0% found this document useful (0 votes)
47 views11 pages

5 Elements Contract-Lecture

The document discusses the key elements of a construction contract, including offer, acceptance, consideration, competent parties, and legal form. It also outlines the typical parts of a construction contract document including bidding requirements, contract forms, conditions, technical specifications, plans and drawings. Rules of contract interpretation are also covered.

Uploaded by

alqazi.designer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views11 pages

5 Elements Contract-Lecture

The document discusses the key elements of a construction contract, including offer, acceptance, consideration, competent parties, and legal form. It also outlines the typical parts of a construction contract document including bidding requirements, contract forms, conditions, technical specifications, plans and drawings. Rules of contract interpretation are also covered.

Uploaded by

alqazi.designer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Dr.

Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Elements of a Contract

rif
A
kh
rru
Fa
r.
D

Elements of a Contract
 A construction contract is an agreement between two parties
for performance by one party and payment by the other
 The law recognizes performance and payment as duties and
provides a remedy if one party fails to perform (i.e. breaches)
the terms of the agreement
 The contract should state the work to be performed, the price,
and when the contractor will be paid
 The contract determines what has to be done and how to
compute time and compensation for work beyond the contract.
 The contract terms are critical in determining the rights and
obligations of the parties in the event of a dispute
 If the issues are not spelled out, you must rely on provisions of
applicable common laws or statutes

1
Page 1 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Elements of a Contract
1. An offer
 Must be clear, complete, and communicated
 It is valid for a “reasonable” duration
 Can be revoked prior to acceptance unless otherwise
specified

2. An acceptance
 Must be absolute and unambiguous

3. Agreement

rif
 There must be a meeting of mind
 A mutual mistake can allow either party to void a contract, but,

A
unilateral error does not
 Ambiguities are usually construed against the drafter of the
document
kh
 Fraud or misrepresentation may enable the victim to void the
contract
rru
Fa
r.
D

Elements of a Contract
4. Valid Consideration
 Is the actual or promised exchange of money, goods, services, or
some action or inaction

5. Between Competent Parties


 The parties must have valid authority to contract for their organization
 A contract signed by either a minor or someone who is mentally
impaired can be voided
 Unlicensed contractors usually cannot enforce payment even if they
have fully performed their obligations

6. Legal Form and Content


 Contract must conform to legal requirements. Contracts for actions
that are illegal or against public policy are unenforceable
 Oral contracts and oral modifications to contracts are generally
enforceable, but difficult to prove
 Most construction contracts require written authorization to perform
extra work, which would generally negate an oral agreement or
contract modification

2
Page 2 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Elements of Construction Contract Documents


Part I: Bidding Requirements
 Advertisement/Invitation to Bid
 Instruction to Bidders
 Proposal Form
 Bid Bond Form
 State and Federal Requirements

Part II: Contract Forms


 Usually on a standard form, prepared by a design professional

rif
association or by the owner who frequently construct projects.
 Performance and payment bond forms are usually included

A
Part III: Conditions of the Contract
kh
 Include the general and special conditions
rru
Fa
r.
D

Elements of Construction Contract Documents

Part IV: Technical Specifications


Describing material required, quality of workmanship, required
procedures or techniques. Usually organized in two levels:

 Level 1: Organization into divisions


 Level 2: Organization of divisions into sections:
 Scope: defines the work covered
 Materials: standards, brands, types, strengths, etc.
 Workmanship: means and methods, testing
 Measurement and payment:, on unit price contracts

Part V: Plans & Drawings

3
Page 3 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Elements of Construction Contract Documents

Other elements of the contract documents

Soil reports and any special studies or tests included or referenced in


the contract documents

Addenda and Contract Modifications (approved C.O.’s)

rif
 Addenda and pre-bid changes to the contract are issued after the

A
bid docs are released to bidders but before bids
 Record approved changes on the plans and specifications and
schedule of values Scope: defines the work covered
kh
rru
Fa
r.
D

Rules of Contract Interpretation


Contract interpretation begins with a careful reading of the Contract.
Only if ambiguous will a contract be interpreted outside the contract
(i.e., from other documents, legal precedents, or conduct of the
parties)

The rule of contract interpretation include:

1. The expressed intent of the parties in the written agreement is the


most important factor. If this is unclear, the intent of the parties may be
inferred from the documents of from their conduct. (Example: a history
of paying for a certain type of changed work on other projects may be
used to require payment for that same work on this contract

2. The interpretation of ambiguities must be reasonable, as made by an


experienced contractor

3. The ordinary meaning of the words is used, with technical or industry-


specific terms given their normal interpretation

4
Page 4 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Rules of Contract Interpretation


4. The implied terms necessary to comply with the explicit terms
become part of the contract (e.g. forming concrete is implicitly required
by a contract to place concrete)
5. Words and phrases must be interpreted within the context, with all
parts given equal weight
6. Special conditions prevail over general conditions
Handwritten terms prevail over printed terms
Words prevail over numbers
7. Absent any other reasonable interpretation, ambiguities are
construed against the drafter of the document. However, the other
party must demonstrate reliance on the contrary interpretation and

rif
prove their interpretation was reasonable
8. Clerical errors are discounted or ignored, unless reasonably relied

A
upon.
A mutual mistake (i.e., both parties misunderstand the true facts of an
issue) can be a reason for reforming a contract to reflect both parties’
intent. kh
rru
Fa
r.
D

Rules of Contract Interpretation

9. Oral or superseded written agreements may be used to interpret an


ambiguous written contract. Prior negotiations are assumed to be
merged into the document and cannot modify unambiguous clauses.
They can be used to clarify ambiguous terms.

10. The conduct of the parties helps to interpret a contract or to imply a


contract, and can modify or supersede portions of an agreement.

11. Separately negotiated, or added, terms and conditions supersede


originally included material or materials that were not separately
negotiated. Therefore, all handwritten changes should be initiated and
dated by both parties

5
Page 5 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Example of Contract Interpretation


 A contract that requires excavation to a “reasonable depth” before
backfilling is ambiguous.

 The judge or arbitrator first reads the contract as a whole to see if


there is any explanation within the contract for “reasonable depth”

 If another part of the contract requires excavation for a similar


condition to at least 10', then 10' may be interpreted as reasonable

 If the contract is silent, the judge then goes outside the contract, i.e., to
extrinsic evidence (not essential part of the contract)

rif
 Negotiation & communication prior to contract award are reviewed
 Prior dealings between the parties are examined. Example, a

A
comment during a pre-bid conference that poor soil conditions may
extend to 6' down would indicate that 6' was reasonable
 Or, 8' was required on a previous contract might be considered
reasonable kh
rru
 If negotiations or prior communication shed no light on the issue, the
judge will look at local and national practice
Fa
r.
D

Patent versus latent Ambiguity


 If an ambiguity is patent (obvious), a contractor has a duty to alert the
owner. Failure to alert the owner may make the contractor
responsible for the increased cost.

 It is difficult to see how an error can be patently obvious to the


contractor during the 2 - 4 weeks bid period, when it was not obvious
to the designer and the owner during the 6 - 12 months design
process.

Industry Practice & Standard


 Can be crucial to interpreting the contract, if the contract is unclear or
does not address an issue. (Example: tolerances)

6
Page 6 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Modification and Clarification of the


Contract - Outside the Contract
Contract provisions can be supplemented or superseded
by state or federal statue and common law.

Statutes: State Statutes (laws) and common law may


supersede certain contract provisions.

 “No damage for delay” clauses have been declared void on public
work projects by the legislature in some states

rif
 State prompt payment acts governing retainage and the time of
payment may apply
 Pay when/if paid clauses may be declared unenforceable

A
 State statutes will dictate licensing or registration requirements and
construction lien proceedings.
kh
You should consult with an attorney to determine what statutes may
modify the contract or otherwise affect recovery
rru
Fa
r.
D

Modification and Clarification of the


Contract - Outside the Contract

Common Law: Legal precedent, also called case law,


consists of previously decided cases or court
opinions.

 Is used to interpret contracts and provides guidance for


conditions not contemplated by the contract
 Example: “Industry Practice” is a common law principle
 Example: the actions of the parties (on this or prior projects)
may be used as evidence of how a contract should be
interpreted. The parties’ actions may modify or waive a
contract provision or be used to interpret the intent of the
parties. (Owners’ history of paying for verbally directed extra
work can supersede a clause requiring a singed CO before the
contractor perform the extra work).

7
Page 7 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Modification and Clarification of the


Contract - Outside the Contract

Equity: Equity means fairness.

Quantum Meruit (one equitable theory of Recovery)


[Latin: As much as is deserved]

rif
A doctrine by which the law infers a promise to pay a reasonable
amount of labor & materials furnished, even in the absence of a
specifically enforceable agreement between the parties.

A
kh
Although seldom used as a legal theory, equity can be invoked as
a theory of recovery when the contract and case law are unclear
rru
or an issue is not addressed by the Contract
Fa
r.
D

Privity of a Contract vis-


vis-a-vis the Designer
 Damages to the contract due to actions/inactions by the
designer ordinarily must be claimed against the owner.
 The owner may seek recovery from the designer in a
separate action
 Under AIA document A201 and case law, the designer
assumes certain legally enforceable contractual duties to
the contractor:
 No-interference
 Reasonable contract administration
 Impartiality in the resolution of disputes
 The owner implicitly warrants the accuracy and sufficiency
of the contract documents, and therefore liable for the
contractor’s costs resulting from inadequate design

8
Page 8 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Privity of a Contract vis-


vis-a-vis the Designer
 In most states, the Economic Loss Rule, which prevents the
recovery of purely economic losses from a party absent a
contract, prohibits a tort (wrongdoing) action by a
contractor against the designer.

 In some states, however, contractors may pursue a tort


action against the designer. This litigation is outside the
contract and is based on the common law principle that the
designer has a duty of reasonable care to third parties
(contractor) who either build or use the project.

rif
A
 Third parties injured on the project after completion of
construction, or subsequent owners of the project who
discover construction deficiencies can also pursue a tort
kh
action against the designer or contractor for alleged design
or construction errors.
rru
Fa
r.
D

Subcontracts

“Flow-down” provisions from the prime contract

 Nearly every subcontract provides that applicable provisions


of the prime contract “flow-down” to the subcontract

 Subs need to understand the prime provisions and have a


copy before signing a subcontract

9
Page 9 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Subcontracts
Privity of Contract

 Means having a direct contractual relationship with another

 Although most subcontracts bind the S/C to “applicable


terms” of the prime contract, this provision does not create a
direct contractual relationship between the subcontractor and
the owner.

rif
 Subcontractors cannot pursue claims directly against the
owner but must “pass through” their claim the general

A
contractor who submits the claim to the owner.

kh
 If unable to obtain a pass-through agreement with the GC.,
subcontractors can file a lien on private projects which forces
the owner to respond through the general contractor.
rru
Fa
r.
D

Subcontracts
The Severin Doctrine
The owner is not liable for damages to the subcontractor,
unless the GC is obligated to pay the subcontractor (for
damages caused by the Owner)

Subcontractor Claims against the GC or other Subs


Are becoming more common, especially for scheduling
delays.

GC claims against subcontractors and suppliers


Collect damages by back charges

10
Page 10 of 11
Dr. Farrukh Arif
CE-5018 Construction Law Case Studies (Contextual Lecture)

Subcontracts

Construction Lien

 Subs and suppliers have lien rights or bond claim rights to


obtain payment even without Privity of contract

 Liens apply tremendous pressure on the Owner and GC to


resolve subs issues

rif
 Construction loan agreements typically require that the
project be free of liens, leaving the owner the choice of

A
paying or “bonding around” the lien to avoid termination of
the loan or interest increase.
kh
rru
Fa
r.
D

11
Page 11 of 11

You might also like