0% found this document useful (0 votes)
18 views1 page

26-02-2023 Phyiscal Progress All Lots

The document provides a physical progress report on various construction activities including laying pipes of different diameters, pipe production, brickwork on structures like wells and buildings, and excavation work. Quantities completed for over 50 construction items across 4 different areas are listed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views1 page

26-02-2023 Phyiscal Progress All Lots

The document provides a physical progress report on various construction activities including laying pipes of different diameters, pipe production, brickwork on structures like wells and buildings, and excavation work. Quantities completed for over 50 construction items across 4 different areas are listed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Physical Progress Date: 26-02-2023

LOT # Activities Qty


UC-04:
1 House Connections 50 Nos.
L2.2.2 Tariq bin Zayad (15") pipe laid 3 Nos.
Pak Avuenue Street near Civil Hospital (24'') pipe laid 14 Nos.
L2.2, Tariq bin Zayad (42'') pipe laid 1 No.
L2.2, Tariq bin Zayad (36'') pipe laid 5 Nos.
L2, Faisalabad Road (72'') pipe laid 8 pipe
2

Pipe Production:
21'' dia = 2
24'' dia =6
36'' dia = 4
42'' dia= 4 16 Nos.
Dry well:
Brickwork in core wall (inner side) 1250 cft
3
Office building:
Brickwork in superstructure 112 cft
4 L3, 72'' dia, Manhole # 126 Brickwork 118 cft
Road 1: Fateh Sher
Model Roads Excavation of drain 70 Rft
Spreading of water bound from RD 0+400- 1+000