Vmware Vsphere Professional 8 Exam Dumps PDF (VCP DCV)
Vmware Vsphere Professional 8 Exam Dumps PDF (VCP DCV)
Question #1 Topic 1
An administrator is tasked with applying updates to a vSphere cluster running vSAN using vSphere Lifecycle Manager. Downtime to the ESXi hosts
The administrator has already completed the following steps and no errors have been returned:
Attached the new image to the cluster and run a compliance check against the image for the cluster.
Which two series of steps should the administrator perform to start the remediation of the cluster using the new image? (Choose two.)
A. 1. Use the Remediate option in vSphere Lifecycle Manager to remediate all of the ESXi hosts in the cluster in parallel.
2. Allow vSphere Lifecycle Manager to automatically control maintenance mode on the ESXi hosts.
2. Use the Stage option in vSphere Lifecycle Manager to stage the required software on all ESXi hosts one at a time.
2. Use the Stage All option in vSphere Lifecycle Manager to stage the required software onto all ESXi hosts one at a time.
2. Use the Stage All option in vSphere Lifecycle Manager to stage the required software onto all ESXi hosts in the cluster in parallel.
E. 1. Use the Remediate option in vSphere Lifecycle Manager to remediate all of the ESXi hosts in the cluster in sequence.
2. Allow vSphere Lifecycle Manager to automatically control maintenance mode on the ESXi hosts.
Correct Answer: AD
Selected Answer: CE
CE seems to be the correct answer. Generally you would want to patch a vSAN cluster a node at a time (sequentially) so you do not inadvertently
cause a storage outage in the cluster. Also, if you look in the link below, you cannot remediate a vSAN cluster in parallel mode:
Parallel remediation is deactivated by default, but you can enable it during remediation or in the vSphere Lifecycle Manager general remediation
settings.
You cannot remediate in parallel hosts in a vSAN cluster
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-26EB282E-AD1E-425A-B4CF-1D70C0DE3C8F.html
upvoted 13 times
Selected Answer: DE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-DD04A5FC-752C-405E-9771-69404A5CF105.html
upvoted 8 times
Selected Answer: DE
Cannot be answer A : a vSAN cluster cannot remediate all the hosts at the same time, it has to be update 1 by 1.
Cannot be answer B : It is useless to place the hosts in maintenance for staging
Cannot be answer C : The staging is done in parallel by default
So answers D and E :
- We let the hosts as-is
- We launch the staging, which is performed on all hosts in parallel
- Then we launch the Remediate All option : vLCM will put a host in maintenance and update it, and will continue sequencially.
upvoted 1 times
Selected Answer: DE
D & E are correct. B and C not correct because Staging occurs in parallel by default. A is not correct because Lifcycle Manager does not manage
entry/exit from maintenance mode when parallel mode is chosen.
upvoted 1 times
https://docs.vmware.com/en/VMware-vSphere/6.7/com.vmware.vsphere.update_manager.doc/GUID-B178F453-E78F-43C1-B64C-
54591B76E5F7.html
upvoted 1 times
Remediation:
Non-VSAN cluster = Parallel or Serial depending on resources and option chosen
VSAN cluster = always Serial
https://core.vmware.com/blog/vsphere-lifecycle-manager-feature-spotlight-parallel-
remediation#:~:text=Parallel%20remediation%20is%20deactivated%20by,manually%20prepared%20in%20maintenance%20mode.
I finally voted for AD. Why? There is no mention the downtime for VMs must be minimal. Only for ESXi hosts: "Downtime to the ESXi hosts must be
minimal while the work is completed.". There is no information about the size of the cluster. That's why to have it done as queck as possible I would
remediate as many ESXi hosts in parallel as possible
upvoted 1 times
D -> By default, vSphere Lifecycle Manager performs the staging operation onto all hosts in the cluster in parallel.
E -> vSphere Lifecycle Manager remediates hosts that are part of a vSAN cluster sequentially.
upvoted 2 times
Selected Answer: DE
I tested the process in vSphere 7. When using the stage all option from vSphere Lifecycle Manager, no options are shown to prepare one server at
a time. The server preparation process takes place in parallel. So, I think best answer is DE
upvoted 3 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-DD04A5FC-752C-405E-9771-69404A5CF105.html
„By default, vSphere Lifecycle Manager performs the staging operation onto all hosts in the cluster in parallel.“
upvoted 2 times
Selected Answer: CE
DE
Staging is in parallel by default, but VSAN clusters must be remediated sequentially.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-14265956-573B-46AF-B353-1A19E375C318.html
upvoted 4 times
Question #2 Topic 1
An administrator is working with VMware Support and is asked to provide log bundles for the ESXi hosts in an environment.
A. Generate a combined log bundle for all ESXi hosts using the vCenter Management Interface.
B. Generate a separate log bundle for each ESXi host using the vSphere Host Client.
C. Generate a combined log bundle for all ESXi hosts using the vSphere Client.
D. Generate a separate log bundle for each ESXi host using the vSphere Client.
E. Generate a separate log bundle for each ESXi host using the vCenter Management Interface.
F. Generate a combined log bundle for all ESXi hosts using the vSphere Host Client.
Cannot be A or E : you don't have access to the ESXi logs from the VAMI
Cannot be F : for the Host Client, you can only get the logs of the corresponding host, not the others.
So correct answer is : BCD
upvoted 1 times
B (generate a log bundle for each host via the ESXi interface), C (generate a log bundle for all hosts via vSphere by right clicking the container
object [Datacenter] and selecting Export Logs), D (generate a log bundle for all hosts via vSphere by right clicking the host and selecting Export
Logs). A and E incorrect -- logs are not available via VAMI. F is incorrect because you can only generate logs for the host you are connected to
when using the vSphere host client (ESXi)
upvoted 1 times
B-> with host client you can export logs for specific host (not combined)
C+D -> with vsphere client you can export log for ESXI lever or cluster level
no reference foe log exporting from management interface
upvoted 2 times
From vSphere Client (H5UI) user can select the hosts to generate the log bundles.
So a user can select a single host or all the hosts to generate the log bundles.
This satisfies the option : C and D
Now obviously from each ESXis host client user can download only that hosts log bundle.
So This satisfies option: B
upvoted 3 times
it's so
upvoted 2 times
An administrator needs to consolidate a number of physical servers by migrating the workloads to a software-defined data center solution.
A. VMware Horizon
B. VMware vSAN
C. VMware vSphere
D. VMware NSX
Correct Answer: C
Selected Answer: C
C. the others no
upvoted 1 times
Selected Answer: C
C. VMware vSphere
upvoted 2 times
Question #4 Topic 1
An administrator is tasked with configuring remote direct memory access (RDMA) over Converged Ethernet v2 (RoCE v2).
Which two types of adapters must the administrator configure? (Choose two.)
Correct Answer: BD
Selected Answer: BE
BE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-storage/GUID-F4B42510-9E6D-4446-816A-5012866E0038.html
upvoted 7 times
Selected Answer: BE
B. RDMA network adapter: This is the correct type of adapter for RoCE v2. RDMA network adapters have hardware support for RDMA
operations, enabling efficient data transfers with low latency over Ethernet networks.
C. Software iSCSI adapter: This type of adapter is used for iSCSI storage communication, not for RDMA over Converged Ethernet.
D. Fibre Channel over Ethernet (FCoE) adapter: This type of adapter allows encapsulation of Fibre Channel traffic over Ethernet networks, but it is
not used for RDMA over Converged Ethernet.
E. Software NVMe over RDMA storage adapter: This type of adapter enables NVMe over RDMA, which allows direct access to NVMe storage
devices using RDMA technology, but it is not directly related to RDMA over Converged Ethernet.
upvoted 2 times
"RDMA allows direct memory access from the memory of one computer to the memory of another computer without involving the operating
system or CPU. The transfer of memory is offloaded to the RDMA-capable Host Channel Adapters (HCA) . A PVRDMA network adapter provides
remote direct memory access in a virtual environment"
Option A, the PVRDMA is required to establish the connection and in virtual environments and option B, the RDMA physical adapter is required
for the connection between separate ESXi, this as per KB:
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-9AADBB49-876E-4E44-8149-D0523D8ADA6A.html?
hWord=N4IghgNiBcIEoBECyBBABAewG4FMBOacGAwgKJoBqATCAL5A
upvoted 2 times
Selected Answer: BE
in my humble opinion
upvoted 1 times
B,E - ESXi 7 and later supports RoCE v2 technology, which enables RDMA over an Ethernet network. Hosts use an RDMA network adapter installed
on the host and a software NVMe over RDMA storage adapter.
upvoted 1 times
Selected Answer: BE
Paravirtual RDMA adapters are not directly related to RoCE v2 configuration, and software iSCSI and Fibre Channel over Ethernet (FCoE) adapters
are not specifically required for configuring RDMA over Converged Ethernet v2 (RoCE v2)
upvoted 2 times
Question #5 Topic 1
An administrator has a host profile named Standard-Config. The administrator wants to change the other host profiles to use only the storage
A. Export host customizations and import them to the other host profiles.
B. Copy the storage settings from Standard-Config to all other host profiles.
C. Duplicate the Standard-Config host profile and only modify the storage configuration settings.
D. Export the Standard-Config host profile and attach it to tile other hosts.
Correct Answer: B
Option C (Duplicate the Standard-Config host profile and only modify the storage configuration settings) is the correct approach. By duplicating
the Standard-Config profile, you create a new profile with the same settings, including the storage configuration. Then, you can simply modify the
storage settings in the duplicated profile to suit the requirements for other hosts. This way, you retain the other specific configurations made on
the individual host profiles and only update the storage configuration settings to match the Standard-Config profile.
upvoted 5 times
The question states ‘other host profiles’ implying profiles already exists.
Exporting A and D are not an option.
C duplicating is not an option as it implies replacing the existing ‘other host profiles’
B is correct. Copy setting and apply to ‘other host profiles’
upvoted 1 times
Option A is incorrect because exporting host customizations doesn't address modifying host profiles with specific storage settings.
Option C is incorrect because duplicating the "Standard-Config" host profile would create a new host profile with all settings, not just the
storage settings, and it would not affect the other existing host profiles.
Option D is incorrect because attaching the "Standard-Config" host profile to other hosts doesn't modify their existing host profiles to use the
storage configuration settings defined in the "Standard-Config" profile.
upvoted 5 times
Selected Answer: B
Selected Answer: B
Answer is correct
upvoted 4 times
Question #6 Topic 1
Virtual machines (VMs) are running Production and Test workloads vSphere Distributed Resource Scheduler (DRS) is enabled
Performance monitoring data shows that the Production workload VMs are not receiving their fully allocated memory when the vSphere cluster is
fully utilized.
A combination of which two steps could the administrator perform to ensure that the Production VMs are always guaranteed the full allocation of
A. Assign a custom memory share value to the resource pool containing the Production VMs.
B. Assign a memory reservation value to the resource pool containing the Production VMs.
D. Create a sibling resource pool for each of the Production and Test VMs.
Correct Answer: AB
BC: You guarantee resources by setting a reservation on the pool. You cannot set a reservation on a pool that doesn't exist, so voting BC.
upvoted 10 times
next the question only talks about production, it does not talk about guarantying resources to test. The minimum to complete would be C
upvoted 1 times
About C or D: When you have DRS On, the cluster becomes a parent pool (invisible root resource pool) of all the pools below, so if you
have your Test VMs outside a child pool, they will inherit the resource allocation from the Cluster, which is going to be hierarchically
bigger than Production VMs Pool.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-
641703ED7601.html
upvoted 1 times
Selected Answer: BC
We only want to guarantee resources for the Production VMs, the subject does not care about allocation of resources for Test VMs : so a single
resource pool is sufficient. As we will have a single resource pool, it is a Parent. --> Answer C
I think the type of parent, sibling, child is simply based on hierarchy. "Resource pools and virtual machines that are at the same level are called
siblings. " Said so in this Doc.
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-60077B40-66FF-4625-934A-
641703ED7601.html#:~:text=A%20resource%20pool%20can%20contain%20child%20resource%20pools%2C,The%20cluster%20itself%20represents
%20the%20root%20resource%20pool.
upvoted 1 times
if you create a two RPs and set one with higher shares its the result that if contention occurs, the RP with more shares gets more power. A&D is
more practical because its more dynamic but still gurantee the highest level of performance in the RP with more share if contention occurs.
upvoted 1 times
Selected Answer: BD
Parent is the root folder, hence the pool will be taken as sibling
upvoted 2 times
Selected Answer: AD
I think it's better to work with shares than reservation in this scenario. What about adding a new host? What about upgrading the host's hardware?
Or even adding new VMs to the pool? A percentage-based approach seems better in my opinion, as it is dynamic. The reservation is going to be a
static value for each resource in the pool. If the vSphere DRS Cluster is at its full capacity, then the Production Pool will have higher resource
allocation in comparison to the Testing Pool.
About C or D (Creating one Prod Pool or one Pool for each group of VMs): When you have DRS On, the cluster becomes a parent pool of all the
pools below (invisible root resource pool), so if you have your Testing VMs outside of the Testing Pool, they will inherit the resource allocation from
the Cluster, which is going to be hierarchically bigger than Production VMs Pool. That's why you should create 2 different pools in my opinion.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-641703ED7601.html
upvoted 3 times
B. Assign a memory reservation value to the resource pool containing the Production VMs.
By setting a memory reservation for the resource pool containing the Production VMs, you ensure that a specific amount of memory is reserved
exclusively for these VMs, and it won't be used by other VMs in the cluster, even when the cluster is fully utilized.
C. Create a parent resource pool for the Production VMs.
Creating a parent resource pool for the Production VMs allows you to prioritize the allocation of resources to VMs within that pool. You can then
set resource allocation policies for the parent resource pool to ensure that the Production VMs get the necessary resources.
upvoted 1 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-
641703ED7601.html#:~:text=The%20resource%20pools%20at%20a,the%20root%20resource%20pools%20exist
upvoted 1 times
Selected Answer: BC
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-641703ED7601.html
upvoted 2 times
BD, a pool for Prod, a pool for Test, reservation for the Prod pool
upvoted 1 times
Selected Answer: BC
I believe its BC, you need to create a pool for the production VMs (C) and then assign share values you need these VMs to have. The other options
don't guarantee the production VMs to have what they require.
upvoted 1 times
E. Creating a child resource pool for the Test VMs is unrelated to ensuring that the Production VMs receive their fully allocated memory.
upvoted 2 times
D. Creating a sibling resource pool for each of the Production and Test VMs may not address the issue of memory allocation either. Sibling
resource pools are at the same level in the resource pool hierarchy and do not inherently provide mechanisms to guarantee memory
allocation for specific VMs.
upvoted 1 times
BD and BC are both valid answers... you need a pool to apply reservations but there's no difference between choosing to create only one pool for
Prod. or two sibiling pools beacuse test Vms does not need any particular settings... choosing to create a same level pool gives you a better
classification and order but nothing more
upvoted 1 times
"D. Create a sibling resource pool for each (one) of the Production and Test VMs."
So you create a Pool for the production VMs (C) and allocate the memory to it (B).
upvoted 2 times
Question #7 Topic 1
Which two datastore types store the components of a virtual machine as a set of objects? (Choose two.)
B. VMware vSAN
Correct Answer: AD
B. VMware vSAN: vSAN is a hyper-converged, software-defined storage solution that aggregates local storage devices across multiple ESXi hosts to
create a distributed storage pool. In vSAN, virtual machine components are stored as a set of objects, and each object represents a specific part of
a virtual machine, such as VMDK files, VM configuration files, and snapshots.
D. vSphere Virtual Volumes (vVols): vVols is a storage virtualization technology that allows vSphere to manage storage at the VM level granularity.
With vVols, VMs are stored as individual objects on the storage system, and each VM has its own set of objects, including VMDK files, configuration
files, and snapshots. vVols enables policy-based management of VM storage at the individual VM level.
upvoted 7 times
C. Network File System (NFS) 3: NFS is a network-based file system protocol used for sharing files over a network. NFS datastores store virtual
machine components as a set of files on the NFS file system, rather than as objects.
E. Network File System (NFS) 4.1: Similar to NFS 3, NFS 4.1 is a network-based file system protocol that stores virtual machine components as
files on the NFS file system, not as objects.
upvoted 2 times
Selected Answer: BD
B. vSAN
D. vVol
upvoted 7 times
Selected Answer: BD
Selected Answer: BD
BD for sure!!
upvoted 2 times
Mtb514 5 months, 3 weeks ago
Selected Answer: BD
After updating a predefined alarm on VMware vCenter, an administrator enables email notifications as shown in the attached alarm; however,
Where must the mail server settings be configured by the administrator to resolve this issue?
Correct Answer: C
C shoud be corrrect after you read this document on Configure Mail Sender Settings
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-configuration/GUID-467DA288-7844-48F5-BB44-99DE6F6160A4.html
upvoted 1 times
C is correct
upvoted 1 times
Selected Answer: C
C is correct
upvoted 1 times
An administrator creates a virtual machine that contains the latest company-approved software, tools and security updates. Company policy
requires that only full clones are allowed for server workloads.
A combination of which two tasks should the administrator complete to prepare for the deployment of this virtual machine for multiple users?
(Choose two.)
Correct Answer: AB
Selected Answer: BD
B & D of course
upvoted 1 times
Selected Answer: BD
Selected Answer: BD
BD is correct
upvoted 1 times
B&D, D kind of explains itself, B will allow you to customize the VM and avoid issues that come with just cloning such as repeated IPs, Macs, having
the same hostname, etc, its the best practice.
upvoted 2 times
Selected Answer: BD
why A????
upvoted 3 times
During the staging of a patch on a vCenter Server Appliance, an error was encountered and the process stopped. An administrator resolved the
root cause and is ready to continue with the staging of the patch.
From the vCenter Management Interface, which action should the administrator take to continue the process from the point at which the error
occurred?
Correct Answer: B
Selected Answer: B
If vCenter Server encounters a problem staging the patches, the vCenter Server Management Interface displays the Resume button. Correct the
problem preventing the patches from staging, and click Resume to finish staging the patches. The staging process resumes from the point at which
vCenter Server encountered the problem.
Ref. https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-3E7C2187-42A4-4DD4-9EC8-80D8B0077F82.html
upvoted 1 times
Selected Answer: B
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-3E7C2187-42A4-4DD4-9EC8-80D8B0077F82.html
upvoted 4 times
'If vCenter Server encounters a problem staging the patches, the vCenter Server Management Interface displays the Resume button.'
also describes a resume button 'If a problem that prevents the successful staging of the patches occurs, vCenter Server suspends the staging
process. Review the error messages, correct the problem, and, in many cases, you can resume staging the patches from the point at which
vCenter Server encountered the problem.'
upvoted 2 times
To clarify, when staging a patch in vCenter Server Appliance, if an error occurs during the process, the administrator can identify and resolve the
root cause of the issue. Once the issue is fixed, the administrator should proceed with the "Stage and Install" option, which will continue the
patch staging process from where it was interrupted, ensuring both staging and installation of the patch occur as intended.
upvoted 1 times
An administrator is adding a new ESXi host to an existing vSphere cluster. When selecting the cluster, the administrator is unable to use the
B. The administrator must manually add the host to the cluster before using the Cluster Quickstart workflow.
C. The administrator has not been assigned the required permissions to use the Cluster Quickstart workflow.
D. The administrator must enable the Cluster Quickstart workflow option in VMware vCenter.
Correct Answer: B
Selected Answer: A
Answer A. Once you have dismissed the quickstart, you have to "manually" manage your cluster.
Cannot be B : the step 2 of the quickstart is specifically to add host to the cluster
Cannot be C : there is no specific permission for the Quickstart
Cannot be D : there is no option to enable, it is available by default
upvoted 1 times
Selected Answer: A
Answer A
upvoted 1 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsan-planning/GUID-CF9767B6-B3F5-4787-9AF3-D661987AE525.html
upvoted 1 times
If you have once skipped the dialog, you cant resume it.
upvoted 2 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-esxi-management/GUID-F7818000-26E3-4E2A-93D2-FCDCE7114508.html?
hWord=N4IghgNiBcIMYQK4GcCmAnABARUQSzgGtkAXMdEkAXyA
upvoted 3 times
Selected Answer: A
The Quickstart workflow must be available for your vSAN cluster. Networking settings configured while creating the cluster with Quickstart have
not been modified. Procedure Navigate to the cluster in the vSphere
upvoted 2 times
Selected Answer: B
ABCACB is correct.
upvoted 1 times
A company has two sites: Site A and Site B. The administrator would like to manage the VMware vCenter inventories in both sites from a single
Correct Answer: C
Selected Answer: D
D - vCenter Enhanced Linked Mode allows you to log in to any single instance of vCenter Server and view and manage the inventories of all the
vCenter Server systems in the group.
Selected Answer: D
Correct answer is D
upvoted 1 times
Its 100% D
upvoted 1 times
Selected Answer: D
Selected Answer: D
Selected Answer: D
Selected Answer: D
D absolutely!
upvoted 1 times
vCenter Enhanced Linked Mode allows you to log in to any single instance of vCenter Server and view and manage the inventories of all the
vCenter Server systems in the group
upvoted 1 times
Selected Answer: D
sure...
upvoted 1 times
Selected Answer: D
d for me too!
upvoted 2 times
An administrator plans to update the Supervisor cluster and has noticed some of the Tanzu Kubernetes Grid clusters are running an incompatible
version.
Which action must the administrator take before proceeding with the Supervisor cluster update?
A. Update all Tanzu Kubernetes Grid clusters to the latest version prior to the Supervisor cluster update.
B. No action is needed – Tanzu Kubernetes Grid clusters will be updated automatically as part of the update process.
C. No action is needed – Incompatible Tanzu Kubernetes Grid clusters can be manually updated after the Supervisor cluster update.
D. Update incompatible Tanzu Kubernetes Grid clusters prior to the Supervisor cluster update.
Correct Answer: D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-maintenance/GUID-7B4C9B95-E394-42B8-A76E-6D213CB7DF48.html
upvoted 1 times
Selected Answer: D
Which three vSphere features are still supported for Windows-based virtual machines when enabling vSphere’s virtualization-based security
A. vSphere vMotion
B. PCI passthrough
A. C. E (Correct)
The following features are not supported in a virtual machine when VBS is enabled:
Fault tolerance
PCI passthrough
Hot add of CPU or memory
upvoted 8 times
An administrator wants to create virtual machine (VM) templates and store them in a content library. The administrator would like to use the
content library to manage different versions of these templates so that reverting to an earlier version is an option.
Correct Answer: C
Selected Answer: A
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-E9EAF7AC-1C08-441A-AB80-0BAA1EAF9F0A.html
Look under Revert to a Previous Version of a Template
upvoted 1 times
for me too
upvoted 1 times
An administrator is tasked with configuring certificates for a VMware software-defined data center (SDDC) based on the following requirements:
All certificates should use certificates trusted by the Enterprise Certificate Authority (CA).
The solution should minimize the ongoing management overhead of replacing certificates.
Which three actions should the administrator take to ensure that the solution meets corporate policy? (Choose three.)
A. Replace the VMware Certificate Authority (VMCA) certificate with a self-signed certificate generated from the VMCA.
B. Replace the machine SSL certificates with custom certificates generated from the Enterprise CA.
C. Replace the machine SSL certificates with trusted certificates generated from the VMware Certificate Authority (VMCA).
D. Replace the VMware Certificate Authority (VMCA) certificate with a custom certificate generated from the Enterprise CA.
E. Replace the solution user certificates with custom certificates generated from the Enterprise CA.
F. Replace the solution user certificates with trusted certificates generated from the VMware Certificate Authority (VMCA).
I think CDF is the correct answer. You can issue a Certificate for the VMCA, making the VMCA an Intermediate CA in the process. Then, issue the
rest of the certs using the VMCA to simplify the renewal process.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-authentication/GUID-4469A6D3-048A-471C-9CB4-518A15EA2AC0.html#making-vmca-
an-intermediate-certificate-authority-1 ("Making VMCA an Intermediate Certificate Authority" approach)
upvoted 3 times
View the table in the link. It talks about using subordinate CA apporach.
https://blogs.vmware.com/vsphere/files/2017/01/Hybrid-PWT-Table.png
https://blogs.vmware.com/vsphere/2017/01/walkthrough-hybrid-ssl-certificate-replacement.html
upvoted 2 times
CDF. As others have stated, this accomplishes the goal of easy certificate deployment, and since your VMCA cert is issued by the Company CA, all
certs issued by the VMCA will be in that chain.
upvoted 3 times
The Hybrid Scenario change only the machine certifiace for the VMCA but not the certifaces for ESXi Hosts. You can only fulfill the requirement with
less overhaul.
URL: https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-authentication/GUID-4469A6D3-048A-471C-9CB4-518A15EA2AC0.html#making-
vmca-an-intermediate-certificate-authority-1
upvoted 1 times
Reference: https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.security.doc/GUID-A2A4371A-B888-404C-B23F-
C422A8C40F54.html
upvoted 1 times
CDF, replacing VMCA certificate and let VMCA manage other certificates
upvoted 3 times
An administrator is tasked with moving an application and guest operating system (OS) running on top of a physical server to a software-defined
The remote secure location has no network connectivity to the outside world.
The business owner is not concerned if all changes in the application make it to the SDDC in the secure location.
What could the administrator do to create an image of the guest OS and application that can be moved to this remote data center?
A. Create a hot clone of the physical server using VMware vCenter Converter.
B. Create a cold clone of the physical server using VMware vCenter Converter.
Correct Answer: B
Selected Answer: B
Voting for cold cloning, but I don't see cold cloning mentioned in recent VMware docs. If someone else finds it, post a link to it. I can only find
mentions of remote hot cloning, not remote cold cloning. Cold cloning (in older docs) refers to booting from a CD and making a copy of the
physical server. This is the only option that makes sense in this scenario, but it is not specifically mentioned in docs I can find.
upvoted 10 times
Selected Answer: A
Since the DB is handling hing number of volumes, the application cant be shutdown.
A: Create a hot clone of the physical server using VMware vCenter Converter.
upvoted 8 times
Selected Answer: B
https://communities.vmware.com/t5/ESXi-Discussions/Large-VM-Cloning/td-p/843828
Anytime you are dealing with large and highly transactional database it is recommended that you should shut the server done before doing any
P2V or V2V
upvoted 1 times
Selected Answer: C
Answer C of course. All the other solutions need network connectivity between the source and destination, which is not the case here.
In addition, the business owner does not care if the application server is modified during the "migration" process. So it can be backed up on the
source, and then restored in the destination SDDC.
upvoted 1 times
https://kb.vmware.com/s/article/1004588
"If the source is Microsoft Exchange, SQL, or other database server, VMware recommends that the application (Microsoft Exchange/SQL) and
database services be shut down prior to conversion. This minimizes any chance of corrupted database tables or stale data in the destination virtual
machine."
Although the BO is not concerned about having the latest data, which you don't get with shutting down a VM. Potential data loss is never an
option as mentioned in the article.
upvoted 1 times
Selected Answer: B
Option B is correct because it allows the administrator to create a cold clone of the physical server using VMware vCenter Converter, which will
create an image of the guest OS and application that can be moved to this remote data center without requiring network connectivity or affecting
the application’s data. Option A is incorrect because creating a hot clone of the physical server using VMware vCenter Converter will require
network connectivity and may affect the application’s data due to changes during conversion. Option C is incorrect because restoring the guest OS
from a backup will require network connectivity and may not include the latest changes in the application. Option D is incorrect because using
storage replication to replicate the guest OS and application will require network connectivity and may not be feasible for a physical server.
upvoted 2 times
Selected Answer: B
B Cold Clone
In the PDF below it mentions you can export the converted server to a backup image which means this can be used to import in the data center.
Could not find if you can do this with hot convert
https://support.intermedia.com/app/articles/detail/a_id/10288/~/how-do-i-convert-my-physical-server-to-virtual-using-vmware-vcenter-
converter%3F
Selected Answer: A
The business owner is not concerned if all changes in the application make it to the SDDC in the secure location. --> indicates A but in real life i
would choose b for a cold migration
upvoted 1 times
Selected Answer: B
Given the constraints mentioned, the administrator should consider the following approach:
B. Create a cold clone of the physical server using VMware vCenter Converter.
No network connectivity to the outside world: Since the remote secure location has no network connectivity to the outside world, performing a hot
clone (option A) would likely involve network communication. In contrast, a cold clone can be performed without network connectivity.
Business owner is not concerned if all changes make it to the SDDC: A cold clone captures a point-in-time snapshot of the server's state. This
means that it will not capture any changes made to the application and data after the clone is initiated. Given that the business owner is not
concerned about changes, a cold clone is suitable for this scenario.
upvoted 1 times
Selected Answer: C
Both Hot and Cold need network connectivity and it states that there is no connectivity. Replication requires lot more and, in this case, it is physical
server. That leaves answer C.
upvoted 1 times
Selected Answer: C
I have to go for C, restoring a backup of a physical server within the secure location.
Selected Answer: A
Selected Answer: C
All answers are wrong. VMware vCenter Converter requires a destination host. You can install VMware vCenter Converter on your computer and
test on your own.
upvoted 3 times
Question #18 Topic 1
An administrator is tasked with configuring an appropriate Single Sign-On (SSO) solution for VMware vCenter based on the following criteria:
The solution should support the creation of Enhanced Link Mode groups.
All user accounts are stored within a single Active Directory domain and the solution must support only this Active Directory domain as the
identity source.
All user account password and account lockout policies must be managed within the Active Directory domain.
Which SSO solution should the administrator choose based on the criteria?
A. vCenter Identity Provider Federation with Active Directory Federation Services as the identity provider
B. vCenter Single Sign-On with Active Directory over LDAP as the identity source
C. vCenter Single Sign-On with Active Directory (Windows Integrated Authentication) as the identity source
D. vCenter Identity Provider Federation with Active Directory over LDAP as the identity provider
Correct Answer: C
Selected Answer: A
„ In vCenter Server Identity Provider Federation, vCenter Server uses the OpenID Connect (OIDC) protocol to receive an identity token that
authenticates the user with vCenter Server.“
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.authentication.doc/GUID-157188E3-531C-4CC2-BDD4-
8BF01EA26BDC.html
upvoted 8 times
Selected Answer: A
Answer A. It is the only way to bypass the vCenter SSO, and use Active Directory as the only identity source.
upvoted 1 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-authentication/GUID-C5E998B2-1148-46DC-990E-A5DB71F93351.html
upvoted 2 times
An administrator is tasked with looking into the disaster recovery options for protecting a database server using VMware vSphere Replication.
The virtual machine's snapshots must be used as part of the replication process.
C. Perform a full initial synchronization of the source virtual machine to the target location.
Correct Answer: B
Selected Answer: C
Changing my answer to C. D is not required, but recommended. What is required is that a full initial synchronization must be done for a VM to be
protected. Also VSS is not supported on all OS's.
https://docs.vmware.com/en/vSphere-Replication/8.7/com.vmware.vsphere.replication-admin.doc/GUID-C249300C-2BC0-4128-88B5-
046C3DE6BC5B.html
upvoted 7 times
(Optional) Activate quiescing for the guest operating system of the source virtual machine.
Note: Quiescing options are available only for virtual machines that support quiescing. vSphere Replication does not support VSS quiescing
on vVOL.
upvoted 1 times
Virtual machine snapshots are not used as part of the replication process unless VSS quiescing is enabled. <Check chapter Replication Process>
https://core.vmware.com/resource/vsphere-replication-technical-overview#section3
The requirement in the questions says: The virtual machine's snapshots must be used as part of the replication process.
How you can achieve that? Enabling VSS quiescing.
Answer is B
upvoted 2 times
Selected Answer: C
mhn, ill go with C because if you install Vmware tools one part is enable vss. tricky question...
upvoted 1 times
I choose B.
Quiesce: If the flag is 1 or true, and the virtual machine is powered on when the snapshot is taken, VMware Tools is used to quiesce the file system
in the virtual machine. Quiescing a file system is a process of bringing the on-disk data of a physical or virtual computer into a state suitable for
backups. This process might include such operations as flushing dirty buffers from the operating system's in-memory cache to disk, or other
higher-level application-specific tasks.
Selected Answer: C
Selected Answer: D
The VMkernel adapter that you created for outgoing vSphere Replication traffic appears in the list of adapters. The outgoing replication data from
the ESXi host is sent to the vSphere Replication server through this adapter.
upvoted 1 times
Question #20 Topic 1
An administrator must gracefully restart a virtual machine (VM) through the vSphere Client but the option is greyed out. The administrator has full
administrative access on VMware vCenter and all the objects available in vCenter, but has no access to log onto the operating system.
D. Restart vCenter
Correct Answer: B
D. Migrating to another host seems like the sensible option, but this KB suggests Restarting the vCenter might be the answer.
https://kb.vmware.com/s/article/82562
I'm guessing that if the issue is communication between the vCenter and the Host, a vMotion could become stuck if you're unlucky.
As for installing the tools, you need to have access to the OS to do so.
upvoted 10 times
Selected Answer: D
Answer D.
If the restart option is greyed out, that means the VMware Tools are not installed, or there is an issue on vCenter. If the VMware Tools are not
installed, the only way to make the initial install is to log onto the guest OS...which is impossible here.
We can then suppose the VMware Tools are already installed, but the communication with the vCenter does not work. So we restart the vCenter.
upvoted 1 times
Selected Answer: C
Install VM Tools
upvoted 1 times
Selected Answer: C
Installing VMware Tools will enable the graceful restart option for the virtual machine, as well as other features such as time synchronization and
guest OS customization.
It's not necessary to log into the OS in order to install VMware Tools.
In vSphere Client – Hosts and Clusters view > right-click the Virtual Machine > Guest OS > Install VMware Tools.
upvoted 2 times
Selected Answer: D
Must be D since according to this document (https://kb.vmware.com/s/article/1014294), you have to log on to a VM in order to install VMware
Tools. The question says there's no access to the OS, and thus the administrator *cannot* install VMware Tools.
upvoted 2 times
Selected Answer: C
Selected Answer: D
https://kb.vmware.com/s/article/82562
KB article stating issue can be caused by communication issue to be fixed by restarting vCenter
upvoted 2 times
Selected Answer: D
C is not correct, because to install vmtools you need to have access to the OS: if you select install vmtoos from vCenter, there are only two options
available: "mount" and "cancel". So, is not automatic process.
I agree with mkhlszf, option D (restart vcenter) is the best option based in this KB: https://kb.vmware.com/s/article/82562
upvoted 4 times
https://kb.vmware.com/s/article/2004754
upvoted 1 times
Selected Answer: C
Installing VMware Tools will enable the graceful restart option for the virtual machine, as well as other features such as time synchronization and
guest OS customization.
upvoted 1 times
Selected Answer: C
Selected Answer: C
An administrator is tasked with installing VMware vCenter. The vCenter Server Appliance must support an environment of:
400 hosts
Which two resources must be allocated, at a minimum, to meet the requirements? (Choose two.)
A. 16 vCPUs
B. 30 GB Memory
C. 4 vCPUs
D. 8 vCPUs
E. 20 GB Memory
Correct Answer: BD
Selected Answer: BD
Medium environment (up to 400 hosts or 4,000 virtual machine) 8vCPU 28 GB Mem
upvoted 7 times
Selected Answer: BD
the vCenter Server Appliance (vSphere 8.0) for Medium environment (up to 400 hosts or 4,000 virtual machine) requires 8vCPU, and 30GB Memory
upvoted 2 times
Selected Answer: BD
Medium environment (up to 400 hosts or 4,000 virtual machine) vCPU8 and 30 GB Mem
upvoted 1 times
Which VMware offering will allow an administrator to manage the lifecycle of multiple vCenter Server instances in a single software as a service
C. VMware vSphere+
Correct Answer: B
C: VCF is not SaaS, so it cannot be the answer. VCF includes the management domain and multiple workload domains. While VCF does use LCM to
manage vCenter lifecycle, it is on-prem only (for now) and is not SaaS based. That only leave vSphere+. See the video in this link about upgrading
remote vCenters managed by vSphere+. https://www.vmware.com/products/vsphere/vsphere-plus.html
upvoted 12 times
Selected Answer: C
vSphere+ of course : "Update an entire fleet of ESXi hosts in one operation, across multiple vCenters and clusters, and centrally monitor progress
from the Cloud Console"
Source : https://www.vmware.com/products/vsphere/vsphere-plus.html#features
upvoted 1 times
Selected Answer: C
I vote for C
upvoted 1 times
The key here is the Saas requirement , so it's B , without it i would follow Michael24
upvoted 1 times
https://www.vmware.com/content/dam/digitalmarketing/vmware/en/pdf/products/vsphere/vmware-vsphere-pricing-whitepaper.pdf
upvoted 1 times
Selected Answer: C
C - vSphere+ is the SaaS offering and vSphere+ specifically mentions "Entire vCenter lifecycle management is simplified, making it easy to detect
and remediate configuration drift." in the product documentation
upvoted 2 times
Selected Answer: C
With VMware Cloud Foundation, administrators can centrally manage and automate the deployment, configuration, patching, and upgrading of
multiple vCenter Server instances. This helps drive operational efficiency by streamlining and simplifying the management of vCenter Server
environments, reducing manual effort, and improving overall consistency and scalability.
upvoted 2 times
Question #23 Topic 1
Which feature would allow for the non-disruptive migration of a virtual machine between two clusters in a single VMware vCenter instance?
A. vSphere vMotion
Correct Answer: B
Selected Answer: A
vSphere vMotion is a feature that enables the live migration of a running virtual machine from one host to another within a cluster or between
clusters within a single vCenter instance.
upvoted 6 times
Selected Answer: A
vMotion is used to move the VM to a different cluster within the same vCenter. This only works if both clusters share the same storage. If they
don't you also need to perform a Storage vMotion. Cross vCenter Migration is only used to migrate to a different vCenter.
upvoted 5 times
Selected Answer: A
Selected Answer: A
for sure
upvoted 1 times
Question #24 Topic 1
Which four elements can a vSphere Lifecycle Manager image contain? (Choose four.)
B. ESXi configuration
C. Vendor agents
D. Vendor add-ons
E. BIOS updates
G. Independent components
A vSphere Lifecycle Manager image can consist of the following four elements:
ESXi base image
The base image contains an image of VMware ESXi Server and additional components, such as drivers and adapters that are necessary to boot a
server. The base image is the only mandatory element in a vSphere Lifecycle Manager image. All other elements are optional.
Vendor add-on
The vendor add-on is a collection of software components that OEMs create and distribute. The vendor add-on can contain drivers, patches, and
solutions.
Firmware and drivers add-on
The firmware and drivers add-on is a special type of vendor add-on designed to assist in the firmware update process. The firmware and drivers
add-on contains firmware for a specific server type and corresponding drivers. To add a firmware and drivers add-on to your image, you must
install the hardware support manager plug-in provided by the hardware vendor for the hosts in the respective cluster.
Independent components
The component is the smallest discrete unit in an image. The independent components that you add to an image contain third-party software, for
example drivers or adapters.
upvoted 10 times
ADFG or course
upvoted 1 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-9A20C2DA-F45F-4C9B-9D17-A89BCB62E6EF.html
upvoted 1 times
ADGF
ESXi base image
Vendor add-on
Firmware and drivers add-on
Independent components
upvoted 1 times
agree ...
upvoted 1 times
If a distributed switch uses the “Route based on physical NIC load” load balancing algorithm, what does the mean send or receive utilization of an
uplink need to exceed for the flow of traffic to move to the second uplink?
Correct Answer: B
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.networking.doc/GUID-E356DCBF-913B-4FD1-BDB1-C5E63A891B14.html
upvoted 1 times
i guess
upvoted 1 times
Selected Answer: A
The distributed switch calculates uplinks for virtual machines by taking their port ID and the number of uplinks in the NIC team. The distributed
switch tests the uplinks every 30 seconds, and if their load exceeds 75 percent of usage, the port ID of the virtual machine with the highest I/O is
moved to a different uplink.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-959E1CFE-2AE4-4A67-B4D4-2D2E13765715.html
upvoted 4 times
Selected Answer: A
The distributed switch calculates uplinks for virtual machines by taking their port ID and the number of uplinks in the NIC team. The distributed
switch tests the uplinks every 30 seconds, and if their load exceeds 75 percent of usage, the port ID of the virtual machine with the highest I/O is
moved to a different uplink.
upvoted 1 times
An administrator manually configures a reference ESXi host that meets company security standards for vSphere environments. The administrator
now needs to apply all of the security standards to every identically configured host across multiple vSphere clusters within a single VMware
vCenter instance.
Which four steps would the administrator complete to meet this requirement? (Choose four.)
D. Attach the host profile to each cluster that requires the secure configuration.
Correct
(A)Create a Host Profile
(D)Attach or Detach Hosts and Clusters to a Host Profile
(E)Check Compliance
(G)Remediate a Host
upvoted 3 times
Question #27 Topic 1
After a recent unexplained peak in virtual machine (VM) CPU usage, an administrator is asked to monitor the VM performance for a recurrence of
the issue.
E. ESXi Shell
Correct Answer: CD
CE: performance charts is obvious. although it doesn't say real time, I would go with esxtop in the shell
upvoted 7 times
Selected Answer: CE
Selected Answer: CE
From the vCenter Management Interface, you could monitor the performance of the vCenter itself, not the other VMs.
upvoted 4 times
The vCenter Management Interface and vSphere Performance Charts are both tools that can be used to monitor VM performance. The vCenter
Management Interface is a web-based interface that provides a centralized view of all VMs in a vSphere environment. The vSphere Performance
Charts are a set of graphical tools that can be used to track VM performance over time.
The Direct Console User Interface (DCUI), vCenter Command Line Interface, and ESXi Shell are all tools that can be used to manage VMs, but they
are not specifically designed for monitoring VM performance.
upvoted 1 times
Correct Answer: C
Selected Answer: A
Answer is A
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.security.doc/images/GUID-D205B3C1-56BE-497A-B066-4C8F764B068C-
high.png
upvoted 8 times
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-39D8AB34-AD45-4B0A-8FB0-
7A1D16B25C9A.html#:~:text=vSphere%20Trust%20Authority%20Workflow
upvoted 2 times
Selected Answer: A
Selected Answer: A
i agree
upvoted 2 times
Selected Answer: D
The distributed switch has three ESXi hosts, and each host has two 40 Gbps NICs.
The amount of bandwidth reserved for virtual machine (VM) traffic is 6 Gbps.
The administrator wants to guarantee that VMs in the Finance distributed port group can access 50 percent of the available reserved bandwidth
for VM traffic.
Given this scenario, what should the size (in Gbps) of the Finance network resource pool be?
A. 18
B. 80
C. 36
D. 120
Correct Answer: C
Selected Answer: A
It says 50% of the reserved bandwidth. Total reserved bandwidth is 6Gbps x 6 physical NICs = 36Gbps and 50% of that is 18Gbps.
Thus my vote goes to option A
upvoted 14 times
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.networking.doc/GUID-8E957535-7969-4E12-BD11-DF746D6D5379.html
for the question (current reserved vm traffic = 6Gbps for network resource pool ((6 nics x reversed vm traffic 6Gbps) * 50% = 18Gbps reserved
bandwidth for finance group vm traffic)
upvoted 1 times
You have 4 ESXis. Each has ESXi has 2 vmnics. Each nic has 10G.
upvoted 2 times
Selected Answer: A
seems so
upvoted 1 times
Selected Answer: A
Ans: A
The Questions "what should the size (in Gbps) of the Finance network resource pool be"
It should be 18Gbps which is the 50% of total bandwidth reserve with 36Gbps
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-29A96AB2-AEBF-420E-BDD6-48921CD687FF.html
upvoted 1 times
ABCACB 6 months ago
Selected Answer: C
Amount of bandwidth reserved for virtual machine (VM) traffic is 6 Gbps, multiply by 6 Physical NICs on the D-Switch = 36 Gbps Resource Pool
upvoted 1 times
A.
upvoted 1 times
Question #30 Topic 1
A vSphere environment is experiencing intermittent short bursts of CPU contention, causing brief production outages for some of the virtual
machines (VMs). To understand the cause of the issue, the administrator wants to observe near real-time statistics tor all VMs.
Which two vSphere reporting tools could the administrator use? (Choose two.)
B. esxcli
C. resxtop
E. esxtop
Correct Answer: CE
Selected Answer: CE
The resxtop and esxtop command-line utilities provide a detailed look at how ESXi uses resources in real time.
The fundamental difference between resxtop and esxtop is that you can use resxtop remotely, whereas you can start esxtop only through the ESXi
Shell of a local ESXi host.
upvoted 6 times
Selected Answer: CE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-monitoring-performance/GUID-A31249BF-B5DC-455B-AFC7-7D0BBD6E37B6.html
The resxtop and esxtop command-line utilities provide a detailed look at how ESXi uses resources in real time
upvoted 1 times
CE
upvoted 2 times
Selected Answer: AE
Other than esxtop, Advanced Performance Charts also provide the analysis of CPU contention issues.
upvoted 3 times
The resxtop and esxtop command-line utilities provide a detailed look at how ESXi uses resources in real time.
upvoted 2 times
Selected Answer: AE
A is defintely correct...
upvoted 1 times
Advanced Performance Charts and esxtop are both vSphere reporting tools that can be used to observe near real-time statistics for all VMs.
Advanced Performance Charts provides a graphical view of performance data, while esxtop is a command-line tool that provides more detailed
information.
B, C, and D are incorrect answers. B, esxcli, is a command-line tool that is used to manage ESXi hosts. C, resxtop, is a command-line tool that is
used to monitor the performance of ESXi hosts. D, Overview Performance Charts, provides a graphical view of performance data, but it does not
provide near real-time statistics.
upvoted 4 times
An administrator is performing maintenance activities and discovers that a Virtual Machine File System (VMFS) datastore has a lot more used
capacity than expected. The datastore contains 10 virtual machines (VMs) and, when the administrator reviews the contents of the associated
datastore, discovers that five virtual machines have a snapshot file (-delta.vmdk files) that has not been modified in over 12 months. The
administrator checks the Snapshot Manager within the vSphere Client and confirms that there are no snapshots visible.
Which task should the administrator complete on the virtual machines to free up datastore space?
Correct Answer: A
Selected Answer: A
In this case option A is correct, since the snapshots are not visible in the vSphere.
upvoted 1 times
Selected Answer: A
https://docs.vmware.com/es/VMware-vSphere/7.0/com.vmware.vsphere.vm_admin.doc/GUID-2F4A6D8B-33FF-4C6B-9B02-
C984D151F0D5.html#:~:text=La%20presencia%20de,espacio%20de%20almacenamiento.
upvoted 2 times
Selected Answer: C
No such action called "Consolidate". The action is Delete All. It is consolidating the snapshots.
https://kb.vmware.com/s/article/1023657#:~:text=Deleting%20Snapshots&text=Deleting%20a%20snapshot%20does%20not,snapshot%20to%20th
e%20parent%20disk.
upvoted 1 times
Selected Answer: C
To free up datastore space in this scenario where there are lingering snapshots (-delta.vmdk files) that are not visible in the Snapshot Manager, you
should:
These snapshots that are not visible in the Snapshot Manager are often referred to as "orphaned snapshots." Deleting these snapshots will merge
the changes from the snapshot delta files back into the original virtual disks and free up space on the datastore. Make sure to perform this action
carefully to avoid any data loss.
upvoted 1 times
mkhlszf 4 months, 1 week ago
Selected Answer: A
Should be option A:
"For virtual machines that are not reported to have snapshots in the VMware vSphere or Infrastructure Client, commit or remove the snapshot delta
disks."
https://kb.vmware.com/s/article/1005049
upvoted 4 times
Selected Answer: A
The presence of redundant delta disks can adversely affect the virtual machine performance. You can combine such disks without violating a data
dependency. After consolidation, redundant disks are removed, which improves the virtual machine performance and saves storage space.
upvoted 3 times
Question #32 Topic 1
An administrator is attempting to configure Storage I/O Control (SIOC) on five datastores within a vSphere environment. The administrator is being
asked to determine why SIOC configuration completed successfully on only four of the datastores.
What are two possible reasons why the configuration was not successful? (Choose two.)
Correct Answer: AC
Selected Answer: AC
Storage I/O Control is supported on Fibre Channel-connected, iSCSI-connected, and NFS-connected storage. Raw Device Mapping (RDM) is not
supported.
Storage I/O Control does not support datastores with multiple extents.
upvoted 12 times
Selected Answer: R
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-37CC0E44-7BC7-479C-81DC-
FFFC21C1C4E3.html#:~:text=El%20control%20de%20E/S%20de%20almacenamiento%20se,no%20admite%20almacenes%20de%20datos%20con%
20m%C3%BAltiples%20extensiones.
upvoted 1 times
Selected Answer: AC
- Datastores that are SIOC-enabled must be managed by a single vCenter Server system.
- SIOC is supported on Fibre Channel-connected, iSCSI-connected, and NFS-connected storage. Raw Device Mappings (RDMs) are not currently
supported.
- Datastores with multiple extents are not supported by SIOC.
- Before using SIOC on datastores that are backed by arrays with automated storage tiering capabilities, you should check the VMware
Storage/SAN Compatibility Guide to verify whether your automated tiered storage array has been certified to be compatible with SIOC.
upvoted 1 times
Selected Answer: AC
Two possible reasons why Storage I/O Control (SIOC) configuration might not be successful on a datastore are:
A. The datastore contains Raw Device Mappings (RDMs): SIOC does not work with datastores containing Raw Device Mappings.
C. The datastore has multiple extents: SIOC is not supported on datastores with multiple extents.
SIOC is generally compatible with different storage types, including ISCSI and NFS, as long as they meet the other requirements and constraints of
SIOC. The type of disks (e.g., SAS) typically doesn't affect SIOC configuration.
upvoted 1 times
- Storage I/O Control is supported on Fibre Channel-connected, iSCSI-connected, and NFS-connected storage. Raw Device Mapping (RDM) is not
supported.
- Storage I/O Control does not support datastores with multiple extents.
upvoted 1 times
atinivelli 5 months, 1 week ago
Selected Answer: AC
yes finally
upvoted 1 times
C. Ensure that each ESXi host is configured to use a Network Time Protocol (NTP) source.
The company policy states that all physical servers must synchronize time with an external time source that is accurate to the microsecond. In
VMware environments, ESXi hosts are responsible for timekeeping within the virtual infrastructure. By configuring each ESXi host to use a Network
Time Protocol (NTP) source, the administrator can ensure that the hosts synchronize their time with a reliable external time source. NTP is a widely
used protocol for time synchronization and provides sufficient accuracy for most enterprise environments.
upvoted 1 times
Storage I/O Control (SIOC) is a feature of VMware vSphere that helps to improve storage performance by managing the I/O workload across all
virtual machines on a datastore. SIOC can only be configured on datastores that meet the following requirements:
upvoted 1 times
Which two statements are true for this vSphere with Tanzu zonal Supervisor enablement? (Choose two.)
Correct Answer: AD
Selected Answer: BE
BE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-concepts-planning/GUID-3E4E6039-BD24-4C40-8575-5AA0EECBBBEC.html
Selected Answer: AD
When you map vSphere zones to vSphere clusters in a vSphere with Tanzu zonal setup, the following statements are true:
Each zone corresponds to one Supervisor Cluster, and a Supervisor Cluster is created in a specific zone.
D. Individual vSphere Namespaces will be placed into a specific zone.
When you map vSphere zones to clusters, individual vSphere Namespaces are associated with specific zones based on your mapping.
So, you have one Supervisor Cluster in a specific zone, and individual vSphere Namespaces are placed into specific zones according to your
mapping.
upvoted 1 times
Selected Answer: BE
The article states that in a three-zone Supervisor deployment, there are three Supervisor control plane VMs, one in each zone. Each of these control
plane VMs manages the Kubernetes workloads within its respective zone.
E. Individual vSphere Namespaces will be spread across all zones:
The article mentions that a namespace resource pool is created on each vSphere cluster that is mapped to a zone. Since there are three Supervisor
zones, there will be three namespace resource pools, one for each zone. These namespaces are spread across all three underlying vSphere clusters,
and resources are allocated from all three clusters equally.
Therefore, based on the information provided in the article, options A and E are correct for a three-zone Supervisor deployment in vSphere with
Tanzu. Each zone has its own Supervisor, and namespaces are distributed across all zones and their associated vSphere clusters.
upvoted 2 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-installation-configuration/GUID-F776CFFF-F1B2-4121-9BB3-
BBECC80A0D68.html
upvoted 1 times
Selected Answer: BD
Since it doesn't mention a single namespace spread across all 3 zones, I would assume the supervisor would be in a single zone.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-concepts-planning/GUID-3E4E6039-BD24-4C40-8575-5AA0EECBBBEC.html
upvoted 3 times
Selected Answer: AD
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-concepts-planning/GUID-AEC66840-C564-4EF2-B223-1E61A4A1E679.html
upvoted 3 times
Question #34 Topic 1
An administrator is investigating reports of users experiencing difficulties logging into a VMware vCenter instance using LDAP accounts.
B. Lookup Service
Correct Answer: C
Selected Answer: C
Selected Answer: C
https://www.vmware.com/sg/topics/glossary/content/identity-
management.html#:~:text=Identity%20management%20(IdM)%2C%20also,to%20perform%20their%20job%20functions.
upvoted 2 times
When troubleshooting user login issues with LDAP accounts in a VMware vCenter instance, the administrator should check the Lookup Service. The
Lookup Service is responsible for user authentication and identity management, making it a critical component to investigate when encountering
login difficulties.
upvoted 1 times
Selected Answer: C
An administrator is looking to deploy a new VMware vCenter instance. The current environment consists of 75 hosts and is expected to grow up to
A. Medium
B. Tiny
C. Large
D. Small
Correct Answer: A
Selected Answer: D
Selected Answer: D
vCenter Server 8.0 would be sized SMALL for between 10 and 100 hosts (unless running 512 or more shared Storage LUNs / more than 2048 paths,
in which case LARGE would be used)
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-752FCA83-1A9B-499E-9C65-D5625351C0B5.html
upvoted 1 times
With the information we have it s "D - Small" since this will support the 100 hosts. To be able to provide a good answer we should also have an
idea about the amount of VM's that will be running in the environment.
upvoted 1 times
Selected Answer: A
I don't think any administrator would go with a small deployment in this scenario, even though it theoretically fits the requirement. Medium is
correct.
upvoted 1 times
Selected Answer: D
Selected Answer: D
Selected Answer: D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-752FCA83-1A9B-499E-9C65-D5625351C0B5.html
upvoted 4 times
Question #36 Topic 1
An administrator has been notified that a number of hosts are not compliant with the company policy for time synchronization.
All physical servers must synchronize time with an external time source that is accurate to the microsecond.
Which step should the administrator take to ensure compliance with the policy?
A. Ensure that each vCenter Server Appliance is configured to use a Network Time Protocol (NTP) source.
B. Ensure that each ESXi host is configured to use a Precision Time Protocol (PTP) source.
C. Ensure that each ESXi host is configured to use a Network Time Protocol (NTP) source.
D. Ensure that each vCenter Server Appliance is configured to use a Precision Time Protocol (PTP) source.
Correct Answer: C
for sure b
upvoted 3 times
Selected Answer: B
Selected Answer: B
Answer should be B for PTP for microsecond accuracy. NTP is not accurate to that level
upvoted 4 times
Question #37 Topic 1
An administrator is creating a content library to manage VM templates and ISO images. The administrator wants to password-protect the images
Which two tasks must the administration perform when creating the content library? (Choose two.)
E. Enable authentication.
Correct Answer: BE
Selected Answer: AE
AE is the answer. You enable authentication to password protect a content library. The security policy is to protect and enforce strict validation
while importing an synchronizing OVF library items. https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-
A58AF4FD-6CBE-4210-9E67-27EFBDCC1EF2.html
upvoted 6 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-A58AF4FD-6CBE-4210-9E67-27EFBDCC1EF2.html
upvoted 1 times
Selected Answer: AE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-A58AF4FD-6CBE-4210-9E67-27EFBDCC1EF2.html
upvoted 1 times
Selected Answer: AE
You can enable publishing on a local content library by editing its settings.
You can add password protection to the library in the same menu.
upvoted 1 times
Question #38 Topic 1
An administrator is responsible for the management of a VMware vCenter instance that is currently experiencing performance issues. The
administrator quickly identifies that the CPU and memory utilization of vCenter is consistently over 80%. Upon further analysis, it seems that the
A combination of which four steps should the administrator take to resolve the performance issues and ensure that a similar issue can be
C. Power on the vCenter Server Appliance using the vSphere Host Client.
D. Enable CPU and Memory Hot Add on the vCenter virtual machine.
ACDE: You cannot enable hot add while a VM is running, so you must shut it down first. B is wrong, you enable CPU & memory hot add, not just
CPU. You add additional resources while it is powered off to increase performance. Lastly you must power it back on with the host client. You
cannot power on vCenter with the vSphere client when vCenter is not running. ;)
upvoted 10 times
System must be shut down to enable hot add, CPU + Memory needs to be selected for hot add and need to be changed to fix the issue. System
needs to be powered-on using the vSphere Host Client since vCenter is down.
upvoted 2 times
ordering is required,
A- gracefully shutdown.
D- enable add ons.
E- add memory.
F- start vCenter.
upvoted 1 times
An administrator successfully installs VMware ESXi onto the first host of a new vSphere cluster but makes no additional configuration changes.
When attempting to log into the vSphere Host Client using the Fully Qualified Domain Name (FQDN) of the host, the administrator receives the
DHCP: No -
In addition, all host configurations must also meet the following requirements:
Which three high level tasks should the administrator complete, at a minimum, in order to successfully log into the vSphere Host Client using the
A. Ensure a DNS A Record is created for the VMware ESXi host on the corporate DNS servers.
B. Update the VMware ESXi Management Network DNS configuration to use the corporate DNS servers for names resolution.
C. Update the VMware ESXi Management Network IPv4 configuration to use a static a IPv4 address.
D. Configure at least two network adapters for the VMware ESXi Management Network.
E. Set the value of the VMware ESXi Management Network VLAN ID to 10.
The answer is correct based on what is the minimum requirement to log into the host client using the FQDN. B is not required just to log into the
host client, you could set that later.
upvoted 11 times
ADF is correct
The management network must use only IPv4 network protocols.
The management network must be fault tolerant.
other conditions are met
upvoted 6 times
(A) - DNS A record must exist on the DNS servers to connect via FQDN
B - Incorrect, the host is already pointed to the corporate DNS servers
C - Incorrect, "DHCP - No" means the IP is already set to static
(D) - This must be done to meet the requirement "The management network must be fault tolerant"
E - Incorrect, the VLAN ID is already set to 10
(F) - This must be done to meet the requirement "The management network must only use IPv4 network protocols"
upvoted 1 times
If we take all requirements, the correct answer could be ACDEF. But the question is to have the strict minimum to be able to connect to the Host
Client via FQDN. So the answer is ACE.
D and F are the final target required, but not the minimum for the connection to Host Client
B is a best practice, but not mandatory depending on the needs on the infrastructure
upvoted 1 times
Read carefully: Only the ISO have been installed, Management networks have NOT CONFIGURED YET. The info IP, VLAN etc have been provided to
you.
A - You need to make sure that the Network team created a DNS entry for you
C - Setup the management network e.g. IP Mask Gateway DNS
E - Setup the VLAN to 10
The default is automatic. For automatic DNS to work, your network environment must have a DHCP server and a DNS server.
In network environments where automatic DNS is not available or not desirable, you can configure static DNS information, including a host name, a
primary name server, a secondary name server, and DNS suffixes.
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.esxi.install.doc/GUID-D69AB84A-84DA-4AD0-851B-3964CAB53E36.html
I think configure DNS is mandatory
upvoted 1 times
DHCP: No
C. Update the VMware ESXi Management Network IPv4 configuration to use a static a IPv4 address.
ADF, D&F to meet requirements, A is minimum to reach ESXi using FQDN (B is good to do, but question asks for the MINIMUM)
upvoted 1 times
When configuring vCenter High Availability (HA), which two statements are true regarding the active, passive, and witness nodes? (Choose two.)
Correct Answer: AD
Selected Answer: AD
"Network latency between the Active, Passive, and Witness nodes must have less than 10 milliseconds and a minimum of a 1 Gbps network."
https://kb.vmware.com/s/article/2148003
upvoted 1 times
A + D is correct : https://kb.vmware.com/s/article/2148003
upvoted 2 times
Answer is correct
upvoted 4 times
An administrator is deploying a new all flash vSAN cluster based on the vSAN Original Storage Architecture (OSA).
What is the minimum supported network throughput in Gb/s for each host?
A. 50
B. 10
C. 25
D. 1
Correct Answer: C
Selected Answer: B
The answer is B for OSA. 25GB is required for ESA configurations. https://docs.vmware.com/en/VMware-vSphere/8.0/vsan-planning/GUID-
AFF133BC-F4B6-4753-815F-20D3D752D898.html
upvoted 10 times
Selected Answer: B
vSAN OSA: Dedicated 1 Gbps for hybrid configurations, dedicated or shared 10 Gbps for all-flash configurations
vSAN ESA: Dedicated or shared 25 Gbps
upvoted 1 times
To take advantage of the full potential of all-flash storage, a higher network bandwidth is recommended to ensure that data can be quickly and
efficiently transmitted between the hosts in the vSAN cluster.
Selected Answer: B
Ans: B
vSAN Express Storage Architecture (ESA) are only supported with 25Gbps and higher connection speeds. ESA ReadyNodes configured for vSAN
ESA will be configured with 25/50/100Gbps NICs.
vSAN OSA all-flash configurations are only supported with a 10Gb or higher connections. One reason for this is that the improved performance
with an all-flash configuration may consume more network bandwidth between the hosts to gain higher throughput.
https://core.vmware.com/resource/vmware-vsan-design-guide#sec6815-sub3
upvoted 2 times
Selected Answer: B
Ans: B
Networking Minimums 25Gbps minimum for ESA. 10Gbps minimum for OSA
https://core.vmware.com/blog/comparing-original-storage-architecture-vsan-8-express-storage-architecture
upvoted 2 times
Question #42 Topic 1
An administrator enables Secure Boot on an ESXi host. On booting the ESXi host, the following error message appears:
C. The administrator attempted to boot with a bootloader that is unsigned or has been tampered with.
Correct Answer: C
Selected Answer: A
Selected Answer: A
ttps://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-5D5EE0D1-2596-43D7-95C8-0B29733191D9.html
A
Troubleshooting UEFI Secure Boot
If secure boot does not succeed at any level of the boot sequence, an error results.
The error message depends on the hardware vendor and on the level at which verification did not succeed.
If you attempt to boot with a bootloader that is unsigned or has been tampered with, an error during the boot sequence results. The exact
message depends on the hardware vendor. It might look like the following error, but might look different.
UEFI0073: Unable to boot PXE Device...because of the Secure Boot policy
If the kernel has been tampered with, an error like the following results.
Fatal error: 39 (Secure Boot Failed)
If a package (VIB or driver) has been tampered with, a purple screen with the following message appears.
UEFI Secure Boot failed:
Failed to verify signatures of the following vibs (XX)
upvoted 2 times
To keep virtual machines (VMs) up and running at all times in a vSphere cluster, an administrator would like VMs to be migrated automatically
A. Predictive DRS
B. Proactive HA
Correct Answer: B
Selected Answer: B
Answer is correct. Proactive HA remediates based on host degradation. Be familiar with automation level and remediation options as well for the
test.
upvoted 8 times
Selected Answer: B
Proactive HA is used. It works with DRS to move the VMs to other hosts.
Predictive DRS is linked with vRealize Operations to predict the resource usages and better load balance the workloads compared to the simple
DRS. Nothing to see with hardware health status.
upvoted 1 times
HA is used to restart VMs (causing a migration) when a host fails. Proactive HA responds when there is a partial failure on teh host.
DRS will monitor host 'health' and move VMs based on the DRS score and configured automation level.
The question stipulates that VMs will be moved automatically when host health degrades.
Answer is A - Predictive DRS.
upvoted 1 times
Selected Answer: B
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-availability/GUID-3E3B18CC-8574-46FA-9170-CF549B8E55B8.html
https://kb.vmware.com/s/article/92177
upvoted 1 times
Selected Answer: A
The key word her is "VMs to be migrated automatically" when the host hardware health status becomes degraded. (A). Predictive DRS
upvoted 1 times
An administrator wants to allow a DevOps engineer the ability to delete Tanzu Kubernetes Grid (TKG) cluster objects in a vSphere Namespace.
Which role would provide the minimum required permissions to perform this operation?
A. Administrator
B. Can View
C. Owner
D. Can Edit
Correct Answer: D
Selected Answer: D
Answer is correct
upvoted 6 times
D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-tkg/GUID-223D91FB-C4CB-4DA7-8B3F-24721ABDFBC7.html
Can Edit > Can create, read, update, and delete TKG cluster objects in the vSphere Namespace.
upvoted 1 times
Question #45 Topic 1
A group of new virtual machines have been deployed using thin-provisioned disks due to the limited storage space available in an environment.
The storage team has expressed concern about extensive use of this type of provisioning.
An administrator is tasked with creating a custom alarm to notify the storage team when thin provisioning reaches a certain capacity threshold.
A. Datastore
B. Data center
C. Datastore cluster
D. Virtual machine
Correct Answer: C
Selected Answer: A
A datastore cluster is not mentioned, so it should be creating the alarm on the datastore. Answer A
upvoted 7 times
Selected Answer: B
The most effective way is setting one alarm on the DataCenter, covering for all Datastores
upvoted 1 times
You can create an alarm definition for "Datastore Disk Usage" under datacenter, datastore cluster and datastore and spread what you have
triggered under a relevent target type which will be an appropriate child objects (for example "All datastore", "All datastore cluster" and the other
type of objects because you will not find it the "Datastore Disk Usage" ).
So i think the purpose of the question is not "where is it possible to configure" but how should it be configured.
But if you choose "Datastore Cluster" it will monitor the aggregation of all the datastore and it will not be relevent because you can have the
threshold triggered on datastore but it will not trigger the alarm defined under the datastore cluster.
=> "Datastore" Option A
upvoted 2 times
Selected Answer: B
Since no datastores are menthioned, the answer shoulb be "DATACENTER" cause all the DS will be monitored. Otherwise you should set the alarm
manually for all DS.
upvoted 2 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-monitoring-performance/GUID-82933270-1D72-4CF3-A1AF-
E5A1343F62DE.html#:~:text=Datastore%20usage%20on%20disk
upvoted 2 times
Bert_77 2 months, 3 weeks ago
Selected Answer: B
tricky. But as the question do not mention a specific datastore we can consider that this alarm should work for all storage in the organisation. So I
bet for answer B
upvoted 3 times
What are three options an administrator can configure after creating a vSphere Namespace? (Choose three.)
A. Backup schedule
B. Certificates
C. Storage policies
D. Update policies
E. Permissions
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-with-tanzu-services-workloads/GUID-177C23C4-ED81-4ADD-89A2-
61654C18201B.html
upvoted 3 times
Question #47 Topic 1
A VMkernel port is labelled PROD01 and uses the default TCP/IP stack. Currently, this VMkernel port is configured for supporting live virtual
Which configuration change should the administrator make to isolate live VM migration traffic from other network traffic?
A. Remove PROD01 and create a new VMkernel port and set the TCP/IP stack to vSphere vMotion.
B. Remove PROD01 and create a new VMkernel port with the TCP/IP stack set to provisioning.
C. Create a new VMkernel port and set the TCP/IP stack to provisioning.
Correct Answer: D
Selected Answer: A
Answer A
upvoted 5 times
Selected Answer: D
Answer is correct.
upvoted 5 times
Selected Answer: A
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-AA3656B0-005A-40A0-A293-
4309C5ACF682.html#:~:text=Once%20you%20set%20a%20TCP/IP%20stack%20for%20the%20VMkernel%20adapter%2C%20you%20cannot%20ch
ange%20it%20later
upvoted 2 times
Selected Answer: A
seems so
upvoted 3 times
Selected Answer: A
Select a TCP/IP stack from the list. Once you set a TCP/IP stack for the VMkernel adapter, you cannot change it later. If you select the vMotion or
the Provisioning TCP/IP stack, you will be able to use only these stacks to handle vMotion or Provisioning traffic on the host. All VMkernel adapters
for vMotion on the default TCP/IP stack are disabled for future vMotion sessions. If you set the Provisioning TCP/IP stack, VMkernel adapters on the
default TCP/IP stack are disabled for operations that include Provisioning traffic, such as virtual machine cold migration, cloning, and snapshot
migration.
upvoted 3 times
Ans: D
You can change the TCP/IP Stack
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-D4AF4F9F-F274-4ADE-98F4-1CB44ABCC505.html
upvoted 1 times
After adding a new vSphere ESXi host with identical hardware configuration to an existing vSphere cluster, which task would an administrator
Correct Answer: B
Selected Answer: A
Answer is A. It is an identical host and a host profile already exists, so attach the existing host profile to the new host.
upvoted 5 times
Selected Answer: A
Host Profiles can be applied to individual hosts, a cluster, or all the hosts and clusters associated to a host profile. Applying a Host Profile to a
cluster affects all hosts in the cluster and result in a consistent configuration across the applied hosts.
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.hostprofiles.doc/GUID-0E5BF330-A765-4CDB-A97C-1D8C26260E5A.html
upvoted 2 times
sure a
upvoted 2 times
Question #49 Topic 1
An administrator is tasked with deploying a new on-premises software-defined data center (SDDC) that will contain a total of eight VMware
vCenter instances.
All vCenter inventory should be searchable from a single vSphere Client session.
Any administrator must be able to complete operations on any vCenter instance using a single set of credentials.
A. Two Enhanced Linked Mode groups consisting of four vCenter instances each in a Single Sign-On domain.
B. A single Hybrid Linked Mode group consisting of four vCenter instances each in a Single Sign-On domain.
C. A single Enhanced Linked Mode group consisting of eight vCenter instances in one Single Sign-On domain.
D. A single Hybrid Linked Mode group consisting of eight vCenter instances in one Single Sign-On domain.
Correct Answer: C
Selected Answer: C
Answer is correct. Hybrid linked mode is to connect a hyperscaler based SDDC such as VMC on AWS and a single SSO is required based on the
requirements.
upvoted 6 times
Selected Answer: C
You can join up to 15 vCenters with one enhanced linked mode group
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-installation/GUID-4394EA1C-0800-4A6A-ADBF-D35C41868C53.html
upvoted 5 times
Selected Answer: C
C. A single Enhanced Linked Mode group consisting of eight vCenter instances in one Single Sign-On domain.
Enhanced Linked Mode (ELM) is designed to provide a single view of multiple vCenter instances within a single vSphere Client session. It allows you
to search and manage the inventory across these vCenter instances seamlessly while maintaining a single sign-on domain for ease of
administration. This configuration aligns with the stated requirements. Hybrid Linked Mode typically involves linking on-premises and cloud-based
vCenter servers, which is not required for the scenario described.
upvoted 1 times
Join up to 15 vCenter Server appliance deployments with vCenter Enhanced Linked Mode in a single vSphere Single Sign-On domain
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-installation/GUID-4394EA1C-0800-4A6A-ADBF-
D35C41868C53.html#:~:text=join%20up%20to%2015%20vCenter%20Server%20appliance%20deployments%20with%20vCenter%20Enhanced%20L
inked%20Mode%20in%20a%20single%20vSphere%20Single%20Sign%2DOn%20domain.
upvoted 2 times
Question #50 Topic 1
An administrator has Windows virtual machines (VMs) and VMware Tools is installed in each VM. The administrator performs a status check of
What is the VMware Tools status for the Windows VMs if the version of VMware Tools has a known problem and must be immediately upgraded?
A. Version Unsupported
B. Guest Managed
C. Unknown
D. Upgrade Available
Correct Answer: D
Selected Answer: A
Ans: A
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-196AACC7-F5D1-43B8-9DCE-
DD529C017A8C.html#:~:text=VMware%20Tools%20is%20installed%2C%20but%20the%20version%20has%20a%20known%20issue%20and%20mu
st%20be%20immediately%20upgraded.
VMware Tools is installed, but the version has a known issue and must be immediately upgraded.
VMware Tools is installed, but the version is too new to work correctly with this virtual machine.
upvoted 2 times
Selected Answer: A
If VMware Tools has a known problem, the tools status will be Version Unsupported
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere-lifecycle-manager.doc/GUID-12649CBB-F69A-4199-8957-
B4C0170B4E9A.html
upvoted 3 times
Selected Answer: D
Answer is correct.
upvoted 2 times
Which three features are only available when using vSphere Distributed Switches instead of vSphere Standard Switches? (Choose three.)
A. 802.1Q tagging
B. Port mirroring
C. Netflow
E. IPv6 support
F. IPv4 support
BCE are networking monitoring and troubleshooting. AEF are standard networking.
https://www.vmware.com/sg/products/vsphere/distributed-
switch.html#:~:text=physical%20network%20configuration-,Enhanced%20Network%20Monitoring%20and%20Troubleshooting%20Capabilities,-
The%20VDS%20provides
upvoted 1 times
yess so
upvoted 2 times
Answer is correct.
upvoted 2 times
Question #52 Topic 1
An administrator is configuring vSphere Lifecycle Manager to install patches to a vSphere cluster. The cluster runs workload virtual machines
(VMs) that are incompatible with vSphere vMotion, and therefore cannot be live migrated between hosts during the installation of the patches.
Which configuration in vSphere Lifecycle Manager will allow the administrator to reduce the downtime associated with the patching operation
A. Enable Distributed Power Management (DPM) and set the VM power state to the suspend to disk option
B. Enable Quick Boot ana set the VM power stale to the suspend to disk option
C. Enable vSphere High Availability (HA) admission control and set the VM power stale to the suspend to memory option
D. Enable Quick Boot and set the VM power state to the suspend to memory option
Correct Answer: D
Selected Answer: D
Together with Quick Boot, the Suspend to memory option provides faster host upgrades. vSphere Lifecycle Managersuspends to the host memory
and not to the disk the powered on virtual machines on the host. After the Quick Boot, the suspended virtual machines are resumed from memory.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-06A5D316-9452-4A5D-A5BB-
3AEEFE0483B4.html#:~:text=memory%20option%20is%20dimmed.-,Together%20with%20Quick%20Boot%2C%20the%20Suspend%20to%20memo
ry%20option%20provides%20faster%20host%20upgrades.,-vSphere%20Lifecycle%20Managersuspends
upvoted 1 times
Selected Answer: D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-06A5D316-9452-4A5D-A5BB-3AEEFE0483B4.html
upvoted 2 times
Selected Answer: D
The answer looks to be correct. Quick boot + suspend memory allows you to more quickly patch a host when vMotion cannot be used with VMs.
https://kb.vmware.com/s/article/81555
upvoted 2 times
Question #53 Topic 1
An administrator creates a new corporate virtual machine (VM) template every month to include all of the latest patches. The administrator needs
to ensure that the new VM template is synchronized from the primary data center site (London) to two secondary data center sites (Tokyo and
New York). The administrator is aware that datastore space is limited within the secondary data center sites. The administrator needs to ensure
that the VM template is available in the secondary sites the first time a new virtual machine is requested.
Which four steps should the administrator take to meet these requirements? (Choose four.)
ADEG: You create a published library at the primary site, subscribed in each secondary site, configure to download when needed (due to limited)
space and add the template to the primary site.
upvoted 9 times
The administrator should create a new published content library at the primary site (London) and then create a new subscribed content library in
each secondary site (Tokyo and New York). The subscribed content libraries should be configured to download content when needed, except for
the Tokyo subscribed content library, which should be configured to download content immediately. This will ensure that the new VM template is
downloaded to the secondary data centers as soon as possible, while also minimizing the impact on disk space at the Tokyo site.
upvoted 1 times
yess sa
upvoted 1 times
An administrator is tasked with migrating a single virtual machine (VM) from an existing VMware vCenter to a secure environment where
corporate security policy requires that all VMs be encrypted. The secure environment consists of a dedicated vCenter instance with a 4-node
Which two steps must the administrator take to ensure the migration is a success? (Choose two.)
A. Ensure that the source and destination vCenter instances share the same Key Management Server (KMS).
E. Ensure that the source and destination vCenter Servers have a different Key Management Server (KMS).
Correct Answer: AC
you cannot change encryption state during a vmotion so if you want the vm to be protected as soon as it arrives in the new cluster. It should be
protected before leaving...
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vcenterhost.doc/GUID-6865D84A-C286-49C4-A4D4-D62145150242.html
upvoted 3 times
An administrator is tasked with providing users access to objects within an existing VMware vCenter instance. The vCenter inventory has a single
data center with one management vSphere cluster and five workload vSphere clusters.
The following requirements must be met for assigning the users access:
Users must only be able to view all of the inventory objects associated with the management vSphere cluster.
Users must be able to edit all of the inventory objects associated with the workload vSphere clusters.
The administrator creates a custom role to provide the permissions needed to allow users to edit inventory objects.
Which series of steps should the administrator complete to assign the custom role and provide the required level of access to users?
A. Apply Global permissions to assign the Read Only role to the root vCenter object.
Apply vCenter permissions to assign the custom role to the workload vSphere clusters and enable propagation.
B. Apply Global permissions to assign the Read Only role to the root vCenter object and enable propagation.
Apply vCenter permissions to assign the custom role to the workload vSphere clusters and enable propagation.
C. Apply Global permissions to assign the Read Only role to the root vCenter object.
Apply vCenter permissions to assign the custom role to the workload vSphere clusters.
D. Apply Global permissions to assign the Read Only role to the root vCenter object and enable propagation.
Apply vCenter permissions to assign the custom role to the workload vSphere clusters.
Correct Answer: D
Selected Answer: B
"Users must be able to edit ALL OF THE INVENTORY OBJECTS associated with the workload vSphere clusters."
upvoted 1 times
Selected Answer: D
Selected Answer: B
Selected Answer: B
I also opt for option B. What is the point of setting the permission only on the cluster object without propagation? There can be many objects
under a cluster (resource pools, hosts, VMs), etc. I don't want to have to set permissions on them separately. Definitely B!
upvoted 1 times
Selected Answer: D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-esxi-vcenter-801-security-guide.pdf
upvoted 1 times
Propagation is needed
upvoted 2 times
Selected Answer: B
i'd say B
upvoted 2 times
Selected Answer: B
I think I'll go for B. Without propagation on workload clusters, you'll get custom roles only at the root level where you apply permission
upvoted 2 times
Selected Answer: D
An administrator has a requirement to revert a running virtual machine to a previous snapshot after a failed attempt to upgrade an application.
When the administrator originally took the snapshot, the following choices in the Take Snapshot dialog were made:
What will be the result of the administrator selecting the “Revert to Latest Snapshot” option to return the virtual machine to a previous snapshot?
A. The virtual machine will be restored to the parent snapshot in a powered on state.
B. The virtual machine will be restored to the parent snapshot in a powered off state.
C. The virtual machine will be restored to the child snapshot in a powered off state.
D. The virtual machine will be restored to the child snapshot in a powered on state.
Correct Answer: B
On the exam there is same question but with "Snapshot the virtual machine’s memory = true" then the VM will be restored in powered ON state.
upvoted 7 times
Selected Answer: B
From the lecture manual: "The relationship between snapshots is like the relationship between a parent and a child. Snapshots are organized in a
snapshot tree. In a snapshot tree, each snapshot has one parent and one or more children, except for the last snapshot, which has no children." So
definitely reverts to parent. And the powered off state has been well explained already.
upvoted 1 times
Selected Answer: B
Quiesced Snapshots: If the virtual machine is powered off or VMware Tools is not available, the Quiesce parameter is not available.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-50BD0E64-75A6-4164-B0E3-
A2FBCCE15F1A.html#:~:text=the%20virtual%20machine.-,Memory%20Snapshots,-The%20default%20selection
upvoted 1 times
Selected Answer: C
Selected Answer: C
tricky, as we don't know how many snapshot there is. But as it's mentionned in the answer revert to "the" parent snapshot we can imagine that
there is at least another child snapshot. and as we restore to the last snapshot... it must be the child.
upvoted 2 times
surely B
upvoted 1 times
Selected Answer: B
Ans: B
Powered on (does not include memory) Reverts to the parent snapshot and the virtual machine is powered off.
Powered off (does not include memory) Reverts to the parent snapshot and the virtual machine is powered off.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-50BD0E64-75A6-4164-B0E3-A2FBCCE15F1A.html
upvoted 1 times
Answer is correct
upvoted 2 times
Question #57 Topic 1
An administrator is planning to upgrade a VMware vCenter instance to version 8. It is currently integrated with the following solutions:
Which tool can the administrator use to run interoperability reports before the upgrade process?
Correct Answer: C
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vcenter.upgrade.doc/GUID-34912DF0-98DA-49B8-BC9A-D0A0761B71DD.html
upvoted 1 times
Selected Answer: C
Answer is correct for checking interoperability with other VMware products. https://blogs.vmware.com/vsphere/2020/04/vsphere-7-update-
planner.html
upvoted 4 times
Question #58 Topic 1
An administrator decides to restore VMware vCenter from a file-based backup following a failed upgrade.
C. vSphere Client
Correct Answer: B
Selected Answer: D
Selected Answer: D
Answer is D
You can use the vCenter Server appliance GUI installer to restore a vCenter Server to an ESXi host or a vCenter Server instance. The restore
procedure has two stages. The first stage deploys a new vCenter Server appliance. The second stage populates the newly deployed vCenter Server
appliance with the data stored in the file-based backup.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-installation/GUID-F02AF073-7CFD-45B2-ACC8-DE3B6ED28022.html
upvoted 1 times
The vCenter GUI Installer is a graphical user interface that can be used to deploy and restore a vCenter Server appliance. It can be used to restore a
vCenter Server appliance from a file-based backup.
upvoted 1 times
Question #59 Topic 1
An administrator needs to provide encryption for workloads within an existing vSphere cluster.
C. Host Encryption
D. VM Encryption
Correct Answer: C
Selected Answer: D
To meet the requirements of encrypting workloads at rest, automatically encrypting workloads during transit, and not requiring specific hardware,
the administrator should configure:
D. VM Encryption
VM Encryption provides encryption for virtual machines and meets all the specified requirements. It encrypts the VM's data at rest and also ensures
that the data is encrypted during transit. Additionally, VM Encryption does not require specific hardware, making it a suitable choice for this
scenario.
Options A, B, and C do not directly address all of the specified requirements. Encrypted vSphere vMotion (A) is specifically related to encrypting the
vMotion traffic, not the VMs themselves. UEFI Secure Boot (B) is a security feature for booting and does not provide VM-level encryption. Host
Encryption (C) typically refers to encrypting the data on the host's storage devices, which is different from VM-level encryption.
upvoted 2 times
Answer is VM Encryption.
With vSphere Virtual Machine Encryption, you can encrypt your sensitive workloads in an even more secure way. Access to encryption keys can be
made conditional to the ESXi host being in a trusted state.
vSphere vMotion always uses encryption when migrating encrypted virtual machines.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-E6C5CE29-CD1D-4555-859C-
A0492E7CB45D.html#:~:text=encrypt%20your%20sensitive%20workloads
upvoted 2 times
Selected Answer: C
Why not C?
Take a look at the following article:
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-E6C5CE29-CD1D-4555-859C-A0492E7CB45D.html
"Prerequisites and Required Privileges for Virtual Machine Encryption Tasks
Virtual machine encryption tasks are possible only in environments that include vCenter Server. Also, the ESXi host must have encryption mode
activated for most encryption tasks"
I think Host Encryption is a requirement for perform VM Encryption.
In addition, the letter specifies that encryption must occur in transit
upvoted 1 times
Selected Answer: D
Selected Answer: D
VM Encryption, cause this is the only option that not require specific hardware
upvoted 3 times
Selected Answer: D
After a number of outages within a production VMware software-defined data center, an administrator is tasked with identifying a solution to meet
Reduce the risk of outages by proactively identifying issues with the environment and resolving them.
Reduce the complexity of uploading log bundles when raising support tickets.
Correct Answer: C
Selected Answer: B
From O,S,Sv8 7-104; "Skyline Advisor Pro is a self-service web application with which you can view proactive findings and recommendations on-
demand, within a web browser." I think proactive is the key word here.
upvoted 1 times
B:
https://www.vmware.com/ca/support/services/skyline.html
"Automated Log Transfer
Reduce the time and effort you spend on uploading manual log requests with 17 times faster support provided by Skyline Log Assist"
upvoted 1 times
Selected Answer: B
It could be B as this KB also refers to skyline Advisor making it easy to upload logs to the SR.
https://kb.vmware.com/s/article/1008525
upvoted 1 times
Selected Answer: C
I have Skyline Health installed on my production environment precisely for this reason.
upvoted 1 times
Selected Answer: B
B: According to the Skyline Advisor Pro, it meets these requirements, where Skyline Health does not do anything for uploading logs.
https://www.vmware.com/ca/support/services/skyline.html
upvoted 1 times
Selected Answer: B
B, proactive
upvoted 1 times
Selected Answer: C
Answer is correct
upvoted 2 times
Identically configured vSphere ESXi hosts (esx01, esx02, esx03 and esx04)
All workloads are deployed into a single VMFS datastore provided by the external storage array vSphere High Availability (HA) has not been
enabled vSphere Distributed Resource Scheduler (DRS) has not been enabled
Given this scenario, which two actions are required to ensure VM1 continues to run when esx01 is placed into maintenance mode? (Choose two.)
A. Fully automated DRS must be enabled on the cluster so that VM1 will be automatically migrated to another host within the cluster when
B. VM1 must be manually shut down and cold migrated to another host within the cluster using vSphere vMotion before esx01 is placed into
maintenance mode.
C. vSphere HA must be enabled on the cluster so that VM1 will be automatically migrated to another host within the cluster when esx01 is
D. VM1 must be manually live migrated to another host within the cluster using vSphere vMotion before esx01 is placed into maintenance
mode.
E. VM1 must be manually migrated to another host within the cluster using vSphere Storage vMotion before esx01 is placed into maintenance
mode.
Correct Answer: BD
Selected Answer: AD
AD: it seems they are asking which two options would you take to enable moving a VM. you can either enable fully automated DRS and let it move
the VM when the host is put into MX mode or you can manually live migrate it. B is wrong as shutting down the VM is not required for vMotion. C
is wrong as that has nothing to do with moving a VM to a different host. E is wrong because that would only move the storage the VM is on, not
the host.
upvoted 8 times
A and D, but the question seems to be formulated wrong. The question suggest which 2 non optional actions need to be performed; you can use
either of them in the scenario, only one is required at a given time.
upvoted 1 times
Selected Answer: AD
Selected Answer: AD
Ans: A and B
Virtual machines that are running on a host entering maintenance mode need to be migrated to another host (either manually or automatically by
DRS) or shut down. The host is in a state of Entering Maintenance Mode until all running virtual machines are powered down or migrated to
different hosts.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-8F705E83-6788-42D4-93DF-63A2B892367F.html
upvoted 2 times
An administrator needs better performance and near-zero CPU utilization from the ESXi hosts for networking functions and processing. The
administrator creates a new vSphere Distributed Switch and enables network offloads compatibility.
Correct Answer: C
Selected Answer: A
Should be A, the DPUs are used by vSphere Distributed Services Engine which is the solution:
"In vSphere 8.0 and later, vSphere Distributed Services Engine enables the offloading of infrastructure functions from the CPUs of a host or a server
to data processing units (DPUs, also known as SmartNICs), thus freeing up CPU cycles to serve applications."
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-6BB96B0C-2F19-4312-AD10-0CEF03D5D725.html
upvoted 9 times
Selected Answer: B
Selected Answer: A
The vSphere Distributed Services Engine will use the DPUs to offload the networking tasks.
The DPUs are hardware, not a solution in the VMware wording. vSphere Distributed Services Engine is the solution used.
upvoted 1 times
Selected Answer: A
vSphere Distributed Services Engine uses the CPU which has already been configure so it's vSphere Distributed Services Engine which is required
upvoted 1 times
Selected Answer: A
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-41AB1101-D943-490A-BF1A-
E53433855C07.html#:~:text=Starting%20with%20vSphere,processing%20units%20(DPUs).
upvoted 1 times
A, because the question says that network offloads have already been enabled, and that presumes existing DPUs.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-D21B3241-0AC9-437C-80B1-0C8043CC1D7D.html Weird question
though.
upvoted 1 times
vSphere Distributed Services Engine alone does not allow networking operations from CPU to the DPU device.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-41AB1101-D943-490A-BF1A-
E53433855C07.html#:~:text=The%20network%20offloads%20compatibility%20allows%20you%20to%20offload%20networking%20operations%20t
o%20the%20DPU%20device.
upvoted 2 times
Selected Answer: B
Selected Answer: B
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-41AB1101-D943-490A-BF1A-E53433855C07.html
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-security/GUID-6BB96B0C-2F19-4312-AD10-0CEF03D5D725.html
upvoted 1 times
Selected Answer: A
In vSphere 8, vSphere Distributed Services Engine unlocks the power of SmartNICs/Data Processing Units (DPUs) for hardware accelerated data
processing to boost infrastructure performance.
upvoted 4 times
An administrator needs to perform maintenance on a datastore that is running the vSphere Cluster Services (vCLS) virtual machines (VMs).
Which feature can the administrator use in this scenario to avoid the use of Storage vMotion on the vCLS VMs?
B. vSphere vMotion
Correct Answer: D
Selected Answer: D
Answer D of course
upvoted 1 times
Selected Answer: D
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-F98C3C93-875D-4570-852B-37A38878CE0F.html
upvoted 1 times
Selected Answer: D
Answer is correct.
upvoted 1 times
Question #64 Topic 1
A. Provide a live shadow instance of a virtual machine (VM) that mirrors the primary VM to prevent data loss and downtime during outages
B. Implement Quality of Service (QoS) on network traffic within a vSphere Distributed Switch
D. Redistribute virtual machines across vSphere cluster hosts to comply with user-defined affinity and anti-affinity rules following host failures
Correct Answer: D
Selected Answer: C
Distributed Services Engine modernizes virtual infrastructure by utilizing DPUs to accelerate network functions and secure workloads
upvoted 1 times
D is DRS
upvoted 1 times
Distributed Services Engine modernizes virtual infrastructure by utilizing DPUs to accelerate network functions and secure workloads
upvoted 1 times
Selected Answer: C
Answer is C. Again referring to SmartNics, which speeds up infrastructure by offloading network data from CPU.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-41AB1101-D943-490A-BF1A-E53433855C07.html
upvoted 2 times
Question #65 Topic 1
A vSphere cluster has the following vSphere Distributed Resource Scheduler (DRS) group configuration:
The administrator wants to force the VMs in the DB group to run on the hosts in the PROD11 group. However, if all the hosts in PROD11 go offline
for maintenance, then the VMs in the DB group should run on hosts in PROD55.
Which VM/Host rule must the administrator create to ensure that these requirements are met?
Correct Answer: C
Selected Answer: A
... surely
upvoted 3 times
A preferential rule between the DB group and the PROD11 group. This is the only rule that accomplish them.
upvoted 3 times
Selected Answer: A
A: If you add a required rule, the VMs will only run on the specified cluster and cannot run anywhere else.
upvoted 4 times
Question #66 Topic 1
An administrator is asked to configure a security policy at the port group level of a standard switch.
Correct Answer: D
Selected Answer: D
https://kb.vmware.com/s/article/1002934
upvoted 2 times
Selected Answer: D
networking basis
upvoted 2 times
Selected Answer: D
Answer is correct.
upvoted 3 times
Question #67 Topic 1
Following a merger with another company, an administrator is tasked with configuring an identity source for VMware vCenter so that all vSphere
administrators can authenticate using their existing Active Directory accounts. Each company has user accounts in their own Active Directory
forests.
The corporate policy states that only Windows-based machine accounts are allowed in Active Directory.
Which action should the administrator take to configure vCenter Single Sign-On (SSO) to meet this requirement?
A. Configure SSO to use Active Directory over LDAP as the identity source.
D. Configure SSO to use Active Directory (Integrated Windows Authentication) as the identity source.
Correct Answer: D -
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.authentication.doc/GUID-1F0106C9-0524-4583-9AC5-
A748FD1DC4C5.html
upvoted 1 times
"The Active Directory over LDAP identity source is preferred over the Active Directory (Integrated Windows Authentication) option. The OpenLDAP
Server identity source is available for environments that use OpenLDAP."
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.authentication.doc/GUID-98B36135-CDC1-435C-8F27-5E0D0187FF7E.html
upvoted 3 times
Selected Answer: A
a because of depreciation
upvoted 3 times
Selected Answer: A
Answer is correct.
upvoted 1 times
An administrator notices a performance issue in VMware vCenter. To try and understand more about the performance issue, the administrator
needs to gather more information about the vCenter database to eliminate a potential disk space issue.
B. Perfmon
C. df
D. esxtop
E. vSphere Client
Correct Answer: AE
Selected Answer: AC
Selected Answer: AC
An administrator notices a Fibre Channel adapter in an ESXi host has been experiencing incon-sistent connectivity states.
Which trigger can be used to quickly identify the issue and alert the administrator so that the is-sue can be resolved?
Correct Answer: D
Selected Answer: B
Selected Answer: D
https://kb.vmware.com/s/article/1003680#:~:text=SCSI%3A%204506%3A%20%22Cannot%20find%20a%20path%20to%20device%20vmhba1%3A0
%3A8%20in%20a%20good%20state%22
https://kb.vmware.com/s/article/2021948
upvoted 1 times
I think it D
upvoted 1 times
Selected Answer: D
Selected Answer: D
Selected Answer: D
Selected Answer: D
https://kb.vmware.com/s/article/2021948
upvoted 1 times
Selected Answer: B
Complicated, the question does not comment on whether the path is redundant, if not redundant the correct answer would be D, but if we take
into account good practices, the FC would be redundant, and the correct answer would be B.
https://kb.vmware.com/s/article/2014553
upvoted 2 times
An administrator is tasked with looking into the disaster recovery (DR) options for a software-defined data center (SDDC).
A. Configure VMware Cloud Disaster Recovery (VCDR) and combine it with array-based stor-age replication.
B. Configure VMware a Site Recovery Manager and combine it with vSphere Replication.
D. Configure VMware Site Recovery Manager and combine it with array-based storage replica-tion.
Correct Answer: B
Selected Answer: B
https://kb.vmware.com/s/article/84322
upvoted 1 times
Selected Answer: B
The correct answer I believe is B, the VCDR is not manageable by the vSphere Client.
https://blogs.vmware.com/virtualblocks/2017/11/29/vsr-technicaloverview/
upvoted 3 times
An administrator needs to update a VMware vCenter instance to a newer minor release version. Due to restrictions within the environment, the
vCenter instance does not have access to the In-ternet. As a first step, the administrator downloads the required update on another machine.
What are the next steps the administrator must perform to complete the update?
A. Place the update ISO file in a Virtual Machine File System (VMFS) datastore.
Use the vSphere Client to select the update ISO file as the source for the update.
B. Mount the ISO update file to the CD-ROM drive of the vCenter instance.
Use the vCenter Management Interface to select the CD-ROM as the source for the update.
C. Place the ISO update file in a folder accessible to the vCenter instance over HTTPS.
Use the vCenter Management Interface to select the update file as the source for the update.
D. Place the ZIP update file in a folder accessible to the vCenter instance over HTTPS.
Use the vSphere Client to select the update file as the source for the update.
Correct Answer: B
Selected Answer: B
Selected Answer: D
Selected Answer: B
Here are the steps to update a vCenter instance with an update ISO file that is not accessible over the Internet:
Place the update ISO file in a VMFS datastore that is accessible to the vCenter instance.
Log in to the vSphere Client.
Click Hosts and Clusters.
Right-click the vCenter instance that you want to update and select Update.
In the Select Update Source dialog box, select Local File.
Click Browse and select the update ISO file that you placed in the VMFS datastore.
Click Next.
Review the update details and click Install.
The vCenter instance will be updated.
The other options are incorrect:
upvoted 1 times
An administrator is tasked with allowing a single user the ability to take snapshots on a virtual machine. When looking in vCenter, the
administrator can see that there are already users and groups assigned permissions on the virtual machine as follows:
• The group VM_Users has the Virtual Machine Power User role.
The administrator confirms that the user requesting the additional access is currently one of five members of the VM_Viewers group.
Which two steps should the administrator take to grant this user the additional access required without impacting the user access of others?
(Choose two.)
A. Add the user to the VM_Users group and leave the permissions on the virtual machine object unchanged.
B. Add a new permission on the virtual machine object selecting the user and the new custom role.
C. Edit the Read Only role to add the Virtual Machine Snapshot Management privileges.
D. Create a new custom role with the Virtual Machine Snapshot Management privileges.
E. Add a new permission on the virtual machine object selecting the VM_Viewers group and the new custom role.
Correct Answer: BD
Selected Answer: BD
B-> Assign a role to a particular user to give that user permissions to perform specific tasks on a virtual machine.
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.hostclient.doc/GUID-ECBC6397-3BBE-4F9A-A70E-E80E65EB37DB.html
D-> Virtual machine snapshot management privileges control the ability to take, delete, rename, and restore
snapshots.https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.security.doc/GUID-222FE721-0968-4E9E-9F98-
7CB03E7185E8.html
upvoted 1 times
An administrator is preparing to perform an update to vSphere clusters that are running vSAN. The administrator wants to ensure that the
• All hosts in the cluster are updated with the same software.
• The new software versions are checked for compliance against the vSAN Hardware Compatibility List.
Which three steps should the administrator take to meet these requirements? (Choose three.)
ABE
"...to perform firmware updates on hosts that are of ESXi version 8.0 and later and that are in a vSAN cluster, you must manage that cluster with a
single image. You must also deploy an OEM-provided hardware support manager and register it as a vCenter Server extension. The hardware
support manager inspects the hardware of the hosts in the cluster and lists available and compatible firmware versions, which you can add to the
image for the cluster. The actual firmware update happens upon remediating the cluster against an image that contains a firmware add-on."
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-6906DCFA-F4A4-4A67-A86D-2F56AB0B3B38.html
upvoted 8 times
Answers can be found by using both documents listed below. The first one explains options A+B the second one explains option E
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-lifecycle-manager/GUID-6906DCFA-F4A4-4A67-A86D-2F56AB0B3B38.html
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere-lifecycle-manager.doc/GUID-34AF5B19-FC80-4915-8358-
D5FCC8A8E69E.html
upvoted 2 times
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere-lifecycle-manager.doc/GUID-34AF5B19-FC80-4915-8358-
D5FCC8A8E69E.html#GUID-34AF5B19-FC80-4915-8358-D5FCC8A8E69E
upvoted 1 times
A. because you must use an image, B. the server vendor HW manager must be registered, it will show you the needed firmware updates that D. you
should download from the vendor depot and add to the image.
upvoted 3 times
To meet the requirements of the scenario, the administrator should take the following steps:
Configure vSphere Lifecycle Manager with an image for the cluster. This will ensure that all hosts in the cluster are updated with the same software.
Run a hardware compatibility check using vSphere Lifecycle Manager. This will ensure that the new software versions are checked for compliance
against the vSAN Hardware Compatibility List.
Configure vSphere Lifecycle Manager with a baseline for the cluster. This will ensure that the firmware versions on the hosts are updated.
upvoted 1 times
An administrator is asked to segregate virtual machine (VM) traffic by VLAN on a vSphere standard switch.
B. None
Correct Answer: C
Selected Answer: C
https://kb.vmware.com/s/article/1004252?lang=es
upvoted 1 times
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-networking/GUID-7225A28C-DAAB-4E90-AE8C-795A755FBE27.html
upvoted 2 times
C - (Virtual machine)
upvoted 1 times
An administrator wants to use tag-based placement rules on their virtual machine disks using VMware vCenter.
Correct Answer: A
A is correct
https://vnote42.net/2020/01/15/vcenter-tag-based-vm-placement/
upvoted 5 times
Selected Answer: A
VM Storage Policy
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.storage.doc/GUID-D025AA68-BF00-4FC2-9C7E-863E5787E743.html
upvoted 1 times
A combination of which two components of the software-defined data center (SDDC) are re-sponsible for the initial abstraction of CPU, memory,
disk, and network resources and their sub-sequent management? (Choose two.)
C. VMware vCenter
D. VMware ESXi
Correct Answer: CD
Selected Answer: CD
What are two use cases for VMware vSphere+? (Choose two.)
A. Enhance on-premises workloads by managing them through the VMware Cloud Console.
D. Allow the creation of affinity and anti-affinity rules to be used during failover events.
Correct Answer: AE
Selected Answer: AE
A : Centralized Cloud Console. Enable IT administrators to consolidate management of all vSphere deployments with the vSphere+ Cloud Console.
E: vCenter Lifecycle Management Service. Update an entire fleet of ESXi hosts in one operation, across multiple vCenters and clusters, and centrally
monitor progress from the Cloud Console
https://www.vmware.com/products/vsphere/vsphere-plus.html#features
upvoted 1 times
An administrator is completing the configuration of a new vSphere cluster and has enabled vSphere High Availability (HA) and vSphere Distributed
After adding the ESXi hosts to the cluster, which networking information will the administrator be prompted to provide when using the Cluster
Quickstart workflow?
A. vMotion networking
B. Management networking
C. vSAN networking
Correct Answer: A
Selected Answer: A
A is correct
upvoted 2 times
An administrator plans to bring VMware vCenter offline in order to perform hardware mainte-nance on the host where the vCenter Server Appliance
is running.
Which vSphere feature must be configured to ensure that vCenter users experience minimal downtime?
Correct Answer: C
Selected Answer: A
With DRS if you put the host in maintanance mode it will migrate the VM to the other host without downtime right ? With HA there will be
downtime.
upvoted 1 times
C is correct
upvoted 2 times
Which two tasks can be completed using vSphere LifeCycle Manager? (Choose two.)
A. Manage the firmware lifecycle of ESXi hosts that are part of a managed cluster with a single image.
B. Check that the ESXi hosts are compliant with the recommended baseline and update the hosts.
D. Check the hardware compatibility of the hosts in a cluster against the VMware Compatibility Guide (VCG) using baselines.
E. Manage the firmware lifecycle of ESXi hosts are part of a managed cluster using baselines.
Correct Answer: AB
Firmware updates and Hardware compatibility checks are not supported with baslines (only with iamges).
.A - Manage the firmware lifecycle of ESXi hosts that are part of a managed cluster with a single image. - You can do it.
B - Check that the ESXi hosts are compliant with the recommended baseline and update the hosts. - You can do it.
C - Upgrade VMware vCenter from version 7 to 8. - Haha
D - Check the hardware compatibility of the hosts in a cluster against the VMware Compatibility Guide (VCG) using baselines. - You cannot do it
with baselines.
E - Manage the firmware lifecycle of ESXi hosts are part of a managed cluster using baselines. - You cannot do it with baselines.
Selected Answer: AD
I believe its A and D.. Key word is use of image for vCLM.
Software & firmware updates happen simultaneously in a single workflow.
Specifically, a vLCM Image is a combination of software, drivers, and firmware
installs & upgrades all packaged together. When creating an Image, there are 4
potential components you can add:
§ ESXi version – this component is mandatory; others are optional
§ Vendor add-on
§ Firmware and drivers add-on
§ Any additional components
Another advantage of vLCM is the ability to check ESXi Hosts hardware against
the VMware Compatibility Guide (VCG).
upvoted 2 times
AB
D is wrong, cause lilecycle manager only checks vsan hardware compatibility (network and storage devices)
upvoted 2 times
Selected Answer: BD
vSphere Lifecycle Manager automates the process of validating the hardware compliance of hosts and clusters against a selected ESXi version
upvoted 1 times
An administrator is tasked with implementing a backup solution capable of backing up the Su-pervisor cluster, vSphere Pods, and persistent
volumes.
Which two solutions must be used to meet this requirement? (Choose two.)
A. VMware vCenter
C. NSX-T Manager
Correct Answer: BE
I agree with BE
https://docs.vmware.com/en/VMware-vSphere/7.0/vmware-vsphere-with-tanzu/GUID-9816E07A-466C-451D-A43B-D415B2FAB7D6.html
upvoted 8 times
Selected Answer: BE
You can use the Velero Plugin for vSphere to backup and restore workloads running on a Tanzu Kubernetes cluster by installing the Velero Plugin
for vSphere on that cluster. https://docs.vmware.com/es/VMware-vSphere/7.0/vmware-vsphere-with-tanzu/GUID-E34B8859-A23D-4661-8165-
99E6AB9DA99E.html
You can backup and restore Tanzu Kubernetes cluster workloads using standalone Restic and Velero. https://docs.vmware.com/es/VMware-
vSphere/7.0/vmware-vsphere-with-tanzu/GUID-9816E07A-466C-451D-A43B-D415B2FAB7D6.html
upvoted 1 times
Selected Answer: BE
VMware vCenter provides centralized management and orchestration capabilities for your entire vSphere environment, including Supervisor
clusters, vSphere Pods, and associated resources. It's an essential component for managing and configuring backups.
Velero is a popular open-source tool for Kubernetes cluster backups, including backing up vSphere Pods and persistent volumes. When used in
conjunction with Restic, it offers robust backup capabilities for container workloads in your environment.
upvoted 1 times
Question #82 Topic 1
An administrator receives reports from the application team of poor performance of a virtual ma-chine (VM). The administrator reviews the virtual
machine and discovers that it has 20 snapshots that are over 12 months old.
Correct Answer: C
Selected Answer: C
c correct
upvoted 1 times
A vSphere cluster hosts a three-tier application. The cluster has 50% resources available. If a host in the cluster fails, the database server must be
online before the application server, and the appli-cation server must be online before the Web server.
A. Predictive DRS
D. Proactive HA
Correct Answer: B
Selected Answer: B
https://www.yellow-bricks.com/2018/10/15/ha-futures-orchestrated-restart-restarting-and-restart-priority/
upvoted 1 times
Selected Answer: B
While both B and C can be used to control restart order, answer B makes more sense in the given scenario.
NOTE: for folks using chatGPT to find answers, please triple-check them before posting :)
upvoted 2 times
Pledian is incorrect, C is used when a host is restarted and the order in which VMs would restart, B refers to VMs that rely on each other that need
rebooting in an order, see jennyka76's answer with a useful URL.
upvoted 4 times
vSphere HA Restart Priority allows you to specify the order in which virtual machines are restarted after a host failure. This can be used to ensure
that critical virtual machines are restarted first.
In the scenario described, the database server is the most critical virtual machine, followed by the application server, and then the Web server. You
would therefore set the restart priority for the database server to 1, the application server to 2, and the Web server to 3.
This would ensure that the database server is restarted first, followed by the application server, and then the Web server. This would minimize the
impact of the host failure on the three-tier application
upvoted 2 times
What is the minimum network throughput in Gb/s for vSAN using the Express Storage Architec-ture (ESA)?
A. 50
B. 25
C. 1
D. 10
Correct Answer: B
Selected Answer: B
https://core.vmware.com/blog/comparing-original-storage-architecture-vsan-8-express-storage-
architecture#:~:text=Networking%20Minimums,25Gbps%20minimum.
upvoted 1 times
vSAN ESA requires minimum 25Gbps, for vSAN OSA 10Gbps is enough
upvoted 1 times
Which step is completed during Stage 1 of the vCenter Server Appliance deployment?
Correct Answer: C
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vcenter.install.doc/GUID-39B42E70-9241-45AA-A0FB-
2F369418501A.html#:~:text=Select%20the%20deployment%20size%20for%20the%20vCenter%20Server%20appliance%20for%20your%20vSphere
%20inventory.
upvoted 1 times
Step10:
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vcenter.install.doc/GUID-1E39EF05-1DD7-4E9B-B9FE-6F373AA81862.html
upvoted 2 times
Question #86 Topic 1
An administrator is tasked with adding two additional hosts into an existing production vSphere cluster to support the need for additional
capacity.
The vSphere cluster currently has four identically configured ESXi hosts (esx01, esx02, esx03 and esx04) that utilize Intel Skylake-based CPUs.
The two new hosts (esx05 and esx06) are con-figured identically in terms of memory and storage to the existing hosts, but utilize Intel Ice Lake-
based CPUs.
• Any virtual machine migrates to any of the six ESXi hosts running in the cluster.
• There is no virtual machine downtime during the process of adding the new hosts.
A. Create a new vSphere cluster with Enhanced vMotion Compatibility (EVC) enabled and move all hosts into the new cluster.
B. Create a new vSphere cluster and move only three hosts into the new cluster.
C. Configure Enhanced vMotion Compatibility (EVC) mode on the existing cluster and add the two new hosts into the cluster.
D. Create a new vSphere cluster with vSphere High Availability (HA) enabled and move all hosts into the new cluster.
Correct Answer: C
Selected Answer: C
Answer C : the VMs already on the existing cluster will have EVC automatically activated as the CPUs are Skylake processors. So the cluster EVC
configuration can be modified without having to power off the VMs or putting any host in maintenance (tested a few minutes ago).
upvoted 2 times
Selected Answer: A
Selected Answer: A
From the lecture manual: To activate EVC on an existing cluster, all hosts must be placed in maintenance mode, and therefore all VMs in the
existing cluster must be powered off or suspended. To avoid VM downtime, the recommended method for activating EVC is to activate this feature
on a new, empty cluster.
upvoted 4 times
Selected Answer: C
C
You would enable EVC on the existing cluster as skylake, all the VMs are already using skylake so they would be able to move to the New hosts ok.
If you create a new cluster you have to put the hosts in Maint mode when moving between clusters.
upvoted 4 times
Selected Answer: C
You can use the Enhanced vMotion Compatibility (EVC) feature to help ensure vMotion compatibility for the hosts in a cluster. EVC ensures that all
hosts in a cluster present the same CPU feature set to virtual machines, even if the actual CPUs on the hosts differ. Using EVC prevents migrations
with vMotion from failing because of incompatible CPU
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vcenterhost.doc/GUID-9F444D9B-44A0-4967-8C07-693C6B40278A.html
upvoted 1 times
yazmeh 1 month, 4 weeks ago
The correct answer is:
C. Configure Enhanced vMotion Compatibility (EVC) mode on the existing cluster and add the two new hosts into the cluster.
upvoted 1 times
Selected Answer: A
'A' seems to be the better answer. Creating a new cluster with EVC enabled allows you to add hosts with active VMs as long as the host features are
lower or equal than the EVC mode; otherwise , active VMs shall be stopped prior the host joins the EVC cluster.
https://docs.vmware.com/en/VMware-vSphere/6.7/com.vmware.vsphere.vcenterhost.doc/GUID-B5D48BB5-8DDA-44FF-825B-478915589862.html
upvoted 3 times
https://docs.vmware.com/en/VMware-vSphere/6.7/com.vmware.vsphere.vcenterhost.doc/GUID-B5D48BB5-8DDA-44FF-825B-478915589862.html
upvoted 1 times
EVC allows you to migrate virtual machines between different generations of CPUs.
https://community.spiceworks.com/how_to/189148-using-vmware-evc-mode-for-clusters-in-vsphere
https://kb.vmware.com/s/article/1005764#What_is_EVC:~:text=EVC%20allows%20you%20to%20migrate%20virtual%20machines%20between%20di
fferent%20generations%20of%20CPUs%2C%20with%20EVC%20you%20can%20mix%20older%20and%20newer%20server%20generations%20in%2
0the%20same%20cluster%20and%20be%20able%20to%20migrate%20virtual%20machines%20with%20vMotion%20between%20these%20hosts.
upvoted 2 times
After creating a new cluster with skylake based EVC mode, you can perform live migration of VMs and moving existing servers to the new cluster.
The best answer is A based on the indicated requirements (no downtime)
upvoted 4 times
Selected Answer: C
You would only need to power-off VM's feature sets greater than the EVC mode, which would not be the case here. You enable EVC and set it to
"Skylake", then you can add the new Ice-Lake based systems to the cluster
upvoted 2 times
Selected Answer: A
To create an EVC cluster with minimal disruption to your existing infrastructure, create an empty EVC cluster and move hosts into the cluster.
https://docs.vmware.com/en/VMware-vSphere/6.7/com.vmware.vsphere.vcenterhost.doc/GUID-B5D48BB5-8DDA-44FF-825B-478915589862.html
upvoted 4 times
Selected Answer: C
C
https://blogs.vmware.com/vsphere/2019/06/enhanced-vmotion-compatibility-evc-explained.html
upvoted 2 times
testing_soon 4 months, 2 weeks ago
That same blog says "To enable EVC on a live environment with virtual machines powered on, you would need to power down the virtual
machines in order to change the EVC configuration. " The question says no VM down time.
upvoted 1 times
Where can the administrator find log files containing information related to user login activities?
Correct Answer: C
Selected Answer: C
you have the vcenter logs to check, theses administration when you configure single sign on. Must be the vcenter server itself
upvoted 1 times
Selected Answer: D
I think D: https://docs.vmware.com/en/VMware-vSphere/6.7/com.vmware.psc.doc/GUID-C6207AF4-43DC-44F6-9764-2F3530C7FB56.html
upvoted 1 times
Selected Answer: C
The answer is C. From the vCenter Server Appliance we can look for the logon failures log
upvoted 4 times
What are two uses cases for VMware Tools? (Choose two.)
Correct Answer: AC
Selected Answer: DE
https://docs.vmware.com/en/VMware-Tools/12.2.0/com.vmware.vsphere.vmwaretools.doc/GUID-6994A5F9-B62B-4BF1-99D8-E325874A4C7A.html
upvoted 5 times
DE
A - no NTP support in VMware Tools
B - no official support in doc
C - no support for ESXi only Workstation
D - describle in doc
E - VMXNET 3 is not supported by OS drivers
upvoted 5 times
VMware Tools allows you to open file share paths between hosts and VMs as an experimental feature.
However, this is not recommended for vSphere environments due to security concerns, so it's hard to see this as a use case.
So I'm going to go with a very vague statement: unsupported network driver support.
upvoted 1 times
Selected Answer: CD
AD
the official blue print only mentions Time sync and remote shutdown
Yes you can share folders but thats using vmware workstation; this exam doesn't include this.
upvoted 1 times
Selected Answer: CD
VMTools also enables Shared Folders between host and guest file systems ( on VMware Workstation and VMware Fusion ).
https://docs.vmware.com/en/VMware-Workstation-Pro/17/com.vmware.ws.using.doc/GUID-D6D9A5FD-7F5F-4C95-AFAB-EDE9335F5562.html
upvoted 1 times
Answers are found in the student book: Under 7-13 About VMware Tools.
D - Ability to shut down the VM remotely
C - Shared folders between host and guest file systems
A is incorrect as the VMware does not use NTP for time synchronization.
upvoted 3 times
Selected Answer: DE
Definitely D and also E. Time sync is with the host and not ntp directly, so not A. Also C is not possible with Esxi as it is blocked by default as a
security measure.
upvoted 2 times
C&D
CM8, 7-13 - About VMware Tools
- Ability to shut down the vm remotely. -> Answer D is 100% correct
- Shared folders between host and guest file systems. -> Answer C is 100% correct.
upvoted 1 times
Selected Answer: AC
C is 100%.. E: is tricky as it states "support for unsupported network drivers". The vSphere 8: Install, Configure Manage Student Lecture Manual
stated device drivers ie SVGA display, vmxnet/vmxnet3, baloon driver for memory management, sync driver for quiescing I/O, Paravirtual SCSI
controller..Regarding Time Synchronization, the manual did not specifically mention NTP but the fact it is used for time syncrhonization, I would go
with A over E.
upvoted 1 times
Selected Answer: CD
As per vSphere 8: Install, Configure Manage Student Lecture Manual, the correct answers are definitely C and D.
Also, Time synchronization is mentioned as a feature but in a way that guest OS syncs with host time (not specifically NTP). So since only two
answers are needed, it should be C and D.
upvoted 1 times
Selected Answer: DE
this one is tricky but A states that can sync with a NTP server , actually syncs with the esxi hosts itself , not as a ntp server , it doesn't matter if the
host esxi is using a ntp.
it must be D as we know, and E also because it also isntall the vmxnet3
upvoted 4 times
Selected Answer: CD
An administrator has configured Storage I/O Control (SIOC) on a Virtual Machine File System (VMFS) datastore.
1. A gold tier VM
2. A silver tier VM
3. A bronze tier VM
Assuming the datastore latency does not exceed 29ms, what is the maximum number of IOPS the bronze tier VM is entitled to?
A. 30,000
B. 20,000
C. 10,000
D. 5,000
Correct Answer: D
Selected Answer: A
https://docs.vmware.com/fr/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-7686FEC3-1FAC-4DA7-B698-B808C44E5E96.html
upvoted 1 times
A for sure.
I/O control does not trigger as treshold is not reached
upvoted 1 times
Since there is no active latency-based throttling happening when the latency is below 29 ms, the bronze tier VM is not limited to any specific
number of IOPS in this scenario.
upvoted 4 times
My understanting is A
upvoted 2 times
Storage I/O Control (SIOC) is a feature of VMware vSphere that helps to ensure that all virtual machines on a datastore have a fair share of IOPS.
SIOC works by assigning each virtual machine a number of shares, and then allocating IOPS to the virtual machines based on their shares.
In this scenario, the datastore supports 30,000 IOPS, and the administrator has set SIOC to manual. This means that SIOC will not be triggered
unless the datastore latency exceeds 30 ms.
Selected Answer: A
"Storage I/O shares are similar to shares used for memory and CPU resource allocation"
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-D964A753-0844-4343-A96F-27A4C769F92D.html
"Shares specify the relative importance of a virtual machine (or resource pool). If a virtual machine has twice as many shares of a resource as
another virtual machine, it is entitled to consume twice as much of that resource when these two virtual machines are competing for resources."
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-C0D2EFAE-1FE4-4867-AC3F-
3E70D9A9ED59.html#GUID-C0D2EFAE-1FE4-4867-AC3F-3E70D9A9ED59
upvoted 2 times
An administrator needs to configure a content library solution based on the following infor-mation:
• A new corporate virtual machine (VM) template is created every month to include all of the latest patches.
• The new VM template should be downloaded from the primary data center site (London) to two secondary data center sites (Tokyo and New
• There is limited disk space available at one of the secondary data center sites (Tokyo) due to an ongoing data center consolidation project.
Which four steps should the administrator take to configure the content library solution before adding a VM template? (Choose four.)
B. Configure the New York subscribed content library to download content immediately.
D. Configure the Tokyo subscribed content library to download content when needed.
F. Configure the New York subscribed content library to download content when needed.
E-G-B-D
There is limited disk space available at one of the secondary data center sites (Tokyo) so is correct:
Configure the Tokyo subscribed content library to download content when needed.
upvoted 6 times
In the order, EGBD (or EGDB) : you create the published content library on primary site, and then the subscribed content libraries on secondary
sites.
Tokyo will be configured to download content when needed to avoir consuming disk space if not necessary. New York content can be downloaded
immediately.
upvoted 1 times
Even if Tokyo has limited space, having the latest VM template will be a priority from a security perspective.
upvoted 2 times
E-G-B-D There is limited disk space available at one of the secondary data center sites (Tokyo)
upvoted 4 times
An administrator is required to configure several Microsoft Windows virtual machines (VMs) to support Secure Boot for a critical secure
application.
• The corporate security policy states that all forms of data encryption must utilize a key provider.
• The firmware of each VM is currently set to use Unified Extensible Firmware Interface (UEFI).
• Due to the nature of the application running within the VMs, the guest operating system for each VM is currently a minimum of Windows Server
Which security feature should the administrator implement to meet these requirements?
Correct Answer: D
Selected Answer: A
Answer is A, vSphere VM Encryption. B says "Visualization", C (SGX) is for protected memory areas, not encryption. D (vTPM) is only compatible
with W10/2016 and newer.
Further - A uses KM servers, which supports the policy "all forms of encryption must utilize a key provider"
upvoted 1 times
This security feature should be implemented to meet the requirements of configuring Windows virtual machines (VMs) to support Secure Boot for
a critical secure application. The vTPM provides hardware-based security functions, including Secure Boot, that can be used to enhance the security
of VMs, ensuring that the guest operating systems meet the corporate security policy and utilize key providers for data encryption.
upvoted 2 times
An administrator is preparing for a deployment of a new vCenter Server Appliance. The follow-ing information has been provided to complete the
deployment:
Which two actions must the administrator complete before starting the installation of the vCenter Server Appliance? (Choose two.)
B. Create a DNS CNAME record for the ESXi Host server (esx01.corp.local).
D. Create a reverse DNS A record for the ESXi Host server (esx01)
Correct Answer: AE
Selected Answer: CE
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-752FCA83-1A9B-499E-9C65-D5625351C0B5.html
If you plan to use an FQDN for the appliance system name, you must verify that the FQDN is resolvable by a DNS server, by adding forward and
reverse DNS A records.
upvoted 8 times
Selected Answer: CE
Selected Answer: CE
To use an FQDN for the appliance system name, make sure the FQDN can be resolved by a DNS server. Add forward and reverse DNS A records for
verification.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vcenter-upgrade/GUID-752FCA83-1A9B-499E-9C65-D5625351C0B5.html#GUID-
24D34C53-B00E-47B7-92A7-6B0155DF6889__GUID-D5BC40DF-91CA-4B56-A041-
BFCED5FA2806:~:text=If%20you%20plan%20to%20use%20an%20FQDN%20for%20the%20appliance%20system%20name%2C%20you%20must%2
0verify%20that%20the%20FQDN%20is%20resolvable%20by%20a%20DNS%20server%2C%20by%20adding%20forward%20and%20reverse%20DN
S%20A%20records.
upvoted 2 times
AB, new deployment, not an upgrade, the bare minimum are forward records.
upvoted 1 times
Selected Answer: CE
C E is correct. to use FQDN you need both forward and reverse DNS A records
upvoted 4 times
An administrator manages VM templates and ISO images for a remote office. Their main re-quirements are to store these templates in a single
A. A vSAN datatore
Correct Answer: C
Selected Answer: C
Answer C is correct. We are only speaking about 1 remote office, and 1 place to centralize the templates. A local content library is sufficient.
Using a subscribed content library would need you already have a published content library somewhere, which is not presented here.
upvoted 2 times
Selected Answer: D
I may have missed the bus...but the question indicates minimum two sites that must have a single content library. So it will have to be subscribed
content library.
upvoted 2 times
An administrator needs to create affinity rules for the following vSphere cluster setup:
• The cluster contains two virtual machines (VMs) named app01 and app02.
• The app01 and app02 VMs run software that is licensed to run only on esx11, esx12, or esx13.
Which set of steps must the administrator perform to ensure that the licensing requirements are met for app01 and app02?
C. 1. Add the VMs to a VM group and the esx11 – esx13 hosts to a host group.
2. Create a VM-Host required rule between the VM group and the host group.
D. 1. Add the VMs to a VM group and the esx11 – esx13 hosts to a host group.
2. Create a VM-Host preferential rule between the VM group and the host group.
Correct Answer: C
Selected Answer: C
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-0591F865-91B5-4311-ABA6-84FBA5AAFB59.html
upvoted 4 times
Question #95 Topic 1
The vCenter inventory contains a virtual machine (VM) template called Linux-01. The adminis-trator wants to install a software patch into Linux-01
Which series of steps should the administrator take to accomplish this task?
2. Clone Linux-01
B. 1. Convert Linux-01 to a VM
4. Check in Linux-01.
D. 1. Clone Linux-01.
Correct Answer: B
Selected Answer: C
It is stated that the administrator must install a patch INTO Linux-01. So the idea is to update the template, and not to create a new one. So
answers B and D do not work.
The answer A is not the right process to update a template.
Answer C is correct : you checkout the template (which generates a VM), your modify the VM, and you checkin it.
upvoted 1 times
Difficult question - the question doesnt mention any CL but the procedure makes the most sense. ill go with C
upvoted 1 times
No A -> Does not regenerate the template after applying the patches
No B -> When converting the template to VM, the template is no longer available for vms deployment while the update is being done
No C-> The procedure is correct, but the letter says that the template is in the vCenter inventory, but does not mention a content library.
Yes D -> the procedure maintains the original template while the clone is updated and then regenerates a new template upon completion.
upvoted 3 times
Selected Answer: C
C is correct
Ref. https://blogs.vmware.com/vsphere/2020/04/vsphere-7-content-library.html
upvoted 2 times
Selected Answer: C
When you create a VM template in a content library, the library item is backed by a VM template in the vCenter Server inventory.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-E9EAF7AC-1C08-441A-AB80-0BAA1EAF9F0A.html
upvoted 3 times
Selected Answer: C
C - I believe is the best answer as the first step is to verify Linux-01 template is in CL. If it is those are the right steps to ensure the template is still
usable for deployment while the checked out version is being patched.
D -While it assumes there is no content library in this, the sequence can accomplish the task however you will end up with 2 Linux-01 templates;
Linux-01 without patch, then another Lixnux-01%% name that contains the patched version. We dont want to do this otherwise it will become a
challenge maintaining 2 templates - it defeats the purpose.
upvoted 2 times
Selected Answer: D
because the template is in the vcenter inventory not in the content library
upvoted 1 times
Selected Answer: D
D has all the steps you need to have a second template while the other is still usable
upvoted 1 times
A - No template ad end
B - when converted template is not available fpr provision machines
(https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vm_admin.doc/GUID-D632CAC5-BA5E-4A1E-959B-
382D9ACB1DD0_copy.html=
C Checkout does not provide a vm - only a template - so you can't install a patch
D Makes sense - orginal teplate stays intact for provisioning, result is a second updated template
upvoted 2 times
An administrator remotely deploys VMware ESXi using an out of band management connection and now needs to complete the configuration of
the management network so that the host is ac-cessible through the vSphere Host Client.
• DHCP: No
In addition, all host configurations must also meet the following requirements:
Which four high level tasks should the administrator complete in the Direct Console User Inter-face (DCUI) in order to meet the requirements and
A. Set the value of the VMware ESXi Management Network VLAN ID to 10.
B. Configure at least two network adapters for the VMware ESXi Management Network.
C. Update the VMware ESXi Management Network IPv4 configuration to use a static IPv4 ad-dress.
D. Create a DNS A Record for the VMware ESXi host on the corporate DNS servers.
G. Update the VMware ESXi Management Network DNS configuration to use the corporate DNS servers for names resolution.
I would say abce, work that needs to be done in local interface. Not external dns or something
upvoted 2 times
• vlan 10 (A)
• The management network must be fault tolerant. ( Two uplinks required) B
• DHCP: No (Use Static IP) C
• The management network must use only IPv4 network protocols.(disable IPV6) E
upvoted 2 times
Here are the steps to configure the management network on the ESXi host:
Set the value of the VMware ESXi Management Network VLAN ID to 10.
Configure at least two network adapters for the VMware ESXi Management Network.
Update the VMware ESXi Management Network IPv4 configuration to use a static IPv4 address.
Disable IPv6 for the VMware ESXi Management Network.
Update the VMware ESXi Management Network DNS configuration to use the corporate DNS servers for names resolution.
I'll go for E and not D because "The management network must use only IPv4 network protocols." and without DNS you can still access the host
using the IP
upvoted 3 times
Question #97 Topic 1
Given the configuration shown in the exhibit, what should the administrator do if the latest VM template contains changes that are no longer
needed?
Correct Answer: C
Selected Answer: B
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vm_admin.doc/GUID-D69B0279-CC9B-495B-9CA3-AE975AF9C865.html
upvoted 8 times
Selected Answer: B
Answer B is correct.
C is not correct : the Delete option will be available only on App-LibTemplate(2), and will consist in deleting it and keep the version 3.
upvoted 1 times
Selected Answer: B
By using the vertical timeline, you can revert VM templates back to their previous state.
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-E9EAF7AC-1C08-441A-AB80-
0BAA1EAF9F0A.html#:~:text=revert%20VM%20templates%20back%20to%20their%20previous%20state
upvoted 1 times
Selected Answer: B
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-vm-administration/GUID-E9EAF7AC-1C08-441A-AB80-0BAA1EAF9F0A.html
upvoted 2 times
If the latest VM template contains changes that you no longer want to keep or you made a mistake during your last checkin, you can revert the VM
template to the previous version.
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vm_admin.doc/GUID-D69B0279-CC9B-495B-9CA3-AE975AF9C865.html
upvoted 1 times
An administrator configures a distributed switch and adds the first VMware ESXi server to it.
When attempting to perform a health check of the teaming policy, the health status of the Team-ing and Failover reports as “Unknown”, as seen in
the exhibit.
What can the administrator changes in the distributed switch for the health status to report cor-rectly?
Correct Answer: B
Selected Answer: B
Teaming policy check – There must be at least two active uplinks in the teaming and at least two hosts in the VDS.
https://kb.vmware.com/s/article/2032878#:~:text=Teaming%20policy%20check%20%E2%80%93%20There%20must%20be%20at%20least%20two%
20active%20uplinks%20in%20the%20teaming%20and%20at%20least%20two%20hosts%20in%0Athe%20VDS.
upvoted 1 times
Selected Answer: B
Ref. https://kb.vmware.com/s/article/2032878
Teaming policy check – There must be at least two active uplinks in the teaming and at least two hosts in the VDS.
upvoted 2 times
After removing an ESXi host from a cluster for maintenance, a number of virtual machines have encountered the warning seen in the exhibit.
Which step should the administrator take to move the triggered alarm to its normal state?
A. Ignore
B. Acknowledge
C. Disable
D. Reset to Green
Correct Answer: D
Selected Answer: A
When the "issue is resolved", the VM will return to a normal state. The alarm will come back to a normal state automatically, there is nothing to do.
Answer A.
upvoted 1 times
• The distributed switch has four ESXi hosts, and each host has two 10 Gbps NICs.
• In the Network I/O Control configuration, the amount of bandwidth reserved for virtual machine (VM) traffic if 4 Gbps.
The administrator wants to guarantee that VMs in the Retail distributed port group can access 50 percent of the available reserved bandwidth for
VM traffic.
Given this scenario, what should the size (in Gbps) of the Retail network resource pool be?
A. 40
B. 32
C. 8
D. 16
Correct Answer: D
Selected Answer: D
4Gbps*8Nic=32Gbps*50%=16Gbps
upvoted 7 times
1. Resource Pool “RP-MOM” has a reservation of 6GHz and one running virtual machine (VM) “VM-M1” with 1 GHz reserved.
2. Resource Pool “RP-KID” has a reservation of 2GHz, and expandable reservations is activated.
The administrator creates two VMs, “VM-K1” and “VM-K2”, in the “RP-KID” resource pool with 2GHz reserved for each, and turns on “VM-M1.”
B. The administrator can create a third VM (“VM-K3”) at RP-KID and reserve 6GHz.
C. VM-K2 can be powered on because it can get the resources needed from RP-MOM.
D. VM-K2 cannot be powered on because there are not enough resources in RP-KID.
Correct Answer: D
Selected Answer: D
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-641703ED7601.html#GUID-
BB688011-0A5E-48A0-8D17-45988B1FC7A0__GUID-0390E882-05B0-486D-8AAD-
0787210BAF54:~:text=available%20to%20S2.-,Expandable%20Reservations%20Example%202,-This%20example%20shows
upvoted 1 times
Selected Answer: C
Key is expandable
Expandable
(default)
The system considers the resources available in the selected resource pool and its direct parent resource pool. If the parent resource pool also has
the Expandable Reservation option selected, it can borrow resources from its parent resource pool. Borrowing resources occurs recursively from the
ancestors of the current resource pool as long as the Expandable Reservation option is selected. Leaving this option selected offers more flexibility,
but, at the same time provides less protection. A child resource pool owner might reserve more resources than you anticipate
upvoted 2 times
Selected Answer: C
No local resources are available for VM-K2, so it borrows resources from the parent resource pool,
RP-MOM. RP-MOM has 6GHz minus 1GHz (reserved by the virtual machine) minus 2GHz (reserved
by RP-KID), which leaves 3GHz unreserved. With 3GHz available, you can power on the 2GHz virtual
machine.
upvoted 1 times
hironmoy00 4 months ago
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-641703ED7601.html
upvoted 2 times
When the check box is selected (default), expandable reservations are considered during admission control.
If you power on a virtual machine in this resource pool, and the combined reservations of the virtual machines are larger than the reservation of the
resource pool, the resource pool can use resources from its parent or ancestors.
upvoted 2 times
https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-60077B40-66FF-4625-934A-641703ED7601.html
upvoted 4 times
Selected Answer: C
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.resmgmt.doc/GUID-76691829-06AD-408A-98AE-6D58555936F5.html
upvoted 4 times
Question #102 Topic 1
An administrator is tasked with adding new capacity to an existing software-defined data center (SDDC).
• The SDDC currently hosts two vSphere clusters (ClusterA and ClusterB) with different CPU compatibilities.
• vSphere vMotion and vSphere Distributed Resource Scheduler (DRS) are currently in use in the SDDC.
• The new capacity will be implemented by provisioning four ESXi hosts running a new generation of Intel Skylake CPUs.
• All workload virtual machines (VMs) must support live migration to any cluster in the SDDC.
The administrator noticed the running critical "evc1" virtual machine (VM) shown in the exhibit is not migrating using vSphere vMotion to the
original Clusters A or B.
Which three steps must the administrator take to support this functionality? (Choose three.)
E. Configure the Enhanced vMotion Compatibility (EVC) on vSphere Cluster A and B to sup-port Intel Skylake.
Powered off shows machine state so its enabled on VM - have to disable (a)
Cluster has different cpus before. Has to be configured for new Skylakes(e)
And of course - power on VM after that (d)
upvoted 1 times
Looking exhibit the VM is already Powered Off so B and F are not correct
also EVC are already Enabled so C are not correct
so probably correct answers are A D E
upvoted 4 times
Question #103 Topic 1
An administrator has a requirement to revert a running virtual machine to a previous snapshot af-ter a failed attempt to upgrade an application.
When the administrator originally took the snap-shot, the following choices in the Take Snapshot dialog were made:
What will be the result of the administrator selecting the “Revert to Latest Snapshot” option to return the virtual machine to a previous snapshot?
(Choose two.)
Correct Answer: AD
Selected Answer: AB
Selected Answer: AB
Powered on (does not include memory) which Reverts to the parent snapshot and the virtual machine is powered off.
upvoted 2 times
Selected Answer: AB
Selected Answer: AB
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vm_admin.doc/GUID-3E1BB630-9223-45E8-A64B-DCB90D450673.html