Erection Methodology For MPH For Approval29032011
Erection Methodology For MPH For Approval29032011
Owner : KMPCL
Contractor: SEPCO
ERECTION METHODOLOGY
FOR
MPH STRUCTURE
CONTENT
1. SCOPE
2. General
3. Construction Scope
4. Erection Sequence
5. Erection Tools
1. SCOPE
The scope of this document is to present the controls and methodology adopted by
Punj Lloyd Limited for the erection of steel structures for Main Power House 1, 2, 3,
2. GENERAL
Punj Lloyd Limited is responsible for the erection of Unit # 1 to 6 of Main Power
Main Power House Building include A-B Bay (L 30.6 Meters and H 34.7 Meters), B-
C Bay (L 10 Meters and H 34.7 Mtrs) and C-D Bay (L 13 Mtrs and H 48.8 Mtrs) MPH
The MPH steel structure includes H-Shape columns/ beams, bracing, roof truss,
stairs, platform, traveling crane rails, coal bunkers, walk way gallery etc
The MPH is constructed of II tiers A-B Bay at El+ 6.66 M and El+13.46 M, & B-C
Bay of III tiers at El+ at 6.66 M, 13.46 M, 23.76 M ,to the height of 33.7 meters. C-D
3. Construction Scope
• Erection machinery like Crawler cranes of capacity 250MT and 150MT and
Hydra cranes, trailers of all capacity are to be provided by PLL; Cranes for
• Erection engineers, work men and tools for erection are to be provided by PLL.
4. Erection Sequence
1. Erection of D-C Bay grid # 29 to # 27 using 250 MT crane placing between B-C bay
,after completion of D-C Bay up to # 27 Erection of A-B and C will be taken up for the
same grid. Placing the 250T crane in between B-C Bay the crane will be taken back as
We will place 250 MT Crane on Row-C and Grid-24 to erect the Column No. D-22, D-23,
C-22, C-23. Including all tie beams and vertical bracings. Then we will move the crane
backward and placed Grid 26 in same axis. After erecting the column no D-24,D-25 & C
24,C25 with tie beams and vertical bracing. The crane continuously moved and placed
in grid 28 and complete the erection of column no D-26,C-26 & D-27,C-27. Then we will
move the crane to B-row axis for erecting hopper in between Grid-22 to Grid-23, Grid-23
to Grid-24, Grid-24 to Grid-25, Grid-25 to Grid-26 & Grid 26 to Grid 27.Column no. C-1/19,
C-20 and C-21 will be erected including tie beam & bracing after erection of hopper
between grids mentioned above. Roof Truss will be erected simultaneously.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
At the same time, we will place another more 150/80 MT crane outside Row-A for
erection of column, tie beams & vertical bracings of Row-A,3/A,2/A,1/A if possible. EOT
crane gird will be erected simultaneously.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
D-C Bay erection sequence after handing over of the foundations from SEPCO
v) Grouting of tier-1
x) Alignment of tier-11
xviii) Erection of plate forms, gratings and hand rails. and erection of roof beams and
traveling rails
I) Erection of base plate, alignment with packing plate and wilding for A- B bay
IX) subsequently for the three grids #29 to #27 erection will be carried
rd rd
1/19to21 B-Row 1st tier column erection including tie beam 3 May 3 May
th th
B-C Bracing erection, column alignment &Grouting 4 May 5 May
th th
B-C Bay floor beam eretionEL.6.660M 9 May 9 May
th th
B-C Bay floor beam eretionEL.13.460M 11 May 11 May
rd rd
21 - 23 B-Row 1st tier column erection including tie beam 3 May 3 May
th th
Bracing erection, column alignment &Grouting 4 May 5 May
th th
B-C Bay floor beam eretionEL.6.660M 9 May 9 May
th th
B-C Bay floor beam eretionEL.13.460M 11 May 11 May
th th
23 - 25 B-Row 1st tier column erection including tie beam 6 May 6 May
th th
Bracing erection, column alignment &Grouting 7 May 8 May
th th
B-C Bay floor beam eretionEL.6.660M 10 may 10 may
th th
B-C Bay floor beam eretionEL.13.460M 12 May 12 May
25- 27 B-Row 1st tier column erection including tie beam th
6 May th
7 May
th th
Bracing erection, column alignment &Grouting 7 May 8 May
th th
B-C Bay floor beam eretionEL.6.660M 10 may 10 may
th th
B-C Bay floor beam eretionEL.13.460M 12 May 12 May
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
st st
1/19to21 A-Row column 1st tier erection including tie beam 1 June 1 June
th th
A-B 3/A & 2/A,1A Column erection including tie beam 7 June 7 June
nd rd
Bracing erection, column alignment & Grouting 2 June 3 June
th th
A-B Floor beam EL.6.660 M 9 June 10 June
th th
A-B Floor beam EL.13.460 M 13 June 14 June
st st
21 - 23 A-Row column 1st tier erection including tie beam 1 June 1 June
th th
3/A & 2/A,1A Column erection including tie beam 7 June 7 June
nd rd
Bracing erection, column alignment & Grouting 2 June 3 June
th th
A-B Floor beam EL.6.660 M 9 June 10 June
th th
A-B Floor beam EL.13.460 M 13 June 14 June
th th
23 - 25 A-Row column 1st tier erection including tie beam 4 June 4 June
th th
3/A & 2/A,1A Column erection including tie beam 8 June 8 June
th th
Bracing erection, column alignment & Grouting 5 June 6 June
th th
A-B Floor beam EL.6.660 M 11 June 12 June
th th
A-B Floor beam EL.13.460 M 15 June 16 June
th th
25- 27 A-Row column 1st tier erection including tie beam 4 June 4 June
th th
3/A & 2/A,1A Column erection including tie beam 8 June 8 June
th th
Bracing erection, column alignment & Grouting 5 June 6 June
th th
A-B Floor beam EL.6.660 M 11 June 12 June
th th
A-B Floor beam EL.13.460 M 15 June 16 June
2nd Activity
SL Start Finish
NO AXIS DESCRIPTION Date Date
th th
22 - 23 D-Row 2nd tier column erection including tie beam 16 April 16 April
th th
D-C C-Row 2nd tier column erection including tie beam 16 April 16 April
th th
D & C Row column alignment 16 April 17 April
D-C Floor Beam EL.23.760 18 April
th
18 April
th
th th
1/19to21 B-C Row 2nd tier column erection including tie beam 13 May 13 May
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
th th
B-C Bracing erection & column alignment. 14 May 15 May
B Row crane girder erection th
19 May
th
20 May
B-C Floor Beam EL 23.760m & Roof structure rd
23 May
th
25 May
th th
21-23 B-Row 2nd tier column erection including tie beam 13 May 13 May
th th
Bracing erection & column alignment. 14 May 15 May
th th
B Row crane girder erection 19 May 20 May
th th
B-C Floor Beam EL 23.760m & Roof structure 25 May 27 May
23-25 B-Row 2nd tier column erection including tie beam 16th
May 16th
May
th th
Bracing erection & column alignment. 17 May 18 May
st nd
B Row crane girder erection 21 May 22 May
th th
B-C Floor Beam EL 23.760m & Roof structure 27 May 29 May
25-27 B-Row 2nd tier column erection including tie beam 16
th
May 16
th
May
th th
Bracing erection & column alignment. 17 May 18 May
st nd
B Row crane girder erection 21 May 22 May
th st
B-C Floor Beam EL 23.760m & Roof structure 29 May 31 May
th th
1/19to21 A-Row column 2nd tier erection including tie beam 17 June 17 June
th th
A-B Alignment 18 June 19 June
rd th
Crane Girder &Roof structure erection 23 June 24 June
th th
21-23 A-Row column 2nd tier erection including tie beam 17 June 17 June
th th
Alignment 18 June 19 June
th th
Crane Girder &Roof structure erection 25 June 26 June
th th
23-25 A-Row column 2nd tier erection including tie beam 20 June 20 June
st nd
Alignment 21 June 22 June
th th
Crane Girder &Roof structure erection 27 June 28 June
th th
25-27 A-Row column 2nd tier erection including tie beam 20 June 20 June
st nd
Alignment 21 June 22 June
th th
Crane Girder &Roof structure erection 29 June 30 June
3rd Activity
SL DESCRIPTION Start Finish Date
NO AXIS Date
D-Row 3rd tier column erection including tie th
29 April
th
29 April
22 -23 beam
th th
D-C C-Row 3rd tier column erection including tie beam 29 April 29 April
th th
D & C Row column alignment 29 April 30 April
Erection of Coal bunkers &Erection of Roof st
1 May
st
1 May
Structure
D-Row 3rd tier column erection including tie th
29 April
th
29 April
23 -25 beam
th th
C-Row 3rd tier column erection including tie beam 29 April 29 April
th th
D & C Row column alignment 29 April 30 April
Erection of Coal bunkers &Erection of Roof st
1 May
nd
2 May
Structure
D-Row 3rd tier column erection including tie th
29 April th
29 April
25- 27 beam
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
th th
C-Row 3rd tier column erection including tie beam 29 April 29 April
th th
D & C Row column alignment 29 April 30 April
Erection of Coal bunkers &Erection of Roof st
1 May
nd
2 May
Structure
Unit # 3 MPH Structure beams kept hold for Erection for Turbine Equipments erection
(like Deaerator/HP Heater/LP Heater etc) A row #24 - #26 at El+ 6.66m , A-B #27 to
CD Bay 28-29 are Kept Hold for EOT Crane and other Eqpt.
31 D-Row 1st tier column erection including tie beam 13th May 14th May
D-C C-Row 1st tier column erection including tie beam 2nd May 2nd May
D & C Row column alignment ,& Grouting 2nd May 2nd May
D-C Floor Beam EL.13.560 3rd May 5th May
D-C Floor Beam EL.17.260 9th May 10th May
37to36 B-Row 1st tier column erection including tie beam 3rd June 3rd June
B-C Bracing erection, column alignment &Grouting 4th June 5th June
B-C Bay floor beam eretionEL.6.660M 9th June 9th June
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
37to36 A-Row column 1st tier erection including tie beam 1st July 1st July
A-B 3/A & 2/A,1A Column erection including tie beam 7th July 7th July
Bracing erection, column alignment & Grouting 2nd July 3rd July
A-B Floor beam EL.6.660 M 9th July 10th July
A-B Floor beam EL.13.460 M 13th July 14th July
35to34 A-Row column 1st tier erection including tie beam 1st July 1st July
3/A & 2/A,1A Column erection including tie beam 7th July 7th July
Bracing erection, column alignment & Grouting 2nd July 3rd July
A-B Floor beam EL.6.660 M 9th July 10th July
A-B Floor beam EL.13.460 M 13th July 14th July
33to32 A-Row column 1st tier erection including tie beam 4th July 4th July
3/A & 1/A Column erection including tie beam 8th July 8th July
Bracing erection, column alignment & Grouting 5th July 6th July
A-B Floor beam EL.6.660 M 11th July 12th July
A-B Floor beam EL.13.460 M 15th July 16th July
31 A-Row column 1st tier erection including tie beam 4th July 4th July
3/A & 1/A Column erection including tie beam 8th July 8th July
Bracing erection, column alignment & Grouting 5th July 6th July
A-B Floor beam EL.6.660 M 11th July 12th July
A-B Floor beam EL.13.460 M 15th July 16th July
2nd Activity
SL Start
AXIS DESCRIPTION
NO Date Finish Date
37to36 D-Row 2nd tier column erection including tie beam 16th May 16th May
D-C C-Row 2nd tier column erection including tie beam 16 h May 16th May
D & C Row column alignment 16th May 17th May
D-C Floor Beam EL.23.760 18th May 18th May
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
37to36 A-Row column 2nd tier erection including tie beam 17th July 17th July
A-B Alignment 18th July 19th July
Crane Girder &Roof structure erection 23rd July 24th July
35 to34 A-Row column 2nd tier erection including tie beam 17th July 17th July
Alignment 18th July 19th July
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
3rd Activity
SL DESCRIPTION Start Date Finish
NO AXIS Date
37 to 36 D-Row 3rd tier column erection including tie beam 29th May 29th May
D-C C-Row 3rd tier column erection including tie beam 29th May 29th May
D & C Row column alignment 29th May 30th May
Hopper Erection 1st June 2nd June
Roof Structure 10th June 11thJune
35 -34 D-Row 3rd tier column erection including tie beam 29th May 29th May
D-C C-Row 3rd tier column erection including tie beam 29th May 29th May
D & C Row column alignment 29th May 30th May
Hopper Erection 3rd June 5th June
Roof Structure 10th June 11th June
33 to 31 D-Row 3rd tier column erection including tie beam 29th May 29th May
D-C C-Row 3rd tier column erection including tie beam 29th May 29th May
D & C Row column alignment 29th May 30th May
Hopper Erection 6th June 9th June
Roof Structure 10th June 11th June
30 to 28 D-Row 1st tier column erection including tie beam 1st August 1st August
2nd
D-C 1st August
C-Row 1st tier column erection including tie beam August
C&D Row column alignment & Grouting 3rd August 4th August
D-C Floor Beam EL.13.560 1st August 1st August
D-C Floor Beam EL.17.260 1st August 1st August
D-Row 2nd tier column erection including tie beam 5th August 5th August
C-Row 2nd tier column erection including tie beam 5th August 5th August
D & C Row column alignment 5th August 6th August
D-C Floor Beam EL.23.760 6th August 6th August
D-C Floor Beam EL.32.000 6th August 6th August
D-C Floor Beam EL.40.690 7th August 7th August
D-Row 3rd tier column erection including tie beam 8th August 8th August
C-Row 3rd tier column erection including tie beam 8th August 8th August
D & C Row column alignment 8th August 8th August
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
th
Hopper Coal bunkers 9th August 10 August
th th
Erection of Roof Structure 10 August 10 August
th th
C-B B-Row 1st tier column erection including tie beam 11 August 11 August
th th
Bracing erection, column alignment &Grouting 11 August 12 August
th th
B-C Bay floor beam eretionEL.6.660M 12 August 12 August
th th
B-C Bay floor beam eretionEL.13.460M 12 August 13 August
th th
B-Row 2nd tier column erection including tie beam 14 August 14 August
th th
Bracing erection & column alignment. 14 August 14 August
th th
B Row crane girder erection 15 August 15 August
th th
B-C Floor Beam EL 23.760m & Roof structure 15 August 15 August
B-A A-Row 1st tier column erection including tie beam 16
th
August 16
th
August
th th
Bracing erection, column alignment &Grouting 16 August 17 August
th th
B-A Bay floor beam eretionEL.6.660M 18 August 18 August
th th
B-A Bay floor beam eretionEL.13.460M 18 August 18 August
th th
A-Row 2nd tier column erection including tie beam 19 August 19 August
th th
Bracing erection & column alignment. 19 August 19 August
th th
A Row crane girder erection 20 August 20 August
th th
B-A Floor Beam EL 23.760m & Roof structure 20 August 20 August
For unit 2/unit 1, the same sequence as unit 3 from #19 axis to #1 axis; and for unit
5/unit 6, the same sequence as unit 4from #1/37 axis to #58 axis.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
5. Erection Tools
32 crane 250T 2
33 crane 150T 3
34 crane 70T 4
35 crane 40T 2
36 crane 20T 3
37 Trailer 40 T 3
i) Site In – Charge 1
v) Quality Supervisors, 4
vii) Fitter, 15
ix) Rigger, 30
x) Welder, 15
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
xii) Grinder 10
All special type personnel must have the corresponding qualifications and work
experience. They must be trained and qualified to perform boiler structure erection.
All personnel working at height will be approved by the examination. Medically fit
personals are allowed to work at height. Proper identification cards will be provided for
PLL work men.
Alignment of
Fixing of lifeline & Columns after box
safety nets formation
Lifting & fixing of
connecting
beams & bracings
Bolt tightening of
Removal of columns & beams by
ladder
• 350NM torque
tightening
• 700NM shearing
27. After the erection of Tier#1 alignment and bolt tightening to be done before
start of Tier#2.
28. Lifeline and safety nets to tie at top of columns before Tier#2 erection.
29. In same above procedure Tier#2 to be erected.
30. The same procedure shall be followed for all structural erection works for
erecting the Tier # 3, Tier up to roof level
1. The civil foundations for the structural shall be checked for any defects. Center to
center distance between the foundations to be checked as per drawing.
2. The PCD of the foundation bolt and diagonal across the bolt holes shall be checked
3. Accepted signed protocol should be taken from civil before starting of erection for
record purpose.
4. Column base plate center line alignment with respect to the center line of the
Foundation (by using level m/c).Approval for acceptance of base plate alignment
to be taken from M/s. SEPCO & M/s.KSK.
5. Tightening of base plate bolt with spanner and carrying out of grouting as per
specification.
6. Base plate alignment protocol should be made for record purpose.
7. Tier#1 column erection to be carried after the above procedure.
8. Center line marking & punching on the columns and put the scaling sticker on 2
sides (X-Y direction) while erection.
9. After boxing of columns & beams verticality checking of columns to be carried out
(by using Theodolite)
10. Verticality checking to be done in both directions (X-Y) (a,b Row & grid).
11. Ø 16mm Coi rope to arrange with length according to height and work area. U-
Clamp, D-shackles and Chain blocks of 3T/5T capacity as per load requirement to
arrange and shift to work site. Ø 14mm PP rope to arrange for lifting purpose.
12. Boxed up columns (i.e. 4 columns) vertical top center position to be checked with
respect to base plate center position by theodolite in both directions (X-Y).
13. Coi rope (Ø 16mm) of required length (approx. 30M for Tier #1) to be lifted with PP
rope to particular column which require centering.
14. Boxed up columns with beams is to be ensured with proper lifeline and safety nets
for work approach.
15. Tie the PP rope Ø 14mm along the ladder with fall arrestor at columns.
16. Column is to tie with coi rope at top by providing packing (gas cut pipes) in
between coi rope at all four ends of column to avoid from damage.
17. The opposite end of ghai rope is to be fixed with chain block and counter weight, to
the direction where by manual pulling of chain blocks load will be applied to move
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
the column to the center position so as to match with the center line of the base
plate (confirming by using Theodolite).
18. Chain Blocks to be used 3T for minimum movement (approx.5 to 10mm) of columns
and 5T for (more than 10mm and above) maximum movement. Chain block is to be
fixed with U-clamps (min.3nos.) with coi rope.
19. Boxed column to column center distance and diagonal distance to be checked
with measuring tape.
20. After centering the boxed-up columns the same to be approved by M/s. SEPCOI &
M/s. KSK. and protocol to be maintained for record purpose.
21. After alignment bolt tightening to be done to columns, beams and bracings
keeping chain blocks on load.
22. Accordingly other boxed up columns are to be aligned in the same above
procedure.
23. After the erection of Tier #2, alignment can be done by
following same procedure.
24. The same procedure shall be followed for all the tiers.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
COLUMN
FOUNDATION
Counter wt.
Fig .I Fig.II
1. Required quantity of bolts is shifted from SEPCO store to PLL store near MPH area.
These bolts are stored in weather proof area free from dust and water.
2. The quantity required for the day is taken from the package and if left out, the same
is returned to the same package.
3. The bolts are checked for the freeness of nut over bolt, thread damages and rust free
before use. Also when using the bolt, it is not to be polluted.
4. The bolts are used as per the dimensions mentioned on the approved drawings.
6. After manual tightening, torque tightening is done with torque wrench. The torque
value is provided by the quality department of SEPCO.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
7. The deviation of torque value should be with in ±10 %. After torque tightening is
completed, the bolt is marked with paint for distinguishing.
9. Record of bolt tightening is maintained by PLL for billing and for future records.
10.Boxed up columns after alignment Coi rope are to be kept in load with chain blocks
til bolt tightening have been done.
11. Boxed up columns with beams is to be ensured with proper lifeline and safety nets
for work approach.
12. Tie the PP rope Ø 14mm along the ladder with fall arrestor at columns.
13. Arrange 350NM torque bolt tightening m/c and 700NM torque bolt shear m/c. from
M/s.SEPCO and shift to the work site.
14. Also to arrange for the power cable 2.5mm2 with plug about 50mtr.long for each
type torque m/c. connection and switch board with power connection. Arrange Ø
14mm PP rope for lifting the torque machine.
15. Before taking m/c. at height ensure proper running condition of machine, workmen
should take safety measures by wearing hand gloves while running the machine to
prevent from electric shock.
16.1st lift the 350Nm tightening m/c with pp rope to work area then tight the bolts for
Column and base plate joints, next tight the bolts for main beams with columns and
next tight for beams and bracings.
15. After the completion of 350Nm torque m/c., apply the 700Nm shear cutting m/c. in
the same above process, then release the load from coi rope and remove the ladder &
platform.
16. Always ensure to apply 350Nm tightening m/c. approx.30sec.max. And then 700Nm
shear m/c. til the bolt gets cut.
17. After the bolt tightening for Tier#1; Tier#2 can be erected.
18.After alignment of Tier#2, 1st Tier#1 column to Tier#2 column to be tightened and
cut, next beams and bracings in the same above process.
Project: 6 x 600 MW KSK MAHANADI POWER PROJECT
Owner : KMPCL
Contractor: SEPCO
19. The same procedure shall be followed for all the tiers.