1. The document provides a job safety analysis for deshuttering of a column. It identifies hazards such as untrained workers, falls, falling material, and working at height. 2. Risk control measures include using trained workers, conducting toolbox talks, providing fall protection like harnesses and life lines, erecting approved scaffolding, and ensuring proper lighting for night work. 3. Sign off is required from site supervisors, engineers, and HSE officers to ensure all safety precautions are in place before starting the high risk deshuttering work.

Uploaded by

Viron Baxhia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views1 page

Deshuttering of Column JSA HSE Professionals

1. The document provides a job safety analysis for deshuttering of a column. It identifies hazards such as untrained workers, falls, falling material, and working at height. 2. Risk control measures include using trained workers, conducting toolbox talks, providing fall protection like harnesses and life lines, erecting approved scaffolding, and ensuring proper lighting for night work. 3. Sign off is required from site supervisors, engineers, and HSE officers to ensure all safety precautions are in place before starting the high risk deshuttering work.

Uploaded by

Viron Baxhia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

JSA (Job Safety Analysis) Sheet

Activity Name:- Deshuttering of Column Ref-

Location:- Date

Sr.No. Sub-Activity Name Type Of Hazard Risk(s) Involved Risk Control measures
Manpower Untrained worker,lack Only inducted worker shall be deputed at the work place.
1 Personal injury
Mobilization of skill awareness Given Tool Box Talk to all workers.

Area barricade to restrict entry.

Ensure full body safety harness anchor by each workmen.

Engaged trained & experienced psreson on the job.


2 Deshuttering Fall of material Personal Injury
Maintain good house keeping at work site.
Ensure all hand tools are inspected.
Conduct tool box talk before starting the work.

Ensure recommended PPE should be worn the worker such as safety


Unispected FBSH Fall of person
shoes,helmet, hand gloves goggles & dust mask.
Without edge Inspected FBSH having double lanyard, shockabsorber should be
Fall of person
protection provided.
3 Working at height Life line, hard barication and safety net should be provided on edge.
Unapproved scaffold Fall of person

Scaffold shall be erected on even surface by providing base plate, side


support, and ledger at every at 500mm with side supports wherever
height increases beyond 2 mtrs .

Night work permit to be taken from concern engg.and safety dept.


Darkness, fall of
Personal injury, Ensure proper illumination during dark hours.
4 Work during dark hours person, fall of
damage to property Electrical cable should lead min 2 m height. No exposed electrical
machinery
wire.Earthing.
Route shall be illuminated.

Name & Signature of Site Engineer / Supervisor :___________