MS - Piling Works
MS - Piling Works
METHOD
STATEMENT
for the construction
of
BORED PILES
1|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
Scope of Work
The method statement for bored piling below describes the whole construction
procedures including material and equipment required for the construction of bored
cast-in-situ piles. The piles to be constructed will be of a nominal specified diameter,
bored through overlying soils and upon completion to withstand loads with shaft
friction and end bearing as designed by the Engineer/Consultant.
References
IS 2911-1-1 (2010): DESIGN AND CONSTRUCTION OF PILE FOUNDATIONS
456: 2000: Plain and reinforced concrete — Code of practice (fourth revision)
1786: 1985: Specification for high strength deformed steel bars and wires for concrete
reinforcement (third revision)
Access to the site will be prepared before the machine is mobilized. The minimum
width of the access road is 3m, and overhead obstructions (e.g. cable, gantry etc.)
with a minimum clear height of 5m. The access road will be compacted and laid with
stones if necessary.
Working Platform
The working platform has to be relatively flat but well drained to prevent water
ponding. The platform will be compacted to withstand pressure equivalent to machine
weight and steel blocks with additional 20% allowance. Generally, it is about 2.5
times the specified pile working load. A soil bearing capacity of 1.0 to 1.5 tons per
sq.ft. is deemed sufficient. For higher capacity pile installation, the working platform
will be laid with a layer of stones to further strengthen it.
2|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
The working platform will be free from existing underground utilities such as water
pipes and electricity cables. If relocation of these utilities is not possible, a piece of
steel plate will be overlaid to protect them. During pile installation, the machine will
avoid exerting pressure over them as far as possible.
3|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
machine. Rotate the auger in the opposite direction to remove the soil from the
auger.
3. The auguring process is repeated until the required depth is reached or hard layer
or rock is reached.
4. A boring/drilling bucket can also be used to drill into soil or harder material,
usually in flooded boreholes.
5. If necessary, use a cleaning bucket to clean the bored hole with the process
similar to the auger. However, for dumping of soil/spoils, the bucket needs to be
released by pulling a pin manually.
6. For hard soils and solid rock, if necessary, rock auger head can be employed to
grind into hard soils and rock and subsequent removal of fragments by bucket.
7. Continue the above procedure until the tentative completed level / sound rock
level has reached. Soil samples & rock fragments will be collected for inspection.
4|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
1. Extension of the steel casing (if necessary to prevent collapse) can be done by
welding on additional casing during excavation. A sample is shown in Fig.1.
However, the method may vary from site-to-site, depending on the soil condition.
If the soil is soft, simple full welding is sufficient. Verticality of the casing will be
monitored by means of spirit level from time to time.
5|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
2. The use of drilling mud (chemical polymer-type hole stabilizer) can be employed
to stabilize a flooded borehole. The polymer shall be added and mixed in a tank
prior to being pumped into the borehole to stabilize it. Boring can then continue
with the polymer stabilizing the borehole. The polymer can be either recycled to
clean away augured mud/soil using a recycling system tank or it can be discarded
away from site as sludge/soil. The main aim is to advance the hole as deep as
possible without causing a collapse. The quantity and time of polymer mixture
shall be at the discretion of the bore piler with experience in determining hole
stability. (See catalog from www.thl.com.sg/consumable/poly/index.php)
3. If bentonite is used and recycled, the properties of recycled bentonite shall be sent
to a lab for testing to ensure compliance with the specifications.
4. The bored hole shall be concreted as soon as possible to prevent further collapse.
However, if casing or polymer is in the hole, it can hold up the soil and prevent
collapse longer.
6|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
7|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
8|Page
Method Statement for
Construction of Bored Piles
Doc. No.:
J4C/DX/BOM10/SOO/CL/132
Rev No. R0
Date: 04-01-2024
9|Page