Madhapur, Rajasthan

Lighting and road marking completed near Ankleshwar, Gujarat


Iconic 8 lane cable stayed bridge across Narmada River near Ankleshwar, Gujarat

Toll plaza completed near Sohna, Haryana


Toll Plaza near Garoth, Madhya Pradesh