Kpplant Report
Kpplant Report
JUNE 1, 2023
REPORT ON KIDATU HYDROPOWER PLANT.
CONTENTS :
Chapter 1
❖ Introduction
Chapter 2
Chapter 3
REPORT ON KIDATU HYDROPOWER PLANT.
❖ Operation structure of the kidatu hydropower plant and maintenance in
power house
Chapter 4
❖ Switch yard
Chapter 5
Chapter 6
Chapter 7
❖ Conclusion
❖ Recommendations
REPORT ON KIDATU HYDROPOWER PLANT.
ACKNOWLEDGMENT
We would also like to extend our deepest appreciation to Mr. Kombe, the
Head of the Department, for his guidance and support throughout the
planning and execution of this visit. His expertise and dedication have been
invaluable in ensuring a seamless experience for all involved.
Our heartfelt thanks also go to Engineer Mary, the Safety Manager, for
ensuring our visit was conducted in a safe and secure manner. Her meticulous
attention to safety protocols and commitment to our well-being is
commendable and greatly appreciated.
Last but not least, we extend our gratitude to Engineer Nelson, the Electrical
Technician Engineer of the power plant, for his comprehensive explanations
regarding the plant's electrical systems. His patience and willingness to answer
our questions contributed significantly to our understanding of the plant's
electrical operations.
In conclusion, we are deeply grateful to all those mentioned above for their
invaluable contributions in making our visit to the Kidatu Hydropower Plant a
truly enriching and memorable experience. Their support and guidance have
undoubtedly broadened our horizons and deepened our understanding of
hydropower generation. We hope this report effectively conveys the
knowledge and insights gained during our visit, inspiring future generations of
engineers to explore the realm of sustainable energy generation.
REPORT ON KIDATU HYDROPOWER PLANT.
CHAPTER 01
● INTRODUCTION
The estimation of inflows into the reservoirs is also dealt with in this paper
since rivers entering into them are not gauged at the rim of these reservoirs.
The gauges were destroyed after the impoundment of the river.
Therefore, one cannot say with a high level of confidence how much water
enters the reservoirs on a day-today basis without adequate mathematical
model of the same. This information is absolutely necessary for optimal
operation of the reservoir system as well as to help in the investigation of the
failure of reservoir system. Land use change can also adversely affect the
REPORT ON KIDATU HYDROPOWER PLANT.
accuracy of the inflows’ estimates as well. In addition, estimation of loss of
water from the Mtera Reservoir was carried out. This was done because it was
anticipated that perhaps the amount of water lost through evaporation and
also to a certain extent due to
seepage and percolation is much higher than what was assumed at the design
stage. The developed simulation/operational model was tested with the
TALSIM
The Mtera Reservoir is the larger than Kidatu Reservoir with surface area of
620 km2 at full capacity. It is 8.5 m deep
ranging from 690.0 m above Mean Sea Level (MSL) to 698.5 m above MSL.
Corresponding values for the Kidatu Reservoir are a surface area of 9.5 km2 at
full capacity and a depth of 17 m ranging from 433 m above MSL to 450 m
above MSL.
Three main rivers contribute to the Mtera Reservoir, namely; the Great Ruaha
River, the Little Ruaha River and the Kisigo River. The Great Ruaha River at
Msembe Ferry (1ka59) provides about 56% of the runoff into the reservoir. The
Little Ruaha River at Mawande (1ka31), which joins the Great Ruaha River
downstream of Msembe Ferry, provides an additional 18%, whilst the Kisigo
(i.e. 1ka42, joining it further downstream) is about 26 %
There are several tributaries between Mtera and Kidatu Reservoirs that also
contribute to the inflows at Kidatu. The ones considered in this paper are
flows from Mtera, Lukosi at Mtandika (1ka37a), Yovi (1ka38)
and of course the contribution of rainfall within this intervening catchment (i.e.
between Mtera and Kidatu).
TECHNIQUES OF INVESTIGATION
The methodology used to investigate the possible causes of the failure of the
Mtera-Kidatu Reservoir System are as follows:
Three main rivers - the Great Ruaha, the Little Ruaha and the Kisigo -
contribute inflows into the Mtera
Reservoir. These rivers are gauged some distance away from the rim of the
reservoir. As a result, one cannot directly calculate inflows into Mtera
Reservoir without modelling these inflows into the reservoir.
The models are Simple Linear Model (SLM), Linear Perturbation Model (LPM)
and Linear Varying Gain
Factor Model (LVGFM). These models were used to relate the flow at Mtera
(1ka5) with the flows from
1ka31, 1ka42 and 1ka59, and to relate the flow at Kidatu (1ka3) with the flows
from 1ka37a, 1ka38 and the average rainfall within the intervening catchment.
The SLM is a multiple regression model where the dependent variable is the
runoff at the outlet of the catchment/basin and the independent variables are
rainfall and/or upstream flow values. The LPM is a modification of the SLM
where seasonal variations in the variables are accounted for in the regression
equation, and the LVGFM is a further extension of the regression equation,
where non-linearity due to high intensity of rainfall is accounted for. The
mathematical details of these models are presented in Appendix 1.
Since Mtera Reservoir was impounded in 1980, the model was calibrated for
pre-impoundment period of 1957 to 1975. The data of 19 years was used for
the calibration of the model and the remaining 4 years, 1976 to 1979, was used
for the verification of the model. All the three models registered an efficiency
REPORT ON KIDATU HYDROPOWER PLANT.
(R2) of above 90% during calibration, with LVGFM having the highest efficiency
of 94.26% and LPM the least of 90.35%. The results are presented in Table 2.
The same order of efficiency was observed during verification with LVGFM
having an efficiency of 73.53% while LPM had an efficiency of 69.85%. SLM was
used for further investigations of the system’ failure because it had the best
estimate of flow volume compared to LPM and LVGFM. It is also the simplest
among the three models and the results are not vastly different from the
others. River flow data at Kidatu (1ka3) was consistently available from 1954
to 1975; prior to impoundment of the reservoir. Scanty discharge data after
impoundment of the reservoir was also available for the period 1982 to 1985.
Observed flow at three flow stations; 1ka5, 1ka37a and 1ka38 were combined
with the average rainfall
over the intervening catchment to estimate flow at the Kidatu gauging station.
Similarly, the three models (SLM, LPM and LVGFM) were calibrated over a
period of 12 years from 1958 to 1969. Model verification was done from 1970
to 1975 (6 years). Good model efficiencies were obtained, with all models
registering an average R² of about 91% during calibration and 89% during
verification period Losses
It had been mentioned that perhaps the amount of water lost through
evaporation is much higher than what was assumed at the design stage, hence
causing the failure of the reservoir system.
Main losses that occur in a reservoir are due to evaporation followed by losses
due to seepage or ground water percolation and direct pumping (but there is
no evidence of direct pumping from the Mtera Reservoir).
It is hardly likely that losses due to percolation increased suddenly at the end
of 1990, i.e., after the reservoir has been in operation for nearly seven years. It
is also very unlikely that losses due to evaporation increased suddenly at the
end of 1990. But for the completeness of investigation, annual and expected
seasonal losses due to evaporation, using the Morton model, are compared
with the combined losses due to evaporation and percolation calculated by the
water balance of the reservoir.
It is assumed that the losses due to percolation and seepage are small
compared to the losses due to evaporation. As a result, it is expected that the
REPORT ON KIDATU HYDROPOWER PLANT.
losses calculated by water balance should be comparable in magnitude to the
evaporation losses estimated by the mathematical model (i.e. Morton model).
Hydropower generation
In fact, the opposite is true. There was rather an acute shortage of power in
the early 1990s in Tanzania.
Unnecessary Spill
If the amount of water that was spilled from Mtera was more than what was
necessary to feed the Kidatu Reservoir then it could have been the cause of
low water levels in 1991 and 1992. Investigation of this possible cause was
carried out in two different ways. The first course of investigation relied on
searching for clues from the records of spill from the Mtera and the Kidatu
Reservoirs, comparing the total outflow from
REPORT ON KIDATU HYDROPOWER PLANT.
the Mtera and from the Kidatu and by comparing the observed losses from the
Mtera Reservoir with losses estimated from the reservoirs using mathematical
models.
Construction of the first phase started in 1969. This involved a 40m high, rock-
fill dam; an underground power station large enough to accommodated four
50MW machines; about 350km of high – voltage transmission line from Kidatu
to Dar es Salaam; and the installation of two generating units to supply
100MW to the grid system. Phase 1 of this project was commissioned in mid-
1975 and inaugurated by President J.K Nyerere in the same year.
Phase II development of the Great Ruaha Power Project started in 1977 and
involved the construction of a 45 m concrete dam at Mtera, 170km upstream
from Kidatu, installation of the two remaining 50MW generating units at
Kidatu power station; and the relocation of the Iringa/Dodoma road to pass
over the Mtera dam. These works were completed in early 1981.
REPORT ON KIDATU HYDROPOWER PLANT.
In order to connect the northern towns of Arusha and Moshi to the coastal grid
system, a transmission line from Hale power station to the Kiyungi substation
at Moshi was commissioned in 1975. This was also financed by the Canadian
and Tanzania Governments.
In 1979 work commenced on the second major transmission line from the
Kidatu power station. This line, to be commissioned in 1983, runs westward to
Iringa & then to the Mufindi pulp and paper mill. It was planned to extend the
line from Mufindi to Mbeya by 1984.
The installed capacity of the hydroelectric power station at Kidatu was doubled
in 1980 and its capability was augmented by the construction of the storage
dam and reservoir at Mtera, opened by President J.K Nyerere in February
1981.
The main objective of the Corporate Plan was to collectively assess and
manage risks in aspiring to achieve organisational long-term goals. It helps
management to assess the company’s capacity to survive shocks, to adapt to
sudden change, and to capture new opportunities.
REPORT ON KIDATU HYDROPOWER PLANT.
Phase I (1970-1975)
Phase I of the project involved the construction of a 40m high and 350m long
earth rock fill dam and an underground power plant at Kidatu installed with
two generating units each with a capacity of 50MW totaling 100MW. The rock
fill dam located about 10km upstream of the underground power house
created a regulation reservoir for the plant with storage capacity of 125 million
m3 and unlined headrace intake tunnel of 9.6km long down to the power
station.
Phase II (1977-1981)
Kidatu power plant was built in two phases under the name of Great Ruaha
Power Project that was carried out in 1970’s for phase one and 1980’s for
phase two. Phase I was completed in 1975 that comprised of construction of
an earth-rock fill dam, an initial capacity of 2 x 50MW, and 220kv transmission
line to Dar es Salaam via Morogoro. Phase II completed 1980 which involved
additional of 2 x 50MW, and construction of a bigger storage dam at Mtera
with capacity of 3,200 Mill m3.
The plant has undergone two major rehabilitation works. Rehabilitation phase I
covered repair turbine one and two, replacement of excitation equipment and
repair of a damaged generator unit one. The works were executed from 1993
to 1994. Estimate cost of the project was 25 Million SEK. Financiers were SIDA
and TANESCO. The rehabilitation commence from 1999 to 2003. Major works
were computerizing the control and protection system, repair on turbines,
replacement of runners on units 1and 2, generators and water ways. The
project was financed by SIDA, NORAD and TANESCO. Estimated cost was about
12 Million US$.
Energy Contribution
REPORT ON KIDATU HYDROPOWER PLANT.
The power station generates an average of about 0.8 billion units yearly for the
past five years, however for the good hydrological year the station can
generate over 1 billion units.
Kidatu power plant contributes about 36% of the total hydro installed capacity.
The new control system is divided into three main parts namely station control
unit, local control unit and data control and supervision system. The station
control unit controls the whole station while the local control units control the
individual plants like machines, dam and 220/33kV substation. All the local
control units are connected to the data control and supervision system
(SCADA) via station control unit. The unit control units are connected through
profibus. There is a provision of starting the machines from the local control
unit if the SCADA or station control unit fails. Also there is a provision of
remote start/stop of machines from the Ubungo grid control center.
Initially maintenance was carried out using the bar chart maintenance system
until the introduction of computerized maintenance management system
called Job Tech, supplied by nor consult Norway during the rehabilitation
phase II. The bar chart system was done manually, very slow, no proper
reliable records keeping and difficult in follow up. The Job Tech computerized
system helps to plan work tasks and resources utilization, ensures that no
planned work tasks are overlooked, builds up valuable maintenance
information and history, secure a cost effective operation of plant and obtain
optimal maintenance thus prevent unexpected breakdowns. However the
system has failed due to technical problem of the computer server. The
process to revive the system is in progress.
Future plans
REPORT ON KIDATU HYDROPOWER PLANT.
Phase II rehabilitation project could not cover all necessary repairs of plant and
equipment therefore it is planned to have Phase III rehabilitation project. The
project that will cover the following:
Modification of the 220kV system because the substation is the major link of
interconnections e.g. Kihansi, Mtera, and new power stations to be built in a
near future.
Construction cost for phase I was about 102 Million US$ financed by
International Bank for Reconstruction and Development, the Swedish
International Development Authority, the Canadian International Development
agency and the Government of Tanzania. Main contractors and Consultant the
supervision for project layout and kidatu dam and power station was done by
the Swedish Consulting Group (SWECO) Stockholm. Other contractors were as
follows:
● KIDATU CONTRACTORS
REPORT ON KIDATU HYDROPOWER PLANT.
The plant had deteriorated considerately with age in due course and its output
availability had dropped to about 175MW from the installed capacity of
200MW.
The rotary excitations system for all the units had to be replaced between
1991-1993 by new static excitation system as part of urgent repairs that were
conceived as Phase I of Kidatu Rehabilitation. A failure on excitation system of
unit 1 during that period had triggered the need for replacement of the old
rotary excitation system for all the four units.
Turbine works
Runners
Cavitations damages on runners for unit 1 and 2 were found to be severe and
considerable repairs
Waterways
The steel lined waterways were also found to be in poor conditions and
reconditioning of the steel , with new protective layer of paint was necessary.
Corrosion had developed considerably and further corrosion could lead to
complete failure collapse and the steel lining.
It was recommended to carry out sandblasting and painting all the waterways
(mainly 185m high vertical shafts) with area approximated to 8,000m2 Turbine
leakages
Governors:
The governors for unit 1 and 2 were found to have deteriorated considerably.
They were no longer reliable in governing the units. Oil leakages on the
governor pressure system were severe and complete replacement of the
governors was recommended for units 1 and 2. Generators
Cooling
The capacity of all the four generators at Kidatu was found to be limited due to
heating problems
Oil leakages on the bearings were also found to be severe. (The leakage was
approximately 2 litres/day).
The old slip ring house also served as ventilation from the generator pit.
Carbon dust soaked in oil from the generator pit went out via the slip ring. The
combination of oil vapor/carbon dust negatively influenced the insulation of
the winding in the excitation system as well as the generator windings.
Oil pumping efficiency The pumping efficiency on the bearings oil system was
studied further, and it was found necessary to modify the pump holes for
increased cooling efficiency.
Preliminary studies found the pumping holes on the bearing oil pumping
systems to have been rather oversized and recommended for reduction of the
same to improve oil-pumping efficiency.
REPORT ON KIDATU HYDROPOWER PLANT.
CHAPTER 2
1.Board of Directors/Shareholders:
The highest level of leadership responsible for overseeing the operations and
strategic direction of the hydropower plant.
The top executive responsible for the overall management of the hydropower
plant and its day-to-day operations. They report directly to the Board of
Directors
3. Executive Team:
This may include positions such as Chief Operating Officer (COO), Chief
Financial Officer (CFO), Chief Engineer, and other relevant roles, depending on
the size and complexity of the organization. They report to the CEO and oversee
specific functional areas.
4. Department Heads/Managers:
These individuals are responsible for managing different departments within the
hydropower plant, such as Operations, Maintenance, Finance, Human
REPORT ON KIDATU HYDROPOWER PLANT.
Resources, Environmental Compliance, and other relevant areas.
5. Supervisors/Team Leaders:
6. Staff/Workers:
These are the employees who perform the operational tasks and maintenance
activities necessary for the functioning of the hydropower plant. They work
under the supervision of the team leaders and report any issues or concerns to
their immediate supervisors.
The operation structure of the Kidatu Hydropower Plant power house involves
a complex system of components and processes that work together to
generate electricity from the power of water. In this explanation, we will
explore the various elements and their functions within the power house of
the Kidatu Hydropower Plant.
The operation of the Kidatu Hydropower Plant begins with the intake
structure, which is responsible for capturing water from the source, in this
case, the great Ruaha River. The intake structure consists of screens and trash
racks to prevent debris and large objects from entering the system.
The captured water then flows into the forebay, a reservoir-like structure that
acts as a storage area. The forebay helps regulate the flow of water into the
power house, ensuring a steady supply for power generation.
2. Penstock:
From the forebay, the water is directed into the penstock, a large pipe or
tunnel that carries the water to the turbines in the power house. The penstock
is designed to withstand high pressure and is often made of steel or reinforced
concrete.
The penstock is sized and engineered based on the desired flow rate, head,
and turbine capacity. It plays a critical role in maintaining the necessary
hydraulic pressure for efficient turbine operation.
3. Francis Turbines:
Within the power house, the water from the penstock is directed to the Francis
turbines. The Kidatu Hydropower Plant utilizes Francis turbines, which are
reaction turbines designed for medium to high head applications.
REPORT ON KIDATU HYDROPOWER PLANT.
The Francis turbines consist of a runner with curved blades and a spiral-shaped
casing. Water enters the turbine through the guide vanes and flows onto the
runner blades. The kinetic energy of the water is converted into mechanical
energy, causing the runner to rotate.
4. Generator:
The stator, surrounding the rotor, contains a set of stationary coils. The
rotating magnetic field induces an electric current in the coils, generating
electricity. The electricity produced by the generator is then sent to the
transmission system for distribution to consumers.
The power house includes a control room where operators monitor and
control the operation of the turbines, generators, and other equipment. The
control room is equipped with advanced monitoring and control systems that
provide real-time data on various parameters, such as water flow rate, turbine
speed, generator output, and system stability.
Many defects were noted on the plant control system. Some of the
electromechanical relays were malfunctioning, presenting an operation risk on
the reliability of the system. Lack of spare parts for the components that had
been in operation of over 25 years was also distinguished as a major risk
Other areas
The feasibility study also looked at other areas of the plant and recommended
improvement actions.
Plant Output
The need to optimize plant out put was dwelt into details. However, with
several dynamic factors that influence total efficiency factor, it was found to
be very difficult for operators to select optimum setting for individual units and
the plant as a whole. It was proposed as an alternative to introduce RANAID
software alongside the computerized control system as a means to optimize
out put from the units.
- The general outlook of the power plant needed to be face lifted. The ambient
temperature in the cavern was not comfortable (about 30oC). Noise level was
found to relatively high while insufficient illumination and dirtiness were also
sighted as problems. The working environment required considerable
improvement
REPORT ON KIDATU HYDROPOWER PLANT.
CHAPTER 4
1.Dam:
2. Reservoir:
REPORT ON KIDATU HYDROPOWER PLANT.
The reservoir is a large body of water created by the dam. It stores water that
can be released as needed to generate electricity.
3. Intake Structure:
The intake structure is located near the dam and controls the flow of water
into the power plant.
4. Penstock:
The penstock is a large pipe or conduit that carries water from the intake
structure to the turbine.
5. Turbine:
The turbine is a mechanical device that converts the energy of flowing water
into mechanical energy. It is connected to a generator.
6. Generator:
The generator is responsible for converting the mechanical energy from the
turbine into electrical energy.
REPORT ON KIDATU HYDROPOWER PLANT.
REPORT ON KIDATU HYDROPOWER PLANT.
7. Powerhouse:
8. Transformers:
9. Transmission Lines:
SWITCH YARD
1.Power Transformation:
The switchyard contains power transformers that step up or step down the
voltage to the desired level, depending on the requirements of the
transmission and distribution network.
The switchyard also plays a vital role in voltage regulation and control within
the power system. Voltage levels need to be maintained within certain limits
to ensure the proper functioning of electrical equipment and the stability of
the network.
These are some of the common components found in a hydropower plant, but
the specific design and features can vary depending on the size, capacity, and
location of the plant. For accurate and detailed information about the
components of the Kidatu Hydropower Plant, I recommend referring to official
sources, documents, or contacting the relevant authorities or project
developers associated with the plant.
REPORT ON KIDATU HYDROPOWER PLANT.
CHAPTER 5
2. Industrial Development
The presence of the Kidatu Hydropower Plant has had a positive impact on
industrial development in Tanzania. Reliable and cost-effective electricity
supply is a crucial factor for attracting investment and promoting
REPORT ON KIDATU HYDROPOWER PLANT.
industrialization. Industries require a stable power supply to operate
machinery, run production processes, and meet the energy demands of their
operations.
With the availability of electricity from Kidatu, industries in Tanzania have been
able to expand their operations, increase production capacities, and improve
efficiency. Various sectors, such as manufacturing, food processing, textiles,
and mining, have benefited from the reliable power supply, enabling them to
scale up production and enhance their contribution to the national GDP.
3. Rural Electrification
The Kidatu Hydropower Plant has also played a crucial role in rural
electrification efforts in Tanzania. Access to electricity in rural areas has
numerous benefits, including improved education, healthcare, and agricultural
productivity. It enables the establishment of small businesses, the use of
modern farming techniques, and the provision of essential services in remote
areas.
1.Electricity Generation:
kidatu Hydropower plants generate about 0.8 billion units yearly for the past
five years, however for the good hydrological year the station can generate
over 1 billion units which is a substantial amount of electricity, which is crucial
for driving economic activities across various sectors. Industries, businesses,
and households rely on electricity to power their operations, leading to
increased productivity and economic growth. A reliable and sufficient
electricity supply stimulates economic development and attracts investment.
2.Industrial Development:
Near kidatu HPP there is a huge factory of sugar called Kilombero sugar
company,one factor influences allocation of the industry was presence of
Kidatu hydropower plant.Hydropower provides a cost-effective and
sustainable source of energy for industries. With reliable and affordable
electricity, industries can expand their operations, increase production
REPORT ON KIDATU HYDROPOWER PLANT.
capacity, and create jobs. This leads to an overall boost in the GDP as industrial
output and employment opportunities increase.
3.Infrastructure Development:
4.Rural Electrification:
villages nearby Kidatu HPP benefits from the plants due to facilitation of rural
electrification by extending electricity access to remote areas. Access to
electricity in rural regions can lead to improved agricultural productivity, better
healthcare services, enhanced education opportunities, and the growth of
small-scale enterprises. These developments contribute to poverty reduction,
increased incomes, and overall economic development.
It's important to note that the specific contribution of the Kidatu Hydropower
Plant to the national GDP would require detailed analysis of the electricity
generation capacity, utilization rates, and the overall economic context of
Tanzania. For the most accurate and up-to-date information regarding the
plant's contribution to the national GDP, it is advisable to consult official
reports, economic studies, or contact relevant government agencies or energy
authorities in Tanzania.
REPORT ON KIDATU HYDROPOWER PLANT.
CHAPTER 6
The Kidatu Hydropower Plant in Tanzania utilizes Francis turbines for its power
generation. Francis turbines are a common type of hydroelectric turbine widely
used in medium to high head applications. In this explanation, we will explore
the properties, maintenance requirements, advantages, and disadvantages of
Francis turbines in the context of the Kidatu Hydropower Plant.
Francis turbines are reaction turbines, meaning they operate based on both
the impulse and reaction principles. They consist of a runner with curved
blades and a spiral-shaped casing. Water enters the turbine through the guide
vanes and flows onto the runner blades, where the kinetic energy is converted
into mechanical energy, turning the shaft connected to the generator.
2. High Efficiency:
Francis turbines are known for their high efficiency, especially in medium to
high head applications. The runner and guide vane design is optimized to
achieve maximum energy conversion, resulting in a high overall efficiency for
power generation. This efficiency is crucial for maximizing the electricity output
of the Kidatu Hydropower Plant.
The blades of Francis turbines are adjustable, allowing for precise control of
the turbine's output. By adjusting the blade angles, the power generation can
be optimized according to the demand and variations in water flow. This
control capability is advantageous for managing fluctuations in electricity
demand and ensuring grid stability.
1. Regular Inspections:
Proper lubrication and cooling are essential for the smooth operation of
Francis turbines. Lubricants need to be regularly monitored and changed, and
cooling systems should be checked for efficiency. Maintaining the lubrication
and cooling systems ensures that the turbines operate within acceptable
temperature ranges and prolongs their lifespan.
Accurate alignment of the turbine components and balancing of the rotor are
critical for efficient and reliable operation. Regular alignment checks should be
REPORT ON KIDATU HYDROPOWER PLANT.
conducted to ensure that the rotating parts are properly aligned, minimizing
vibrations and reducing stress on the turbine components.
The Kidatu Hydropower Plant is located on the Ruaha River, which may carry
debris and sediments. Regular cleaning of the intake structures, screens, and
trash racks is necessary to prevent clogging and damage to the turbine
components. Effective debris management systems should be in place to
minimize the risk of foreign object damage.
The installation of advanced monitoring and control systems is crucial for early
detection of any abnormal operating conditions. Real-time monitoring of
parameters such as water flow rate, head, temperature, and vibration helps
identify potential issues and allows for timely maintenance interventions.
1. High Efficiency:
Francis turbines are known for their high efficiency, resulting in maximum
energy conversion and electricity generation. This allows the Kidatu
Hydropower Plant to produce more electricity from the available water
resources, maximizing its power generation capacity.
The wide operating range of Francis turbines enables the Kidatu Hydropower
Plant to adapt to varying flow and head conditions, ensuring continuous power
generation even during seasonal fluctuations or changes in water availability.
REPORT ON KIDATU HYDROPOWER PLANT.
3. Controllable Output:
The adjustability of Francis turbine blade angles allows for precise control of
the power generation output. This flexibility is beneficial for matching the
electricity demand and grid requirements, as the turbine's output can be easily
adjusted to meet varying load demands.
4. Reliability:
3. Capital Intensive:
5. Limited Applicability:
Francis turbines are most suitable for medium to high head applications. Their
efficiency may be compromised in low head scenarios, limiting their
applicability in certain geographic locations. The suitability of Francis turbines
should be assessed based on the specific characteristics of the site and water
resources available.
REPORT ON KIDATU HYDROPOWER PLANT.
In conclusion, Francis turbines at the Kidatu Hydropower Plant offer several
advantages, including high efficiency, wide operating range, controllable
output, reliability, and durability. However, they also have drawbacks such as
sensitivity to sediment and debris, potential environmental impacts, capital
intensiveness, dependency on water resources, and limited applicability in
certain scenarios. Understanding these properties, maintenance requirements,
and pros and cons of Francis turbines is essential for effective operation and
management of the Kidatu Hydropower Plant.
CHAPTER 7
Conclusion;
Recommendations: