Role and Responsibilities of The RE - 27 Oct 22 - 2 Slides Per A4
Role and Responsibilities of The RE - 27 Oct 22 - 2 Slides Per A4
Amarnath Boyjoo
One’s position
in a team
Amarnath Boyjoo
1
27/10/2022
Amarnath Boyjoo
2
27/10/2022
Contractual Relationships
Employer
Engineer Contractor
No Contractual
Relationship
3
27/10/2022
4
27/10/2022
10
5
27/10/2022
11
12
6
27/10/2022
Sub-Clause 3.1
13
14
7
27/10/2022
15
Timeline
Start
16
8
27/10/2022
Timeline
Start Construction
17
Timeline
Defects
Start Construction Notification
Period
18
9
27/10/2022
Timeline
Defects
Start Construction Beyond
Notification
19
Contents
• Insurances
• Advance Payment Guarantee
• Delegation of Authority • Contract Document
• Internal Start-up Meeting • Programme
• Outstanding Works • Disputes
• Principal Events • Cash Flow
• Defects • Settlement
• Start-up Meeting with • Supervision
• Performance Certificate • Arbitration
Contractor • Payment Certificates
• Performance Security • Meetings
• Claims
• Taking-Over Certificate
20
10
27/10/2022
Start
21
22
11
27/10/2022
23
AREs
24
12
27/10/2022
Delegation of Authority
Reference
Date
Contractor
25
Delegation of Authority
All duties and authority of the Engineer given in the
Engineer Conditions of Contract are delegated to (name and
title), excluding duties and authority under the
Quality Administration
following Sub-Clauses:
1. Sub-Clause 3.5 [Determinations]
2. Sub-Clause 8.8 [Suspension of Work]
Engineers Resident Engineer Specialists 3. Sub-Clause 10.1 [Taking Over of the Works and
Sections]
4. Sub-Clause 13.3 [Variation Procedure]
AREs 5. Sub-Clause 11.9 [Performance Certificate]
6. Sub-Clause 14.13 [Issue of Final Payment
Certificate].
Inspectors Surveyors Others
26
13
27/10/2022
Delegation of Authority
All duties and authority of the Engineer given in the
Engineer Conditions of Contract are delegated to (name and
title), excluding duties and authority under the
Quality Administration
following Sub-Clauses:
1. Sub-Clause 3.5 [Determinations]
2. Sub-Clause 11.9 [Performance Certificate]
Engineers Resident Engineer Specialists 3. Sub-Clause 14.13 [Issue of Final Payment
Certificate].
27
28
14
27/10/2022
• Timing
Engineers Resident Engineer Specialists
• Financial
AREs
29
• Timing
Engineers Resident Engineer Specialists
• Financial
• Staffing deployment AREs
30
15
27/10/2022
31
32
16
27/10/2022
33
Before Commencement …
Issue of Submission Issue of the SC 8.1
Tender of the Letter of Commencement
Documents Tender Acceptance Date
Base < 42 d
CIDB Certificate
Date of Registration
for foreign
Contractors
? 28 d < 28 d
34
17
27/10/2022
During Construction …
Issue of Submission Issue of the SC 8.1
Tender of the Letter of Commencement
Documents Tender Acceptance Date
Base < 42 d
Date Time for Completion Delay in Completion
? 28 d < 28 d
35
During DNP …
Issue of Submission Issue of the SC 8.1 SC 10.1 Issue SC 11.9 Issue of the
Tender of the Letter of Commencement of Taking-Over Performance
Documents Tender Acceptance Date Certificate Certificate
Base < 42 d
Date Time for Completion Delay in Completion DNP
? 28 d < 28 d SC 11 < 21 d
Notification
of Defects
Remedying
SC 1.6 Entering into a Contract Agreement of Defects
Tender Period SC 4.2 Issue of Performance Security SC 4.2 Return of the
SC 9.1 Tests on Performance Security
Completion
36
18
27/10/2022
… and Beyond
Issue of Submission Issue of the SC 8.1 SC 10.1 Issue SC 11.9 Issue of the
Tender of the Letter of Commencement of Taking-Over Performance
Documents Tender Acceptance Date Certificate Certificate
Disputes
< 42 d Amicable Settlement
Base
Time for Completion Delay in Completion DNP Arbitration
Date
? 28 d < 28 d SC 11 < 21 d
Notification
of Defects
Remedying
SC 1.6 Entering into a Contract Agreement of Defects
Tender Period SC 4.2 Issue of Performance Security SC 4.2 Return of the
SC 9.1 Tests on Performance Security
Completion
37
38
19
27/10/2022
39
40
20
27/10/2022
41
42
21
27/10/2022
43
44
22
27/10/2022
45
46
23
27/10/2022
47
48
24
27/10/2022
49
50
25
27/10/2022
Minutes of Meeting
• Do not delay
• Write the
minutes
immediately
after
• Be factual
51
Performance Security
• SC 4.2 – Performance Security • Form of Performance Security in
the Bid Documents
52
26
27/10/2022
Performance Security
• SC 4.2 – Performance Security • Financial security behind the
Contractor’s obligation for proper
performance
1. Demand Guarantee
Unconditional obligation to pay
when a demand has been made
2. Surety Bond
Requires certain conditions to be
met before payment is made
53
Performance Security
• SC 4.2 – Performance Security • Financial security behind the
Contractor’s obligation for proper
performance
1. Demand Guarantee
Unconditional obligation to pay
when a demand has been made
2. Surety Bond
Requires certain conditions to be
met before payment is made
54
27
27/10/2022
55
56
28
27/10/2022
• Expiry Date
57
58
29
27/10/2022
Construction
59
Insurances required …
• SC 18.2 - Works and Contractor’s
Equipment
• SC 18.3 - Third-party
• SC 18.4 - Contractor’s Personnel
60
30
27/10/2022
Insurances
• SC 18.2 - Works and Contractor’s • In the joint names of the
Equipment Employer and Contractor
• SC 18.3 - Third-party
• SC 18.4 - Contractor’s Personnel Key feature of this type of policy:
The insured parties are unable
to claim against one another in
respect of an insured loss, as
they are considered to be one-
and-the-same for the purposes
of the insurance.
61
Insurances
• SC 18.2 - Works and Contractor’s
Equipment
• SC 18.3 - Third-party
• SC 18.4 - Contractor’s Personnel • In the Contractor name.
Compensates Contractor’s
employees for bodily injury, wages
and medical expenses.
• Usually yearly
62
31
27/10/2022
Insurances
• SC 18.2 - Works and Contractor’s
Equipment
• SC 18.3 - Third-party
• SC 18.4 - Contractor’s Personnel
63
64
32
27/10/2022
Insurance Covers …
65
14 d
28 d
Insurance
Policies Write to
Contractor Remedying
Original Time for Completion EOT of Defects
66
33
27/10/2022
67
68
34
27/10/2022
• Expiry Date
69
Contract Document
• What to include?
• Contract Agreement
• Performance Security (Copy)
• Letter of Acceptance
• Letter of Bid
• Preamble to Bill of Quantities
• Bill of Quantities
• Specification
• Drawings
• General Conditions of Contract (by reference)
• Particular Conditions of Contract
• Etc.
• Bidder’s Technical
• What not to include? Proposal
• Instructions to Bidders
• Addenda
• Tender Programme
• Minutes of
Negotiation Meeting
70
35
27/10/2022
Contract Document
• What to include?
• Contract Agreement
• Performance Security (Copy)
• Letter of Acceptance
• Letter of Bid
• Preamble to Bill of Quantities
• Bill of Quantities
• Specification
• Drawings
• General Conditions of Contract (by reference)
• Particular Conditions of Contract
• Etc.
• Bidder’s Technical
• What not to include? Proposal
• Instructions to Bidders
• Addenda
• Tender Programme
• Minutes of
Negotiation Meeting
71
Programme of Works
72
36
27/10/2022
Programme to include …
• SC 8.3: Programme • Order in which the Contractor intends
to carry out the Works
• Work by each nominated
The Contractor shall submit a Subcontractor
detailed time programme to the • Sequence and timing of inspections
Engineer within 28 days after and tests specified in the Contract
receiving notice of the • Supporting report:
Commencement Date. • Methodology
• Resources
73
74
37
27/10/2022
• Commencement Date
• Completion date
• Durations (In-built floats)
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
75
Programme of Works
What to look for?
• Commencement Date
• Completion date
• Durations (In-built floats) Cascade
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
76
38
27/10/2022
Programme of Works
What to look for?
• Commencement Date
• Completion date
• Durations (In-built floats)
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
77
Programme of Works
What to look for?
• Commencement Date
• Completion date
• Durations (In-built floats)
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
No predecessors No successors.
Wrong
78
39
27/10/2022
Programme of Works
What to look for?
• Commencement Date
• Completion date
• Durations (In-built floats)
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
79
Programme of Works
What to look for? Calendar: Standard vs customized
• Commencement Date
• Completion date
• Durations (In-built floats)
• Programming logic
• Critical path
• Floats
• Predecessors, successors
• Resources
• Calendar
• Sectional completion (If any)
80
40
27/10/2022
The Programme …
81
82
41
27/10/2022
Monitoring Progress
SC 8.3: Programme
• The Contractor shall also submit a • Revision initiated by the Contractor
revised programme whenever the
previous programme is inconsistent
with actual progress or with the
Contractor's obligations.
• If the Engineer gives notice to the • Revision initiated by the Engineer
Contractor that a programme fails to
comply with the Contract or to be
consistent with actual progress …., the
Contractor shall submit a revised
programme …
83
Tracking Progress
SC 8.6: Rate of Progress
• If, at any time actual progress is too
slow and/or progress has fallen (or
will fall) behind the current
programme, other than as a result of
a cause listed in Sub-Clause 8.4, then
the Engineer may instruct the • Progress must be tracked by the
Contractor to submit a revised Engineer
programme.
84
42
27/10/2022
Tracking Progress
SC 4.21: Progress Reports
(h) comparisons of actual and planned • Tracking progress by the Contractor
progress, with details of any events or
circumstances which may jeopardise
the completion in accordance with the
Contract, and the measures being (or to
be) adopted to overcome delays.
85
86
43
27/10/2022
Impact Analysis
SC 20.1: Contractor’s Claims
• … the Contractor shall send to the • Impact analysis
Engineer a fully detailed claim which
includes full supporting particulars of
the basis of the claim and of the
extension of time and/or additional
payment claimed.
87
Cash Flow
SC 14.4: Schedule of Payments 800
Rs Millions (Inc.VAT)
700
1-Jul-14
1-Jul-15
1-Jul-16
1-Jul-17
88
44
27/10/2022
Rs Millions (Inc.VAT)
Flow and actual payments 700
600
500
400
100
1-Jul-13
1-Jul-14
1-Jul-15
1-Jul-16
1-Jul-17
Payment Due Date
89
Site Supervision
90
45
27/10/2022
Organigrams
Engineer Contractor
91
Organigrams
Engineer Contractor
92
46
27/10/2022
Organigrams
Engineer
• Your eyes and ears on Site.
Quality Administration • Their role is to supervise the
Contractor’s work.
Engineers Resident Engineer Specialists • They are not the Contractor’s
foremen.
AREs
• The duties of inspectors demand
practical experience, objectivity and
Inspectors Surveyors Others tact.
93
Inspection
SC 7.3: Inspection
94
47
27/10/2022
Inspection
Sub-Clause 7.3
The Contractor shall give notice to the • Request for Inspection (RFI) or
Engineer whenever any work is ready Request for Approval (RFA)
and before it is covered up, put out of
sight, or packaged for storage or
transport.
95
Inspection
Sub-Clause 7.3
Work Item
The Contractor shall give notice to the
Engineer whenever any work is ready
and before it is covered up, put out of Materials
sight, or packaged for storage or
transport.
96
48
27/10/2022
Site Supervision
• Supervision at stages of construction • Approval of materials
before covering up • Trial mixes
• Objective is to ensure that work is • Compliance certificates
being carried out in accordance with • Staged inspections
drawings and specifications
• Inspections during site visits
• Inform Contractor if something is
wrong even when he has not
requested inspections
• Tests
• Always use calibrated equipment
• Do not accept substandard work
97
Site Supervision
• Supervision at stages of construction • Site staff need to be experienced
before covering up • Discuss site issues with Contractor
• Objective is to ensure that work is • H&S to be at the forefront
being carried out in accordance with
drawings and specifications • Safety walkround
• Ensure that site staff are using the
latest Drawings
• Site staff to keep a daily site diary
• Contractor to submit a daily
programme, over and above the
Programme of Works
98
49
27/10/2022
Site Supervision
• Supervision at stages of construction • Remember, your site staff are not the
before covering up Contractor’s foremen
• Objective is to ensure that work is • Follow up on tests results, such as
being carried out in accordance with concrete cube test results
drawings and specifications • Etc.
99
Meetings
• Monthly progress meetings
• Technical meetings
• H&S meetings
• Claim consultation meetings
• Ad hoc meetings
100
50
27/10/2022
101
≤ 56 d
≤ 70 d
≤ 28 d ≤ 28 d
• SC 14.3: Monthly Statement must be submitted
MONTHLY INTERIM ≤ 42 d
together with supporting documents
PAYMENTS Engineer verifies the
statement. Contractor • Check that rates match bid rates
submits information
• Check the preamble to BOQ
• Materials on Site
• Cost Adjustment
• The Contract may require that work has passed
tests before certification
• Do not certify more work than done
102
51
27/10/2022
Final Statement
• Value of all work done
• Further sums the Contractor considers due
• Quantities must be fully substantiated
• Based on as-built Drawings
≤ 56 d • If no agreement on the draft final statement
then issue an IPC
≤ 28 d ≤ 28 d • Disagreement to be resolved through dispute
MONTHLY INTERIM resolution procedure
PAYMENTS Engineer verifies the
statement. Contractor
FINAL PAYMENT submits information
≤ 28 d ≤ 56 d
103
PPO Directive 48
SC 14.3 SC 14.6 SC 14.7
Contractor submits Engineer issues Interim Employer makes the
Statement to the Engineer Payment Certificate payment to the Contractor
≤ 56 d
≤ 28 d ≤ 28 d
MONTHLY INTERIM
PAYMENTS Engineer verifies the
statement. Contractor
FINAL PAYMENT submits information
≤ 28 d ≤ 56 d
104
52
27/10/2022
PPO Directive 48
For Works contracts above Rs
300 M Contractors must be
SC 14.3 SC 14.6 SC 14.7 paid not later than 42 days.
Contractor submits Engineer issues Interim Employer makes the
Statement to the Engineer Payment Certificate payment to the Contractor
≤ 28 d ≤ 21 d ≤ 56 d ≤ 21 d
105
Claims
106
53
27/10/2022
Claims arise …
107
Under …
108
54
27/10/2022
Claim’s Procedure
EOT,
Revised
Additional Determination
Programme
Costs
109
Claim’s Procedure
Employer’s
Approval
EOT,
Revised
Additional Determination
Programme
Costs
110
55
27/10/2022
Claim’s Procedure
Employer’s
Approval
Amicable
Arbitration Dispute Determination
Settlement
111
Claim’s Procedure
Employer’s
Approval
Amicable
Arbitration Dispute Determination
Settlement
112
56
27/10/2022
Claim’s Procedure
Claim in ≤ 42 d or such other
≤ 28 d period approved by Engineer Response on the principles of the claim in ≤ 42 d
Employer’s
SC 3.2: Delegation by the Engineer Approval
However, unless otherwise agreed by
both Parties, the Engineer shall not
delegate the authority to determine any
matter in accordance with Sub-Clause EOT,
Revised
3.5 [Determinations]. Additional Determination
Programme
Costs
Engineer’s Approval/disapproval in ≤ 42 d or
such other period approved by Contractor
113
114
57
27/10/2022
Sub-Clause 20.1
• If the Contractor considers himself to
be entitled to any extension of the
Time for Completion and/or any
additional payment, under any Clause
of these Conditions or otherwise in Under the law for example
connection with the Contract, the
Contractor shall give notice to the
Engineer, describing the event or
circumstance giving rise to the claim.
115
Sub-Clause 20.1
• The notice shall be given as soon as
practicable, and not later than 28 days
after the Contractor became aware,
or should have become aware, of the Should the Contractor give notice for
event or circumstance. exceptionally adverse climatic
conditions ?
116
58
27/10/2022
Sub-Clause 20.1
• If the Contractor fails to give notice of
a claim within such period of 28 days,
the Time for Completion shall not be
extended, the Contractor shall not be
entitled to additional payment, and A condition-precedent
the Employer shall be discharged
from all liability in connection with
the claim.
117
Sub-Clause 20.1
• Within 42 days after the Contractor
became aware (or should have
become aware) of the event or
circumstance giving rise to the claim,
or within such other period as may If the Contractor requires more time
be proposed by the Contractor and
approved by the Engineer, the
Contractor shall send to the Engineer
a fully detailed claim which includes
full supporting particulars of the basis
of the claim and of the extension of Separate claim for time and Cost not
time and/or additional payment acceptable
claimed.
118
59
27/10/2022
Sub-Clause 20.1
• Within 42 days after receiving a claim
or any further particulars supporting a
previous claim, or within such other
period as may be proposed by the
Engineer and approved by the If the Engineer requires more time
Contractor, the Engineer shall
respond with approval, or with
disapproval and detailed comments. Approval/disapproval must be reasoned
119
Sub-Clause 20.1
• He may also request any necessary
further particulars, but shall
nevertheless give his response on the
principles of the claim within such Approval/disapproval and response to
time. be within 42 days
120
60
27/10/2022
Sub-Clause 20.1
• Each Payment Certificate shall include
such amounts for any claim as have
been reasonably substantiated as
due under the relevant provision of
the Contract. Unless and until the
particulars supplied are sufficient to
Rarely done while the claim is being
substantiate the whole of the claim,
the Contractor shall only be entitled processed
to payment for such part of the claim
as he has been able to substantiate.
121
Sub-Clause 20.1
• The Engineer shall proceed in
accordance with Sub-Clause 3.5 Determinations cannot be delegated to
[Determinations] to agree or the RE unless agreed by the Employer
determine: and Contractor
(i) the extension (if any) of the Time for
Completion (before or after its expiry) in
accordance with Sub-Clause 8.4 [Extension
of Time for Completion], and/or
122
61
27/10/2022
Sub-Clause 20.1
Other Sub-Clauses for Contractor’s Claims
• The requirements of this Sub-Clause Sub-Clause Title
are in addition to those of any other 1.9 Delayed Drawings or Instructions
Sub-Clause which may apply to a 2.1 Right of Access to the Site
claim. 4.7 Setting Out
4.12 Unforeseeable Physical Conditions
7.4 Testing
Five sub-paragraphs 8.4 Extension of Time for Completion
8.9 Consequences of Suspension
10.3 Interference with Tests on Completion
12.4 Omissions
13.7 Adjustments for Changes in Legislation
16.1 Contractor’s Entitlement to Suspend Work
123
Sub-Clause 20.1
Other Sub-Clauses for Contractor’s Claims
• The requirements of this Sub-Clause Sub-Clause Title
are in addition to those of any other 1.9 Delayed Drawings or Instructions
Sub-Clause which may apply to a 2.1 Right of Access to the Site
claim. 4.7 Setting Out
4.12 Unforeseeable Physical Conditions
7.4 Testing
124
62
27/10/2022
Sub-Clause 20.1
• If the Contractor fails to comply with • No notice or late notice
this or another Sub-Clause in relation • Notice given within 28 days, but no
to any claim, any extension of time claim
and/or additional payment shall take
account of the extent (if any) to • Notice given within 28 days, claim
which the failure has prevented or submitted but not fully substantiated
prejudiced proper investigation of
the claim, unless the claim is excluded
under the second paragraph of this
Sub-Clause.
125
126
63
27/10/2022
127
128
64
27/10/2022
129
130
65
27/10/2022
Engineer’s Approval/disapproval in ≤ 42 d or
such other period approved by Contractor
131
132
66
27/10/2022
133
Engineer’s Authority
134
67
27/10/2022
Benefits of an EOT …
The benefit of an EOT to the Contractor is to relieve him of liability for
delay damages. It allows for reprogramming of the Works to
completion.
135
136
68
27/10/2022
137
Taking Over
• SC 10.1: Taking Over of the Works … the Works shall be taken over by the
and Sections Employer when:
“Works” means the Permanent i. the Works have been completed in
Works accordance with the Contract, and
“Section” means a part of the Works ii. a Taking-Over Certificate for the Works has
specified in the Appendix to Tender been issued, or is deemed to have been
issued in accordance with SC 10.1
138
69
27/10/2022
Taking Over
• SC 10.1: Taking Over of the Works
and Sections The Contractor may apply by notice to
“Works” means the Permanent the Engineer for a Taking-Over
Works Certificate not earlier than 14 days
“Section” means a part of the Works before the Works will, in the
specified in the Appendix to Tender Contractor's opinion, be complete and
ready for taking over.
139
Taking Over
• SC 10.1: Taking Over of the Works
and Sections … issue the Taking-Over Certificate to
“Works” means the Permanent the Contractor, stating the date on
Works which the Works or Section were
“Section” means a part of the Works completed in accordance with the
specified in the Appendix to Tender Contract, except for any minor
outstanding work and defects which will
not substantially affect the use of the
Works or Section for their intended
• SC 10.2: Taking Over of Parts of the purpose …
Works
part not defined
140
70
27/10/2022
Taking Over
• SC 10.1: Taking Over of the Works
and Sections
“Works” means the Permanent
Works
“Section” means a part of the Works
specified in the Appendix to Tender
If the Employer use any part of the
Works before the Taking-Over
Certificate is issued the part which is
• SC 10.2: Taking Over of Parts of the used shall be deemed to have been
Works taken over as from the date on which it
part not defined is used …
141
Signed: ………………………………………
Engineer/Resident Engineer
• Check delegation
Date: ………………………………………
142
71
27/10/2022
DEFECTS NOTIFICATION
143
DNP
SC 11.3
DNP can be extended by up to 2 years if
the Works/Section cannot be used for
the purposes for which they are intended
by reason of a defect or damage.
144
72
27/10/2022
145
146
73
27/10/2022
147
Performance Certificate
EMPLOYER
148
74
27/10/2022
BEYOND
149
150
75
27/10/2022
151
Before concluding
152
76
27/10/2022
… the following:
• Correspondence
• Write with the reader in mind
• Tests
• Results useless without calibration
of testing equipment
• Reports
• Be factual
• Records
• Never too many
• Must be organised
153
Guidance on claims 100 in previous ed. Basic guide SCL Delay and
Now 200. Answers Disruption Protocol.
all (nearly) your Very useful guide
questions
154
77
27/10/2022
To conclude …
The Resident Engineer draws his role and responsibilities from the
Engineer. He not only needs sound engineering skills to manage the
project but he also needs excellent soft skills to manage his team and
the relationship with the Contractor’s team.
155
156
78
27/10/2022
Thank you
157
79