MTP132-Daily Report 06 July 2023

The document provides a daily progress report for a tailings mine filtration project. It includes details on manpower levels and work hours, equipment on site, and rainfall records for the construction phase of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views4 pages

MTP132-Daily Report 06 July 2023

The document provides a daily progress report for a tailings mine filtration project. It includes details on manpower levels and work hours, equipment on site, and rainfall records for the construction phase of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Thursday, 06 July 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night
Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift

Direct Labor * 141 89 1023

Skilled Worker (Source : Jakarta) 110 82 979

Rebarman 25 23 253

Mason 20 18 198

Carpenter 25 24 264

Fitter 12 5 55

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 4 44

Unskilled Worker (Source : Local) : Watchmen 3 3 33

Indirect * 68 54 567

Construction Manager 1 1 11 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11 Manhour use for Recyn Project :

Surveyor 3 2 22 From 8th May to 05th July :

Field Engineer/Project Engineer 1 1 11 10076 Hr (Indirect & direct)

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

GA & Supporting 1

Administration 1 1 11

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 1 11 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 1 11 Mixer Truck 03 1

Scaffolder 7 7 77 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 3 33 Tractor Head 6X6 1

Logistic and Warehouse 2 2 22 LV 01 (Pajero) 1

Rigger 3 3 33 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 11 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Thursday, 06 July 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2 1 8

TOTAL 206 143 1546

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirects)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100% 0.36% 0.06% 19.96% 9.51% 10.45% 90.49% 9.51%

Mechanical Work Percent 100% 0.04% 1.03% 1.03% 100.00%

Piping Work Percent 100% 0.01% 0.01% 0.50% 0.37% 0.13% 99.63% 0.37%

Structural Steel Percent 100% 0.05% 1.71% 1.71% 100.00%

2. MAJOR HIGHLIGHT

Thursday, 06 July 2023 Friday, 07 July 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Chipping LC EMB Shear Key Continue hipping LC EMB Shear Key

Install formwork footing Switch Room Continue install formwork footing Switch Room

Install EMB footing rebar Continue install EMB footing rebar

Dismantle PERI UP scaffolding to 4 m Continue dismantle PERI UP scaffolding to 4 m

Install rebar Transformer Bay Continue install rebar Transformer Bay

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 54 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 33 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10

Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10

Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10

Joint pipe HDPE Field Piping Ø 355 PN16 Joint 22 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Hold PERI UP installation GL 15-11 Hold PERI UP installation GL 15-11

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -13.65%

Base on updated Schedule R

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Thursday, 06 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting TBM at Recyn


CIVIL

Continue fabricaion formwork footing EMB Install rebar Tranformer Bay

Install support formwork Switchroom Drill for EMB footing formwork west side

Chippping EMB south side Fabrication spacer rebar


Piping
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Thursday, 06 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Join 54 Dia 400 PN10 Fit up HDPE pipe

star fitup dn 355 pn 16 Join 21 Dia 355 PN16 PE100

Join 22 Dia 355 PN16 PE100 Fit up HDPE pipe

Unloading HDPE pipe


Prepared by : Approved by :

Project Control