Requisition Form 49
Requisition Form 49
Supply of Valves including required documentation, mandatory testing requirements and packaging for sea and
road transport.
The Supplier is responsible to furnish equipment and accessories of a sound mechanical design in accordance
with good working practices to meet the design conditions as specified.
Drawings and mechanical data sheets shall be submitted to the client for approval prior to commencement of
valve manufacture.
It is preferable for Gearbox Housings to be made from Cast Steel (as opposed to Cast Iron).
Trunnion mounted ball valves shall be supplied with approved grease fittings in accordance with 0000-TS-L006 for seat
injection and stem injection. 6” and 8” valves shall have 1 fitting per seat. 10” valves and above shall have 2 fittings per
seat. 4” valves and above shall have a stem grease fitting for lubrication of the stem.
All ball valves shall be supplied with Fire Safe Certificates in accordance with 0000-TS-L006.
All materials for pressure components shall be supplied with material certificates in accordance with Type 3.1 of BS
EN ISO 10204.
In accordance with documents listed in Section 2 of this requisition, and the following additional requirements;
1. Drawings and mechanical data sheets shall be submitted to the client for approval prior to commencement of
manufacture or dispatch from Vendor’s Shop.
2. Valve Castings: ASME Class 900, 1500 and 2500 valve bodies, including flanges, shall be inspected as per the
requirements of Specifications 0000-TS-L006.
3. In addition to the requirements of API-598/API-6D any valve bodies (cast or forged) manufactured in China or
India shall be subject to an extended hydrostatic shell test duration of 10 minutes.
4. Inspection level: Final inspection of goods and documentation at Supplier’s works prior to dispatch.
5. No goods shall be dispatched from Supplier without an inspection release note.
Quality Assurance AS/NZS ISO 9001
Supplier shall apply a quality system that complies with the requirements of AS/NZS 9001 and is currently certified
as complying with that standard by a recognised Third Party.
QA Documentation that the Supplier will be required to submit after award of purchase order is detailed in the Supplier
Data Requirement Form.
Company, and or representative of Company, shall have all reasonable right of access to Supplier’s, and where
applicable to Supplier’s sub-contractor’s, offices and works, for verification, inspection and expediting of any aspect
of the manufacturing program.
Page 1 of 4
G:\360\2008\00479 - Technical Evaluation of LLI\13.0 Procurement\Valve Requisition.doc
Engineering Requisition
for Equipment / Services Form
26
27
28
This Supplier / Sub-contractor shall supply a Compliance Statement that confirms complete compliance with the
Requisition and referenced documents or lists specific deviations and exceptions.
Page 2 of 4
G:\360\2008\00479 - Technical Evaluation of LLI\13.0 Procurement\Valve Requisition.doc
Engineering Requisition
for Equipment / Services Form
Company
Date
Signature
Required
Item Description No Approval / Info Certified
No Type A/I Wks No Type Wks
QA / Inspection & Testing
1 Supplier Drawing and Data Index 1 E A 1 1 E&P 2
2 Manufacturing / Delivery Schedule 1 E A 1
3 Quality Assurance / Safety Plan
4 Inspection & Test Plans 1* E A 1 1 E&P Note 4
Engineering & Design Documents
5 Piping and Instrument Diagrams
6 General Arrangement Drawing(s) 1* E&P A 2 1 E&P In MDR
Page 3 of 4
G:\360\2008\00479 - Technical Evaluation of LLI\13.0 Procurement\Valve Requisition.doc
Engineering Requisition
for Equipment / Services Form
Required
Item Description No Approval / Info Certified
No Type A/I Wks No Type Wks
22 Instrument Connection Diagrams (inc. JBs)
23 Hazardous Area Certificates
24 Weight Calculations
Other Documents
25 Weld Procedures
26 Material Test Certificates (Mech & Inst) 1 E&P In MDR
Note:
(1) Submittal of any of the above listed drawings on CAD diskettes will be acceptable ONLY with prior approval.
(2) These items to be submitted pre-delivery.
(3) These items may be submitted post delivery two (2) weeks.
(4) These items to be submitted at time of goods dispatch.
Legend:
* = Critical Data P = Print
A = Approval T = Transparency
Page 4 of 4
G:\360\2008\00479 - Technical Evaluation of LLI\13.0 Procurement\Valve Requisition.doc