Tiling Safe Work Method Statement (SWMS)
Lesiba Moatshe
Created Wed, 03 Apr 2024, 12:47 PM (UTC+02)
Organisation Details
Contact Name and
Company Name Company Address Position Contact Phone Number Project Name Project Address
[insert] [insert] [insert] [insert]
Method Statement Details
Person responsible for Measures in place to Occupational Health
Work Activity (Job ensuring compliance Developed in ensure compliance with Safety or Environmental Codes and/or Standards
Description) with method statement: consultation with the method statement Reviewed by Legislation Applicable to the Works
[insert] [insert] [insert] [insert] [insert]
Possible hazards
PPE required:
Method Statement
Printed version is uncontrolled This PDF was created at
Page 1 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Preparation of substrate Chips and debris Moderate (4-9) = Wear appropriate Low (1-3) = Work able to Supervisor
from removing Permission from worker eye protection proceed
PVC pipes and in charge to proceed and dust mask.
concrete can Employ dustless
cause grinding or
eye/respiratory vacuum system.
injury Wear P2 face
Cut tiles edges mask when
may cause hand sweeping or
injury carrying out
dusty work.
Wear appropriate
gloves when
removing tile off
cuts
Entry and access to site Access over Moderate (4-9) = Ensure access is Low (1-3) = Work able to Supervisor
patios and Permission from worker in accordance proceed Principal
porches in charge to proceed with Aus. Contractor
insufficient standard. Check
substrate and fall protection
temporary and entry into
access over the job is
works in sufficient to allow
progress equipment and
Insufficient fall personnel to
protection traverse safely
into building.
Confirm with
Builder
Printed version is uncontrolled This PDF was created at
Page 2 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Cooling and ventilation of Injury to limbs High (10-15) = Inspect guarding Moderate (4-9) = Supervisor
the work area from fans and Permission from high of fans before Permission from worker Employee
propellers level management to operating in charge to proceed
proceed Do not move
fans or adjust
fans while
operating
Initial trial and set out Cuts and Moderate (4-9) = Dymark sharp or Low (1-3) = Work able to Supervisor
lacerations from Permission from worker unprotected proceed
fittings and in charge to proceed water pipes and
fixtures on walls taps in walls and
above work area floor
Falls from trestle Ensure trestles
and planks are set 200mm
Head injury from from set downs
falling straight in slabs with
edges and levels 200mm
overhand on
plans with
clamps
Lay all aluminium
straight edges
and levels along
ground
Gloves worn
when settling out
and sharp
objects are
present
Printed version is uncontrolled This PDF was created at
Page 3 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Laying tiles Dermatitis and High (10-15) = Remove gloves Moderate (4-9) = Supervisor
skin irritation Permission from high when working Permission from worker
from constantly level management to with adhesives in charge to proceed
wet hands proceed and wash water.
(sweat and Allow hands to
water) in rubber remain dry
and fabric
gloves
Abrasive action
of trowel handles
on wet skin
Cartage of tiles and Strains from High (10-15) = Use trolleys for Moderate (4-9) = Supervisor
materials lifting heavy tile Permission from high weight over Permission from worker
Mixing glues and grouts boxes, adhesive level management to 20KGS in charge to proceed
and grout drums proceed Use retractable
or Bags knives when
Cuts from box cutting boxes
knives when Wear P2 type
opening tile dust mask when
boxes mixing powdered
Water spills adhesives
causing Remove mixing
electrocution drills from rinse
Ingestion of buckets when
Crystalline not in use
silicates Only use drills
with dry hands
remove gloves to
prevent
electrocution
All electrical
equipment to be
connected to
RCD
Printed version is uncontrolled This PDF was created at
Page 4 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Cutting tiles with grinder Eye injury from Moderate (4-9) = Wear double eye Low (1-3) = Work able to Supervisor
chips of tile and Permission from worker protection, safety proceed Employee
diamond blades in charge to proceed glasses to AS
under face
shield
Inspect diamond
blades before
use for cracks or
excessive wear.
Only use
Grinders with dry
hands, remove
gloves to prevent
electrocution
Printed version is uncontrolled This PDF was created at
Page 5 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Cutting aluminium trim Lacerations and Moderate (4-9) = Lubricate blades Low (1-3) = Work able to Supervisor
with drop saw loss of limbs Permission from worker before use - proceed Employee
in charge to proceed Safety Glasses
and Face shield
Ensure saw is
setup on flat
ground
Use pieces of
timber support
off cut sections
under.
Clamp section to
back boards or
hold firm keeping
hands well clear
(200mm)
Use hack saws
for all sections
under 200mm
long. If a blade
jams STOP-
Check if it is
bent. Report to
coworkers and
supervisor
immediately.
Printed version is uncontrolled This PDF was created at
Page 6 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Grouting of tiles Skin irritations on Moderate (4-9) = Wear suitable Low (1-3) = Work able to Supervisor
hands from Permission from worker rubber gloves to proceed
epoxy grout in charge to proceed eliminate skin
Run off of wash irritation
water & slurry Wash hands
into drains after grouting
Eye injury from with soap
wash water Dispose of Wash
water in
allocated sand
bund or IVC on
site
Wear suitable
safety glasses to
AS
Cleaning of works area, Trowels Moderate (4-9) = Clean trowels Low (1-3) = Work able to Supervisor
tools and finishes work immersed in dirty Permission from worker and place on proceed Employee
buckets of water in charge to proceed side of bucket to
may cause cuts avoid collision
or lacerations to with hands.
hands. Dispose of water
Run off of wash as above
water & slurry Capture water in
into drains Bunds or IVCs
Cut tile edges Wear appropriate
may cause hand gloves when
injury removing tile off
cuts
Method Statement (Additional Steps)
Printed version is uncontrolled This PDF was created at
Page 7 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Risk Score
(Consequence x Risk Score (After Control
Job Step Potential Hazards Likelihood) Controls Measures) Person Responsible
Risk Matrix
Printed version is uncontrolled This PDF was created at
Page 8 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Legend
C = Consequence
5 = Catastrophic = Fatality, permanent disability, long term widespread impacts, huge financial loss
4 = Major = Permanent disability or extensive injuries, medium to long term widespread impact, major financial loss
3 = Moderate = Lost time injury, reversible medium term local impact, high financial loss
2 = Minor = Medical treatment, reversible short – medium term impact to local area, medium financial loss
1 = Insignificant = First aid, limited impact to minimal area, low financial loss
-----
L = Likelihood
5 = Almost Certain = It is almost certain that the risk will occur in most circumstances
4 = Likely = The risk is likely to occur in most circumstances
3 = Possible = There is uncertainty that the risk could occur
2 = Unlikely = The risk could occur at some time but there is confidence that it will not
1 = Rare = The impact/risk may occur only in exceptional circumstances
Compliance
I have been consulted and assisted in developing the work method statements which apply to my work activities. I will comply with its safe work practice.
Worker Sign-off (Scan Sitemate app IDs)
Name Company Signature Date Time Location
There are no signatures to display yet.
Worker Sign-off (Manual) Not signed yet.
Printed version is uncontrolled This PDF was created at
Page 9 of 10 Wed, 03 Apr 2024, 12:47 pm
Filepath: she consulting/Your First Project/Your First Team Template ID: DP-SWMS-035
Template Version: 3
Form Version: 0
Supervisor Sign-off Not signed yet.