0-ITP For Tank Bottom Plate Replacement 9008

This document outlines an inspection and test plan for bottom plate repair of a storage tank. It lists 15 activities to be inspected including document approval, welding procedures, NDT procedures, blasting and painting procedures. Responsibilities and acceptance criteria are defined for each activity.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
529 views9 pages

0-ITP For Tank Bottom Plate Replacement 9008

This document outlines an inspection and test plan for bottom plate repair of a storage tank. It lists 15 activities to be inspected including document approval, welding procedures, NDT procedures, blasting and painting procedures. Responsibilities and acceptance criteria are defined for each activity.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

INSPECTION AND TEST PLAN Doc No.

: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 1 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668

LEGEND Details Personals Signature & date

AZ : AL ZAMIL METAL WORKS FACTORY Contractor: AL ZAMIL METAL WORKS FACTORY


ITP : INSP.ECTION & TEST PLAN
SC : SUB CONTRACTOR
QCE : ASSIGNED QUALITY CONTROL ENGINEER Prepared by: Sreedhar
QA : QUALITY ASSURANCE
QC : QUALITY CONTROL

R : REVIEW (Checking the specific data & Position: Welding Inspector


documentation as to determine that the
item is conforming to the prescribed
requirements)

H : HOLD (Requires a release prior to proceed) Approved by: Gohar Khan


W : WITNESS (Appropriate party, at his
discretion may choose not to observe &
work may proceed if the fabricator are so
Position: QA/QC MANAGER
notified)

S : SURVEILLANCE (Random verification via


direct/indirect Inspections to assure Client : LUBEREF
conformation of the activity)

Name:

Position: PROJECT ENGINEER


0 25-06-11 Issued for approval
Rev No.: Date Description:
ITP Revision history
Form: AZ-QCF-12, Rev:0
INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 2 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
1.0 Documents Approval
API-650 & Engineering
1.1 Drawings Contract Scope Drawings Approval H H
API-653 Manager
ASME
Welding procedure specifications & Sec-IX QA/QC
1.2 Contract Scope WPS Register Approval H H
Procedure qualification record Manager

ASME
Sec-IX QA/QC
1.3 Welder performance qualification Contract Scope Welder List Approval H H
Manager

ASME Sec-V PT & RT


1.4 NDT Procedure Contract Scope SC Approval H H
& Sec-VIII D1 Procedures
API-650 & QA/QC Procedure:
1.5 Procedure for Bottom plate replacement Contract Scope Approval H H
API-653 Manager AZ-QCP-18
API-650 & QA/QC Procedure:
1.6 Procedure for Consumables Control Contract Scope Approval H H
API-653 Manager AZ-QCP-04
API-650 & QA/QC Procedure:
1.7 Penetration Oil Test Procedures Contract Scope Approval H H
API-653 Manager AZ-QCP-10
API-650 & QA/QC Procedure:
1.8 Vacuum Box test Procedures Contract Scope Approval H H
API-653 Manager AZ-QCP-11
QA/QC Procedure:
1.9 Hydrostatic Pressure test Procedure ASME B31.1 Contract Scope Approval H H
Manager AZ-QCP-19
API-650 & QA/QC Procedure:
1.10 Hydrostatic Leak Teat Procedure Contract Scope Approval H H
API-653 Manager AZ-QCP-06

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 3 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
QA/QC Paint Information
1.11 Paint system specifications SSPC Contract Scope Approval H H
Manager Sheet
QA/QC Procedure:
1.12 Blasting & Painting Procedure SSPC Contract Scope Approval H H
Manager AZ-QCP-13
QA/QC Inspector
1.13 Paint Inspector Qualification BGAS/NACE Contract Scope Approval H H
Manager Certificate
QA/QC Blaster
1.14 Blaster Qualifications NACE Contract Scope Approval H H
Manager Certificates
QA/QC Painter
1.15 Painter Qualifications NACE Contract Scope Approval H H
Manager Certificates
QA/QC Procedure:
1.16 Painting Holiday Test Procedure SSPC Contract Scope Approval H H
Manager AZ-QCP-17
2.0 Tank isolation
Check for blinding off all connection to Approved Drawings &
2.1 API-653 QCE Maintain H W
tank Procedure:AZ-QCP-16
Tank reinforcement and door sheet
3.0
removal.
Check Reinforcement Beams fitup and Approved Drawings &
3.1 API-653 QCE Maintain W S
dimensions Procedure:AZ-QCP-18
Check door sheet layout marking & Approved Drawings &
3.2 API-653 QCE Visual Insp Report Submit H W
Cutting dimensions Procedure:AZ-QCP-18
4.0 Removal of heating steam coils
4.1 Check location of marking for cutting API-653 Approved Drawings & QCE Cutting Plan Submit W R

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 4 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
Procedure:AZ-QCP-18
4.2 Check cutting and removal of coil API-653 Approved cutting plan QCE Maintain W S
Removal of bottom plates (except
5.0
under center column & shell)
Check marking for cutting and removal Approved Drawings &
5.1 API-653 QCE Maintain W S
all bottom plates with sump completely Procedure:AZ-QCP-18
6.0 Tank Jacking up
Check temporary support for lifting Approved Drawings &
6.1 API-653 QCE Visual Insp Report Submit W S
tank fit up and dimensions Procedure:AZ-QCP-18
Check lifting tank with jacks to Approved Drawings &
6.2 API-653 QCE Visual Insp Report Submit H W
required height Procedure:AZ-QCP-18
7.0 Removal of remaining bottom plates
Check marking for cutting and removal
Approved Drawings &
7.1 of bottom plates below the center API-653 QCE Maintain W W
Procedure:AZ-QCP-18
column
Check marking for cutting and removal Approved Drawings &
7.2 API-653 QCE Maintain W W
of bottom plates below the bottom shell Procedure:AZ-QCP-18
Check bottom shell plates cut location Approved Drawings &
7.3 API-653 QCE Maintain W W
grinding and edge preperation for fitup Procedure:AZ-QCP-18
7.4 Check DPT 100% at shell edge grinded API-653 PT Procedure SC PT Report Submit H W
8.0 Replacement of sand cushion
Remove 75 mm existing of top sand Approved Drawings &
8.1 API-653 QCE Maintain H W
cushion & All contaminted sand to be Procedure:AZ-QCP-18
Form: AZ-QCF-12, Rev:0
INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 5 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
removed

Check new sand (Luberef approved) Approved Drawings & Sand Test
8.2 API-653 SC Submit H R
material Procedure:AZ-QCP-18 Certificate
Check filling new sand bed compaction Approved Drawings &
8.3 API-653 QCE Visual Insp Report Submit H W
& slope dimensions Procedure:AZ-QCP-18
9.0 Shop fabrication
Mill Test
Check new materials (bottom plate, API-650 & Approved Drawings & Certificate &
9.1 QCE Submit H R
sump plate) against mill certificates API-653 Procedure:AZ-QCP-18 Material Insp
Report
Check cut layout and dimensions of all Approved Drawings & Dimensional Insp
9.2 API-653 QCE Submit H S
bottom plates Procedure:AZ-QCP-18 Report
Check shop fabricated sump with DPT API-650 & Approved DPT
9.3 check for all welds API-653 Procedure
SC DPT Report Submit H S

Ckeck blasting and painting of bottom Batch cert &


Paint info. sheet &
9.4 plates & sump upper side as per luberef SSPC QCE Painting Insp Submit H S
Procedure:AZ-QCP-04
approved (only primer) Report
Ckeck painting of bottom plates & Batch cert &
Paint infor. sheet &
9.5 sump under side full system as per SSPC QCE Painting Insp Submit H S
Procedure:AZ-QCP-04
luberef approved (coal tar epoxy) Report
Check visual and dimensions fabricated Approved Drawings & Visual & Dim Insp
9.6 API-653 QCE Submit H R
sump Procedure:AZ-QCP-18 Report

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 6 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
Check sump hydrostatic leak test with Approved Drawings & Hydrostatic Leak
9.7 API-653 QCE Submit H W
full water Procedure:AZ-QCP-18 Test Report
10.0 Installation of new bottom plates
Approved Drawings & Visual & Dim Insp
10.1 Install the sump and compact sand API-653 QCE Submit H S
Procedure:AZ-QCP-18 Report
Check layout and fitup dimensions Approved Drawings &
10.2 API-653 QCE Fit up Insp Report Submit H S
between bottom plates Procedure:AZ-QCP-18
Check visually all weld joints between Approved Drawings & Visual & Dim Insp
10.3 API-653 QCE Submit H W
sketch plates and bottom plates Procedure:AZ-QCP-18 Report
Check Vacuum Box test for all new API-650 & Approved Drawings & Vacuum Check
10.4 QCE Submit H W
bottom plate and sump welds API-653 Procedure:AZ-QCP-11 Report
11.0 Tank jacking down
Check visually the location lowering
Approved Drawings & Visual & Dim Insp
11.1 the tank exactly on bottom plate (shell API-653 QCE Submit H W
Procedure:AZ-QCP-18 Report
diameter marking)
12.0 Shell to bottom welding
Check fitup and dimensions between Approved Drawings &
12.1 API-653 QCE Fit up Insp Report Submit H W
bottom shell plate to bottom plate Procedure:AZ-QCP-18
Check visually all around weld joint
Approved Drawings & Welding Insp
12.2 between bottom shell plate to bottom API-653 QCE Submit W W
Procedure:AZ-QCP-18 Report
plate (weld size & finish)
Check Penetration oil (diesel) for shell API-650 & Approved Drawings & Diesel oil Check
12.3 QCE Submit H W
to bottom inside root weld API-653 Procedure:AZ-QCP-10 Report

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 7 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
DPT 100% check for Shell to bottom API-650 &
12.4 PT Procedure SC PT Report Submit H R
plate final welds API-653
API-650 & Approved Drawings & Roundness Check
12.5 Roundness check for tank QCE Submit H W
API-653 Procedure:AZ-QCP-18 Report
Plumbness check for Tank (<1/100 API-650 & Approved Drawings & Plumbness Check
12.6 QCE Submit H W
with Max 5 inch) API-653 Procedure:AZ-QCP-18 Report
13.0 Reinstallation of heating coil
Check layout, fitup and dimensions of Approved Drawings &
13.1 API-653 QCE Fit up Insp Report Submit H W
pipe joints (with sufficient supports) Procedure:AZ-QCP-18
ASME Sec
13.2 Check DPT 100% all root pass PT procedure SC PT Report Submit H R
VIII D-1
Approved Drawings &
13.3 Check visually all pipe weld joints API-653 QCE Weld Insp Report Submit H W
Procedure:AZ-QCP-18
ASME Sec
13.4 Check RT 10% for all butt welds RT procedure SC RT Report Submit H R
VIII D-1
Hydrostatic pressure test check by ASME Sec Approved Drawings & Hydrostatic pres
13.5 QCE Submit H W
potable water and ensure no leakage VIII D-1 Procedure:AZ-QCP-12 test Report
Approved Drawings &
13.6 Repair if required for steam coil API-653 QCE Visual Insp Report Submit H W/R
Procedure:AZ-QCP-18
14.0 Re Installation of cut Door sheet
Check DPT 100% to door sheet edges ASME Sec
14.1 PT procedure SC PT Report Submit H R
(after edge preparation) VIII D-1

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 8 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
Check joint preparation fitup and Approved Drawings &
14.2 API-653 QCE Fit up Insp Report Submit H S
dimensions Procedure:AZ-QCP-18
Check visual & dimensional weld Approved Drawings &
14.3 API-653 QCE Weld Insp Report Submit H W
joints between door sheet to shell plate Procedure:AZ-QCP-18
ASME Sec RT Map &
14.4 RT 100% for new weld joints SC RT Report Submit H R
VIII D-1 RT procedure
15.0 Tank touch-up for temporary welds
Check for touch up welding at API-650 & Approved Drawings & Visual Insp Report
15.1 QCE Submit H S
thickness reduced on tank shell API-653 Procedure:AZ-QCP-18 UT Report
Visual inspection for ground areas by API-650 & Approved Drawings & Visual Insp Report
15.2 QCE Submit H W+R
UT thickness gauge API-653 Procedure:AZ-QCP-18 UT Report
16.0 Hydrostatic leak testing for tank
Fill approved water (sea water with API-650 & Approved Drawings &
16.1 QCE Maintain H S
chemical inhabitor) full tank API-653 Procedure:AZ-QCP-06
Visually check the tank to ensure no API-650 & Approved Drawings & Hydrostatic Leak
16.2 QCE Submit H H
leakage API-653 Procedure:AZ-QCP-06 test Report
API-650 & Approved Drawings & Tank Settlement
16.3 Check tank levelling (settlement) QCE Submit H W
API-653 Procedure:AZ-QCP-18 Report
17.0 Tank Painting
Batch Certificates &
Check paint materials against manufacturer API-650 & Approved Drawings &
17.1 certificates API-653 AZ-QCP-18
QCE Material Inspection Submit H R
Report

Form: AZ-QCF-12, Rev:0


INSPECTION AND TEST PLAN Doc No.: AZ/ITP/02
Project: MISCELLANEOUS STORAGE TANK REPAIR WORKS Page: 9 of 9
Title: BOTTOM PLATE REPAIR FOR TANK – 9008 Contractor: AZ Revision No.: 1
Customer: LUBEREF-1, JEDDAH P.O No.: 1200805159 Our Job No.: JF/JS/668
SL Activity Acceptance Record Inspection
Reference Doc’s Responsi bility Quality Records
No. Description Criteria Status AZ Luberef
Batch Certs &
Check external painting (as existing) Approved Drawings &
17.2 SSPC QCE Painting Insp Submit H W
for shell course 0.5m from bottom Procedure:AZ-QCP-04
Report
Check touch up painting for tank shell API-650 & Contract scope & AZ- Painting Inspection
17.3 course external same as existing API-653 QCP-13
QCE
Report
Submit H W

Ckeck Paint holiday test for bottom Approved Drawings & Holiday Insp
17.4 SSPC QCE Submit H W
plates to ensure no pin holes Procedure:AZ-QCP-17 Report
18.0 Seal off bottom
Check for application of approved Batch Certificate
Approved Drawings &
18.1 sealant in gap between bottom plate API-653 QCE & Visual Insp Submit H R
Procedure:AZ-QCP-18
edge and foundation all around the tank Report
19.0 Tank Calibration and strapping
Approved Drawings &
19.1 Ensure Tank calibration and Strapping API-653 AZ Calibration Report Submit H R
Procedure:AZ-QCP-18
20.0 Tank Release
Completion &
Contract Approved Drawings &
20.1 Ensure complete the work and accepted QCE Acceptance cert & Submit H R
Scope Procedure:AZ-QCP-18
Quality Dossier

Form: AZ-QCF-12, Rev:0