Construction Equipment Management: Problem On Truck Speed Calculation

This document contains steps to calculate the production of trucks and truck fleets for hauling materials. It provides formulas to calculate the hourly output of loaders and trucks based on factors like capacity, efficiency, cycle time, and distance. An illustrative example is included that calculates the number of loaders and trucks required to haul 5 million cubic meters of material over 5 years based on given parameters.

Uploaded by

avant.07012024
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
141 views3 pages

Construction Equipment Management: Problem On Truck Speed Calculation

This document contains steps to calculate the production of trucks and truck fleets for hauling materials. It provides formulas to calculate the hourly output of loaders and trucks based on factors like capacity, efficiency, cycle time, and distance. An illustrative example is included that calculates the number of loaders and trucks required to haul 5 million cubic meters of material over 5 years based on given parameters.

Uploaded by

avant.07012024
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

12-04-2023

Problem on Truck Speed Calculation

Construction Equipment
Management
CMT 522
Session 2
Trucks and Hauling Equipment - Illustration

Aritra Halder
| Aritra Halder | Assistant Professor
Assistant Professor | School of Construction

Steps to Solve Performance Chart

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

1
12-04-2023

Calculating Truck/Truck Fleet Production Calculating Truck/Truck Fleet Production

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

Output of loader and number of trucks


Illustrative Example
required • Quantity of material to be handled=5000000 cum
𝑸×𝑱 ×𝑬 ×𝑭 ×𝑺 ×𝟔𝟎 𝒎𝒊𝒏 • Capacity of loaders to be engaged (Q) = 2.3 cum
• 𝑶𝒖𝒕𝒑𝒖𝒕 𝒐𝒇 𝒍𝒐𝒂𝒅𝒆𝒓 𝒑𝒆𝒓 𝒉𝒐𝒖𝒓 = 𝒄𝒚𝒄𝒍𝒆 𝒕𝒊𝒎𝒆 𝒄𝒕 (𝒎𝒊𝒏)
• Capacity of dumpers = 30 cum
• Yearly working hour for project = 2000 hours
• Q = capacity of loader bucket •

Project to be completed in 5 years
Job condition factor (J) = 0.7
• J = Job condition factor • Operating Efficiency (E) = 0.85
• Bucket fill Factor (F) = 0.85
• E = Operating efficiency • Swell Factor (S) = 0.9
• Cycle time for loader (Ct)= 0.5 mins
• F = Bucket Fill Factor • Lead distance = 6 km
• S = Swell Factor • Speed @ empty haul = 25 km/hour, Speed @ loaded haul = 20 km/hour
• Dumper takes 10 min break in every working hour
𝟔𝟎 𝒎𝒊𝒏×𝑯𝒂𝒖𝒍𝒆𝒓 𝒔 𝒑𝒂𝒚𝒍𝒐𝒂𝒅 𝒑𝒆𝒓 𝒄𝒚𝒄𝒍𝒆
• 𝑯𝒂𝒖𝒍𝒆𝒓 𝒑𝒓𝒐𝒅𝒖𝒄𝒕𝒊𝒐𝒏 𝒑𝒆𝒓 𝒉𝒐𝒖𝒓 = ∗ 𝐄𝐟𝐟𝐢𝐜𝐢𝐞𝐧𝐜𝐲
𝒄𝒚𝒄𝒍𝒆 𝒕𝒊𝒎𝒆 𝒄𝒕 (𝒎𝒊𝒏)
• Calculate the loader and dumper requirement.

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

2
12-04-2023

Illustrative Example Example


𝑸×𝑱 ×𝑬 ×𝑭 ×𝑺 ×𝟔𝟎 𝒎𝒊𝒏 . . . . .
• 𝑂𝑢𝑡𝑝𝑢𝑡 𝑜𝑓 𝑙𝑜𝑎𝑑𝑒𝑟 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟 = = = 125.63 cum
𝒄𝒚𝒄𝒍𝒆 𝒕𝒊𝒎𝒆 𝒄𝒕 (𝒎𝒊𝒏) . • You are supposed to plan equipment for excavation of 1,00,000 m3 sandy clay at a construction site. The
• 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑡𝑜 𝑏𝑒 ℎ𝑎𝑛𝑑𝑙𝑒𝑑 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟 = = 500 cum. material has a fill factor of 110% and a swell percentage of 35%. You are provided with a hoe excavator
having a bucket capacity of 3 cy. Considering conservative loading criteria, road conditions, slope the
• 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑙𝑜𝑎𝑑𝑒𝑟𝑠 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = = 4 𝑛𝑢𝑚𝑏𝑒𝑟𝑠. 𝑎𝑑𝑑 1 𝑠𝑡𝑎𝑛𝑑𝑏𝑦 ;
hauling speed (steady state) is fixed at 16 mph. The return speed (empty, steady state) is fixed at 22 mph.
The hauling distance is 3 miles. The dump time is 2 min (average). The cycle time for the hoe is 20
• 𝒉𝒆𝒏𝒄𝒆 𝒓𝒆𝒒𝒖𝒊𝒓𝒆𝒅 𝒏𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒍𝒐𝒂𝒅𝒆𝒓𝒔 = 𝟓 seconds. The loose unit weight of the soil to be excavated is 2150 lcy/cy. The efficiency factor to be
considered is 50 min hour. The maximum number of haulers available is only 16. Each hauler is having a
• 𝐿𝑜𝑎𝑑𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 𝑓𝑜𝑟 𝑎 𝑐𝑎𝑟𝑟𝑖𝑒𝑟 = = 14.4 mins heaped capacity of 18.3 cy and it can carry a maximum payload of 22 tonnes. Considering the conditions
of the road, your safety officer instructs to light load the hauler. How many days will it be required to
• Empty haul time@ 25 km/hour for 6 km lead = = 14.4 𝑚𝑖𝑛𝑠 complete the work if the maximum time available to work in a day is only 8 hours and with 25 working
days in a month? If the excavator and hauler hire charges are Rs. 3000 per hour and Rs. 1500 hours per
• Loaded haul time @20 km/hour for 6 km lead = = 18 mins hour respectively, what is the rate per cubic meter of excavation for the current job if the expected profit
percentage including overheads is 25%.
• Consider misc. times = 2 mins, • Conversion factors
• Total time = 14.4+14.4+18+2 = 48.8 mins • 1 mph = 88 fpm
• Hourly output of truck (Dumper) = = 36.88 𝑐𝑢𝑚 ; • 2000 lb = 1 tonne
.
• 1 cy = 0.76 m3
• (considering 50 min per hour working) Actual Output = 36.88*50/60 = 30.73 cum
• 1 mile = 5280 feet
• Number of dumpers required = .
= 16.27 (say 17)
• Keeping 2 standby, total number of trucks = 19

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

Thank You!
Contact Me
at
[email protected]
+91-8504017164

| Aritra Halder | Assistant Professor

You might also like