TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Thursday, 06 July 2023
DAILY PROGRESS REPORT
0. DAILY PROGRESS & MANPOWER Construction Phase
MANPOWER WORK HOURS RAINFALL RECORD
PLAN ACTUAL ACTUAL ACTUAL
DISCIPLINE/ACTIVITY
Night
Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift
Direct Labor * 141 89 1023
Skilled Worker (Source : Jakarta) 110 82 979
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 24 264
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
HDPE Piping 4 4 44 OTHER CONDITION
Welder Steel (SMAW+GTAW) 8 2 22
Total
Start End Remarks
Hours
Painter 2
Unskilled Worker (Source : Local) : Helper 31 4 44
Unskilled Worker (Source : Local) : Watchmen 3 3 33
Indirect * 68 54 567
Construction Manager 1 1 11 Total Hours :
Site Manager 1 1 11 Note :
Planner 1 1 11 Manhour use for Recyn Project :
Surveyor 3 2 22 From 8th May to 05th July :
Field Engineer/Project Engineer 1 1 11 10076 Hr (Indirect & direct)
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1
Administration 1 1 11
Civil Foreman 2 2 22
Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY
Civil QC Engineer 2 1 11
Civil Superintendent 1 1 11 Roughter Crane 50 Ton 1
QC Staff 2 2 22 Roughter Crane 90 Ton 1
Mechanical 6 1 8 Boomtruck 15 Ton 1
SMP Foreman 2 2 22 Concrete Pump 1
SMP Supervisor 1 1 11 Mixer Truck 01 1
SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1
Scaffolding Inspector 1 1 11 Mixer Truck 03 1
Scaffolder 7 7 77 Mixer Truck 04 1
HSE Supervisor 1 Telehandler 1
Safety Officer 3 3 33 Tractor Head 6X6 1
Logistic and Warehouse 2 2 22 LV 01 (Pajero) 1
Rigger 3 3 33 LV 02 Double Cabin 1
Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1
Assistant CM 1 1 11 Generator 45 kVA 4
Electrician 2 2 22 Generator 165 kVA 1
Operator Crane 50T 1 1 11 Compressor 2
Operator Crane 90T 1 1 11 Stamper 4
Operator Telehandler 1 1 11 Light Tower 2
Operator Manlift 1 Total Equipment 26
Operator Boom Truck 1 1 11
Operator Trailer 1 1 11
Operator Concrete Pump 1 1 8
Driver Concrete Pump 1 1 8
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Thursday, 06 July 2023
DAILY PROGRESS REPORT
Assistant Ops Concrete Pump 1 1 8
Operator Mixer Truck 4 4 32
PERI UP Supervisor 2 1 8
TOTAL 206 143 1546
1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Overhead (Indirects)* Percent 100% Monthly Update
On Site Management and Control* Percent 100% Monthly Update
Construction
Civil Work Percent 100% 0.36% 0.06% 19.96% 9.51% 10.45% 90.49% 9.51%
Mechanical Work Percent 100% 0.04% 1.03% 1.03% 100.00%
Piping Work Percent 100% 0.01% 0.01% 0.50% 0.37% 0.13% 99.63% 0.37%
Structural Steel Percent 100% 0.05% 1.71% 1.71% 100.00%
2. MAJOR HIGHLIGHT
Thursday, 06 July 2023 Friday, 07 July 2023
ACTIVITY UNIT QTY ACTIVITY UNIT QTY
A. Civil A. Civil
Chipping LC EMB Shear Key Continue hipping LC EMB Shear Key
Install formwork footing Switch Room Continue install formwork footing Switch Room
Install EMB footing rebar Continue install EMB footing rebar
Dismantle PERI UP scaffolding to 4 m Continue dismantle PERI UP scaffolding to 4 m
Install rebar Transformer Bay Continue install rebar Transformer Bay
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Mobilize HDPE piping material Continue Mobilize HDPE piping material
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 54 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 33 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 22 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
Hold PERI UP installation GL 15-11 Hold PERI UP installation GL 15-11
G. Others G. Others
Online & offline Training Online & offline Training
Concern :
Overall progress minus -13.65%
Base on updated Schedule R
Prepared by : Checked By : Acknowledged By :
Project Control Site Manager
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Thursday, 06 July 2023
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
General Pre-start meeting TBM at Recyn
CIVIL
Continue fabricaion formwork footing EMB Install rebar Tranformer Bay
Install support formwork Switchroom Drill for EMB footing formwork west side
Chippping EMB south side Fabrication spacer rebar
Piping
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Thursday, 06 July 2023
DAILY PHOTOGRAPH
PHOTOGRAPH
Join 54 Dia 400 PN10 Fit up HDPE pipe
star fitup dn 355 pn 16 Join 21 Dia 355 PN16 PE100
Join 22 Dia 355 PN16 PE100 Fit up HDPE pipe
Unloading HDPE pipe
Prepared by : Approved by :
Project Control