Annex 1 Commissioning Check List
Annex 1 Commissioning Check List
DETAILS OF CLIENT
Client
Address
Address
= Yes
Engineer Declaration = No Comments
N/A
1 The system complies with the original specification / design
Any changes to original specification/design have been referred to
2
the system designer for approval
System has been installed to meet requirements of category
3
L1, L2, L3, L4, L5, P1, P2, M, other
Variations to the defined category have been identified and the
4
schedule of variations agreed with the client
5 Cables meet requirements for standard /enhanced /mixed
Cables are segregated as required and suitably supported with fire
6
resistant fixings (Where visibly checked)
7 Cables are mechanically protected as required
Junction boxes are correctly labelled and identified on drawings
8
(Where visibly checked)
All cable insulation and continuity resistance measurements are
9
logged
All cable penetrations are sleeved and fire stopped (Where visibly
10
checked)
Mains supply is dedicated, local isolation is provided lockable in the
11
isolate & normal positions and labelled correctly
12 Mains supply is correctly identified at all distribution boards
Standby battery verification has been carried out for all power
13
supplies
All batteries are clearly marked and labelled with date of
14
installation
Field wiring is labelled and correctly terminated in all control and
15
ancillary equipment
All detection devices have been checked for correct siting &
16
spacing
All detection devices have been functionally tested for correct
17
operation with the phenomenon they are designed to detect
All multi sensor detection devices have been functionally tested for
18 correct operation with the appropriate combination that they are
designed to detect
19 All MCP’s tested for correct operation
20 All visual alarm devices tested for correct operation
21 All ancillary devices (input/output) tested for correct operation
Line isolators are fitted as appropriate, operate correctly and are
22
marked on drawings
Correct text description (display) for all points [addressable
23
systems only]
Cause and effect of the system has been tested and results of the
24
tests have been recorded
25 There is a minimum of two sounder circuits installed
26 Sound pressure levels have been checked and recorded
MCPs are located correctly and travel distance is appropriate to the
27
system category
28 Remote signalling has been checked for correct operation to ARC
As fitted drawings are complete and have been updated where
29
required, including cable size and routing
Zone Plan(s) has been fitted in all appropriate locations (adjacent
30
to control equipment and repeaters)
Log book and operating instructions have been issued to the
31
premises management
The premises management has been adequately trained in the use
32
of the fire alarm system
The premises have been left in a tidy condition and all materials
33
and equipment removed from site
34 Does the system require Verification clause 43 BS 5839-1:2017
35 Commissioning certificate issued
The following work could not be completed for reasons beyond the control of the company:
Reasons (use continuation sheet if necessary)
I certify that the above checks & functional test have been completed in accordance with manufacturers
recommendations and/or applicable
codes of practice
Signature_________________________Print________________________________Date____________________
Annex 2 Service check list
DETAILS OF CLIENT
Client
Address
Address
The following work could not be completed for reasons beyond the control of the company:
Reasons (use continuation sheet if necessary)
I certify that the above checks & functional test have been completed in accordance with manufacturers
recommendations and/or applicable codes of practice
Signature_________________________Print________________________________Date____________________
Annex 3 Installation schedule of test results