Decision Making
Decision Making
LECTURE NOTES
COURSE: ACC224 – MANAGERIAL ACCOUNTING
TOPIC: DECISION MAKING UNDER CERTAINTY AND UNCERTAINTY
INTRODUCTION
In day to day business life, managers are obliged to make decisions on the course of action
that has to be taken. Decisions are frequently classified as those made under certainty and
those made under uncertainty. Models, formulas and calculations shall form the basis of
argument and finally the decision making.
RELEVANT INFORMATION
Relevant information is that information which will affect the decision to be made.
Information that will not affect the decision to be made is obviously irrelevant information.
Relevant costs or benefits are those costs or benefits that will differ between various
alternatives considered. In other words, only differential or incremental cash flows
should be taken into account
Compare the following two alternatives: Manufacturing components and Buying the
components from outside.
Manufacture Buy
100 components 100 components
TZS TZS
Direct Labour 10,000 10,000
Direct Materials 30,000 -
Variable overheads 5,000 -
Fixed overheads 20,000 20,000
Supplier’s purchase price - 50,000
Total 65,000 80,000
Costs which remain the same under both alternatives are irrelevant for decision
making
Now, let us take the relevant costs only:
Manufacture Buy
100 components 100 components
TZS TZS
1
For the purpose of decision making, the cost of manufacturing one component will be
TZS 350
However, for the purpose of stock valuation, the cost of manufacturing one
component will be TZS 650, i.e. all costs will be included.
Illustration 1:
Think of a situation whereby we have to make decision on whether to re-arrange our labour
force and incur a labour cost of TZS 1.8 per unit or do nothing and incur a labour cost of TZS
2 per unit. We want to produce 100,000 units. If we are quite certain of these outcomes, then
the probability is 100% or 1 for each outcome. We can show this in the following decision
table:
ACTIONS: OUTOME:
(Labour cost)
Do nothing TZS 2 x 100,000 x 100% (labour cost) = TZS 200,000
Re-arrange TZS 1.80 x 100,000 x 100% = TZS 180,000
The most desirable outcome should be the one giving the least labour cost, TZS 180,000
A decision under uncertainty is when there are many unknowns and no possibility of
knowing what could occur in the future to alter the outcome of a decision. We feel
uncertainty about a situation when we can’t predict with complete confidence what the
outcomes of our actions will be. We experience uncertainty about a specific question when
we can’t give a single answer with complete confidence.
2
Decision under uncertainty applies the following model:
An objective is a target that the decision maker is hoping to achieve. For example to
maximize profits or to achieve a certain present value of cash flows. The
quantification of an objective is often called OBJECTIVE FUNCTION. An
objective function is used to evaluate the alternative courses of action and provides
the basis for choosing the best alternative.
The search for alternative courses of action that will enable the objective to be
achieved
Because decision problems exist in an uncertain environment, it is necessary to
consider those uncontrollable factors that are outside the decision maker’s control and
that may occur for each alternative course of action. These uncontrollable factors are
called EVENTS or STATES OF NATURE. For example, in a product launch
situation, possible states of nature could consist of events such as similar product
being launched by a competitor at a lower price or no similar product being launched.
Each outcome (result) is conditionally dependent on a specific course of action and a
specific state of action.
The value (payoff) of each possible outcome is measured in terms of the decision
maker’s objectives. Payoffs are normally expressed in monetary terms such as profits
or cash flows, but in some problems the decision maker may be interested in other pay
off such as time and market share etc.
Selection of a course of action
‘Risk’ is applied to a situation where there are several possible outcomes and there is
relevant past experience to enable statistical evidence to be produced for predicting the
possible outcomes.
‘Uncertainty’ exists where there are several possible outcomes, but there is little
previous statistical evidence to enable the possible outcomes to be predicted.
3
A person who is a risk neutral will be indifferent to all available alternatives if
they have the same expected value.
Illustration 2:
Two proposals have been submitted to the Management of Asaad Company Ltd:
Proposal A:
Invest in textile manufacturing business.
Proposal B:
Invest in transportation business
The expected cash inflows (Revenues) per annum with their respective probabilities from
each proposal are shown in Table 1.
Table 1:
Investment Proposals
Proposal A Proposal B
(Textile Manufacturing) (Transportation)
CALCULATION
The question is: Which proposal should be accepted and why? In order to be able to answer
this question, we need to carry out calculations of expected values, standard deviation and
coefficient of variation.
4
n
A = ∑ AiPi
i=1
= 0.1 (3,000) + 0.2 (3,500) + 0.4 (4,000) + 0.2 (4,500) + 0.1 (5,000)
SDA = √ ∑ (A – A)
n
i
2
Pi
i=1
= √ 300,000
= TZS 547.72 million
CVA = SDA
A
= 547.72
4,000
= 0.137
SDB = √ ∑n (B – B) i
2
Pi
i=1
5
= √ 2,427,500
= TZS 1,558.04 million
CVB = SDB
B
= 1,558.04
4,350
= 0.358
WORKINGS:
For Proposal A:
You can tabulate the results obtained from the illustration as follows:
Implement proposal A.
It should be born in mind that predictions are more subjected to uncertainty than historical
events.
6
General approach to uncertainty
Suppose in illustration 1, the manager of accompany is faced with equal likelihoods of
success or failure regarding doing nothing and re-arranging the labour force and the
shown cost data is given, the one-column decision table becomes a two column
decision table
EVENT Success Failure Expected value of
cost
Probability of event 0.5 0.5
Cost Cost
ACTIONS:
Do nothing TZS 200,000 TZS 200,000 TZS 200,000
Re-arrange TZS 100,000 TZS 260,000 TZS 180,000
The manager would decide to re-arrange the labour force since re-arrangement has a
lower expected labour cost, TZS 180,000
By selecting the re-arrangement option, the company expects to save TZS 20,000 i.e.
TZS 200,000 – 180,000. If the manager thinks that the amount of saving is
reasonable, then it will be wise to select the re-arrangement option.
The accountant provides most of the data required in these decision models.
Since the perfect information that the company is considering buying will contain one
of the two predictions, the expected value with perfect information will be:
(TZS 200,000 x 0.5) + (TZS 100,000 x 0.5) = TZS 150,000
The maximum amount that can be paid t to a consultant in order to obtain perfect
information is TZS 30,000.
7
Buying imperfect information
In reality, it may be difficult to obtain perfect information
But, imperfect information may still be worth buying
The consultant will have to consider each of the three possible reports:
o Neutral
o Optimistic
o Pessimistic
The optimistic and pessimistic reports would change the manager’s assessment of
probabilities of success or failure and hence change the decision table:
Cost Cost
ACTIONS:
Do nothing TZS 200,000 TZS 200,000 TZS 200,000
Re-arrange TZS 100,000 TZS 260,000 TZS 132,000
Pessimistic Report:
Probability of event 0.2 0.8
Cost Cost
ACTIONS:
Do nothing TZS 200,000 TZS 200,000 TZS 200,000
Re-arrange TZS 100,000 TZS 260,000 TZS 228,000
Suppose the manager assesses a probability of 40% neutral, 30% optimistic and 30%
pessimistic, then we can proceed determining the maximum price of the imperfect
information by preparing the following decision table:
ACTIONS:
Do nothing TZS 200,000 60,000
Re-arrange TZS 180,000 TZS 132,000 111,600
Total 171,600
8
Value of imperfect information
TZS
Expected value with existing information 180,000
Expected value with imperfect information 171,600
Value of imperfect information 8,400
The maximum amount that can be paid to the consultant in order to obtain imperfect
information is TZS 8,400.
Illustration 3:
Each of two managers has been given an opportunity to submit his proposal which costs TZS
10,000 to prepare. There is a 50 – 50 chance that the proposal will be accepted, in which case,
there would be a TZS 25,000 after deducting all associated costs (including the TZS 10,000
proposal cost). If you were one of the managers, would you submit the proposal?
In order to be able to answer this question, let us prepare the following decision table:
The two managers may have different attitudes towards the situation:
(i) The manager who does not have adequate capital (funds) may decide to forego the
opportunity.
(ii) The managers who has adequate capital may decide to take the opportunity
(iii) The decision of each manager will also depend on their conceived utility value of
dollar.
(iv) The manager who is prepared to take risk may decide to take the risk of losing
TZS 10,000 and take the opportunity.
(v) The manager who is not prepared to take risk (risk averse manager) may decide to
avoid risk of losing TZS 10,000 and forego the opportunity.
9
COST OF PREDICTION ERROR
Cost of prediction error = Expected financial results under an alternative parameter value
LESS
Expected financial results under the original prediction
under the alternative parameter value
Illustration 4:
You are given the following information about product M:
Per unit
TZS
Selling price 90
Variable cost 50
The sales manager predicted that 1,000 units of product M would be purchased and sold
during April, 2008. Unfortunately, due to the unforeseen competition in the market, only 600
units were sold. The Manager had a privilege of returning the unsold products at no cost and
getting back a refund for the price paid. What was the cost of prediction error- that is, the cost
of the Sales Manager’s failure to predict demand accurately?
SOLUTION:
(1) Initial predicted sales = 1,000 units
Optimal original decision: Purchase 1,000 units
Expected net income = (1,000 x TZS 40 contribution)
Less: TZS 20,000 fixed costs
= TZS 20,000
10
Suppose in the illustration, the Manager had no privilege of returning any unsold
products. Instead because of their souvenir marketing they became worthless. What
would be the cost of prediction error?
SOLUTION:
DECISION TREES
A decision tree is a diagram showing several possible courses of action and possible
events (i.e. state of nature) and the potential outcomes for each course of action.
Illustration 5:
A company is considering whether to develop and market a new product. Development costs
are estimated to be TZS 180,000, and there is a 0.75 probability that the development effort
will be successful and a 0.25 probability that the development effort will be unsuccessful.
If the development is successful, the product will be marketed, and it is estimated that:
Each of the above profit and loss calculations is after taking into account the development
cost of TZS 180,000. The estimated probabilities of each of the above events are as follows:
11
Very successful 0.4
Moderately successful 0.3
Failure 0.3
REQUIRED:
Present the problem in a decision tree, calculate the expected values and select the course of
action to be taken.
Maximin criterion is that the worst possible outcome will always occur and the decision
maker should therefore select the largest payoff under this assumption. In the illustration 6
below, the worst outcomes are TZS 100,000 for machine A and TZS 10,000 for machine B.
So machine A should be purchased using the maximin decision rule.
Maximax criterion is based on the assumption that the best payoff will occur. The highest
payoffs in the illustration 6 are TZS 160,000 for machine A and TZS 200,000 for machine B.
So machine B will be selected under the maximax criterion.
Regret criterion is based on the fact that, having selected an alternative that does not turn out
to be the best, the decision maker will regret not having chosen another alternative when he
or she had he opportunity.
Illustration 6:
You are provided with the following profits data for two machine options in two possible
demand conditions:
Low demand(TZS) High demand(TZS)
Machine A 100,000 160,000
Machine B 10,000 200,000
What will the decision maker decide under maximin, maximax and regret critetia?
If probability of low demand and high demand is currently estimated at 50-50 what amount
of money will the company be willing to pay for perfect prediction of demand?
12
DECISION MAKING UNDER CERTAINTY AND UNCERTAINTY
ILLUSTRATIONS
Illustration 1
Compare the following two alternatives: Manufacturing components and Buying the
components from outside.
Manufacture Buy
100 components 100 components
TZS TZS
Direct Labour 10,000 10,000
Direct Materials 30,000 -
Variable overheads 5,000 -
Fixed overheads 20,000 20,000
Supplier’s purchase price - 50,000
Total 65,000 80,000
What are the relevant costs? And what the decision the management will take?
Illustration 2
Think of a situation whereby we have to make decision on whether to re-arrange our labour
force and incur a labour cost of TZS 1.8 per unit or do nothing and incur a labour cost of TZS
2 per unit. We want to produce 100,000 units. If we are quite certain of these outcomes, then
the probability is 100% or 1 for each outcome. What decision the m managers will take?
Illustration 3
Two proposals have been submitted to the Management of Asaad Company Ltd:
Proposal A:
Invest in textile manufacturing business.
Proposal B:
Invest in transportation business
The expected cash inflows (Revenues) per annum with their respective probabilities from
each proposal are shown in Table 1.
Table 1:
Investment Proposals
Proposal A Proposal B
(Textile Manufacturing) (Transportation)
13
Illustration 4
Suppose in illustration 1, the manager of accompany is faced with equal likelihoods of
success or failure regarding doing nothing and re-arranging the labour force and the shown
cost data is given in the table below. What will the manager decide?
Illustration 5
Suppose in the illustration 4 a consultant can provide perfect information (information that
gives absolute certainty) to the company that the ‘do nothing’ option will fail and the re-
arrangement option will succeed, what would be the maximum amount that the company
would be willing to pay for the consultant’s wisdom?
Illustration 6
The optimistic and pessimistic data is given in the table below:
Cost Cost
ACTIONS:
Do nothing TZS 200,000 TZS 200,000
Re-arrange TZS 100,000 TZS 260,000
Pessimistic Report:
Probability of event 0.2 0.8
Cost Cost
ACTIONS:
Do nothing TZS 200,000 TZS 200,000
Re-arrange TZS 100,000 TZS 260,000
Suppose the manager assesses a probability of 40% neutral, 30% optimistic and 30%
pessimistic, what is the maximum price of the imperfect information?
Illustration 7
Each of two managers has been given an opportunity to submit his proposal at a cost TZS
10,000. There is a 50 – 50 chance that the proposal will be accepted, in which case, there
would be a TZS 25,000 after deducting all associated costs (including the TZS 10,000
proposal cost). If you were one of the managers, would you submit the proposal?
14
Illustration 8
You are given the following information about product M:
Per unit (TZS)
Selling price 90
Variable cost 50
The sales manager predicted that 1,000 units of product M would be purchased and sold
during April, 2008. Unfortunately, due to the unforeseen competition in the market, only 600
units were sold. The Manager had a privilege of returning the unsold products at no cost and
getting back a refund for the price paid. What was the cost of prediction error- that is, the cost
of the Sales Manager’s failure to predict demand accurately?
Illustration 9
Suppose in the illustration 8, the Manager had no privilege of returning any unsold products.
Instead because of their souvenir marketing s, they became worthless. What would be the
cost of prediction error?
Illustration 10
A company is considering whether to develop and market a new product. Development costs
are estimated to be TZS 180,000, and there is a 0.75 probability that the development effort
will be successful and a 0.25 probability that the development effort will be unsuccessful.
If the development is successful, the product will be marketed, and it is estimated that:
Each of the above profit and loss calculations is after taking into account the development
cost of TZS 180,000. The estimated probabilities of each of the above events are as follows:
REQUIRED:
Present the problem in a decision tree, calculate the expected values and select the course of
action to be taken.
Illustration 11:
You are provided with the following profits data for two machine options in two possible
demand conditions:
Low demand(TZS) High demand(TZS)
Machine A 100,000 160,000
Machine B 10,000 200,000
What will the decision maker decide under maximin, maximax and regret critetia?
If probability of low demand and high demand is currently estimated at 50-50 what amount
of money will the company be willing to pay for perfect prediction of demand?
15