Electrical Inspection Report SA Side 24 April 2024

Uploaded by

arainzada807
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views3 pages

Electrical Inspection Report SA Side 24 April 2024

Uploaded by

arainzada807
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

KFCA Project – Inspection Report

Location: SA Side Service Type: Electrical Date 24/04/2024

Preventive Maintenance Inspection

Bldg. No:
Sr.
W.O Number Description Observations Photo Required Action Status Remarks
No Location:

Bldg.# SA16-
Preventive Maintenance of Electrical
1 Reception WO25618386 PM Task has Been Done PM completed
Low Voltage Panel
Bldg.

Bldg.# SA98- Preventive Maintenance of Electrical


2 WO25618400 PM Task has Been Done PM completed
Service Bldg. Low Voltage Panel

Bldg.# SA12-
Preventive Maintenance of Internal
3 Cargo Transit WO25618454 PM Task has Been Done PM completed
Lightings
Area

Bldg.# SA22- Preventive Maintenance of Internal


4 WO25618462 PM Task has Been Done PM completed
Service Bldg. Lightings

Approved: QHSE Manager Date: May 2022


Doc. Owner: TM Doc. ID: QMS-FM-HS-IN-GEN-FR-1-00 Revision: 00 Page 1 of 3
KFCA Project – Inspection Report

Weekly Inspection of Emergency


Bldg.# S19A-
5 WO25620814 Generator # 1(HIMOINSA-1000KVA@ PM Task has Been Done PM completed
Service Bldg.
220/380V)

Weekly Inspection of Emergency


Bldg.# S19A-
6 WO25620842 Generator # 2(HIMOINSA-1000KVA@ PM Task has Been Done PM completed
Service Bldg.
220/380V)

Weekly Inspection of Emergency


Bldg.# S19A-
7 WO25620870 Generator # 3(HIMOINSA-1000KVA@ PM Task has Been Done PM completed
Service Bldg.
220/380V)

Weekly Inspection of Emergency


Bldg.# SA24-
8 WO25620898 Generator(CUMMINS-500KVA@ PM Task has Been Done PM completed
Service Bldg.
220/380V)

Weekly Inspection of Emergency


Bldg.# SA24-
9 WO25620926 Generator(HIMOINSA-1000KVA@ PM Task has Been Done PM completed
Service Bldg.
220/380V).

Routine Inspection Maintenance of Exit


10 Bldg.# S100 WO25624881 PM Task has Been Done PM completed
Light.

Approved: QHSE Manager Date: May 2022


Doc. Owner: TM Doc. ID: QMS-FM-HS-IN-GEN-FR-1-00 Revision: 00 Page 2 of 3
KFCA Project – Inspection Report

Bldg.# SA98- Preventive Maintenance of Battery


11 WO25618860 PM Task has Been Done PM completed
Service Bldg. Charger-Sealed Lead Acid.

Inspected By

Olive Arabia O&M Contractor

Yasir Safari

Approved: QHSE Manager Date: May 2022


Doc. Owner: TM Doc. ID: QMS-FM-HS-IN-GEN-FR-1-00 Revision: 00 Page 3 of 3