List of Projects Completed 2022
List of Projects Completed 2022
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
RW01349/17 RAND WATER 14km × DN750 Continuously June 2019 July 2021 R197,632,024
Welded Steel Pipeline and
DESIGN AND Ms T Mtshali Associated Works
CONSTRUCTION OF
VARIOUS Cell: 073 744 2685 Only 70% is our Leading
PIPELINES Tel: (011) 682 0911 Partner portion on the JV
705/17 MIDVAAL WATER Replacing North 1,2 & 3 January November R24,000,000.00
COMPANY Pipelines 2018 2018
REPLACEMENT OF 1.8km of 800 and 600 steel
NORTHERN Mr W Gilson pipeline.
PIPELINES Tel: 018 482 9500
2015/005 UMGENI WATER Construction of 1.8km DN 1600 May 2015 June 2017 R127,312,761.01
Steel Pipeline
UMGENI WATER Mr. Stephen Burke
Contract no. GIBB DURBAN Bulk Water Supply Aug 2014 Oct 2016 R118,023,245.60
AW2013/14/34 Infrastructure Upgrade –
Mr Duncan Shaw Construction of a 22km DN500
AMATOLA WATER Tel. 031 267 8591 Steel Mqanduli
Cell. 083 636 1334
Contract no. GIBB DURBAN Construction of a 3.7km long May 2015 Oct 2016 R61,824,857.27
AW2013/14/14 DN900 plus 2 No 1 km long
Mr Duncan Shaw DN600 continuously welded
AMATOLA WATER Tel. 031 267 8591 steel pipelines from Thornhill
Cell. 083 636 1334 Water Treatment Works to
Signal Hill
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Contract no. Camdekon Engineers Ncoro Scheme Mar 2014 Sept 2016 R66,009,491
33/2013 MD (BL) Primary Steel Pipe Lines to
Mr Andrei Lemmer Cluster 5 and Zone C and 32.67
CHRIS HANI Tel: 043 722 2738 km from 350mm to 200mm
DISTRICT Steel Welded Pipe
MUNICIPALITY
Contract no. GIBB DURBAN Construction of 4.1km of April 2014 Jan 2016 R39,978,713.97
AW2013/14/16 DN600 Steel welded pipe Steel
Mr Duncan Shaw Signal Hill to Zamukulungisa
AMATOLA WATER Tel. 031 267 8591 Gravity Main
Cell. 083 636 1334
Contract no. 2159/21 TRONOX KZN Construction of 30.2km of Aug 2014 Sept 2015 R181,000,000
SAND 750mm welded Steel Pipe, and
HILLENDALE PUMP 0.96km of 710mm welded
STATION Mr Garry Wrightson HDPE Pipe, with associated
MECHANICAL AND 083 425 0061 concrete chambers and
ELECTRICAL AND earthworks. Construction of a
BULK WATER concrete pump station 1000kW
SUPPLY LINE (2 pumps) with related
mechanical and electrical works
FAIRBREEZE MINE
EMPANGENI
Contract no. W0911C Bigen Africa Construction of 11.34 km of Jan 2014 Feb 2016 R75,997,685.64
800mm to 500mm Steel Welded
Mr Llewellyn Biggs Pipeline
MANGAUNG: Tel. 051 430 1423
CONSTRUCTION OF
THE LONGRIDGE
WATER
DISTRIBUTION
MAIN
Contract no. 4285 RAND WATER 100km of existing A/C Pipes Nov 2013 Sept 2014 R45,589,423
(500 to 300mm diam) tested for
EMERGENCY Mr Adam Campbell leaks, ± 200 leaks repaired
SUPPORT PROJECT replacing the A/C with PVC
FOR ALLEVIATION Cell: 082 702 7589 Pipes and installing cascade s.s.
OF WATER clamps, ± 100 of valves various
SHORTAGES IN sizes were replaced and NWTW
ERMELO AND all old equipment replaced with
WESSELTON AND new ones.
UPGRADE
NORTHERN WATER
TREATMENT
Contract No. Mhlathuze Water Construction of 1500mm Aug 2013 April 2014 R7,972,283.79
MW000229 diameter Steel Rising Main
Ms Andile Ngwenya
UPGRADE OF NSEZI 035 902 1078
WATER
TREATMENT PLANT
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Contract no. 592/12 Midvaal Water Construction of 3.5 km of 800 Jan 2013 April 2014 R26,000,000.00
Company diam welded steel pipeline and
REPLACEMENT OF specials
SECTIONS OF THE Mr . F.G. Ellis
WEST 1 AND WEST 018 482 9500
2 PIPELINES
Contract no. W10326 Department of Water Construction of 22.2km of Sept 2011 Sept 2013 R117,325,593.90
Affairs 700mm welded steel pipe,
CONSTRUCTION OF 2.7km 500mm dia. welded steel
THE ACORNHOEK Mr. J. Jooste pipe and 2,8km of 400mm dia.
BULK PIPELINE welded steel pipe incl.
Tel: 031 759 7478 earthworks and concrete works
Cell: 082 458 7566
Contract no. Department of Water Construction of 2.7km of 700 Jan 2012 June 2013 R31,628,968.47
W0034WTE Affairs dia. steel pipeline
Contract no. Bigen Africa Construction of 58km of 1100 March 2011 June 2013 R688,034,369.18
TCTA-06-001 dia. steel pipe and 13km of 800
Mr. Corrie Marx dia. steel pipe as well as pump
CONSTRUCTION OF Tel.: 082 881 7853 station 1500kW (3 pumps)
THE KOMATI
WATER SCHEME
AUGMENTATION
PROJECT
Contract no. City of Tshwane Construction of Moreletspruit Aug 2009 Nov 2011 R72.620.710
CB26/2009 Outfall Sewer: Pipe diameter
Mr. J. Wessels 1200mm to 900mm = 4km
AUGMENTATION
OF THE Tel: 012 358 7638
MORELETASPRUIT
OUTFALL SEWER
PHASE 2
REHABILITATION Department of Water Refurbishment of steel piping May 2010 July 2011 R37.437.770
OF THE VALVE Affairs and specials and concrete
CHAMBERS ON THE chamber structures
WESTOE TO Mr. R. Hill
JERICHO PIPELINE
(PHASE 2) Tel: 012 336 8514
GAS PIPELINE Sasol Gas Limited 700m of 400m diameter gas Aug 2009 Feb 2011 R13.000.000
DEVIATION pipeline deviation
ACROSS NATIONAL
ROUTE N17 NEAR
THE R508 AND N17 Mr. B Mhlotshana
ROAD CROSSING Tel: 011 865 8628
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Contract no. W9895 Department of water 1 km of 1900mm diameter steel April 2009 August R45.273.173
Affairs pipeline 2009
GAMTOOS SIPHON
– INSTALLATION, Tel. 012 336 8514
EARTHWORKS &
CONCRETE WORKS
Contract no. City of Tshwane Construction of concrete sewer Sept 07 Sept 09 R35.000.000
CB216/2006 pipeline with concrete works
Mr J. Wessels and associated earthworks
MORELETASPRUIT Tel: 012 358 7638 8,5km of 900mm to
OUTFALL SEWER 1200mm dia. pipeline
PHASE 1A
Contract no. W9179 Department of Water Rehabilitation of 26,9 km of June 2007 June 2008 R37.437.770,31
Affairs 900mm diam steel pipeline.
REHABILITATION
OF THE JERICHO
DAM TO Mr Roy Hill
ONVERWACHT Tel: 012 336 8514
RESERVOIRS –
SOUTH PIPELINE
Contract no. City of Tshwane Construction of sewer 1,2km of July 2007 September R34.903.000
CB318/2006 pipeline of 1800m diameter and 2008
Pipe Bridge
CONSTRUCTION /
AUGMENTATION Mr Johann Wessels
OF THE Tel: 012 358 7638
PIENAARSRIVER
OUTFALL SEWER:
SECTION
MAMELODI
Contract no. City of Tshwane Construction of sewer tunnel July 2005 Jun 2008
C78/73210 770 m long, 3,0 m high &
3,4km of pipeline of 1500mm
CONSTRUCTION / and 1800m diameter.
AUGMENTATION Mr Johann Wessels R37.000.000
OF THE Tel: 012 358 7638 Tunnel component R44.000.000
PIENAARSRIVER Pipeline component
OUTFALL SEWER:
SECTION
MAMELODI
LINDEN 1 & 2 Johannesburg Water Construction of 300m steel by- May 2006 Nov 2006 R1.450.000
RESERVOIRS pass pipework
Juliet Bologo
Tel: 011 688 1400
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Contract no. City of Tshwane Construction of Atteridgeville Feb 2005 Nov 2005 R9.115.456
C78/43107 outfall sewer 1.1 km 900-1050
Mr Izak de Villiers dia. Sewer, 260m pipe jacking
ATTERIDGEVILLE Tel: 012 358 8055 & concrete works
OUTFALL SEWER
PHASE 3
PRETORIA WEST
RAND WATER Rand Water The earthworks and the July 2004 May 2006 R7.103.772
ZWARTKOPJES construction of valve chambers
PUMPSTATION Mr. Manfred Aust for the 1.6 km 2100mm
(ALBERTON) Tel: 011 682 0911 diameter steel ring main.
LEEUWKOP RELIEF Johannesburg Water 4km of 1500mm concrete sewer June 2003 November R52.000.000
OUTFALL SEWER pipe, 600m of tunnel and 237m 2004
(Johannesburg) Mr. Paul Müller of bridge structure
Tel: 6881400
Mr W.J. Halkerston
011-4076585
FRANCISTOWN Minister of Govt. and Construction of new Sewage February August R50.000.000
New Sewage Land purification works in Joint 2000 2001 Our portion
Purification Botswana Venture with Stefanutti & R13.400.000
Works Bressan
Mr Hetolang
09267-309953
EMPANGENI BULK Mhlathuze Water Construction of 13,52 km of January October R 15.900.00
WATER SUPPLY 800,600,450 mm diameter steel 1999 1999 (excluding value
Mr. Rob Buller welded pipeline of pipes)
035-9021020
RUSTENBURG Midwest for Civil Work for 17 km of 1100, January September R 4.400.000
PIPELINES MAGALIES 900 and 700mm steel Pipeline 1999 1999
WATER
Mr. Mi. Johnston
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Road Crossing for Protekon 500 m of 355 mm diameter steel December December R 400.000-
LANGLAAGTE PO Box 8135 oil pipeline for road crossing 1992 1992 (excluding value
RUSTENBURG Elandsfontein of pipes)
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Eden Park Eden Park Construction of 3km of 600mm May 1991 August R629,700.
Municipality diameter steel pipeline 1991
Venter Grobler
Contract R.W. 1737 Rand Water Excavation and backfilling February April 1991 R629,700.
Meredale Johannesburg trenches for 2800m of 1400mm 1991
Mr. Alan Tonks NB steel rising main
Tel: 682-0911
Contract TE9/89 Brakpan City Council Construction of 13,5,km of March 1990 May 1991 R6,779,226.
Brakpan Stewart Scott concrete sewer pipes from
Mr. Ian Gibson or 450mm to 1050mm diameter
See page 14 of Mr. Bill Alexander
brochure
Tel: 780 0611
BRUMA EXT. PHASE City of Johannesburg Construction of 6.2km of outfall April 1989 November R7.000.000
2 OUTFALL SEWER Main Contractor:- sewer 2000mm diam. concrete 1990 (value of pipes
Southern Pipeline pipes excluded)
011-903-8454
Mr J.C. Perro
BRUMA EXT. PHASE City of Johannesburg Construction of 3700m of August 1988 November R5.500.000
1 OUTFALL SEWER Main Contractor:- 2300mm of reinforced concrete 1989 (value of pipes
Southern Pipeline pipes excluded)
See page 12-13 of 011-903-8454
brochure Mr J.C. Perron
Contract W-0083 Water Affairs/Hall Excavation, backfilling and civil August 1989 October R545,118.
Scheiding pump station Longmore work for the 740m of 1800mm 1989
near P.K. LeRoux dam Mr. E. Sedlmeiecr NB steel rising main
O.F.S (retired)
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Contract N31/87 Boksburg City Construction of 9,1km of April 1987 May 1988 R7,527,400.
Boksburg Council 1200mm and 1350mm diameter
Stewart Scott concrete sewer pipe including a
See pages 10-11 of Mr. Ian Gibson or 276m long concrete pipe bridge.
brochure Mr. Bill Alexander
VAAL Rand Water Board Excavation, backfilling and civil May November R 3 000 000-
TRIANGLE PO Box 1127 JHB structure for 23km of 2300mm 1986 1988
Tel (011) 682 0911 diameter steel pipeline
See page 16 of
brochure
CISKEI Hall Longmore Construction of 14km steel May March R 817 000-
PO Box 4029 welded gravity main in 700mm 1986 1987
Luipaardsvlei 600mm and 500mm diameter
Contract RW 1562 Rand Water Excavation and backfilling for August 1985 February R440,000.
Arcon Park Johannesburg 8400m of 800mm steel ater 1986
Vereeniging Mr. Alan Tonks pipeline for Arcon Park-
Houtkop-Langerand
See page 15 of Tel: 682-0911
brochure
Kriel to Kendall Power Department of Water Construction of 38km of January September Approximately
Station Affairs 900mm and 1200mm NB steel 1985 1985 R4,000,000
Mr. Alex Bell or Mr. rising main to Kendall power (excluding value
Roy Hill station of pipes)
Contract W8310 Department of Water Construction of 6,8km of April 1984 September R1,240,423.
Heyshope Dam Affairs 1820mm OD Heyshope rising 1984 (excluding value
Mr. Alex Bell or main of pipes)
Mr. Roy Hill
Tel:012-3368514
Contract RW 1515 Rand Water Excavation, backfilling and civil January June 1984 R310,073.
Selcourt-Nigel Johannesburg structure for the 8900m of 1984
Mr. Alan Tonks 900mm NB steel pipeline.
Tel: 682-0257
ROODEPOORT Rand Water Board Excavation and backfilling for November April R 350.000-
Johannesburg 3,5 km of 900 mm diameter 1983 1984
steel pipeline
Contract RW 1488 Rand Water Excavation and backfilling for August 1983 October R230,000.
Lethabo Power Station Johannesburg the main supply pipeline to 1983
Lethabo Power Station 3km of
Tel: 682-0257 1500mm NB
NAME AND NAME AND BRIEF DESCRIPTION MONTH & SCHED. ESTIMATED
LOCATION ADDRESS OF OF WORKS YEAR COMPL. FINAL
OF PROJECT EMPLOYER STARTED DATE COST
Emergency Water Water Affairs & Hall Excavation, backfilling and civil August October R 800 000-
Supply for Longmore PO Box work for 12km of 800mm 1983 1983
NEWCASTLE 4029 Luipaardsvlei diameter steel pipeline
MUNICIPALITY
STANDERTON Rand Water Excavation and backfilling of March 1983 July 1983 R120,567.
Contract RW 1442A Johannesburg trenches for 3,6km of 600mm
Zuikerbosch Mr. Alan Tonks and 800mm steel pipeline
Tel: 682-0257
Water Supply Scheme Water affairs / Hall 19 km of 1200 mm diameter August 1982 May R 1.200.000-
for TUTUKA POWER Longmore pipeline, excavation, backfilling 1983
STATION Box 4029 and civil work
Luipaardsvlei
ZUIKERBOSCH Rand Water Board Excavation and backfilling of May July R 110.000-
Johannesburg 1.5 km of 1800 mm diameter 1982 1982
steel pipeline
Water supply for Water affairs / Hall 27 km of 900 mm diameter September August R 1.500.000-
VAAL GAMAGARA - Longmore pipe, excavation and backfilling 1981 1982
SISHEN Box 4029
Luipaardsvlei
BRAKPAN Rand Water Board Excavation and backfilling of August January R 321.980-
Johannesburg 4235 m trench, construction of 1981 1982
valve chambers etc. 1200 mm
Tel (011) 682-0911 diameter
URANIUM Hall Longmore Excavation and backfilling for January June R 64.000-
ENRICHMENT CO Box 4029 3km steel water pipeline 1980 1980
Luipaardsvlei
FINCH DIAMOND Hall Longmore Excavation and backfilling, January March R 35.000-
MINE Box 4029 concrete work for 1,8 km of 324 1980 1980
Luipaardsvlei OD
MS pipeline
Additional Water Hall Longmore 9 km of 900 mm diameter steel September May R 500.000-
Supply for Box 4029 pipeline, excavation, backfilling 1980 1981
MUNICIPALITY OF Luipaardsvlei and civil work
WITBANK
MEREDALE Rand Water Board Excavation and backfilling of 3 January April R 120.000-
RESERVOIR Johannesburg km of 900 mm diameter pipe 1980 1980
Meredale Tel (011) 682-0911
TONOTA Department of Water Construction of sewer treatment February June 2003 P38,633,884
Affairs, Botswana works, pump station, 13200m of 2002
G.L.S. outfall sewer and 2000m of
Mr. J. Dayton rising mains 500mm Ø
+267-3901128 comprising of two steel tank
reservoir
FRANCISTOWN Ministry of Local Construction of new purification January October 34% of
Government, Lands works in joint venture with S&B 2000 2002 P40,869,144
and Housing, Botswana
Stewart Scott
International
Mr. D. Main
+267-3952557
GABORONE WEST Morteo-Condotte 15 km of outfall sewer from 375 October July P 22 million
Phase 3 09 267 356-378 to 600 mm diameter, 17 km of 1991 1993
BOTSWANA ductile iron water pipeline from
400 mm to 700 mm diameter,
75 km of sewer reticulation 160
mm diameter100 km of water
reticulation from 63 mm to 110
mm diameter