0% found this document useful (0 votes)
22 views

Systematization of The Simulation Process of Trans

This document describes a process for simulating transformer inrush current using the Electromagnetic Transients Program (EMTP). It outlines two methods for modeling the nonlinear characteristics of transformers using EMTP. Both methods involve deriving data from transformer test reports to generate current-flux curves and inputting these values into EMTP models. The paper then presents a simulation example using data from a 154 kV transformer test in Korea.

Uploaded by

Michael Ngo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

Systematization of The Simulation Process of Trans

This document describes a process for simulating transformer inrush current using the Electromagnetic Transients Program (EMTP). It outlines two methods for modeling the nonlinear characteristics of transformers using EMTP. Both methods involve deriving data from transformer test reports to generate current-flux curves and inputting these values into EMTP models. The paper then presents a simulation example using data from a 154 kV transformer test in Korea.

Uploaded by

Michael Ngo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

Article

Systematization of the Simulation Process of


Transformer Inrush Current Using EMTP
Hun-Chul Seo 1 and Gi-Hyeon Gwon 2,*
1 School of Electronic & Electrical Engineering, Yonam Institute of Technology, 52821 Jinju-si,
Gyeongsangnam-do, Korea; [email protected] or [email protected]
2 Department of Smart Electrical & Electronic Engineering, Yonam Institute of Technology,

52821 Jinju-si, Gyeongsangnam-do, Korea


* Correspondence: [email protected]; Tel.: +82-55-751-2045

Received: 2 May 2019; Accepted: 6 June 2019; Published: 12 June 2019

Abstract: An inrush current is generated when a transformer is energized. This current has a large
magnitude and rich harmonics, thereby causing mal-operation of the protection relay. Therefore,
the development of countermeasures against inrush current is necessary, and this study has been
performed by computer simulations. However, it is difficult for a power system operator to
perform a computer simulation as it is difficult to determine what data should be selected and
entered. Therefore, this paper establishes the simulation process of transformer inrush current
using the Electromagnetic Transients Program (EMTP). Two methods to simulate the transformer
inrush current are described in detail. Based on the actual 154 kV transformer test report in Korea,
the simulation results of the inrush current using the two methods are discussed.

Keywords: current-flux value; EMTP; leakage impedance, saturation point; test report;
transformer inrush current

1. Introduction
Transformers are essential components of power systems. However, energization of the
transformer is necessary for the operation of power systems. When the transformer is energized, an
inrush current of large magnitude and rich harmonics is generated. This current adversely affects
the power system causing a reduction in the lifetime of the transformer, damage, and mal-operation
of the protective relay. Therefore, several studies have been carried out on the inrush current of a
transformer to counteract these adverse effects. References [1–5] studied the discrimination
strategies between transformer faults and inrush current. References [6–13] studied the reduction
techniques of inrush current. Moreover, [6–9] studied the controlled energization of transformers,
while [10,11] studied the utilization of uninterrupted power supply and photovoltaic systems. In
addition, [12–17] studied the power quality and protection of power systems by inrush current. The
studies above were performed using a power system simulation program. [1,3,4,9] used Power
Systems Computer Aided Design Electromagnetic Transients including DC (PSCAD/EMTDC).
References [2,5] used MATLAB. References [6,7,10,14,15] used Electromagnetic Transients Program
(EMTP). Reference [16] used Electromagnetic Transients Program—Restructured Version
(EMTP-RV). Reference [17] used DigSILENT software, and [11] performed laboratory experiments.
References [8,12,13] did not provide any simulation software information. References [1–17] did not
provide detailed information for the simulation of the transformer inrush current.
For a transient simulation program, it is necessary to derive the data based on the current–flux
curve necessary for simulating the transformer inrush current. In addition, data such as impedance
ratio, impedance voltage, no-load losses, and winding resistance in transformer test reports are
required. However, it is often difficult to determine what data should be used and how they should

Appl. Sci. 2019, 9, 2398; doi:10.3390/app9122398 www.mdpi.com/journal/applsci


Appl. Sci. 2019, 9, 2398 2 of 17

be processed when the power system operator performs transformer inrush current simulations.
Therefore, this paper provides detailed information on the simulation of transformer inrush current
to power system operators. The novel contribution of this paper is as follows:
1) The simulation process of transformer inrush current using EMTP has been systematized.
2) The necessary data for the simulation are derived from the test report.
3) The method for simulating transformer inrush current using these data is described in detail.
4) Based on the method proposed in this paper, the power system operator can easily perform the
inrush current simulation.
Therefore, this paper establishes the simulation process of transformer inrush current using
EMTP, which simulates transient electromagnetic phenomena and is one of the most widely used
electric utilities programs. Alternative Transients Program Draw (ATPDraw) is a graphical,
mouse-driven pre-processor to the ATP version of EMTP [18–20]. Based on the established
simulation process, the simulation example of transformer inrush current is presented using 154 kV
transformer test data in Korea.
The remainder of this paper is organized as follows: Section 2 discusses the inrush current. In
Section 3, two methods of the simulation process of transformer inrush current using EMTP are
introduced. Section 4 discusses the simulation results using 154 kV transformer test data in Korea.
Finally, the conclusions derived from the study are presented in Section 5.

2. Transformer Inrush Current


At the initial energization of the transformer, there is an injection of current to create the
magnetic field of the transformer, which is called magnetizing inrush current. When the transformer
is initially energized, the magnetic flux and winding current become repeatedly larger and smaller.
This current can be several times larger than the rated current of the transformer, which can lead to
mal-operation of the protective relay. Its duration varies from a few cycles to several seconds [1–4].
The magnitude of the inrush current is based on the closing point on the voltage waveform and
residual flux. The greater the residual magnetic flux, the higher the possibility that the magnetic flux
exceeds the saturation magnetic flux, such that the possibility of inrush current generation increases.
When the transformer is energized, at the instant when the voltage becomes zero, the magnetic flux
becomes larger than the saturation flux and a large inrush current is generated. However, when the
transformer is energized, at the instant when the voltage becomes peak value (90 degree) on the
waveform, the possibility that the magnetic flux becomes smaller than the saturation flux is low.
Hence, the possibility of inrush current generation is also low. However, if the residual magnetic
flux is large, the inrush current may exceed the saturation flux.

3. Simulation Process of Transformer Inrush Current Using EMTP


There are two methods for simulating the nonlinear characteristics of the transformer as shown
in Figure 1. The methods are different for Step 1 and 2, and the same for Step 3.
Appl. Sci. 2019, 9, 2398 3 of 17

Figure 1. The simulation methods of transformer inrush current.

3.1. Method 1

3.1.1. Step 1: Estimation of Current–Flux


To simulate the inrush current, hysteresis (current–flux) curves are required to express the
nonlinear characteristics of the transformer. These curves can be obtained using voltage and
excitation current. Meanwhile, the auxiliary routine SATURA program provided by EMTP is used to
convert the root mean square (RMS) (V–i) curve in the test report into the current–flux curve
required for transient simulation [21]. However, the auxiliary routine SATURA is not supported by
EMTP/ATPDraw. Therefore, the value must be entered in a text format and run in DOS mode after
inputting all the SATURA values. The user can see the result by opening the punch file after
execution. The current–flux data generated by the SATURA is symmetrical in the first and third
quadrants. Therefore, the SATURA method has a disadvantage in that it cannot model the residual
magnetic flux. The result of this method can be entered into the current–flux data of the Type 98
device or the current–flux data in the saturation transformer model of EMTP.

3.1.2. Step 2: Input of Current–Flux Values


(1) Input of current–flux values using Type 98 device
Type 98 device in the Branch/Nonlinear library of EMTP can be used to enter the current–flux
value. The results obtained by running SATURA in Step 1 are inputted in this device. The current
value in steady state is inputted in the CURR section of the Type 98 device, while the flux value in
steady state is inputted in FLUX section. However, for this value, the first value among the current–
flux values extracted in Step 1 is inputted. Meanwhile, the current–flux values are inputted in the
Characteristic tab. The current–magnetic flux curve is then generated by clicking the View button at
the bottom of the screen.
Meanwhile, this Type 98 device corresponds only to the magnetizing current in the actual
transformer equivalent circuit. The leakage resistance and leakage reactance in the primary side can
be represented by introducing resistor and inductor model in the Branch/Linear library of EMTP. In
addition, the transformer in the equivalent circuit can be represented by the transformer model. It
should be noted that a single Type 98 device supports only a single-phase transformer model.
Appl. Sci. 2019, 9, 2398 4 of 17

Moreover, a three-phase transformer model can be developed using three Type 98 devices. The
method will be described in detail in Step 3.
(2) Input of current–flux values in the transformer model
The next step is to input the current–flux value in the transformer model. The saturable
three-phase transformer model in the Transformers library is selected among the models provided
by EMTP. On the Attributes dialog box that appears, the primary and secondary voltages, leakage
resistance, and leakage reactance can be inputted. Meanwhile, the Characteristic tab allows the users
to input current–flux values.

3.1.3. Step 3: Power System Modeling


(1) Using a Type 98 device
Since Type 98 devices do not support three-phase modeling, three Type 98 devices should be
used. Figure 2 shows an example of the entire modeling. The primary-side leakage resistance and
leakage reactance should be located on the left side of the Type 98 device, represented by R–L
elements in the red portion of Figure 2. The transformer model should select either a saturable
single-phase model or a saturable three-phase model in the Transformers library. When selecting a
saturable single-phase model, the transformer winding must be connected directly as the △ or y
winding. Figure 2 shows an example of y–y winding.
Meanwhile, BCTRAN model in Transformers library of EMTP can also be used to input the
transformer internal parameters. It converts the transformer into mutually coupled [R]–[L]-1
elements [21]. However, nonlinear devices such as Type 98 or Type 96 must be connected externally
as the saturation characteristics are not included. In the Input section, the number of phases and of
windings, iron core type, and frequency are inputted; while the rated voltage and capacity in the
primary, secondary, and tertiary windings are inputted in the Rating section. In the Connection
section, winding method is selected. Herein, ‘A’ is selected for the case of an autotransformer, while
‘Y’ and ‘D’ are selected for y and delta connections, respectively. In the Factory Test section, open
circuit test and short circuit test data are inputted. For the open test, the voltage (%), excitation
current (%), and iron loss (kW) are inputted; while the test results of % impedance, capacity (MVA),
and load loss (kW) are inputted for short circuit tests.

Figure 2. System configuration using Type 98 device.

(2) Input of the current–flux value inside the transformer model


When inputting the current–flux value inside the transformer model described in Step 2 (2), the
saturable three-phase model in the Transformers library should be selected. However, the primary
leakage resistance and the leakage reactance must be inputted into the transformer model since no
separate current–flux input device exists in the library.
Appl. Sci. 2019, 9, 2398 5 of 17

3.1.4. Discussion
For Method 1, the current–flux value is derived using the SATURA auxiliary routine in Step 1.
The users can then simulate the inrush current by inputting the current–flux values in a Type 98
device or transformer model and modeling the entire system. If the voltage–current values are
inputted directly in the transformer model, the process of deriving and inputting the current–
magnetic flux value obtained by the SATURA auxiliary routine in Step 1 and 2 can be omitted.
However, it has a disadvantage that the users cannot determine the actual current–flux value. In
addition, it does consider the residual magnetic flux that greatly affects the inrush current of the
transformer.

3.2. Method 2

3.2.1. Step 1: Estimation of Current–Flux


The HYSDAT auxiliary routine provided by EMTP can be used to estimate the current–flux
values of the hysteresis curve and the characteristics of the residual magnetic flux [21]. When
inputting the values in HYSDAT, the current–flux of the saturation point should be inputted. As this
method does not exist in EMTP/ATPDraw, it must be configured in a text format. After simulation,
the current–flux values are included in the punch file.
This method has an advantage in that the modeling of the hysteresis curve and the residual
magnetic flux can be performed. However, users need to first estimate the current–flux at the
saturation point, which can be done using SATURA discussed in Method 1. The saturation point can
be roughly estimated from the simulation results using SATURA. Alternatively, the saturation point
can be estimated from the open test results. The saturation point estimated should then be inputted
in HYSDAT, and the results should be inputted as the current–flux values in the Type 96 device in
Step 2.

3.2.2. Step 2: Input of Current–Flux Values


The current–flux values derived using the HYSDAT auxiliary routine must be inputted using
Type 96 device located in the Branch/Nonlinear library. The current value in steady state is inputted
in the CURR section in the Attributes screen of Type 96, while the flux value in steady state is
inputted in the FLUX section. For this value, the first value in the first quadrant of the extracted
current–flux values can be inputted. Residual flux can be inputted in RESID. In the Characteristic tab
of the Type 96 device, current–flux values are inputted and the current–flux curve is generated by
clicking the View button at the bottom of the screen.

3.2.3. Step 3: Power System Modeling


When using a Type 96 device, the method for the entire system configuration is the same as
shown in Figure 2 except that the Type 98 device is replaced with the Type 96 device. The
primary-side leakage resistance and the leakage reactance are located on the left side of the Type 96
device, while a transformer model exists on the right side of the Type 96 device.
The transformer model can be selected from among saturable single-phase, saturable
three-phase, and BCTRAN models. For a double winding transformer, saturable single-phase and
three-phase models are suitable. Meanwhile, saturable three-phase and BCTRAN models can be
used for a three-winding transformer. However, since the equivalent circuit of a three-winding
transformer is derived based on the star connection, the leakage inductance may become negative
based on the transformer test result, thereby resulting in numerical instability. In this case, the
BCTRAN model can be used.

3.2.4. Discussion
For Method 2, the SATURA auxiliary routine may be used to obtain the saturation point using
the Type 96 device. The current–flux values should be derived through the HYSDAT auxiliary
Appl. Sci. 2019, 9, 2398 6 of 17

routine using only the saturation point, and the derived values should be inputted in the Type 96
device. Finally, the inrush current simulation can be performed by modeling the entire system. In
this method, the process is more complicated than in the previous method. However, the advantage
is that the residual flux value, which has a large effect on the transformer inrush current, can be
considered.

4. Simulation of Transformer Inrush Current Using 154 kV Transformer Test Report

4.1. Transformer Test Report


In this section, an example of transformer inrush current simulation based on Methods 1 and 2
will be described. Table 1 shows the test list in the transformer test report.

Table 1. Test list in transformer test report.

12. Insulation strength test of operation and control


1. Structure and Exterior test
circuit
1.1 Structure test 13. Noise level
1.2 Exterior test 14. Short circuit test of transformer
2. Turns ratio measurement, polarity test, and angle 14.1 Short circuit test (Primary -Secondary
displacement test winding)
2.1 Turns ratio measuremnt 14.2 Short circuit test (Primary -Tertiary winding)
2.1.1 Primary - Secondary winding 14.3 Winding temperature during short circuit test
2.1.2 Primary –Tertiary winding 14.4 Confirmation test after short circuit test
14.4.1 Turns ration measurement, polarity
2.1.3 Secondary - Tertiary winding
test and angle displacement test
14.4.2 Impedance voltage and full load loss
2.2 Polarity test and angle displacement test
test
3. Impedance voltage and full load loss test 14.4.3 No load loss and excitation current test
4. No load loss and excitation current test 14.4.4 Winding resistance measurement
14.4.5 Power frequency withstand voltage
5. Winding resistance measurement
test
14.4.6 Induced withstand voltage test and
6. Power frequency withstand voltage test
partial discharge test
7. Induced withstand voltage test and partial
14.4.7 Insulation power factor test
discharge test
8. Insulation power factor test 14.4.8 Motor test
14.4.9 Insulation strength test of operation
8.1 Phase A
and control circuit
8.2 Phase B 14.4.10 Variation ratio of reactance
14.4.11 Visual inspection after short circuit
8.3 Phase C
test
15. Poly Chlorniated Biphenyls (PCB) analysis test in
9. Temperature rise test
insulation oil
9.1 Temperature rise test 16. Winding insulation resistance measurement
9.1.1 Primary and Secondary winding 16.1 Before short circuit test
9.1.2 Tertiary winding 16.2 After short circuit test
Appl. Sci. 2019, 9, 2398 7 of 17

9.2 Dissolved gas test 17. Frame and core insulation test
10. Lightning impulse withstand voltage test 17.1 Before short circuit test
11. Motor test 17.2 After short circuit test
11.1 Fan power consumption measurement and
18. Conclusion
rotating direction test
11.2 On Load Tap Changer (OLTC) operation test

The necessary data from the transformer report should be extracted as follows:
(1) Turns ratio measurement, polarity test, and angle displacement test
(2) Impedance voltage and full-load loss test
(3) No-load loss and excitation current test
(4) Winding resistance measurement.

4.2. Calculation of Leakage Impedance Using the Results in Test Report


To select the appropriate transformer model, the leakage impedance of the transformer must be
calculated. Since this transformer is a three-winding transformer, the leakage impedance can be
calculated using Equations (1–3).

𝑍 = 𝑍 +𝑍 −𝑍 , (1)

𝑍 = 𝑍 +𝑍 −𝑍 , (2)

𝑍 = 𝑍 +𝑍 −𝑍 , (3)

where
𝑍 : Leakage impedance of primary side;
𝑍 : Leakage impedance of secondary side;
𝑍 : Leakage impedance of tertiary side;
𝑍 : Per-unit leakage impedance measured from winding 1, with wind 2 shorted and winding 3
open;
𝑍 : Per-unit leakage impedance measured from winding 1, with wind 3 shorted and winding 2
open; and
𝑍 : Per-unit leakage impedance measured from winding 2, with wind 3 shorted and winding 1
open.

Based on the calculation method, the value is obtained using Excel as shown in Figure 3. If the
values in the red boxes are inputted, the base impedance, equivalent per-unit (pu) impedance, and
actual value are calculated. Finally, the values required for the EMTP model are the actual values
shown in the green box. The unit is calculated in ohms.
Appl. Sci. 2019, 9, 2398 8 of 17

Figure 3. Calculation of transformer leakage impedance using Excel.

In Figure 3, the equivalent pu impedance of the tertiary side has a negative value; and, hence,
the actual value is calculated as the negative value. This means that the equivalent impedance
calculated using the measured results has a negative value. However, the actual leakage impedance
value is positive. Since the user cannot input negative impedance in the saturable transformer model
in EMTP, the BCTRAN model should be used.

4.3. Method 1

4.3.1. Step 1: Estimation of Current–Flux


The open circuit test results are inputted into the SATURA auxiliary routine as shown in Figure
4. The execution result is presented in Figure 5.

Figure 4. SATURA input.


Appl. Sci. 2019, 9, 2398 9 of 17

Figure 5. Simulation result of SATURA.

4.3.2. Step 2: Input of Current–Flux Values


Figure 6 shows the input screen of a Type 98 device using the result shown in Figure 5. In this
case, only BCTRAN model should be used based on the discussions in Section 4.2. Therefore, the
current–flux value cannot be inputted directly into the saturable transformer model.

Figure 6. Data input in Type 98 component.

4.3.3. Step 3: Power System Modeling


If the negative leakage impedance on the tertiary side calculated in Figure 3 is inputted into
saturable three-phase model, the execution is stopped due to numerical instability. Therefore, it is
not appropriate to enter the transformer leakage resistance and leakage reactance using the saturable
three-phase model. The test data in transformer test report should be inputted using the BCTRAN
model.
The system modeling using BCTRAN model is shown in Figure 7, where the red part is the
BCTRAN transformer model. Since the excitation characteristics are not represented in this model,
the corresponding part is added using the Type 98 device as shown in the green part.
Moreover, the data input screen of BCTRAN is shown in Figure 8. The results of the open circuit
test and the short circuit test are inputted. The winding on which the open circuit test had been
performed can be set at “Performed at” and “Connect at” in BCTRAN model. Therefore, the Type
98 device should be connected in the same manner as set here. Since the transformer test data used in
Appl. Sci. 2019, 9, 2398 10 of 17

this paper was performed on the secondary side, the LV winding is selected and the Type 98 device
is connected to the secondary side.

Figure 7. Power system modeling using BCTRAN.

Figure 8. BCTRAN input.

4.3.4. Simulation Results


Figure 9 shows the simulation result of the inrush current. Figure 9a shows the current flowing
in the primary side of the transformer. After energizing the transformer at 0.1 s, a DC offset
waveform is generated. As the time passes, the current magnitude decays and becomes closer to the
rated current. Figure 9b shows the magnetizing current. The typical inrush current waveform larger
than the rated current with DC offset and harmonics is observed. Figure 9c shows the frequency
analysis of the current flowing in the primary side of the transformer. It shows a typical form of
inrush current with second harmonics.
Figure 9 shows the typical characteristics of inrush current with DC offsets having a magnitude
larger than the rated current and a rich second harmonic. Therefore, the simulation process using
Method 1 is appropriate.
Appl. Sci. 2019, 9, 2398 11 of 17

(a)

(b)

(c)
Figure 9. Simulation results. (a) Current flowing in the primary side of the transformer; (b)
magnetizing current; and (c) frequency analysis.

4.4. Method 2

4.4.1. Step 1: Estimation of Current–Flux


To input the current–flux values in HYSDAT, the saturation point should be selected. Based on
the results in Figure 5, this paper sets the saturation point as (62.6, 54.799). This value is inputted in
HYSDAT as shown in Figure 10. The simulation result is presented in Figure 11.
Appl. Sci. 2019, 9, 2398 12 of 17

Figure 10. HYDSAT input.

Figure 11. Simulation result of HYSDAT.

4.4.2. Step 2: Input of Current–Flux values


Figure 12 shows the input screen of the Type 96 device using the simulation results of Figure 11.
Appl. Sci. 2019, 9, 2398 13 of 17

Figure 12. Data input in Type 96 component.

4.4.3. Step 3: Power System Modeling


Based on the same reason in Method 1, only the BCTRAN model should be used. The modeling
method using BCTRAN is similar to the method shown in Figure 7. However, it is necessary to
change the Type 98 device to a Type 96 device.

4.4.4. Simulation Results


The simulation results of inrush current by Method 2 are shown in Figure 13. Figure 13a shows
the current flowing in the primary side of the transformer. It has a DC offset after energizing the
transformer at 0.1 s. However, this DC offset decreases with time and the rated current eventually
flows. Figure 13b shows the magnetization current waveform with DC offset and harmonics. Figure
13c is the frequency analysis result of Figure 13a, which contains a large second harmonic. On the
other hand, Figures 9 and 13 show the typical characteristics of inrush current with DC offsets
having a larger magnitude and second harmonic than the rated current. Therefore, the simulation
process using Method 2 is appropriate.
In Figures 9 and 13, the maximum value of the current flowing in the primary side of the
transformer is slightly different. The results in Figure 9 do not consider the residual magnetic flux
since the current–flux curve passes through (0, 0). However, the results in Figure 13 consider the
residual flux. Therefore, the magnitude of the inrush current is larger because the hysteresis curve
that passes through (0, −47) is inputted.
In this paper, the simulations of inrush current are performed for a simple power system. The
Methods 1 and 2 presented in this paper can be applied to complex power systems such as an
Institute of Electrical and Electronics Engineers (IEEE) test system [22–24].
Appl. Sci. 2019, 9, 2398 14 of 17

(a)

(b)

(c)
Figure 13. Simulation results. (a) Current flowing in the primary side of the transformer; (b)
magnetizing current; and (c) frequency analysis.

4.5. Discussion
The test result of the inrush current cannot be obtained in the test report. Therefore, the
simulation results cannot be compared with field test results. Meanwhile, the absolute value of
residual flux can be quite different from one transformer to another. Its true nature has not been
experimentally clarified because the flux values in the transformer core cannot be measured directly
Appl. Sci. 2019, 9, 2398 15 of 17

and field tests cannot be easily conducted [25–27]. However, [28,29] conducted the field test of
inrush current. In [28], the Subestacao Eunapolis in Brazil was selected to be the site test due to an
experienced undesired trip of the transformer of a neutral overcurrent protection during the
energizing of one of the three parallel transformers. In [29], Korea Electric Power Corporation
conducted the field test of inrush current at 765 kV transmission lines because they did not conduct
the long-term field test for the substation equipment. References [28,29] performed field tests in
actual transmission lines based on the requirements of the electric power corporation such as
undesired operation and deterioration of electric facilities.
Thus, the studies on inrush current have been performed using simulations. In this paper, data
from ‘2. Turns ratio measurement, polarity test, and angle displacement test’, ‘3. Impedance voltage
and full-load loss test’, ‘4. No-load loss and excitation current test’, and ‘5. Winding resistance
measurement’ in Table 1 were used for simulations. Therefore, the actual characteristic of the
transformer inrush current was considered in our simulations. In addition, although the simulation
results cannot be compared with the field test results, the simulations using actual parameters are
well performed based on the analysis of the simulation results presented in Sections 4.2 and 4.3.

5. Conclusion
Since EMTP provides several transformer models and a large amount of information exists in
the transformer test data, it is difficult for the power system operator to simulate the transformer
inrush current directly. Therefore, this paper establishes the simulation process of the transformer
inrush current using EMTP so that any power system operator can easily perform it. The method
presented in this paper consists of three steps: (1) Estimation of current–flux values, (2) input of
current–flux values, and (3) power system modeling. In this paper, the methods of inputting
current–flux values are explained in detail in each step. An example of transformer inrush current
simulation using actual 154 kV transformer test report data is described by applying these methods.
Thus, both Method 1 and 2 in this paper can be utilized to simulate the transformer inrush current.
However, it is recommended to apply Method 2 if the actual transformer contains a large amount of
residual magnetic flux; otherwise, either Method 1 or Method 2 may be applied.
When the mal-operation of the protection relay occurs in actual power systems due to a very
large inrush current, the power system operator will attempt to identify this problem and provide
solutions. Since the inrush current of the transformer cannot be actually tested, the problem can be
solved using computer simulation. If the power system operator has no experience with inrush
current simulations and does not understand the well-organized simulation method, it will take a
long time to provide a solution. Therefore, the simulation process described in this paper can aid the
power system operator in analyzing the problem using inrush current simulation in a short time and
developing a solution to achieve stable power system operation.

Author Contributions: H.-C.S. conceived, designed, and performed the experiments. H.-C.S. and G.-H.G.
analyzed the data and wrote the paper.
Funding: This work was supported by a 2019 Yonam Institute of Technology grant.
Conflicts of Interest: The authors declare no conflict of interest.

References

1. Wencong, W.; Tianyao, J.; Mengshi, L.; Qinghua, W. Using mathematical morphology to discriminate
between internal fault and inrush current of transformers. IET Gen. Trans. Distrib. 2016, 10, 73–80.
2. Bagheri, S.; Moravej, Z.; Gharehpetian, G.B. Classification and Discrimination Among Winding
Mechanical Defects, Internal and External Electrical Faults, and Inrush Current of Transformer. IEEE
Trans. Ind. Inform. 2018, 14, 484–493.
3. Ali Sahebi; Haidar Samet; Teymoor Ghanbari. Evaluation of power transformer inrush currents and
internal faults discrimination methods in presence of fault current limiter. Renew. Sustain. Energy Rev. 2017,
68, 102–112.
Appl. Sci. 2019, 9, 2398 16 of 17

4. Dashti, H.; Davarpanah, M.; Sanaye-Pasand, M.; Lesani, H. Discriminating transformer large inrush
currents from fault currents. Int. J. Electr. Power Energy Syst. 2017, 75, 74–82.
5. Ibrahim, O.M.S.O.; Zheng, T.; Zheng, X. Power transformer inrush current identification using relative
wavelet energy. In Proceedings of the International Conference on Computer, Control, Electrical, and
Electronics Engineering, Khartoum, Sudan, 12–14 August 2018.
6. Cui, Y.; Abdulsalam, S.G.; Chen, S.; Xu, W. A sequential phase energization technique for transformer
inrush current —Part I: Simulation and experimental results. IEEE Trans. Power Deliv. 2005, 20, 943–949.
7. Ramón Cano-González; Alfonso Bachiller-Soler; José Antonio Rosendo-Macías; Gabriel Álvarez-Cordero.
Controlled switching strategies for transformer inrush current reduction: A comparative study. Electr.
Power Syst. Res. 2017, 145, 12–18.
8. Sahoo, S.K.; Modi, A.; Balamurugan, M.; Sultana, R.; Chhawchharia, S. Reduction of inrush current using
point on wave switching in power transformers. In Proceedings of the Innovations in Power and
Advanced Computing Technologies, Vellore, India, 21–22 April 2017.
9. Parikh, U.; Bhavesh, R.B. Mitigation of magnetic inrush current during controlled energization of coupled
un-loaded power transformers in presence of residual flux without load side voltage measurements. Int. J.
Electr. Power Energy Syst. 2016, 76, 156–164.
10. Fang, S.; Ni, H.; Lin, H.; Ho, S.L. A novel strategy for reducing inrush current of three-phase transformer
considering residual flux. IEEE Trans. Ind. Electr. 2016, 63, 4442–4451.
11. Bukhari, S.S.H.; Lipo, T.A.; Kwon, B. An online UPS system that eliminates the inrush current
phenomenon while feeding multiple load transformers. IEEE Trans. Ind. Appl. 2017, 53, 1149–1156.
12. Abdelsalam, A.A.; Hany, A.A. Mitigation of transformer-energizing inrush current using grid-connected
photovoltaic system. Int. J. Electr. Power Energy Syst. 2016, 79, 312–321.
13. Burkard, J.; Biela, J. Transformer inrush current mitigation concept for hybrid transformers. In
Proceedings of the European Conference on Power Electronics and Applications, Warsaw, Poland, 11–14
September 2017.
14. Chiesak, N.; Mork, B.A.; Høidalen, H.K. Transformer model for inrush current calculations: Simulations,
measurements and sensitivity analysis. IEEE Trans. Power Deliv. 2010, 25, 2599–2608.
15. Nagpal, M.; Martinich, T.G.; Moshref, A.; Morison, K.; Kundur, P. Assessing and limiting impact of
transformer inrush current on power quality. IEEE Trans. Power Deliv. 2006, 21, 890–896.
16. Hun-Chul Seo; Chul-Hwan Kim. The analysis of power quality effects from the transformer inrush
current: A case study of the Jeju power system, Korea. In Proceedings of the IEEE Power and Energy
Society General Meeting, Pittsburgh, PA, USA, 20–24 July 2008.
17. Sadeghi, M.H.; Damchi, Y.; Shirani, H. Improvement of operation of power transformer protection system
during sympathetic inrush current phenomena using fault current limiter. IET Gen. Trans. Distrib. 2018, 12,
5968–5974.
18. Seo, H.-C. New configuration and novel reclosing procedure of distribution system for utilization of BESS
as UPS in smart grid. Sustainability 2017, 9, 507.
19. Seo, H.-C. Development of reclosing method in a distribution system with distributed generation and
battery energy storage system. Energies 2018, 11, 1407.
20. Seo, H.-C. Novel adaptive reclosing scheme using wavelet transform in distribution system with battery
energy storage system. Int. J. Electr. Power Energy Syst. 2018, 97, 186–200.
21. Meyer, W.S.; Liu, T.H. Alternative Transients Program ATP Rule Book EEUG; Canadian/American EMTP
User Group: Portland, USA, 1987.
22. Mohammadi, F.; Zheng, C.; Su, R. Fault diagnosis in smart grid based on data-driven computational
methods. In Proceedings of the 5th International Conference on Applied Research in Electrical, Mechanical
& Mechatronics Engineering, Tehran, Iran, January 2019.
23. Mohammadi, F.; Zheng, C. A Precise SVM Classification Model for Predictions with Missing Data. In
Proceedings of the 4th National Conference on Applied Research in Electrical, Mechanical, Computer, and
IT Engineering, Shiraz, Iran, 4 October 2018.
24. Mohammadi, F.; Zheng, C. Stability analysis of electric power system. In Proceedings of the 4th National
Conference on technology in Electrical and Computer Engineering, Tehran, Iran, December 2018.
25. Hase, Y.; Kamesawa, T.; Inoue, S.; Yamamura, S. Experimental study of transformer residual flux and the
method of restraining inrush current. Electr. Eng. Jap. 2014, 188, 54–67.
Appl. Sci. 2019, 9, 2398 17 of 17

26. Ge, W.; Wang, Y.; Zhao, Z.; Yiang, X.; Li, Y. Residual flux in the closed magnetic core of a power
transformer. IEEE Trans. Appl. Supercond. 2014, 24, 1–4.
27. Ekwue, A.O.; Rawn, B. Investigations into the transformer inrush current problem. Nig. J. Technol. 2018,
37, 1058–1065.
28. Herivelto, S.B.; Servulo, O.P.; Jonsson, P.; de Olivera, J.C.; Chaves, M.L.R. Transformer inrush
mitigation—Part II: Field test on a 100MVA three-phase transformer. In Proceedings of the IEEE/PES
Transmission & Distribution Conference and Exposition, Caracas, Venezuela, 15–18 August 2006.
29. Shim, E.B.; Woo, J.W.; Jung, G.J. The field test and computer simulation on the inrush current and
circulating current of KEPCO’s 765 kV transformer. In Proceedings of the CIGRE, Paris, France, 30
August 2004.

© 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access
article distributed under the terms and conditions of the Creative Commons Attribution
(CC BY) license (http://creativecommons.org/licenses/by/4.0/).

You might also like