0% found this document useful (0 votes)
135 views2 pages

TELESTAR International RMConflict Managememnt

Telestar International was awarded a $475,000 contract by the Department of Energy Resources to develop and test two waste treatment plants. By February 1979, costs were projected to exceed the contract amount by $468,000. The project manager stopped work in some departments, including structural analysis. The structures manager warned that testing the plant without completing the structural analysis risked failure. The plant exploded during testing due to a structural deficiency.

Uploaded by

Naveed Rabbani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views2 pages

TELESTAR International RMConflict Managememnt

Telestar International was awarded a $475,000 contract by the Department of Energy Resources to develop and test two waste treatment plants. By February 1979, costs were projected to exceed the contract amount by $468,000. The project manager stopped work in some departments, including structural analysis. The structures manager warned that testing the plant without completing the structural analysis risked failure. The plant exploded during testing due to a structural deficiency.

Uploaded by

Naveed Rabbani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Telestar International

On November 15, 1978, the Department of Energy Resources awarded Telestar a $475,000 contract
for the developing and testing of two waste treatment plants. Telestar had spent the better part of
the last two years developing waste treatment technology under its own R&D activities. This new
contract would give Telestar the opportunity to “break into a new field”—that of waste treatment.
The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by
Telestar. The original bid was priced out at $847,000. Telestar’s management, however, wanted to
win this one. The decision was made that Telestar would “buy in” at $475,000 so that they could at
least get their foot into the new marketplace. The original estimate of $847,000 was very “rough”
because Telestar did not have any good man-hour standards, in waste treatment, on which to base
their man-hour projections. Corporate management was willing to spend up to $400,000 of their
own funds to compensate the bid of $475,000.

By February 15, 1979, costs were increasing to such a point where overrun would be occurring well
ahead of schedule. Anticipated costs to completion were now $943,000. The project manager
decided to stop all activities in certain functional departments, one of which was structural analysis.
The manager of the structural analysis department strongly opposed the closing out of the work
order prior to the testing of the first plant’s high-pressure pneumatic and electrical systems.

Telestar International Structures manager: “You’re running a risk if you close out this work order.
How will you know if the hardware can withstand the stresses that will be imposed during the test?
After all, the test is scheduled for next month and I can probably finish the analysis by then.”

Project manager: “I understand your concern, but I cannot risk a cost overrun. My boss expects me
to do the work within cost. The plant design is like one that we have tested before, without any
structural problems being detected. On this basis I consider your analysis unnecessary.”

Structures manager: “Just because two plants are similar does not mean that they will be identical in
performance. There can be major structural deficiencies.”

Project manager: “I guess the risk is mine.”

Structures manager: “Yes, but I get concerned when a failure can reflect on the integrity of my
department. You know, we’re performing on schedule and within the time and money budgeted.
You’re setting a bad example by cutting off our budget without any real justification.”

Project manager: “I understand your concern, but we must pull out all the stops when overrun costs
are inevitable.”

Structures manager: “There’s no question in my mind that this analysis should be completed.
However, I’m not going to complete it on my overhead budget. I’ll reassign my people tomorrow.
Incidentally, you had better be careful; my people are not very happy to work for a project that can
be cancelled immediately. I may have trouble getting volunteers next time.”

Project manager: “Well, I’m sure you’ll be able to adequately handle any future work. I’ll report to
my boss that I have issued a work stoppage order to your department.”

During the next month’s test, the plant exploded. Post analysis indicated that the failure was due to
a structural deficiency.
1. Who is at fault?

2. Should the structures manager have been dedicated enough to continue the work on his own?

3. Can a functional manager, who considers his organization as strictly support, still be dedicated to
total project success?

You might also like