Construction Method Statement For Cement-Mixed Pile On The West Bank
Construction Method Statement For Cement-Mixed Pile On The West Bank
CONTENTS
Revision 2 Ⅰ
Method Statement for Cement-mixed Pile on West Bank
Revision 2 Ⅱ
Method Statement for Cement-mixed Pile on West Bank
1.1 Terminology
1.1.1CMP
Cement-Mix Pile.
1.1.1 Reverse Mortar
Displaced mixture of sludge and cement after the mortar is injected in.
1.1.2 Guidance Groove
The groove preventing sludge from overflowing
1.1.3 Hanging Method
After the pile machine is assembled adjust the drill pipe to vertical with a transit instrument, the weld the
verticality calibration point of the pile machine to the barrel, hang a plumb bob at 5m above the ground right
aligning with the calibration point to ensure the pile machine vertical. The ratio of the distance between the
tip of plumb bob and verticality calibration point to the height of the plumb bob is the verticality deviation,
according to section 7.14 of Technical Code for Ground Treatment of Building IGJ79-2012, the deviation
shall be controlled within 1%.
Revision 2 1 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 2 / 26
Method Statement for Cement-mixed Pile on West Bank
3,0
3,0
17.45
14
Working shaft
2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2
2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2
2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2 2 9 2
3 10 3 3 10 3 3 10 3 3 10 3 3 10 3 3 10 3 3 10 3 3 10 3 3 10 3 3 10 3
4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4
4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4
4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4 4 11 4
5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5
5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5
5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5 5 12 5
6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6
6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6
6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6 6 13 6
7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7
7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7
7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7 7 14 7
8 15 8 8 15 8 8 15 8 8 15 8
1.8
8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8
8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8
8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8 8 15 8
9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9
9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9
9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9 9 16 9
0.6
11 181111 1811 11 181111 1811 11181111 1811 11 181111 181111181111 1811
11 181111 1811 11 181111 1811 11 181111 1811 111811111811
11 1811111811 11 181111 1811 11 181111 1811 11181111 1811
0.85
14 221414 2214 23 23 23 23 23
14 221414 2214 14 221414 2214 14 221414 2214 23 23 23 23 23 23 23 23 8 8 23 23 8 8 23 9 9 9 9
24 24 24
23 23 23 23 24 24 9 9 24 24 24 24 10 10 24
23 23 23 23 24 24 24 24 8 8 24 24 24 24 9 9 10 10 25 25 25 25
24 24 24 24 24 24 8 8 8 8 25 25 25 25 10 10 25 25 11 25 25 11 11
24 24 8 25 25 25 25 9 9 25 25 10 10 11 26 26 26 26 26
25 25 25 8 8 25 25 8 25 25 9 9 9 9 26 26 26 26 11 11 26 26 12 26 12 12
25 8 8 26 26 26 26 10 10 26 26 11 11 12 27 27 27 27
26 26 26 9 9 26 26 9 9 26 26 10 10 10 10 27 27 27 27 12 12 27 27 13 27 27 13 13
26 9 9 10 10 27 27 11 27 27 11 11 27 27 12 12 13 28 28 28 28 28
27 27 10 10 27 27 27 27 11 11 11 28 28 28 28 13 13 28 28 28 14 14
27 27 10 10 28 28 28 28 12 12 28 28 13 13 14 14
28 28 11 11 28 28 11 11 28 28 12 12 12 12 29 29 14 14 29 29
28 28 11 11 29 29 13 13 29 29 29 29 14 14
12 12 29 12 12 29 29 13 29 29 13 13
29 29 12 12 29 29 29 13 30 30 14 14 30 30
13 13 13 30 30 30 30 14 14
30 30 13 13 30 30 13 30 30 14 14
14 14 31 31 14 14
31 31 14 14 31 31
Figure 1.0-1 Schematic diagram of working range of triaxial cement-mixed pile (m)
Revision 2 3 / 26
Method Statement for Cement-mixed Pile on West Bank
1 Surveyor 2 2 Measuring
Revision 2 4 / 26
Method Statement for Cement-mixed Pile on West Bank
7 Electrician 1 1 Electrical
Total 15 8 9
(2)Subsequent works: the construction of Site leveling next to the Cement-Mixed Pile. After the cement-mixed
column is constructed the Cast-in-situ Bored Pile within the range of cement-mixed column is constructed.
3.2 Supporting Activities
(1) Sinking speed and rising speed:
The sinking speed and rising speed of drill pipe is calculated with a stopwatch.
(2)Verticality:
Pile machine verticality is controlled with hanging method.
(3)Mud proportion:
the sludge in every tank needs water 900kg, cement 600kg.
Revision 2 5 / 26
Method Statement for Cement-mixed Pile on West Bank
4.1 Sequence
Construction sequence of triaxial cement-mixed pile on the west bank:
KYK2+375-KYK2+367.8
→KYK2+367.8-KYK2+288.6
→KYK2+226.2- KYK2+225
→KYK2+225- KYK2+156.6
4.2 Schedule
Refer to actual construction plan.
4.3 Construction Procedure
Measurement positioning
Maching positioning
Up Mixing Spraying
Figure 4.3-1 Construction Procedure of Triaxial Cement-Mixed Pile
Revision 2 6 / 26
Method Statement for Cement-mixed Pile on West Bank
6.0 MATERIALS
Revision 2 7 / 26
Method Statement for Cement-mixed Pile on West Bank
3d ≥3.5
Flexural
3
Strength(Mpa)
28d ≥6.5
3d ≥17
Compressive
4
Strength(Mpa)
28d ≥42.5
Test method of cement raw material: Refer to 《Test Methods of Cement and Concrete for Highway
Engineering JTG E30-2005》Chapter III.
Revision 2 8 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 9 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 10 / 26
Method Statement for Cement-mixed Pile on West Bank
X=2459249.174
1 B1-5 -6.675 -9.675 3 φ850@600
Y=375991.6426
X=2459247.6762
2 B1-6 -6.675 -9.675 3 φ850@600
Y=375990.6443
X=2459246.1784
3 B1-7 -6.675 -9.675 3 φ850@600
Y=375989.646
X=2459166.1153
4 A12-7 -12.163 -26.163 14 φ850@600
Y=376109.6773
X=2459164.63
5 A12-8 -12.163 -26.163 14 φ850@600
Y=376108.6605
X=2459163.1447
6 A12-9 -12.163 -26.163 14 φ850@600
Y=376107.6436
8.4 Trial Piling Parameters
Table 8.4-1 Pile Parameters List
Down
Cement Up Mixing Cement
Water Pile Mixing Cement
Pile Slurry Spraying Propor
No. Cement Length Spraying Consumption Remarks
No. Density Speed -tion
Ratio (m) Speed (t)
(g/cm3) (m/min) (%)
(m/min)
1 B1-5 1.5 1.37 3 1.2 1.6 20 1.36
(2)In the drilling process, the circulating water flow in the hole shall be adjusted according to the situation in
time to avoid damaging the core. Each footage shall be controlled within 1.5m.
(3)When lifting the drill pipe and taking the sample cores, it shall be done by tightening the drill and the
reamer.
(4)The core samples taken shall be placed in order from top to bottom, with its sampling depth marked.
Revision 2 11 / 26
Method Statement for Cement-mixed Pile on West Bank
Allow Deviation
Project No. Check Item Inspection Method
Unit Value
Check product certificate or
1 Cement Design requirements
sample delivery
Cement
2 Parameter index Water slurry ratio
consumption
The unconfined compresiion
3 Pile strength strength in 28days shall not be less Drilling core
than 1.0Mpa
Pile bottom
Control 4 mm +200 Head depth
elevation
The
Project 5 Pile top elevation mm +100 Level
(2) 42.5 ordinary portland cement shall be used and timely tested after deliver to site. For content of cement
detection see Section 2 of Chapter 6.
(3)The configured slurry shall be of good fluidity and the slurry shall be supplied continuously without
interruption. Water and cement shall be mixed evenly without precipitant in mixed mortar.
(4)The water-cement ratio, cement-mixed column driver sinking and upgrading velocity shall be strictly
controlled. For quality control of water-cement ratio and control of sinking and rising speed of drill pipe see
Section 2 of Chapter 3.
Revision 2 12 / 26
Method Statement for Cement-mixed Pile on West Bank
(5)When it is drilled to the design depth, the stirring head shall spray for about 30s at the pile bottom, and then
upgrade.Pile top surface is higher than the design of the top elevation of 50cm, to ensure the quality of piles.
(2) Whether the wounded is damaged on head, a head inspection and diagnose shall be conducted in case of
Revision 2 13 / 26
Method Statement for Cement-mixed Pile on West Bank
accident of head;
(3) For hemorrhoea injury, cataclasis injury, the rescuer shall know the knowledge of hemostasis, fixing and
binding for cataclasis;
(4) Can use the tourniquet and the practice of stopping bleeding with hands; for electric shocked personnel
shall conduct cardio-pulmonary resuscitation immediately (external cardiac compression of 30 times, artificial
breathing of 2 times);
(5) The contact nearby hospital (Chittagong Maa-O-Shishu Hospital Medical College +88031-2520063),
telling the location, severity of the accident, contact number of the department in detail, and dispatches
someone to meet at the crossing. At the same time report to the leaderships group;
(6) Record the condition of injury, the rescuer on site shall record the first-hand data such as the condition of
the injury, wounded location of grade of wound while rescuing the wounded person.
10.3 Health and Safety
(1)Strengthen the safety management of the construction process, so that the operator familiar with the
understanding of the construction process of risk factors, improve the operator's ability to adapt to safety.
Before working everyday, organize and convene a safety meeting at the safety classroom informing of risks
during construction.
(2)Construction equipment shall be powered off after the end of the work;
(3)Adequate lightings shall be provided to ensure that there are enough lighting on the construction site for the
construction, production and vehicle driving at night. Refer to the attached figure 10.0-3.
(4) Use guardrail for protection around the dug guidance groove; irrelevant personnel is forbidden to stay near
the pile machine.
(5) The constructor shall wear the safety cap, reflective vest and safety shoes.
(6) The arrangement has gotten approval by Naval Academy and Airport.
Revision 2 14 / 26
Method Statement for Cement-mixed Pile on West Bank
Concise and
Drill core Core length
Drill footage(m) to the point Core sketch
number (m)
describe
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
Remarks
Revision 2 16 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 17 / 26
Method Statement for Cement-mixed Pile on West Bank
1.2 S01.4.1.S4-3 Gelogical Design Plan for the Enclosure Structure on the West BankⅠ 2017.10/3.0 No objection
1.3 S01.4.1.S4-3 Gelogical Design Plan for the Enclosure Structure on the West Bank Ⅱ 2017.10/3.0 No objection
1.4 S01.4.1.S4-3 Gelogical Design Plan for the Enclosure Structure on the West Bank Ⅲ 2017.10/3.0 No objection
1.5 S01.4.1.S4-3 Gelogical Design Plan for the Enclosure Structure on the West Bank Ⅳ 2017.10/3.0 No objection
1.6 S01.4.1.S4-10 Floor Plan for Bottom Reinforcement of the Foundation Pit on the West Bank Ⅰ 2017.10/3.0 No objection
1.7 S01.4.1.S4-10 Floor Plan for Bottom Reinforcement of the Foundation Pit on the West Bank Ⅱ 2017.10/3.0 No objection
Revision 2 18 / 26
Method Statement for Cement-mixed Pile on West Bank
Test standards
Environment Sampling Date
Main instrument
& devices and
ID
Test Results
Technical
No. Test items Age Results Pass/Fail Remarks
specification/index
Standards for
judgment
Conclusion
Remarks
Tester: Checker: Issuer: Date:
Revision 2 19 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 20 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 21 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 22 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 23 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 24 / 26
Method Statement for Cement-mixed Pile on West Bank
11.7 Layout
Revision 2 25 / 26
Method Statement for Cement-mixed Pile on West Bank
Revision 2 26 / 26