"Community Support Projects (public facilities/spaces)" According to Schedule below is approximately 28 days
3-Baseline Plan of Work to Complete a Community Support Projects (public facilities/spaces)
PROJECT NAME DURATION PROJECT START DATE PROJECT END DATE
Rehibiltation of (public facilities/spaces) 28 Days 12-02-24 10-03-24
ن ن
المعوقي حركيا اللبنان األشخاص
ي اإلتحاد
Done by Eng.Essam Alhayek
DAY MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN
Category
12-02-24
13-02-24
14-02-24
15-02-24
16-02-24
17-02-24
18-02-24
19-02-24
20-02-24
21-02-24
22-02-24
23-02-24
24-02-24
25-02-24
26-02-24
27-02-24
28-02-24
29-02-24
01-03-24
02-03-24
03-03-24
04-03-24
05-03-24
06-03-24
07-03-24
08-03-24
09-03-24
10-03-24
Task ID
Task
Task
Task Description Start Date End Date
Duration
Prepare PRELIMINARIES 1 12-02-24 12-02-24
0
Civil Work BLOCK WORK & PLASTER 7 13-02-24 19-02-24
1 2 3
X X X X X X X
DW DOORS & WINDOWS 5 19-02-24 23-02-24 X X X X X
Steel Steel Works 6 23-02-24 28-02-24 X X X X X X
Tiles FLOOR & WALL TILES 5 27-02-24 02-03-24
4
X X X X X
Elec ELECTRICAL WORKS 6 02-03-24 07-03-24
5
X X X X X X
Mech MECHANICAL WORKS 6 04-03-24 09-03-24
6
X X X X X X
Al+St Int Works 3 02-03-24 04-03-24
7
X X X
Conct.+Ramps EXTERNAL WORKS 5 05-03-24 09-03-24
8
X X X X X
Closing Project Cleaning and Handover 1 10-03-24 10-03-24
9