Delhi – Mumbai Expressway – Monthly Progress Report
Status as of March 31st, 2023
(Length in km)
Key Plan (Status as of March 31st, 2023)
Delhi - Vadodara Section (Including Delhi-Faridabad-Sohna)
Vadodara – Mumbai (Virar) Section
Spur to JNPT
Delhi – Mumbai Expressway Package Level Status (as of March 31st, 2023)
Chainage Date of Target Physical
Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Dineshchandra R.
1 Haryana Pkg 1 0.000 9.000 9 Under Construction 31-Jul-20 11-Jan-22 12-Jan-24 Agrawal Infracon Pvt. 48%
Ltd.
M/s Dineshchandra R.
2 Haryana Pkg 2 9.000 33.000 25 Under Construction 30-Jul-20 10-Aug-21 11-Aug-23 Agrawal Infracon Pvt. 59%
Ltd.
M/s Dineshchandra R.
3 Haryana Pkg 3 33.000 59.063 26 Under Construction 07-Aug-20 14-May-21 15-May-23 Agrawal Infracon Pvt. 99%
Ltd.
Jewar Awarded - Work to M/s APCO Infratech Pvt.
s4 Uttar Pradesh 0 30 31 01-Aug-22 - - -
Connectivity Commence Ltd.
Delhi – Faridabad - Sohna Total 90
M/s APCO Infratech Pvt.
1 Haryana Pkg 1 0.000 18.460 18 Completed 05-Mar-19 13-Sep-19 Completed 100%
Ltd.
M/s APCO Infratech Pvt.
2 Haryana Pkg 2 18.460 46.960 29 Completed 05-Mar-19 13-Sep-19 Completed 100%
Ltd.
M/s Centrodorstroy India
3 Haryana Pkg 3 46.960 78.760 32 Completed 28-May-19 05-Sep-19 Completed 100%
Pvt. Ltd
M/s H.G. Infra
4 Rajasthan Pkg 4 78.760 115.660 37 Completed 09-Mar-19 10-Dec-19 Completed 100%
Engineering Limited
M/s KCC Buildcon Pvt.
5 Rajasthan Pkg 5 115.660 151.800 36 Completed 09-Mar-19 10-Dec-19 Completed 100%
Ltd.
M/s KCC Buildcon Pvt.
6 Rajasthan Pkg 6 151.800 182.960 31 Completed 09-Mar-19 20-Nov-19 Completed 100%
Ltd.
M/s Gawar Constructions
7 Rajasthan Pkg 7 182.960 214.220 31 Completed 28-May-19 07-Feb-20 Completed 100%
Ltd.
M/s H.G. Infra
8 Rajasthan Pkg 8 214.220 247.270 33 Completed 11-Feb-20 07-Nov-20 Completed 100%
Engineering Limited
M/s H.G. Infra
9 Rajasthan Pkg 9 247.270 292.910 46 Under Construction 26-Feb-20 18-Dec-20 Completed 98%
Engineering Limited
M/s Dhaya Maju
Infrastructure (Asia ) Sdn.
10 Rajasthan Pkg 10 292.910 319.360 26 Under Construction 30-Jun-20 22-May-21 31-Mar-24 Berhad - Crescent EPC 53%
Projects & Technical
Services Ltd.
11 Rajasthan Pkg 11 319.360 330.990 12 Under Construction 19-Jun-20 22-May-21 31-Dec-23 M/s Larsen & Toubro Ltd. 90%
M/s G R Infraprojects
12 Rajasthan Pkg 12 330.990 359.130 28 Under Construction 18-Jun-20 01-Apr-21 31-Dec-23 66%
Limited
M/s CDS Infra Projects
13 Rajasthan Pkg 13 359.130 388.380 29 Under Construction 18-Jun-20 25-Mar-21 31-Dec-23 69%
Limited
M/s Dhaya Maju
Infrastructure (Asia ) Sdn.
14 Rajasthan Pkg 14 388.380 418.960 31 Under Construction 30-Jun-20 24-May-21 31-Mar-24 Berhad - Crescent EPC 55%
Projects & Technical
Services Ltd.
M/s Dilip Buildcon Ltd –
15 Rajasthan Pkg 15 418.960 427.260 8 Under Construction 22-Dec-20 06-Jul-21 31-Mar-24 M/s Altis Holding 23%
Corporation
Chainage Date of Target Physical
Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Dineshchandra R.
16 Rajasthan Pkg 16 427.260 452.390 25 Under Construction 08-Jul-20 05-Jan-21 31-Dec-23 Agrawal Infracon Pvt. 81%
Ltd.
M/s JiangXi Construction
Madhya Engineering (Group)
17 Pkg 17 452.390 484.390 32 Under Construction 11-Feb-20 08-Oct-20 30-Apr-23 94%
Pradesh Corporation Ltd. - MKC
Infrastructure Ltd. (JV)
Madhya M/s G R Infraprojects
18 Pkg 18 484.390 517.390 33 Completed 01-Oct-19 07-Feb-20 Completed 100%
Pradesh Limited
M/s JiangXi Construction
Madhya Engineering (Group)
19 Pkg 19 517.390 546.890 30 Under Construction 11-Feb-20 05-Nov-20 30-Apr-23 92%
Pradesh Corporation Ltd. - MKC
Infrastructure Ltd. (JV)
Madhya
20 Pkg 20 546.890 572.190 25 Under Construction 08-Mar-19 06-Dec-19 Completed M/s GHV (India) Pvt Ltd. 100%
Pradesh
Madhya M/s G R Infraprojects
21 Pkg 21 572.190 602.390 30 Completed 28-May-19 10-Dec-19 Completed 99%
Pradesh Limited
Madhya
22 Pkg 22 602.390 627.390 25 Completed 19-Jun-20 20-Nov-20 Completed M/s Larsen & Toubro Ltd. 100%
Pradesh
Madhya M/s G R Infraprojects
23 Pkg 23 627.390 652.690 25 Under Construction 07-Aug-19 29-May-20 Completed 99%
Pradesh Limited
Madhya M/s G R Infraprojects
24 Pkg 24 652.690 673.740 21 Completed 07-Aug-19 05-Mar-20 Completed 100%
Pradesh Limited
Madhya M/s G R Infraprojects
25 Pkg 25 673.740 696.890 23 Under Construction 07-Aug-19 05-Mar-20 Completed 99%
Pradesh Limited
M/s Atlas Construction
26 Gujarat Pkg 26 696.890 726.390 30 Under Construction 11-Nov-21 02-May-22 30-Jun-24 12%
Pvt. Ltd. - NKC (JV)
27 Gujarat Pkg 27 726.390 755.390 29 Under Construction 30-Jul-21 15-Feb-22 30-Jun-24 M/s GHV (India) Pvt Ltd 28%
28 Gujarat Pkg 28 755.390 780.890 26 Under Construction 27-May-21 16-Nov-21 30-Jun-24 M/s GHV (India) Pvt Ltd 32%
M/s PNC Infratech Pvt.
29 Gujarat Pkg 29 780.890 803.390 23 Under Construction 23-Jul-20 16-Apr-21 30-Jun-24 97%
Ltd.
M/s Patel Infrastructure
30 Gujarat Pkg 30 803.390 824.890 22 Under Construction 05-Oct-20 08-Sep-21 30-Jun-24 52%
Limited
M/s PNC Infratech Pvt.
31 Gujarat Pkg 31 824.890 844.350 19 Under Construction 23-Jul-20 18-May-21 30-Jun-24 80%
Ltd.
Delhi – Vadodara Total 845
M/s IRB Infrastructure
1 Gujarat Pkg 1 355.000 378.740 24 Completed 20-Mar-18 18-Jan-19 Completed 100%
Developers Ltd.
M/s IRCON International
2 Gujarat Pkg 2 323.000 355.000 32 Under Construction 28-Mar-18 31-Jan-19 31-May-23 99%
Limited
M/s Patel Infrastructure
3 Gujarat Pkg 3 292.000 323.000 31 Under Construction 28-Mar-18 08-Mar-19 31-May-23 96%
Limited
M/s Ashoka Buildcon
4 Gujarat Pkg 4 279.000 292.000 13 Under Construction 28-Mar-18 10-Dec-18 31-May-23 97%
Limited
Chainage Date of Target Physical
Length
# State Package Status Award Date Commenc- Completion Concessionaire Progress
(km)
From To ement Date (%)
M/s Sadbhav
5 Gujarat Pkg 5 254.430 279.000 25 Under Construction 28-Mar-18 01-Nov-19 30-Jun-24 27%
Engineering Pvt. Ltd.
M/s G R Infraprojects
6 Gujarat Pkg 6 217.500 254.430 37 Under Construction 30-Jul-20 10-Dec-21 30-Jun-24 35%
Limited
M/s IRB Infrastructure
7 Gujarat Pkg 7 190.000 217.500 28 Under Construction 31-Jul-20 10-Dec-21 30-Jun-24 28%
Developers Ltd.
Awarded - Work to M/s Roadway Solutions
8 Gujarat Pkg 8 154.600 190.000 35 27-May-21 - 30-Jun-24 -
Commence India Infra Ltd.
Awarded - Work to M/s Roadway Solutions
9 Gujarat Pkg 9 128.000 154.600 27 30-Jul-21 - 30-Jun-24 -
Commence India Infra Ltd.
M/s Roadway Solutions
10 Gujarat Pkg 10 103.400 128.000 25 Under Construction 30-Mar-21 21-Mar-22 30-Jun-24 7%
India Infra Ltd.
M/s RKC Infrabuilt
11 Maharashtra Pkg 11 77.000 103.400 26 Under Construction 15-Oct-20 28-May-22 30-Jun-24 26%
Private Ltd.
12 Maharashtra Pkg 12 50.700 77.000 26 Under Construction 15-Oct-20 22-Mar-22 30-Jun-24 M/s Montecarlo Limited 25%
Pkg 13 26.582 50.700 24
13 Maharashtra Under Construction 15-Oct-20 22-Mar-22 30-Jun-24 M/s G R Infraprojects Ltd. 28%
Pkg 13 (Spur
0.000 3.000 3
to JNPT)
Vadodara – Virar Total 355 -
Pkg 14 (Spur M/s IRCON International
1 Maharashtra 3.000 20.200 17 Under Construction 30-Nov-21 10-Nov-22 30-Jun-24 5%
to JNPT) Limited
Pkg 15 (Spur M/s Agroh Infrastructre &
2 Maharashtra 20.200 43.000 23 Under Construction 30-Nov-21 10-Nov-22 30-Jun-24 4%
to JNPT) Developer Pvt. Ltd.
Pkg 16 (Spur M/s Shivalaya
3 Maharashtra 43.000 69.700 27 Under Construction 29-Oct-21 01-Nov-22 30-Jun-24 10%
to JNPT) Construction Ltd.
Pkg 17 (Spur M/s IRCON International
4 Maharashtra 69.700 79.780 10 Under Construction 24-Dec-21 19-Jan-23 30-Jun-24 1%
to JNPT) Limited
Pkg 18 (Spur Bids to be Invited
5 Maharashtra 79.780 94.290 18 - - - - -
to JNPT) shortly
Virar – JNPT Total 91
Delhi - Mumbai Total 1386 -
Photographs
Delhi – Dausa – Lalsot section was inaugurated by Hon’ble Prime Minister on 12th Feb, 2023
Completed expressway near Sohna, Haryana
Interchange near Dausa, Rajasthan
Wayside amenities near Dausa, Rajasthan
8 laning and road marking completed near Vadodara, Gujarat
Clover Interchange near Bharuch, Gujarat
Animal Underpass constriction near Sawai Madhapur, Rajasthan
Lighting and road marking completed near Ankleshwar, Gujarat
Iconic 8 lane cable stayed bridge across Narmada River near Ankleshwar, Gujarat
Toll plaza completed near Sohna, Haryana
Toll Plaza near Garoth, Madhya Pradesh