Project Name: Project Phase: Site Engineer: Weather Condition

The document summarizes the manpower allocation and tasks for a construction project to build a third floor vertical extension. Four masons and four helpers will be working on brick work, window grill jamb plaster, and parapet wall plaster. Special instructions note that a metal anchor for the tower and AC outdoor platform and electrical cables and boards need to be removed. Safety measures are to be followed during exterior plaster work.

Uploaded by

Ah Rashed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views3 pages

Project Name: Project Phase: Site Engineer: Weather Condition

The document summarizes the manpower allocation and tasks for a construction project to build a third floor vertical extension. Four masons and four helpers will be working on brick work, window grill jamb plaster, and parapet wall plaster. Special instructions note that a metal anchor for the tower and AC outdoor platform and electrical cables and boards need to be removed. Safety measures are to be followed during exterior plaster work.

Uploaded by

Ah Rashed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Project Name: Construction of one floor vertical Extension (3rd Floor)

Project Phase: Finishing


Site Engineer: Md. Asraful Hoque
Weather Condition: Sunny

Manpower Allocation
Sr. No. Task Name: Masonry Carpentry Rebar Concrete
M H M H M H M

Brick Work
1 2 2 - - - - -
Window Grill Jamb Plaster
2 1 1 - - - - -
Parapet Wall Plaster
3 1 1 - - - - -

4 - - - - - - -

5 - - - - - - -

6 - - - - - - -

7 - - - - - - -

8 - - - - - - -

9 - - - - - - -

10 - - - - - - -
TOTAL MANPOWER COUNT: 4 4 0 0 0 0 0
#Special Instructions:

#Additional Notes: 1.Metal anchor for tower & Ac outdoor Platform MS A


2.Electrical Cable & Board or all sort of cable need to r
3.Safety Measures shall follow during Exterior Plaster
Prepared By: Checked By:
UCEP GAZIPUR TVET INSTITUTE
North Salna, Gazipur.
Date:
Shift:
*M=
*H=

power Allocation Challenges/


Achievemets/
Concrete Electrical Plumbing Issues/Area of Upcoming Activities
Progress
H M H M H Concern

- - - - -
Steel Shed Installtion
- - - - -
Exterior Wall Plastering
- - - - -
Electrical Work
- - - - -
Thai-Aluminum
- - - - -
Tiles
- - - - -
Louver
- - - - -
Parapet Wall-B/W
- - - - -

- - - - -

- - - - -
0 0 0 0 0

Ac outdoor Platform MS Angle Frame required to remove as early as possible.


r all sort of cable need to remove .
ow during Exterior Plaster Work
Authorized By:
19/12/2023
8:00 AM-05:00 PM
Mason
Helper

Comments