ERRATUM FOR Bid No. 2480GS - 210922
ERRATUM FOR Bid No. 2480GS - 210922
40 Heronmere Road
PO B Box 38766 Tel +27(0) 11 490 7000
Reuven Booysens Fax +27(0) 11 490 7590
Johannesburg 2016
www.citypower.co.za
TENDER ERRATUM
Bid No. 2480GS - DESIGN, SUPPLY, INSTALLATION & COMMISSIONING
OF SOLAR ROOFTOP PV & BATTERY STORAGE SYSTEMS FOR CITY
POWER
• On page 78 of the tender document 5.2 Specification details has been amended
refer to the document below.
• CP_TSSPEC_303 REV 0 Specification for photovoltaics Modules and
CP_TSSTAN_150_Standard for Battery Energy Storage Systems has been
amended as well. Refer to the document below
The specifications has now been revised and prospective bidders are advised to download
the updated specifications from the City Power Website.
Sincerely
…………………
Prudence Hlatshwayo
Supply Chain Management
Non-Executive Directors: D Gibson (Chairperson of the Board), J du Plessis, D Hunt, M Jojozi, N Kgope, P Mabece, M Mashabela, M Mello, B Mpangalasane
Executive Director: T Mashava (Chief Executive Officer), Company Secretary: M Smith
Registration number: 2000/030051/30 - VAT number: 4710191182
INTRODUCTION
5.2: SPECIFICATIONS
5.2.1 INTRODUCTION
City Power intends to install grid tied solar PV system with battery storage at its Head office
in Reuven. The power produced by the solar power system is to be injected into the
reticulation system at City Power Reuven and is to be used for re-charging the energy
storage system and to power the facility.
The energy storage system is to be used for daily energy arbitrage or as backup power for
critical loads (situated at City Power Reuven head office block and B block) in the event of
power interruption (see appendix A for the City Power Reuven, Head Office load profile to
determine the baseline energy consumption of critical loads).
The battery storage is required to cater for up to three (3) hours of power interruption as
well as up to three (3) hours of peak demand period shifting (morning and evening peak
demand period). The control system must cater for both modes of operation, the default
program mode being daily arbitrage, which may be suspended to cater for load shedding
avoidance on a daily basis.
The battery will be charged by the solar PV or by the grid. The control system must cater
for both re-charging modes, the operational mode will be determined by the economics
associated with the cost of solar versus the cost of grid power. At minimum, the battery
storage system shall be capable to run as a power island.
Bidders shall provide all the tests certificate as per the specifications and standards
provided by City Power in the bid document, including certificate of compliance for the
inverter as per NRS 097-2-1, electrical certificate of compliance from the department of
labour. The bidder shall be fully responsible for submitting all the necessary tests
certificates and certificates of compliance including those that might have been omitted in
the bid document.
Page 2 of 4
5.2.2 SCOPE OF WORK
The scope of work for the Solar PV system with battery storage shall include the following
principal elements. The bidder shall be fully responsible for identifying and providing any
and all other additional equipment, components, and services necessary to install a fully
functional Solar PV system with battery storage.
Page 3 of 4
5.2.3 DOCUMENTATION
The bidder shall furnish complete documentation that will be used for determination of
contract compliance, as well as operation and maintenance of the solar PV system with
battery storage. The documentation shall be in English, well detailed and instructive. At a
minimum, these documentations shall consist of the following:
5.2.3.1. Conceptual design package for City Power review,
5.2.3.2. Equipment specifications,
5.2.3.3. Solar PV system with battery storage performance specifications,
5.2.3.4. Complete commissioning plan including test and start-up procedures for
City Power review,
5.2.3.5. Operations and maintenance manual, for all equipment and sub-systems
5.2.4 TRAINING
Training of key City Power personnel shall be required for the daily operation and
preventative maintenance/trouble maintenance/troubleshooting of the Solar PV system with
battery storage at commissioning stage. This training shall be provided by the Contractor
and priced for in the bid submission. The training programme shall cover all aspects of
operations and preventative maintenance/troubleshooting of the system and sub-
components. It shall be preferable to have a combination of theoretical and practical
training for the key personnel as identified by City Power.
The bidder must provide a comprehensive project plan for the Solar PV system with battery
storage implementation.
5.2.6 Cost
The Bidder shall provide a cost proposal that includes the cost of all projected labour,
travel, equipment, and other direct costs required to perform the activities listed in the
scope of works.
Page 4 of 4
REFERENCE REV
TABLE OF CONTENTS
Page
FOREWORD………………………………………………………………………………………………..3
INTRODUCTION………………………………………………………………….………………….….…4
1 SCOPE………………………………………………………………………………….………………...4
2 NORMATIVE REFERENCES……………………………………………….……………………….…4
3 ABBREVIATIONS…………………………………………..……………………………….………......4
4 REQUIREMENTS…………………………………………………………………………….……….....4
5 MATERIAL AND INSTALLATIONS………………………………………….……………………......6
6 ROUTINE MAINTENANCE OF PHOTOVOLTAIC MODULES………………………...............…7
7 TRAINING……………………………………...……………………………………………………...….8
8 QUALITY MANAGEMENT………………………………………………………………………...…...9
9 HEALTH AND SAFETY…………………………………………………………………………...…....9
10 ENVIRONMENTAL MANAGEMENT…………………………….…………………………...……...9
TECHNICAL SCHEDULE……………….……………………………………………….………………10
ANNEX A – BIBLIOGRAPHY………………………………………..………….….............................13
ANNEX B - REVISION INFORMATION……………………………………………............................14
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 2 OF 14
FOREWORD
INTRODUCTION
City Power has implemented sustainable energy solutions to offset the energy usage of
their depots by using more sustainable energy solutions. This is in accordance with the
current IRP/VUCA strategy plan towards a greener economy to lower the energy demand
of City Power and City owned buildings from the grid.
1. SCOPE OF WORK
The document covers only the requirements for the equipment to be used, i.e., solar PV
modules. The detailed design of plant, Procurement, Construction, Commissioning is not
covered in this document. All works shall be executed as described in the specifications,
as well as all other supplies or works as deemed necessary for a complete and functional
Solar PV system. The work shall be carried out in compliance with relevant
Environmental Requirements.
2. NORMATIVE REFERENCES
The following documents contain provisions that, through reference in the text, constitute
requirements of this specification. At the time of publication, the editions indicated were
valid. All standards and specifications are subject to revision, and parties to agreements
based on this specification are encouraged to investigate the possibility of applying the
most recent editions of the documents listed below.
3. ABBREVIATIONS
DC- Direct current
EVA- Ethylene vinyl acetate
IRP – Integrated resource plan
kWp- Kilowatt peak
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 4 OF 14
PV-Photovoltaic
MW-Mega watt
STC –Standard test condition
VUCA-Volatility, uncertainty, complexity, and ambiguity
Wp- Watt peak
4. REQUIREMENTS
4.1 General
This chapter describes the detailed specifications of the required Solar PV Module for
the project. The Contractor is responsible for ensuring that each line item specification is
adhered to in the provision of all equipment and material.
The PV Modules specified shall be a low Iron glass laminate using crystalline technology
with a minimum of 60 cells. The glass laminate shall use a high grade EVA laminate
material. Preferably, fly lead interconnects shall be used inclusive of an IP65 or IP67 or
IP68 junction box rated which includes bypass diode protection. Furthermore, the PV
module shall be framed with a sturdy anodized Aluminium frame with easy mounting
holes and an earth connection.
4.2 PV MODULE
The Photovoltaic (PV) modules shall meet the following minimum requirements:
4.2.1 The module rated peak power shall be ≥ 355 Wp at STC (25°C). The peak
power shall be of the manufacturer’s name plate data sheets for each
individual module
4.2.3 Crystalline modules shall meet SANS 61215 of class II: Crystalline (mono)
PV modules — Design qualification and type approval.
4.2.5 The module shall have a minimum performance guarantee of 80% for the
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 5 OF 14
4.2.7 The PV module shall be on the PVEL and PV-Tech score or shall pass
their tests in addition to SANS 61215.
4.2.8 The tolerance of the rated output of the PV modules offered shall be -
0/+5%
4.2.9 Sample of Flash test reports for modules shall be made available to City
Power with the actual certificates of modules installed prior to installation
stage
4.2.11 Each module shall be factory equipped with output cables which are
connected in a weather proof junction box. The cables shall be a suitably
rated solar cable.
4.2.12 The modules shall be framed with an anodised aluminum frame in such a
way as to allow secure fastening to the PV array mounting structure.
4.2.13 All PV modules shall be of the same type, size and age hence
interchangeable.
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 6 OF 14
5.1.2 The mechanical stress test according to SANS 61215, the module shall be
mounted as per the manufacturer’s and load of 2400 Pa (push and pull 3 times)
is applied
5.1.3 Sufficient distance between the modules to avoid needless loads shall apply
5.1.4 Module clamps shall be correctly selected and fit securely on the module frame
5.2 Connectors
5.2.1 The solar PV connectors shall be MC4 male and female connector type
5.3 Cables
5.4.1 Module cables and connectors shall not lie on the roof
5.4.2 UV protection shall be used if cables are exposed directly to the sun
5.5.1 Cable laying shall be done under consideration of fire protection and existing
thermal installation
5.7 Hooks
5.7.1 Number and position of the hooks shall be determined by structural analysis,
rafter spacing and tile dimensions.
5.8.1 Rail cutting: preferably on the ground to avoid metal scarf on the roof
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 7 OF 14
Maintenance for the Solar PV systems shall be done monthly. This includes cleaning the
panels and checking all system components. Any issues raised with system components are
brought to awarded contactors’ attention and then rectified via a report after site inspection.
Maintenance may be required at a higher rate should the performance of the system dip below
the desired outcome.
The PV modules shall be constantly monitored, and informed via email if any faults occur.
There shall be a 24 hour reaction time to any fault condition.
Maintenance of the PV modules shall be cleaned monthly to keep the production high and the
following maintenance shall be done:
6.2.1 Panel cleaning (cleaned with purely water and micro-fibre brushes)
6.2.2 String test (tested with 1000V multimeter)
6.2.3 Infrared images of electrical connections
6.2.4 Overall system overview (cracks or loose connections etc.)
The annual service report shall provide preventative maintenance procedures to ensure the
validity of any warranties on the system. It shall comprised mechanical and a portal (any
approved/accepted software) report.
i) Check all panels for damage/cracks, water ingress and potential hot spots.
ii) Inspect general condition of roof sheet structure and report any signs of loose
connections.
iii) Torque all middle and end clamps to manufacturers specifications using torque
wrench or similar.
iv) Check for corrosion on any enclosures structure.
v) Check for signs of animal drops in array.
vi) Check labelling on cable trays and cables in order.
6.4 Earthing:
6.4.1 Check that all earthing along trunking/cable trays is present and tight.
6.4.2 Lightning protection: check finials and other protection devices are in good
condition
6.4.3 Conduct grounding tests on all earthing points
7 TRAINING
7.1 The suppliers shall provide comprehensive training courses on the configuration,
installation, operation and maintenance of solar PV system.
7.2 The suppliers shall provide technical support on solar PV system’s and equipment
queries for the duration of the contract.
8. QUALITY MANAGEMENT
A quality management system shall be set up in order to assure the quality during
manufacture, installation, removal, transportation and disposal of scrap material/Waste/E-
waste .Guidance on the requirements for a quality management system may be found in the
following standards: ISO 9001:2015. The details shall be subject to agreement between the
purchaser and supplier.
A health and safety plan shall be set up in order to ensure proper management and compliance
during manufacture, installation, removal, transportation and disposal of scrap
material/Waste/E-waste. Guidance on the requirements of a health and safety plan shall be
found in OHSAS 18001:2007/ ISO 45001:2018 standards. The details shall be subject to
agreement between City Power and the Supplier.
1.1 Manufacturer
2 PV Module Characteristics
Any deviations offered to this specification shall be listed below with reasons for deviation. In addition,
evidence shall be provided that the proposed deviation will at least be more cost- effective than that
specified by City Power.
Item Sub-clause of ? Proposed deviation
No.
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 13 OF 14
ANNEX A – Bibliography
PV GREECARD Training Material: 2019
SPECIFICATION FOR SOLAR PHOTOVOLTAIC REFERENCE REV
MODULES CP_TSSPEC_303 0
PAGE 14 OF 14
Table of Contents
FOREWORD ........................................................................................................................................................................3
INTRODUCTION ................................................................................................................................................................4
1. SCOPE ....................................................................................................................................................................4
4. REQUIREMENTS .................................................................................................................................................5
4.1. General.................................................................................................................................................................5
4.2. Environmental Conditions....................................................................................................................................5
4.3. Battery management system (BMS) ......................................................................................................................7
4.4. Power conversion system (PCS)/BESS Inverter ...................................................................................................7
4.5. Balance of System ................................................................................................................................................8
4.6. BESS Management and Control ...........................................................................................................................8
4.6.1. General .............................................................................................................................................................8
4.6.2. Energy management system (EMS) .................................................................................................................9
4.6.4. Human Machine Interface (HMI) ...................................................................................................................10
4.6.5. GPS Time Synchronisation Device ................................................................................................................11
4.6.6. Power Supplies Requirements ........................................................................................................................11
4.6.7. System Operation ...........................................................................................................................................11
4.7. EMS/BESS SCADA gateway ..............................................................................................................................11
4.8. Safety Requirements ...........................................................................................................................................11
5. LABELLING ........................................................................................................................................................12
6. TESTS ...................................................................................................................................................................12
6.1. General...............................................................................................................................................................12
6.2. Type Test ............................................................................................................................................................13
6.3. Factory acceptance test ......................................................................................................................................13
6.4. Site acceptance test ............................................................................................................................................13
6.5. Functionality and Performance Tests ................................................................................................................14
STANDARD FOR ENERGY STORAGE REFERENCE REV
SYSTEMS CP_TSSTAN_150 0
PAGE 2 OF 17
FOREWORD
INTRODUCTION
Energy storage system (ESS) can be broadly defined as a system or technology that enables energy
produced during a certain period to be used at a different period. Energy storage offers a range of
opportunities/applications for standalone developers, consumers, generators as well as network
operators, and therefore an opportunity for City Power.
1. SCOPE
This specification covers BESS requirements for grid-connected and off-grid storage applications
suitable for City Power.
The supplier/contractor shall be fully responsible for selecting suitable energy storage systems for the
City Power grid and its satisfactory performance in service.
2. NORMATIVE REFERENCES
The following document contain provisions that, through reference in the text, constitute requirements
of this standard. At the time of publication, the editions indicated were valid. All standards and
specification are subject to revision and parties to agreements based on this standard are encouraged
to investigate the possibility of applying the most recent editions of the documents listed below.
SANS 62040-1, Uninterruptible power systems (UPS) Part 1: General and safety requirements for UPS
SANS 62040-1-2, Uninterruptible power systems (UPS) Part 1-2: General and safety requirements for
UPS used in restricted access locations
IEC 62933-2-1 Ed. 1: Electrical energy storage (EES) systems – Part 2-1: Unit Parameters and Testing
Methods – General specification
IEC 62619, Secondary cells and batteries containing alkaline or other non-acid electrolytes – Safety
requirements for large format secondary lithium cells and batteries for use in industrial
applications1
IEC 62620, Secondary cells and batteries containing alkaline or other non-acid electrolytes – Secondary
lithium cells and batteries for use in industrial applications
IEC 62897, Stationary Energy Storage Systems with Lithium Batteries – Safety Requirements
SANS 62109-2, Safety of power converters for use in photovoltaic power systems - Part 2: Particular
requirements for inverters
CP_TSSPEC_017, Specification for Miniature Circuit Breakers
CP_TSSPEC_018, Specification for Moulded Case Circuit Breakers
CP_TSSPEC_214, Specification for Protection Relays
4. REQUIREMENTS
4.1. General
4.1.1. The energy storage system shall be of Lithium-Ion or Vanadium Flow battery technologies and
shall be suitable for grid and off-grid applications requirements in table 1.
4.1.2. The battery system shall have life expectancy of 15-20 years rating under normal operating
conditions, suitable for outdoor installation, and a battery management system (BMS).
4.1.3. The system shall be modular and scalable.
4.1.4. The batteries shall be supplied in robust containers.
4.1.5. Battery string connectors shall be insulated and configured for single and multiple unit
installations.
4.1.6. Balancing of a string/module shall be done online without affecting the operation and required
availability of the system.
4.1.7. Any faulty string/module shall be flagged and isolated without affecting the operation and required
availability of the system.
4.1.8. It shall be possible to introduce improved battery technologies / models in future, whether for
augmentation or upgrading purposes, without changing the connection of the existing battery
modules. The Service provider/contractor shall state how this “future-proofing” shall be
accommodated in existing designs in terms of the Energy Management System (EMS), Battery
Management System (BMS) and Power Conversion System (PCS).
4.2. Environmental Conditions
The system shall be suitable to be operated under the following conditions:
Application Description Response Typical discharge Typical size Charge / Discharge behavior
Time time
Peak shaving Peak shaving to reduce NMD Minutes 2 – 4 hours 100 kW – 10 MW 50 – 500 cycles per year
Energy Arbitrage Generating energy at low-cost periods, Minutes 1 – 6 hours 1 kW – 1 MW 50 – 250 cycles per year
storing, and selling at peak periods.
Load levelling / peak Reducing limited-time peak loads to Minutes 1 – 8 hours 1 – 100 MW 10 – 365 cycles per year
shaving for grid assist in maintaining thermal load and
upgrade deferral voltage within planning limits, thereby
deferring network upgrade.
Electrification (hybrid Off-grid and grid tied systems. Inverter Minutes 2 – 15 hours 10 kW – 1 MW 365 cycles per year (charges
PV and storage) must be capable of grid forming in the during middle of day,
case of grid tied systems. discharges morning and
evening)
Reliability Micro grid / islanded operation during Minutes 1 – 12 hours 1 – 10 MW < 10 cycles per year
planned or unplanned system outages.
Inverter must be capable of grid
forming.
Frequency regulation Automatic absorption or supply of Milliseconds 2 minutes – 1 hour 1 MW – 1 GW 1 000 – 10 000 cycles per
power during a frequency deviation year
event
Renewables smoothing For small fluctuations in intermittent Seconds 30 minutes – 6 hours 1 – 100 MW 250 – 10 000 cycles per year
renewable energy generation.
Load following Used to supply or absorb power to Milliseconds 15 minutes – 1 hour MW – 100 MW 250 – 10 000 cycles per year
compensate for system load variations –1s
around the forecast level.
STANDARD FOR ENERGY STORAGE REFERENCE REV
SYSTEMS CP_TSSTAN_150 0
PAGE 7 OF 17
The contractor shall include a description of the intended energy storage application/s as requested by
City Power. This shall include details and sizing calculations (and or simulations) of how the proposed
BESS will meet the anticipated operation scheme for each application. The BESS capacity
apportionment to provide the different stacked benefits shall be tabulated and additional benefits shall
be stated. Calculation factors to account for operating temperature, expected growth, various discharge
rates under various control modes; capacity degradation etc. shall be stated.
4.3. Battery management system (BMS)
4.3.1. The BMS shall be designed to ensure automatic, unattended operation of the BESS.
4.3.2. The BMS shall provide the necessary monitoring and control to protect the battery
cells/module/string from out of tolerance or unsafe operating conditions.
4.3.3. The BMS shall automatically control the safe charge and discharge of the individual
cells/modules/strings.
4.3.4. The BMS shall automatically control balancing between cells/modules/strings (where applicable)
to ensure optimised state-of-charge, state-of-health and life expectancy.
4.3.5. The BMS shall automatically monitor cell/module/string heath and provide critical safeguards to
protect the batteries from damage.
4.3.6. The BMS shall monitor and report in real time (via SCADA) on the following parameters for each
lowest maintainable unit / module:
a) State-of-Charge (SoC)
b) State-of-Energy (SoE)
c) State-of-Health (SoH)
d) Battery temperature
e) Charge current
f) Discharge current
g) DC bus voltage
h) Cell / Module / Stack voltages (Minimum and maximum)
i) Cell / Module / Stack / Electrolyte temperatures (Minimum and maximum)
4.3.7. The BMS shall monitor and report in real time (via SCADA) on the following alarm or warning
conditions for each lowest maintainable unit / module:
a) Over-temperature
b) Overcharge
c) Over-discharge
d) Undercharge
Safety management functions and operational management functions shall be embedded at different
levels of the BESS.
STANDARD FOR ENERGY STORAGE REFERENCE REV
SYSTEMS CP_TSSTAN_150 0
PAGE 9 OF 17
4.6.3.12. There shall not be redundant communication between the SCADA control centres and the EMS
which shall be taken into account in the redundancy design of the EMS (e.g. switch over of
SCADA communications between the main EMS and standby EMS).
4.6.3.13. Manual (local and remote) intervention shall always be possible at any stage of operation in
compliance with the following priority assignment: Protective commands shall have priority over
manual command and manual commands shall prevail over automatic commands.
4.6.3.14. The control algorithms shall be designed to fulfil primary use cases and optimise stacked
benefits.
4.6.3.15. The EMS shall be capable of computing and displaying business case benefit in the form of
cumulative revenue earned and operating costs incurred, for the life of the asset. Revenue
shall be based on contracted earning formulas and costs shall be based on energy costs and
operating and maintenance costs. These figures shall be included in the reporting and analytics
capability of the installation.
4.6.3.16. The EMS shall be capable of keeping track of how the BESS perform compared to warranty
requirements and report on exceptions.
4.6.3.17. Taking into account the manufacturer’s expected lifespan of the installed battery technology,
the time and date at which the unit was commissioned, the number of charge and discharge
cycles, the depth of discharge etc. the EMS shall be able to indicate the estimated remaining
lifespan of a battery cell, rack and/or string.
4.6.3.18. The EMS shall also indicate based on the estimated lifespan what the maximum
charge/discharge capability of each battery cell, rack and/or string is as a percentage (with
100% representing the designed charge/discharge capacity of the battery when new).
5. LABELLING
The system description shall cover the following information:
5.1. BESS type / classification (either Lithium-Ion or Flow battery).
5.2. BESS Chemistry.
5.3. Identify and classify any dangerous substance/s in the BESS as per SANS 10228. Any
claims of no hazardous / dangerous substances shall be supported with applicable
certification or expert, 3rd party assessment reports.
5.4. Battery Nameplate Energy rating [kWh] – from smallest cell, module, string, container to
full system.
5.5. Battery Nameplate Power rating [kW] – from smallest cell, module, string, container to full
system.
5.6. Number of battery cells, modules, strings and how they are aggregated to the complete
systems.
5.7. Information on the internal cells or stack are to be provided including specifics of the
technology, cell format, electrolyte, electrical rating of the cell or stack, and how many are
contained within a full battery.
5.8. Internal resistance (i.e. the resistance to power flow of the ESS during charge and
discharge)
5.9. Tank configuration and sizes (for flow batteries). Labelling sub-section
5.10. A complete description (inclusive of their functions) of the balance of plant components
such as cooling systems, controls including BMS, pumps, etc.
5.11. Complete footprint [m2] – i.e. physical dimensions with all components in place. Labelling
sub-section
5.12. System placement configuration e.g. stacked or side-by-side or back-to-back, etc.
5.13. Battery manufacturer, model or part number. Labelling sub-section
5.14. Date of manufacture.
5.15. PCS manufacturer, model or part number, nameplate power rating [kW], modularity and
number of PCSs, hardware and software versions. Labelling sub-section
5.16. BMS supplier, model or part number, hardware and software versions. Labelling sub-
section
5.17. EMS supplier, model or part number, hardware and software versions
5.18. Photos, diagrams, drawings and schematics should be provided to give a complete
description of the full system.
6. TESTS
6.1. General
6.1.1. The supplier shall cover the cost of all testing required and is requested to provide City Power with
the details of when and where these tests will be conducted.
6.1.2. All type testing shall be done at accredited local test facilities or accredited international testing
authorities/facilities, unless otherwise permitted for specific BESS.
6.1.3. Only type tested and service proven BESS designs (all components) shall be tendered and
accepted for use by City Power.
6.1.4. Service provider/contractor shall submit all the required type test reports. Certification and type
test reports shall be applicable to the system/solution being proposed.
6.1.5. If the units offered have been tested for compliance with an internationally accepted standard, City
Power may accept those test reports in place of the tests covered by this specification. These type
test reports and alternative test standards shall be submitted with the service provider/contractor,
for City Power’s consideration. However, the Service provider/contractor shall state clearly the
difference between the requested standard and the offered standard by way of a tabulated
comparison. This shall also be noted on the deviation schedule.
6.1.6. The FAT, SAT and routine tests procedures shall be agreed to between City Power and the
manufacturer or supplier of the equipment.
6.1.7. The service provider/contractor shall provide FAT, SAT and routine/periodic tests procedures and
schedules for previous BESS projects that have been executed.
STANDARD FOR ENERGY STORAGE REFERENCE REV
SYSTEMS CP_TSSTAN_150 0
PAGE 13 OF 17
6.2.1. BESS component type test certificates and type test reports shall be provided in the tender
submission.
6.2.2. Type test reports and certification of the entire energy storage system, whereby the individual
components are integrated into the system providing overall system functionality shall be provided
in the tender submission.
The factory acceptance tests (FAT) are tests conducted at the manufacturers premises prior to
equipment release and dispatch to the customer. The tests are conducted on each BESS
unit/components to verify the manufacturer’s declared equipment performance criteria and rectify any
defects arising on the equipment prior to dispatch to the customer.
6.3.1. As a minimum, factory acceptance test certificates shall be provided for the following components:
a. Battery modules;
b. Power Converters;
c. Transformers
d. Control and Management systems.
6.3.2. The manufacturer or supplier shall perform a pre-FAT according to the accepted Factory
Acceptance Test (FAT) Procedure.
6.3.3. The pre-FAT and, FAT procedures shall include as a minimum the following:
a. Proposed FAT
b. Testing methodology and set up process
c. Tests to be performed
d. Test acceptance criteria.
6.3.4. The FAT shall only commence once City Power has approved this pre-FAT report and results.
The manufacturer or supplier and City Power shall agree upon a date when formal FAT shall
commence. The testing shall then be carried out in accordance with the FAT procedure.
6.3.5. In the event of any tests malfunctioning, City Power may elect to restart the complete test
procedure from the beginning.
6.3.6. City Power may elect to conduct an unstructured testing programme (Free-form Tests), at its
discretion, on the manufacturer or suppliers premises for a duration of two weeks. This two-week
period shall not include the time taken to repair any faults.
6.3.7. The manufacturer or supplier, at no extra charge to City Power, shall correct any errors detected.
6.3.8. Once City Power has satisfied itself that the system has passed the prescribed tests, the BESS
unit(s) shall officially be released for factory dispatch.
6.4.1. After delivery of the BESS unit to the pre-determined City Power site, the Supplier, assisted by
the City Power where agreed, shall install the equipment in a substation in accordance with the
applicable standards and OEM manuals.
6.4.2. The SAT procedures shall include as a minimum the following:
a. Proposed SAT
b. Testing methodology and set up process
c. Tests to be performed
d. Test acceptance criteria.
6.4.3. The manufacturer or supplier shall make available at no extra charge to City Power the relevant
hardware, software and/or system specialist.
6.4.4. For a period of one month after the successful completion of the formal SAT, the equipment shall
be subjected to a soak test.
6.4.5. In the event of any non-conformance being detected, the manufacturer or supplier shall be
required to commence the correction of the errors within a 72 h period. Only on completion of the
correction procedure, the one-month test and soak test period shall commence.
6.4.6. In the event that fundamental error(s) are detected and depending on the nature of the fault, City
Power may at its sole discretion elect to restart the SAT.
STANDARD FOR ENERGY STORAGE REFERENCE REV
SYSTEMS CP_TSSTAN_150 0
PAGE 14 OF 17
6.5.1. Performance of the BESS or subsystems shall be conducted by agreed to testing methodologies,
thereby verifying that the declared BESS parameters are in accordance with customer
applications and technical requirements.
6.5.2. Performance tests of the BESS shall conform to:
a) IEC 62933-2-1: Electrical energy storage (EES) systems – Part 2-1 and
b)IEEE Std 2030.3-2016 Standard Test Procedures for Electric Energy Storage Equipment and
Systems for Electric Power Systems Applications, whereby the BESS parameters, system
performance and system implementation shall be tested and verified at various life cycle phases
in the BESS development.
6.5.3. In compliance to IEEE Std 2030.3-2016 Standard Test Procedures for Electric Energy Storage
Equipment and Systems for Electric Power Systems Applications, the BESS system functionality
shall be proven at various phases of the BESS development.
6.5.4. The Service Provider/Contractor shall confirm conformance to the minimum following functionality
tests in Table 2 and deviations to the testing IEC/IEEE methodology or declared values shall be
provided in the deviation schedule.
7. QUALITY MANAGEMENT
A quality management system shall be set up in order to assure the quality during manufacture,
installation, removal, transportation and disposal of scrap material/Waste/E-waste .Guidance on the
requirements for a quality management system may be found in the following standards: ISO 9001:2015.
The details shall be subject to agreement between the purchaser and supplier.
8. ENVIRONMENTAL MANAGEMENT
An environmental management plan shall be set up in order to ensure the proper environmental
management and compliance is adhered to during manufacture, installation, removal, transportation and
disposal of scrap material/Waste/E-waste. Guidance on the requirements for an environmental
management system shall be found in ISO 14001:2015 standards. The details shall be subject to
agreement between City Power and the Supplier. This is to ensure that the asset created conforms to
environmental standards and City Power SHERQ Policy.
ANNEXURE A - BIBLIOGRAPHY